You are on page 1of 26

Construction Health and Safety

EXCAVATION

Section 8B

8B - 1
SPECIAL ACKNOWLEDGEMENTS

Appreciation is expressed for the work of the author of this subsection:


J.R. Illingworth Esq., BSc, FCIOB
Consultant in construction methods and technology

Special acknowledgement is made to the Timber Research and


Development Association for permission to publish the table on p.8B-
45and numerous illustrations, as annotated, from their publication
Timber in excavations, together with free interpretation of parts of
the text of the same publication.

Acknowledgement is also made to the Construction Industry Research


and Information Association for its assistance, in particular for
permission to publish the table on p.8B-9, which is based on a similar
table in CIRIA Report 97 Trenching practice, and to Zetica Ltd for
their help in preparation of the guidance relating to Unexploded
Ordnance.

CONTENTS
Introduction 8B–3
Ordnance 8B–3
Ground conditions 8B–4
Method of excavation 8B–7
Basic principles of support 8B–7
Standard or designed solutions 8B–9
Systems of support 8B–9
Trenches 8B–11
Wide and single sided excavations 8B–15
Shafts 8B–15
Headings 8B–17
Permanent works as temporary support 8B–19
Related safety aspects 8B–20
Check List No.1 – Site conditions and method constraints 8B–22
Check List No.2 – Before work starts 8B–22
Check List No. 3 – Whilst work is in progress 8B–22
Glossary of terms 8B–23
Method statement checklist - groundworks 8B–24
Reference sources 8B–25

8B - 2 June 2005
EXCAVATION
Introduction early stage, before specialist contractors are on site, to
Excavation is an essential element of the construction establish the level of probability of UXO being present.
process particularly in relation to the construction of Maps are available from local authorities and commercial
foundations, drainage work and site regrading of all kinds. organisations showing the density of impacts for specific
Information regarding any hazards identified prior to regions. These are largely produced from information
construction should be included in the Construction Phase gathered during bomb watching duties during WW2. This
Plan required by the CDM regulations 2007. should be available in the pre-construction Information which
In carrying out an excavation, the soil conditions can the Client has a duty to provide under CDM.
vary widely, often in short distances. No soil, whatever its CDM Regulation 34-(3) requires suitable and sufficient
nature, can be relied upon to support its own weight for any steps to be taken to reduce risk from damage or disturbance
length of time - let alone any additional loads which may be of any underground energy distribution installations. This will
imposed by plant and materials. It should never be forgotten apply to any ground penetrations where services may be
that 1m3 of earth weighs approximately 1.3 tonnes. Even a present, regardless of the scale of that work.
small fall of earth is capable of inflicting serious injury, even Particular problems will arise where underground lines
if it does not kill. Unless, therefore, the excavation can be are in close proximity and prudent contractors are well
battered to a safe slope, the sides will need supporting to advised to discuss these matters with the owners of the line
prevent the possibility of collapse and thus: during the tendering process. If the site is in a high risk area
1. provide safe conditions for persons working in or a qualified Explosive Ordnance Clearance (EOC) specialist
adjacent to the excavation and, in some situations, the should be employed to prepare the risk assessment and a
public as well. method statement.
2. enable the works to be carried out without interruption A surface geophysical survey using ground penetrating
and radar can detect ordnance and other obstructions to a level
3. protect adjacent property and/or public services. of 3 metres which, if the ground is clear, will allow
CDM - Part 4 require all practicable steps to be taken to excavation down to that depth. The radar can be then be re-
prevent injury to persons due to the accidental collapse of an employed to examine a further 3 metres of depth, a process
excavation or by any fall of material; neither must which is repeated until the required depth is reached. This is
excavation work be allowed to cause the weakening of any laborious but it is the safest method. This process can cause
structure. Any excavation used as a place of work must be particular difficulties if the contractor is anticipating working
inspected and reports completed in accordance with in an existing water course, e.g. driving piles or shafts in a
Schedule 3 of the CDM - Part 4. Whenever excavation has river bed which would involve the construction of coffers
to be undertaken, therefore, adequate prior consideration dams. Ground penetrating radar can operate from a boat
needs to be given to the soil conditions that will be met, the and specialist contractors are available to carry out this
method of excavation to be used and the manner in which function if required.
any necessary support will be provided. The typical depth of rest of large, air-dropped UXB is
Traditionally, timber has been used in the support of 15m below the surface, and could be greater in, for
excavations. However, modern methods incorporate steel, instance, soft silts. These, and other ferrous objects, can be
and proprietary systems are invariably of metal detected using a probe-magnetometer that is driven into the
construction. It should be noted that the term ‘Timbering’ is ground hydraulically, and can detect UXB and obstructions
frequently used to describe any form of support work, down to the no-risk depth. However, this method is invasive
whatever material is being used. A glossary of other terms and carries a potential risk of striking the UXO with the
used in the support of excavations is given on p.8B-22-23. probe.
In order to assist in the proper design, planning and Emergency procedure plans should also be put in place
execution of excavation work, a series of check lists is in case of unexpected discovery of ordnance because, even
provided at page 8B-23. A general checklist for with the latest technology, detection is not 100% as outside
groundworks method statements is also provided at the end influences can mask or alter the signal reflected from the
of this section. UXB.

Ordnance Whilst working the site


The most likely source of unexploded bombs (UXB) and After 60 or more years in the ground, bombs and other
other ordnance (UXO) is from the thousands of devices items of ordnance generally maintain their shape, but
dropped on major cities during the Second World War. It is become very rusty and decayed. If a suspicious object that is
estimated that 10% of high explosive and as much as 50% similar in size and shape to a WW2 bomb is uncovered
of incendiary devices failed to explode. These continue to during the course of groundworks, the emergency
present a potentially serious hazard to construction workers, procedures should be put into effect. These would include:
property and third parties. Brown field sites that were • Stopping work
previously MoD land are also high risk locations, especially • Evacuating to a safe distance; this may be outside of the
if they were used for training purposes. Whilst these boundary of the site and could involve members of the
comprise the major areas of risk, UXO and UXB are found in public.
the most unexpected places, such as beaches where • Calling the police on 999 to notify the nearest bomb
ordnance is washed up following post war dumping and the disposal unit.
action of underwater currents and wave action over many • Ensuring nobody re-enters the area until told to do so by
years. the authorities.
On discovery of an item of ordnance or a suspect object,
the location of the object should be marked, and the
Prior to starting Work. immediate area evacuated in relation to the size of the
When excavating, piling or drilling in inner city object. The object should not be touched or moved until it
environments, particularly in areas that were subject to has been identified. If in any doubt call the police and they
severe bombardment such as London, Coventry, Liverpool will call the bomb squad.
etc, it is recommended that a risk assessment be made at an

December 2007 8B - 3
Ground conditions the pumping out of water has the effect of lowering the
Before commencing any excavation, it is important ground water table to a level below that to which the
to identify the type of ground in which the excavation is excavation is to be taken. Wells or wellpointing, for their
to be carried out. Detailed information may be available successful use, require a proper soil analysis to make sure
with the contract documentation, or in the form of bore- that the method is feasible. It must also be established, at the
hole or trial pit logs carried out as part of the same time, that no fine material will be drawn from
site investigation. Whichever method is used, it is helpful underneath adjacent property with consequent risk of
to have a simple means of identifying the various strata settlement.
that may be found. The table on p.8B-4 is a very useful Where water is contaminated advice must be sought
guide. from environmental consultants or the Environment Agency,
When examining boreholes or trial pit information, as re-introducing contaminated water back into the ground
particular importance should be paid to the location of any could constitute a criminal offence (see Section 34).
water table. If the water table is going to be exposed by the Modern technology provides alternatives to dewatering
excavation, careful consideration will need to be given to the ground. Stabilisation of the ground can be achieved by
how it may affect the stability of the excavation sides. chemical injection or freezing (see Section 30 – Ground
Ground water can greatly affect the stability of any soil and, Treatment). Injection and freezing methods are always
in particular, non-cohesive materials. Water can also enter expensive compared to dewatering and are therefore only
an excavation as surface run-off used when other methods cannot cope with the situation.
Whatever the source of water, effective action is They require highly skilled technologists to operate them and
necessary, either to stop the water from surface sources will be effective only in soils suitable to their use. Before any
entering altogether or, in the case of ground water, decision is made to use them, specialist advice from a soil
minimising its effects to the greatest possible degree. mechanics expert is essential.
Where a water-bearing strata overlays an impervious
Surface water one and the depth of this impervious strata is not too great,
Surface ditches, streams etc., likely to be interrupted by the use of sheet piling may be more effective and
the excavation, may need diversion. Where the excavation economical. The piling, being substantially watertight, ‘cuts-
is across a slope in the ground, cut-off ditches should be off’ the water from the excavated area, thus enabling the
considered if the work is to be carried out in a rainy period. excavation to proceed in the dry.
Where the location of field drains is visible, they should be
cut off and diverted before the main excavation starts. Ground conditions and slopes
It is worth noting that under the Water Resources Act
1991 “pollution” of any controlled water is an offence. The Notes:
word pollution includes site run-off and silt (see section 34). 1 These are guide figures to slopes based on and subject
to:
Ground water a Temporary conditions (ie generally 1 to 14 days)
The presence of ground water is more difficult to deal b Field safety and experience
with than surface water. It may affect the sides of the c A safety limit of 45 degrees (but see Note 7 below)
excavation to the extent that, even if supported, wash out of d Water seepage can cause wash out and undermining
material will occur between the sheeting. In certain soil 2 ‘Dry’ site: minor or no seepage from excavated faces.
conditions, the bottom of the excavation can become Minor or no surface run-off.
unstable and ‘boil’ with the inevitable total collapse of the 3 ‘Wet’ site: submerged or widespread seepage from
trench. The relationship of ground water to the soil excavated faces.
conditions needs careful analysis before a decision is made 4 The behaviour of soils is influenced by the grading,
as to the support method to be used. particle size, shape and density. In mixed soils the
If the ground is suitable, one of several ground maximum grain size of the smallest 15 per cent by weight
dewatering techniques may be used. Such methods involve of the grading tends to characterise the soil.
either shallow well pumping or wellpointing. In either case, 5 Normally consolidated clays are usually stronger within
a few metres of ground level due to desiccation.
However, the clay crust is fissured for the
same reason (note the fissures may not be visible) and
is seldom greater than 4 metres deep.
Classical soil mechanics theory would suggest that clay
with a cohesion greater than 30kN/m 2 will stand
vertically to 6 metres. However, due to the fissuring, the
face becomes unstable and lumps fall into the trench. In
deeper trenches there is a risk of toe failure due to
underlying softer clay. The suggested slopes are intended
to avoid danger to workmen from these risks and are
offered as a guide only.
6 Flatter slopes may be applicable or required subject to
the evidence on:
a Incipient (structural) failure planes
b Safety precautions against small or large falling
fragments
7 Steeper slopes may be applicable or required and will be
subject to the same assessment as in Note 6.
There is also the growing use of permanent construction
to provide both temporary support and deal with water
problems. Diaphragm walls and seacant piling are
Use of sheet piles to ”cut-off” excavation from water-logged frequently used in this way. Both methods are described in
ground. detail in the paragraphs dealing with “Permanent works as
1. permeable strata. 2. water. 3. impermeable strata. temporary support”, p.8B-18/19.

8B - 4 June 2005
Ground Safe Temporary slopes (1)
type Field tests and descriptions (degrees from horizontal)

‘Dry’ site ‘Wet’ site


GRANULAR i Particles visible BOULDERS (>200mm) 35/45 (6) 30/40 (6)
ii Sands feel gritty COBBLES (60 to 200mm) 35/40 (6) 30/35 (6)
iii Visually assess proportions GRAVEL ( 2 to 60mm) 30/40 10/30
of Boulders/Cobbles/Sand SAND (0.06 to 2mm) 30/35 10/30

COHESIVE i Particles not visible SILT (0.002 to 0.06mm) 20/40 5/20


ii When damp silt and fine sand
are shaken in the hand water
appears on the surface Trench depth (m) 1.23 3-6
iii Soft clay is easily moulded by CLAY (5) Soft 30/45 20/30 10/20
fingers
iv Firm is moulded by strong Firm 35/45 30/40 20/25 (6)
finger pressure
v Stiff is indented by strong Stiff 40/45 35/45 25/35 (6)
finger pressure see (6) and (7)
vi Fissured clay should be
examined for its structure

i Rotten or rotting vegetable PEAT Soft non-fibrous 10/20 5/10


matter (black, grey Firm non-fibrous 15/25 10/15
ii Smell or brown Firm fibrous 35/40 (6) 20/25 (6)
iii Fibrous or non-fibrous clayey or Stiff fibrous 35/45 (6) (7) 25/35 (6) (7)
iv ‘Soft’, ‘firm’ or ‘stiff’ sandy)

FILL i All types of man-placed material As main soil type (eg clay, According to category
ii Note constituents including sand, gravel, etc) above
unnatural inclusions

ROCK i Mass stronger than the above As appropriate to the Check orientation of
soil types predominant constituents and planes
ii Important to note cementation, characteristics
structure and orientation,
(fissures, joints. bedding,
layers, etc)
iii Closely jointed rock may act
as “granular” and weak
weathered rock as “clay”

GROUND- i Levels water encountered Full description necessary See note 1 (d)
WATER ii Rate of entry
iii Standing level
iv Flood conditions

This page is reproduced from the publication Timber in excavations, by coutesy of the Timber Research and Development
Association.

June 2005 8B - 5
Failure modes If battering to a safe angle is not possible, full sheeting of
The importance, and indeed necessity, of providing the excavation will be necessary. The method of installation
proper support to excavations is often hard to explain to site should:
operatives. The reason is not hard to find. Clays, to the 1. allow for the sheeting to be pre-driven before
inexperienced, often look very stable when first excavated. excavation takes place, or
They stand up vertically, in many cases, for a surprisingly 2. be capable of sheeting to a pre-determined depth
long time and a false sense of security is built up. Rock tends before excavation proceeds further, or
to be assumed as being highly stable, and not needing any 3. allow the main supporting members to be installed
support at all. Why such assumptions are dangerous is horizontally as the excavation proceeds downwards
illustrated in the following paragraphs. (see p.8B-11 for the H pile system of support).

Saturated clayey silts present the most difficult problem Firm or stiff clay These clays, with or without a degree of
as the sides will slump into the excavation. The only really sand or gravel present, will stand unsupported after
satisfactory solution is to dewater the ground outside the excavation, but what is often not appreciated is that the
limits of the trench. apparent stability can deteriorate rapidly in a short period of
time; then the face will be liable to collapse without warning.
Saturated silt or sand Dewatering outside the line of the Collapse is initiated in two ways:
proposed trench will, in general, provide the most 1. When a trench is excavated, soil at the sides is relieved
satisfactory and safe solution. If this is not possible, sheet of lateral restraint and tends to swell inwards. Cracks
piling will be needed to provide a watertight support. To occur causing unstable lumps. These, in turn, can break
achieve a safe toeing-in at the bottom of the excavation, the away and fall into the excavation without warning.
piling may need driving to a considerable depth to avoid the

bottom of the excavation boiling up and causing total


collapse of the trench support. Only if the silt or sand
overlays an impervious strata, and a cut-off is possible, will a 2. Many clays contain fissures, or cracks, which appear
really safe and economic solution be possible. due to the drying out of the clay. When rain, or other
Sand Where a degree of silt is present in the sand, the surface water, penetrates the crack or fissure, the clay is
material may well stand up initially. The illusion of stability is softened and lumps can readily break away. Earth falls
false, as a heavy rainfall can provide the lubrication are therefore more frequent in wet weather.
necessary to allow the trench side to slip into the excavation. Battering must be at a shallow enough slope (see table p.
The cohesion of the material is also affected by the sides of 8B–5). If battering is not suitable, properly assessed support
the excavation drying out. Again the sides of the excavation will be necessary.
will collapse, usually without warning. Battered sides are the
best answer, provided that suitable surface water cut-off Rock At first sight, rock excavation would seem to present
drainage is provided. The alternative is to provide adequate the least problems. In fact, all rock masses (including chalk,
support with the minimum of delay. which can be classed as ‘soft’ rock) are separated into
blocks by bedding planes, cleavage planes and fissures. All
Soft clays Battered excavations in soft clays require careful these are planes of weakness; they can contain water or thin
consideration in relation to the slope to be used (see table p. layers of clay which act as lubricants which will facilitate
8B–5 for suggested slopes). If too steep, failure can occur by sliding along the planes.
rotation.

Excavation in steeply dipping rocks.


Collapse of trench side following slide along bedding planes
Remedy-heavy timbering

8B - 6 June 2005
Rock excavation, by its very nature, tends to leave Double sided support
ragged faces. Small but heavy fragments may be held in With this method of support, the forces exerted by the
place quite loosely and vibration, e.g. due to blasting, will earth are transmitted from one side of the excavation to the
dislodge them. All rock excavations should have such loose other by walings and horizontal struts, i.e. the forces
fragments knocked down as the digging proceeds. Further imposed by the earth on the supporting materials are
examinations must be carried out daily, before work com- resisted by the earth on the opposite side of the excavation.
mences in the excavation. Chances must never be taken in Hence, if the support is adequately designed, a state of
rock; support must be provided if there is any doubt. equilibrium is maintained between the two sides.

Method of excavation

Where an excavation has to be provided with a suitable


form of support, the system and the method to be adopted
for the excavation cannot be considered individually, in
isolation. Each will inevitably react on the other and persons
dealing with the temporary support must maintain close
liaison with whoever is making decisions on the plant to be
used. Such liaison is particularly important in drainage
work, when long pipes or large precast manhole rings may
have to be lifted through any supporting struts etc.

Basic principles of support

There are many ways by which excavations can be made


safe to work in, avoid settlement to adjacent land and
buildings and allow work to proceed with minimum
hindrance. There are, however, only the following four
fundamental principles involved: Double sided support. All forces horizontal

Battered sides Of methods using a form of structural support, this is the


This is probably the safest method and accidents resulting most satisfactory, as only horizontal forces are involved. The
from the collapse of properly designed and executed method lends itself to the use of pre-designed (“Standard”)
battered systems are rare. Almost all soils can be excavated solutions and proprietary systems, which are installed in
to a safe batter, provided that sufficient space is available accordance with manufacturers’ tables provided. (Also see
(i.e. The batter will not affect adjacent buildings, etc.) and a the paragraphs dealing with the limitations of standard
safe angle of response is known and adhered to (the table solutions on p.8B-9).
on p.8B-4 gives a guide to temporary safe batters in various In saturated silt and sand, where dewatering is not being
types of ground). used, there is a serious risk of the bottom of the trench
Where waterlogged ground is involved, specialist advice ‘boiling’ upwards. If this happens, total collapse of the
should be taken, as some system of ground dewatering will support system results. In such conditions, therefore,
be needed to improve stability. Only tests can show whether standard solutions must in no circumstances be used. The
or not the ground is capable of being dewatered. penetration of the sheeting is a key factor in the safety of the
Surface water can seriously affect the stability of battered support, which requires design by a competent person.
slopes. Where such flow is likely to happen in wet
conditions, interceptor trenches, to cut off surface water and
lead it away from the excavation, should be provided.

Sheet pile solely in non-cohesive and wet soil

Penetration must be adequate to avoid “boils” or “blows”


and determined by a competent temporary works designer.

June 2006 8B - 7
Single sided with raking support Whether shores or anchors are used, single-sided
Only one face of the excavation is involved. Earth support systems are not suitable for standard solutions. They
pressure from the excavated face is resisted by transferring must be designed by suitably qualified persons and, with
the load through the support material via walings to either ground anchors, the anchors designed and installed by
raking shores or ground anchors. In the raking shore specialists. It should be noted that single-sided support is
approach, an adequate foundation is needed to transfer the most frequently used to protect boundary conditions.
loads involved to the unexcavated ground.
When raking shores are used to resist horizontal forces, Single-sided cantilever support
the load in the raking member is greater than the horizontal Whatever variation of this principle is adopted, it should
load and a vertical uplift force is introduced into the support always be designed by suitably qualified persons. The
system. The design for this type of support must, therefore, method can be used only:
allow for sufficient toeing-in of the sheeting to resist these 1. in ground conditions which are sufficiently stable to
upward forces, as must the design of the connections provide the necessary resistance to balance the overturning
between strut, waling and sheeting. forces, or
2. where the effect of superimposed loads and their stability
is not critical.

With ground anchors,’ the situation is the same, but the


forces are reversed. The ground anchor system is in tension,
while the vertical component is trying to pull the whole All cantilevers will deflect to a degree. Such deflection
assembly downwards. Care must therefore be taken to will create risk to adjoining installations and structures,
ensure that the forces in individual anchors are not too great roads, etc. and their use in these circumstances should be
for the ground to resist their vertical component. avoided.
The use of cantilever systems can be improved, in terms
of deflection, by what is known as a propped cantilever. This
involves tying back the top of the sheeting system to an
appropriate anchor block. The effect of introducing a
horizontal tie-back is to reduce any deflection and at the
same time maintain a system involving horizontal forces
only.

8B - 8 June 2005
Standard or designed solutions Timber
In the majority of cases, the support of excavations is Timber is used as a sheeting material, in the form of
carried out by on site “Standard Solutions”, without recourse poling boards and runners, and also as walings and struts.
to special design. The advent of proprietary equipment has Examples of its use are given later in this section under
greatly increased the scope for such methods. The support of Trenches, Shafts and Headings.
some excavations, however, will require detailed design
work by competent persons. Steel trench sheeting
Trench sheeting has the advantage of easy driving in
poor ground, prior to an excavation being commenced. In
stiffer ground, it can be part driven initially, then further
Standard solutions driven as the excavation proceeds.
It is essential that clear parameters are established in the
adoption and use of standard solutions. These are:
1. The use of standard solutions should be applied only in
the following circumstances:
(a) Double sided, narrow trench support, not exceeding
6m deep in non-water bearing ground.
(b) Shallow pits, not exceeding 6m deep.
(c) Where water problems have been eliminated by
other means, e.g. wellpointing, and the excavation
is within the limitations of (a) or (b) above.
(d) When an unsupported trench, not exceeding 6m
deep, is feasible.
2. When adopting the standard solution approach the
following points need to be followed:
(a) When deciding the safe batter of an excavation,
proper account must be taken of the ground
conditions.
(b) Where support is provided, the method must
comply with recognised good practice in all
details (see TRADA & CIRIA publications listed on
p.8B-25).
(c) Where proprietary systems are used, installation
must be strictly in accordance with manufacturers
instructions.
(d) The system of work to be adopted must be explained
in detail to the persons engaged in placing or
removing supports, and others who will be working
in the excavation.
(e) If possible, the system of work should be illustrated
with drawings or sketches, or with suitable
proprietary literature, together with check lists.
(f) The method of work and instructions and sketches
provided must be strictly adhered to. Steel sheet piling
(g) Specialist advice should be sought if there are any Obtainable in a variety of sectional stiffnesses, sheet
doubts as to the safety and sufficiency of the support piling is interlocking and, being much stiffer than trench
system. sheeting, it can be pre-driven to much greater depths before
The table on p.8B-10 provides a guide to standard any excavation is started.
approaches in the support of trenches. Details of Sheet piling is expensive in the cost of driving and in its
construction are outlined on p.8B-11 and further information subsequent extraction. However, its use has the following
is contained in CIRIA Report 97: Trenching practice. advantages:
1.- By pre-driving, the main structural support is in place
before any excavation is started.
2. The interlocking is reasonably watertight, making its use
Designed solutions ideal where waterlogged or very unstable ground is to be
Where designed solutions are needed, it is essential that supported.
adequate soil data is available. This information will be 3. Because of its structural strength, steel sheet piling can be
provided by bore holes or trial pits resulting from a proper used for any of the basic principles of support referred to
site survey. The interpretation of this information and design on p.8B-7. It is the only really satisfactory material where
of support methods appropriate to the situation requires the a cantilever support is used.
services of a specialist. 4. Where impermeable conditions exist below a water-
General guidance as to where specialised design is logged strata, sheet piling can be used to ‘cut-off’ the
necessary is covered in the paragraphs on “Basic principles waterbearing layer from the excavation. Where no cut-
of support”, p.8B-7. off is economically possible and wet, non-cohesive
material is to be supported, the design of the piling must
allow sufficient penetration to avoid the bottom of the
excavation heaving or ‘boiling’ (see p.8B-7).
In all cases where steel sheet piling is the proposed
Systems of support solution, calculations should be made by a competent
Within the basic principles of support, outlined on person.
p.8B-7, a variety of materials and methods may be used: Guidance on piling operations is given under Piling,
p.8F-2/5.

June 2006 8B - 9
Waling and strut arrangements in the support of trenches
(This page is based on the table on page 31 of CIRIA Report 97, Trenching practice, by permission of the Director of CIRIA).

Unsaturated ground (except soft clays)

Maximum Effective Maximum Timber Timber strut section mm*


horizontal trench vertical waling
spacing of depth - m spacing of section - mm Trench Trench Trench
struts - m walings - m width width width
up to 1m 1 to 1.5m 1.5 to 2m

Up to 1.2 One set 225 x 75 150 x 75 150 x 100 150 x 150


150 x 100
3 1.0 225 x 75 150 x 75 150 x 100 150 x 150
1.8 1.2 150 x 100
4.5 1.0 225 x 75 150 x 100 150 x 150 150 x 150
1.2 150 x 100
6 0.9 225 x 75 150 x 150 150 x 150 150 x 150
1.0 150 x 100
1.2 250 x 100

Up to 1.2 One set 225 x 75 150 x 75 150 x 100 150 x 150


150 x 100
3 0.9 200 x 100 150 x 75 150 x100 150 x 150
1.3 Twin 225 x 75 150 x 100 150 x 100 150 x 150
2.5 spiked together
4.5 0.9 Twin 225 x 75 150 x 100 150 x 150 150 x 150
spiked together
1.5 225 x 150 150 x 150 150 x 150 150 x 150
6 1.1 225 x 150 150 x 150 150 x 150 150 x 150
1.5 300 x 150 200 x 150 200 x 150 200 x 150

Up to 1.2 One set 225 x 75 150 x 75 150 x 100 150 x 150


3 0.9 Twin 225 x 75 150 x 75 150 x 100 150 x 150
spiked together
3.0 1.5 225 x 150 150 x 150 150 x 150 150 x 150
4.5 1.0 225 x 150 150 x 150 150 x 150 150 x 150
1.3 300 x 150 150 x 150 150 x 150 150 x 150
6 0.8 225 x 150 150 x 150 150 x 150 150 x 150
1.0 300 x 150 150 x 150 150 x 150 150 x 150
1.5 250 x 200 250 x 150 250 x 150 250 x 150

Up to 1.2 One set 200 x 100 150 x 75 150 x 100 150 x 150
3 1.1 225 x 150 150 x 100 150 x 100 150 x 150
3.5 1.5 300 x 150 150 x 150 150 x 150 150 x 150
4.5 1.0 300 x 150 150 x 150 150 x 150 150 x 150
1.5 250 x 200 200 x 150 200 x 150 200 x 150
6 0.8 300 x 150 150 x 150 150 x 150 150 x 150
1.1 250 x 200 200 x 150 200 x 150 200 x 150
1.5 250 x 250 250 x 150 250 x 150 250 x 150

Saturated ground (except soft clays and silts)

1.8 3 1.2 225 x 150 150 x 100 150 x 100 150 x 150
4.5 1.2 250 x 200 150 x 100 150 x 150 200 x 150

* Proprietary steel trench struts, of equivalent strength, may be used instead of timber struts. Steel struts should be to BS4074.

8B - 10 June 2005
H-piling or soldier piling
In this system, steel universal column sections are pre-
driven, at determined centres, prior to any excavation
commencing. If the ground conditions make driving difficult
or, if vibration or noise is to be avoided, the steel sections
can be positioned in pre-drilled holes with the bottom end
held in concrete.
As excavation proceeds, the exposed face is supported
by timbering or trench sheeting set horizontally between the
piles. In effect, the sheeting takes the form of horizontal
poling boards, wedged in position as shown below.

‘H’ Piling can be applied to both double or single sided


methods of support. It is not, however, applicable to
cantilever support, or in ground conditions which are
waterlogged. As an engineered system, it must be designed
by competent persons.

Proprietary systems
The number of proprietary systems is constantly growing.
They are designed primarily to allow the support system to
be installed in a trench without the need for persons to enter.
Some methods, however, merely provide a waling and strut
assembly that can be used to support timber or steel trench
sheeting.
Examples of the use of proprietary systems are given in
the following paragraphs under Trenches.

Trenches

Standard solutions can normally be applied up to depth


of 6m, provided that the excavation is in non-water bearing
ground. In all other situations, designed solution must be
used.

Standard solutions
The use of standard solutions in trench excavation will
mean using either “Traditional” methods, or proprietary
The ‘H’ piling method has a number of very important systems.
advantages when heavy support is needed, e.g:
1. The main structural support is in place before excavation Traditional methods
commences. Traditional methods use timber or steel trench sheeting as
2. The sheeting can be kept tight up with the excavation, the sheeting material, timber walings and either timber or
which need not be left unsupported for any length of adjustable steel struts. With these components, a number of
time. options are possible, to suit varying conditions.
3. Maximum economy in sheeting material is possible; e.g. The use of poling boards is dependant on the material
if the ground appears suitable, as exposed, hit and miss to be excavated standing up to a height equal to the length
sheeting may be adequate in some strata while, in other of poling board used during the boards’ installation. Two
levels, close sheeting may be needed. variations in installation are possible:
4. If insufficient sheeting has been used, i.e. if the ground is The middle board method, shown opposite is
seen to be pushing through gaps in the sheeting, it can installed by excavating to a depth equal to the
be cut away and additional sheeting installed in the length of the poling board being used. Poling
gaps. boards are then set up plumb, at a distance apart equal
5. Where services cross an excavation, the ‘H’ pile method to the length decided upon for the walings,
is particularly adaptable (see illustration in next column). on both sides of the trench. The walings are
The piles can be installed between service locations and placed in position and strutted against the first poling
horizontal sheeting located above and below. If the gap boards. The intermediate boards are next
resulting is excessive, vertical sheeting can be tucked located, removing the minimum of face soil to provide a
behind the horizontal members to fill in the gaps. snug fit behind the waling member. When all

June 2005 8B - 11
boards are in position, the final number of struts Although the diagrams show timber struts, these can, of
required are installed. All poling boards between course, be replaced by metal trench struts.
struts must be checked and, where necessary, wedges The Tucking Frame method shown below, only differs
driven between the poling boards and walings to from the middle board approach in that the walings and
provide tight contact with the excavation. struts are located at the top and bottom of the poling boards,
instead of the middle.

(Illustration by courtesy of the Timber Research and


Development Association.)

Excavation can then proceed downwards, for the next


level of poling boards.

The excavation, prior to the installation of a level of


poling boards, needs to be slightly deeper than the
poling board length. This is to enable the board to be
tucked up and behind the waling.
Runners are used where the ground will not stand long
enough to allow the installation of a poling board system.
Runners are longer sheeting members than poling boards
and can be in timber or steel trench sheeting.
In bad ground, where continuous support is needed, the
runners are pitched and held vertically in a temporary
framework (usually a lightweight version of a sheet piling
frame). They are then driven into the ground as far as they
will reasonably go, without damage. A shallow depth of
excavation is carried out and the first level walings and
struts installed. The runners are wedged tightly to the
excavation, and digging continued until the end of the

8B - 12 June 2005
runner is only just held in the unexcavated material. The
wedge on each runner is loosened separately, the runner
driven down again, and the wedge re-tightened. This
continues until the next waling is inserted.
Two sets of wedges have to be dealt with at each runner
position. In this way, the excavated face can be continuously
supported while excavation to the full depth of the runner is
carried out. Extra depth is possible by inserting a new set of
runners inside the first and continuing downwards.
The main features of the use of runners are shown below.

(Illustration by courtesy of the Timber Research and


Development Association).

Proprietary Systems
Proprietary Systems fall into a number of well defined
groups:
1. Hydraulic struts associated with waling systems (usually
in aluminium to save weight).
2. Shields or boxes which are dragged along the trench as
work proceeds.
3. Box or plate supports
4. Special methods.
As there are many suppliers and varieties, the groups
above are only outlined in this section. For further details,
reference should be made to CIRIA Technical Note 95:
Proprietary trench support systems.
All proprietary methods should be used strictly in
accordance with the manufacturer’s instructions.

Hydraulic struts/walings
A typical hydraulic struts/waling system is shown
below. The objective is to provide a strut/waling
assembly which can be lowered into the trench and
hydraulically stressed against the sheeting without
anyone entering the trench. Such Systems are normally
only suitable for the support of trenches up to 6m deep.

Use of runners.

(Illustration by courtesy of the Timber Research and


Development Association.)

Where ground conditions permit, the procedure can be


simplified. A shallow excavation is first cut and the pitching
frame set up in it (as shown opposite). The runners are
pitched and plumbed and excavation carried out to the
depth that the earth will stand. The runners can then be
allowed to drop into the excavated area, or will require only Waling/strut assembly with steel trench sheeting.
the minimum of driving, until they bed into the unexcavated
material. They are then wedged as before and excavation (Photograph reproduced by courtesy of Mechplant Limited).
continued. The sequence is repeated as required -

June 2005 8B - 13
Shields or drag boxes
As the name suggests, these are designed primarily as
a protection for persons working in an excavation, rather
than an excavation support. The side sheeting and
strutting, which keeps the sheeting apart, provide a rigid
box. As the work proceeds, the box is pulled forward by
the excavating machine to the new working area.

Box support system.

(Photograph reproduced by courtesy of Scaffolding (Great


Britain) Limited, distributors of Krings Linings).

Plate lining methods work on the principle of installing


a vertical member and struts at set intervals, between
which heavy plates slide into position.

Typical drag box.

(Photograph shows a box manufactured by Jayville


Engineering Limited and supplied by GKN Kwikform).

Such boxes are simple to make and, as they are rigid


structures, require little maintenance. Inevitably, though,
they are heavy and the excavator has to be powerful
enough to pull them forward in the trench.

Box or plate lining Systems


Box or plate lining systems are designed for support,
not just protection and should not be confused with
shields or drag boxes.
Box support systems, as shown opposite, have strutted
support walls of a modular nature, which can be Plate lining method.
positioned by machine, and built up vertically and
laterally. They are not designed to be dragged along the (Photograph reproduced by courtesy of Scaffolding (Great
trench. Britain) Limited, distributors of Krings Linings).

8B - 14 June 2005
With either box or plate lining systems, cross services Use of poling boards
present a problem, as the run of the system has to be The commonly used technique is very similar to that used
interrupted. Other methods for support have to be used in in trenching and the same length and section of boards are
such areas. used. The ground is opened up to a depth equal to the length
of the poling boards, when the first setting of boards is
Designed solutions installed and supported by walings and struts. Walings may
Where the depth of trench exceeds 6m, the support be installed at mid point of the poling board (middle board
system should be designed by a competent person. To do so, method), or may be positioned at about the quarter points,
an adequate soil report should be available, giving all as shown below.
necessary data on water levels, the depths at which they
occur, and whether any particular strata is liable to boil if
cut-off is not achieved.

Use of runners
While timber or steel trench sheeting can be used in deep
excavations, by installing one set of runners inside another
setting, the labour intensive nature of the method tends to
limit its use.

Sheet piling
Where water-bearing ground has to be dealt with, sheet
piling is the obvious choice. Its interlocking nature and stiff
section enable pre-driving to the full depth of the excavation
and the creating of a watertight barrier. Where the strata is
suitable, the water-bearing strata can be cut-off from the
excavation by the sheet piles penetrating into a non-pervious
layer below.

H-piling (Soldier piling)


If water is not present in the excavation, the H-piling
method of support is normally used. In association with steel
walings and struts, considerable depths can be supported
(see p.8B-11).

Wide and single-sided excavations


When a trench becomes very wide, problems arise with
the strutting. The struts themselves become long, and
bending due to their own weight has to be taken into
account, as well as the compressive forces induced by the
earth pressure. The effect of bending is to reduce the
compressive forces that can be resisted. In these
circumstances, a proper structural analysis needs to be
made by a competent temporary works designer.
An alternative is to adopt a single-sided support method.
Whichever approach is used, a designed solution is
essential.

Single-sided support
It is desirable that the main structure of the support is in
place before any excavation takes place. For this reason,
steel sheet piling and H-piling are the only satisfactory
methods to use, unless permanent construction is being
specified as the sheeting material. (Diaphragm walling,
contiguous bored piles and secant piling, to which
the contractor has to provide temporary support are
described under Permanent works as temporary support,
p.8B-19).
The principles of single-sided support are given on
p.8B-8.

Shafts
The method of supporting a shaft, as with any
excavation, is likely to be determined by the ground
conditions. In reasonably good ground, which will stand for
one metre or more, support systems based on the poling Method of side supports in shafts.
board can be used. In bad ground, systems based on
runners will be needed, unless sheet piling or soldier piling (Illustration by courtesy of the Timber Research and
are considered necessary. Development Association).

June 2005 8B - 15
As in trenching, the waling frames are supported at the same applies to struts. Even so, proprietary systems are
corners of the shaft by puncheons, which may be termed available and can be used when the dimensions are
angle posts. Where an intermediate strut is used, the appropriate.
supporting puncheon is installed as in trenching practice.
The waling frames are normally installed by positioning Use of runners
two walings which run the whole length on opposing sides Where the ground conditions are less stable, the use of
of the trench. The other walings are cut to length between the runners can ensure virtually continuous support to the shaft
inside faces of the walings already positioned and should as the excavation proceeds.
bear on timber stretchers or cleats spiked to them (see Runners, up to 3m long, are used and are driven to form
illustration below, plan at B-B). The frame is then supported the lower level support in much the same manner as
by puncheons placed at the ends of the longer members. described for trenches. The ground is first excavated to a
When the waling frames are positioned and the poling safe depth for the ground conditions. Vertical corner boards
boards tightened against the excavation by wedges are positioned and the first walings cut and installed
between the walings and poling boards, the next phase of between them. The second walings, at right angles, are then
the excavation can proceed and lower levels of poling cut and positioned. Having restrained them by struts, to
boards installed. produce a rigid box frame, the runners are then introduced
During the excavation of shafts, and at the completion of into the gap between the excavation and the walings and
the installation, waling frames should be secured and driven down as far as the ground conditions will allow. Each
supported by lacings, ground props and foot blocks as runner is then forced against the excavation by wedges
appropriate. inserted between the waling and the runner. Wedges are
Both timber and trench sheeting may be used for the progressively eased and retightened as the excavation
poling boards. Timber is well suited for walings as progresses downwards, at the same time as the runners are
dimensional problems can readily be overcome, while the driven down to cover the excavated face.

Notes
1 Method shown is suitable for depths down to 6m.
2 Timber to be strength class SC4.
3 No hydrostatic head.
4 Where the shaft is to be dug in cohesive ground it should
be soft or better and should have a minimum C value of
30 N/mm2,
Shafts with maximum dimension up to 2. 75m showing 5 A uniformly distributed ground load of 10 kN/m2 has
alternative arrangement for poling boards. been allowed.
6 Where higher loads, or point or line loads are expected.
(Illustration by courtesy of the Timber Research and then the shaft should be designed by an experienced
Development Association). person.

8B - 16 June 2005
in excess of these dimensions must be designed by a
competent engineer, as should any heading in rock,
irrespective of its dimensions.

Materials
Timber is the most suitable material, as a great deal of
cutting will be necessary. Wherever the timbering is to be left
in place, new material should be used and treated by
pressure impregnation to protect against decay, using
copper/chrome/arsenic salts in accordance with BS 5589.

Dimensions
Height should not be less than 1.2m measured from the top
of the sills to the underside of the head tree. The width should
not be less than 700mm measured between the inside faces
of the side trees.

Excavation and support


As the greatest reliance is placed on the experience and
expertise of the operatives engaged in the driving of a
heading, no specific sequence of operations is recom-
mended. Three basic support methods are used:

Box setting
This method is only suitable for small headings in firm
ground.

Notes
1 Method shown is suitable for depths down to 4.5m.
2 Timber to be strength class SC4.
3 No hydrostatic head.
4 Where the shaft is to be dug in cohesive ground it should
be medium soft or better and should have a minimum C
value of 30 N/mm2.
5 A uniformly distributed ground load of 10 kN/m2 has
been allowed.
6 Where higher loads, or point or line loads are expected,
then the shaft should be designed by an experienced
person.

Use of runners in shafts up to 1.8m square.

(Illustration by courtesy of the Timber Research and


Development Association).

Steel or timber runners are equally suitable for this


method and steel sheet piling may also be used where wet
ground conditions exist. The waling frames are usually
timber, but proprietary systems or steel sections may also be
used.

Headings
Headings are small tunnels cut into the sides of trenches
or shafts. They constitute the most hazardous sector of
excavation as, in addition to the dangers associated with
trenches and shafts, they introduce the risk of trapping
persons with no alternative escape route. In such cases,
rescue is difficult and dangerous.
The cutting of a heading requires a very high degree of
careful investigation and consideration. This applies to the
design, quality of materials, excavation techniques and
workmanship, as well as to safety and supervision.
The following recommendations apply only to headings
not exceeding 2m either in height or width. Any headings

June 2005 8B - 17
Normally, roof and side boards are not required but, in A poling setting is an extension of the box setting, with
localised areas, they can be inserted by ‘tucking’ between roof and side boards ‘tucked’ between the head and side
adjacent head or side trees and the excavated face. trees so that both ends are supported. The boards should be
in close contact with the top and sides of the heading. They
Poling setting may be spaced apart, or be in edge to edge contact,
This method should be used in ground conditions where depending on the nature of the ground.
pieces start to fall in almost immediately after excavation has In ground where the floor of the heading may boil or
taken place. Examples are: damp or cohesive sandy heave, then floor poling boards should also be introduced
gravelly material, or clays which contain fissures and crack between sills.
into small pieces when drying out takes place.
Piling setting
In poor ground, of the running or flowing category,
continuous support at all stages of the excavation must be
maintained and the piling setting method used.

The method becomes more complicated when the


advancing face of the heading also needs support. Further
details are given in the TRADA publication Timber in
Excavations.

8B - 18 June 2005
Securing the heading efficiently than if the support had to be by raking shores
Regardless of the method used, the excavation of a or long struts right across the width of the excavation.
heading should not cease until a setting under construction is 6. In water-bearing ground, diaphragm walls are
completed, with head and side trees in position. The face of substantially watertight.
the heading should be boarded if the excavation stops for
more than two hours.

Supervision
The supervision of and routine checks on temporary
works in a heading are different from those employed in
open excavations. Routine inspection must be carried out at
the point of maximum risk, i.e. the advancing face of the
excavation.
Another important factor is that speed of the excavation
has a bearing on safety, as the rapid installation of a support
structure is critical to the integrity of the cut face.
Inspection and supervision must therefore be carried
out by experienced persons, who should be able to
inspect, approve and authorise continuation, without
impairing the speed of advance on which the safety of the
work may depend. This means that constant supervision is
necessary.

Permanent works as temporary support


There is frequently the need temporarily to support
systems of retaining wall construction, until the permanent
structure has been sufficiently advanced to provide the
permanent support. What must be appreciated is that, whilst
temporary support is being provided, the walling system is
acting as temporary works. Where there is this division of
responsibility for temporary works, it is essential that the
design of the supporting members is carried out by a
competent person.
The techniques are:-
Diaphragm walls
Contiguous bored piles
Secant pile walls

Diaphragm walls Contiguous bored piles


These are commonly used in clay and sand/gravel Bored piles can also be used to support excavations,
areas, to achieve the perimeter support to basements. Their while providing the main element of permanent support. In
advantage lies in the ability to install the wall before any this role, they are installed as a continuous curtain where the
excavation takes place. A narrow trench, of the required support is needed. Installation is normally carried out by
width of finished retaining wall, is excavated by means of boring alternate piles first and later inserting further piles in
special grabs. As the excavation proceeds, the trench is kept the gaps. The method is normally used in conjunction with
filled with a suspension of bentonite in water. In this way, ground anchors as the temporary support or, if practicable,
trenches can be excavated to considerable depths without with horizontal shores.
further support. When the required depth is reached,
reinforcement is lowered into the liquid, and concrete placed
by tremie. As this is done, the bentonite solution is forced out
of the trench, collected and re-used later.
Diaphragm wall construction is carried out by specialist
sub-contractors. The main contractor, however, is required to
construct the ‘guide’ wall. It should also be noted that the
inside guide wall has to be removed, again by the main
contractor, as the excavation progresses downward. Its
advantages are:
1. Installation free from vibration and excessive noise.
2. No support of the earth face is needed.
3. Walls can be constructed with minimum disruption to
adjacent areas.
4. Such walls serve a dual purpose - they avoid the need for
temporary sheeting to the excavation and become the
final retaining wall, usually with some form of facing for
cosmetic reasons. As a result, the cost of temporary
works is reduced.
5. Where ground anchors can be used as the temporary
support, the whole construction area within the
diaphragm wall is unencumbered with supports and the
permanent construction can proceed much more

June 2005 8B - 19
The unevenness of the pile means that adjacent piles are Ladders must be of sound construction, of adequate
not in complete contact. The method is not, therefore, length and strength, of the correct type and be placed in the
suitable in wet conditions without special and expensive supported part of the trench. They must be effectively
precautions. secured, near the top, to prevent slipping sideways, by
Bored piles are similar in cost to diaphragm walls, and lashing, either to adjacent support material or to stakes
have very similar advantages, except their inability to retain driven firmly into the ground. They must project sufficiently
water. above the excavation to provide a safe handhold (a distance
of 1.05m is recommended).
Secant bored pile walls Gangways are often needed for access purposes across
In secant piling, the bored pile system has been excavations. Where persons might fall and be injured, such
developed further to provide a watertight wall. gangways must be fitted with toeboards, at least 150mm
The wall is formed by a series of individually formed piles high, and main guardrails, at least 910mm high. An
which interlock. The first stage is to construct piles at centres intermediate guardrail, or other rigid barrier, must also be
less than two pile diameters (female piles). Intermediate piles fitted so that there is not an unprotected gap exceeding
(male piles) are then made which, in the boring and 470mm in height. Gangways should be at least 430mm
concreting process, cut secants out of the adjoining female wide for personnel access, or 600mm for persons and
piles. materials.
On large sites, there may be occasions when bridging
units are necessary to allow plant and vehicle movement
across an excavation. In such cases, proper design by
competent persons is essential, both for the safety of the
loads to be carried and to avoid excessive loads on the
edge of the excavation.

Barriers
The edges of all excavations, where anyone might fall
and be injured, must be protected by rigid barriers or,
alternatively, excavations must be securely covered. It is a
wise precaution to protect even shallow excavations.
Non-rigid barriers, which may be used in areas where
access for persons and transport is not required, should give
an obvious warning by being immediately apparent and
brightly coloured.
Spoil heaps can constitute effective barriers, provided
that they are set back a safe distance from the edge. Rope
barriers can also be effective, again provided they are set
back far enough.
Barriers may be omitted to allow access of persons, or for
the movement of plant, equipment or materials, or where it
has not yet been practicable to erect such a barrier since the
formation of that part of the excavation.
Wherever barriers are set back, all access to the
excavation should be confined to the proper paths and no
material should be stacked in the space between barriers
and the edge.
Barriers, or stop blocks, are also necessary to stop
cranes, dumpers, lorries, tipping vehicles, etc. from
manoeuvering too close to the edge of an excavation and
endangering its stability. Timber baulks are effective against
A heavy rig hydraulically forces a tubular casing into the small wheeled machines, but taller barriers are needed for
ground by rotary oscillation, combined with vertical loading. larger wheeled equipment and tracked machines (also see
The soil within the casing is next excavated by a hammer Section 19 - Site Transport).
grab. In this way the soil is supported at all times. As
concrete is placed, the casing is withdrawn. With the piles of
fixed dimensions, due to the formation within the casing,
close contact is certain and a watertight junction achieved.
The system is ideal in water bearing ground to provide a
watertight perimeter, either on a permanent or temporary
basis.
Temporary support must be provided, as for diaphragm
walls and contiguous bored piles. Such support must always
be designed by competent persons. Installation will always
be by specialised firms having the necessary equipment.

Related safety aspects


Apart from safety requirements directly associated with
the support of excavations, the following matters must also
be considered:

Means of access
Safe means of access to and from excavations must be
provided, as must easy means of escape in an emergency.

8B - 20 June 2005
Lighting Means of escape
During darkness, edges of excavation should be All persons working in an excavation should be instructed
illuminated, especially where they are adjacent to public in escape and rescue procedures should an emergency
thoroughfares. arise. This is particularly important where unhealthy
During the winter, or in deep excavations, shafts and atmospheres might arise. Instruction should be given on the
tunnels, lighting will be necessary to enable operations to use of rescue equipment (see Section 23 - Confined Spaces).
proceed safely. Such lighting must be installed with
equipment suitable for use in the excavation.
Damage to underground services
It is essential, at the planning stage, to ensure that proper
Ventilation precautions are taken to avoid damage to underground
Excavations must be kept free from toxic or explosive services. Detailed guidance is given in Section 20 -
gases and it must be remembered that any gases which are Overhead and Underground Services and in HSE Guidance
heavier than air will tend to settle in excavations. The gases Booklet
involved may be natural, like methane and sulphur dioxide, HS(G)47.
or they may arise from nearby internal combustion engines
(carbon monoxide), leakage from liquefied petroleum gas
equipment, or underground storage, or from sewers. Noise
One of the most effective methods of keeping the Occupational and environmental noise is a hazard in
atmosphere healthy, is to use ventilating equipment to blow excavation, particularly in the case of pile driving. Steps
clean air into the excavation, shaft or tunnel, in sufficient should be taken to ensure that noise from plant is reduced at
quantities to dissipate the foul atmosphere. source as far as possible, that noise levels are assessed and
Tests must always be carried out in advance of work ear protection worn where necessary. Further information
starting, and throughout the period of the work. For further and guidance on compliance with the Noise at Work
information, see Section 23 Confined Spaces. Regulations 1989 is given in Section 32 - Noise.

June 2005 8B - 21
Check List No.1 - Site conditions and method with standard solutions, or whether the support will need to
constraints. (Design stage) be designed.

Knowledge of the ground and local constraints (adjacent Check List No.2- Before work starts
buildings etc.) must be available in order to determine the 1. Is the person directly supervising the work fully
method of excavation and the need for support. In addition, experienced and competent in the support of
in the case of trench work in particular, what has to go into excavations?
the trench or excavation will be important. The handling of 2. Have all services been located and proved as to
such items may well affect the form of support that can be position? (see Section 20 - Overhead and Underground
used. The following questions need to be answered before Services).
any decisions are taken: 3. Are the necessary drawings or sketches (where
1. What are the soil types and groundwater conditions? standard solutions are to be used) available? Have the
2. Is there any knowledge of work carried out previously operatives been properly briefed and instructed as to
in the area? what is required of them?
3. Is the excavation adjacent to existing structures or 4. Are all materials necessary available on site and in
roads? accordance with the drawings/sketches?
4. Are there any obstructions to the line of the excavation? 5. Has the excavator to be used a certificate of exemption
e.g. public utility mains or cables, sewers, industrial for lifting material in connection with the excavation
mains, overhead cables, or limited clearance on the and is a copy available on site? (see p. 9-33)
line of the excavation which may restrict choice of 6. What arrangements need to be made in relation to site
excavating equipment? security, particularly in relation to stopping children
5. Has the condition of the adjacent buildings, roads etc. getting on to the site?
been recorded by the client or his representative? (e.g. 7. Is there adequate working space for plant to be used, in
cracks etc.) addition to the requirements for spoil heaps? (Spoil
6. Is there any risk of surface flooding while the work heaps should not be less than 1m from the edge of the
is being carried out? Is flooding from services excavation).
possible? 8. Is material for barriers available and, where working
7. Is the excavation within the site boundary (inside the on the highway, approved traffic signs? (see Section 26
hoarding area), or are special precautions necessary to Roadworks).
protect the public? 9. Will bridges or gangways be needed? If so, is the
8. If the excavation is a trench, what are the maximum equipment available?
depths to be supported and what size and length of 10. Are sufficient ladders on hand for access to and from
pipes have to be handled? Can pipes be tested in short the excavation?
lengths or does the specification require testing 11. Will lighting be required?
manhole to manhole? 12. Is appropriate protective clothing and equipment
9. In the case of wide excavations, what will be the available?
implication of the support system to the permanent work 13. Are operatives experienced in the type of excavation,
- and vice versa? or will extra supervision be needed?
10. What surcharge loads are likely to arise? 14. Are water pollution prevention measures in place?
11. Will the method involve vibration? Will it affect 15. Is the site in a high risk area for unexploded ordnance?
the stability of the excavation and/or adjacent 16. Are emergency procedure plans in place for use in the
buildings? event of the discovery of unexploded ordnance?

When answers to the above questions have been Check List No.3- Whilst work is in progress
obtained, the following need to be asked: The following list covers the main items which need to be
checked in carrying out the inspections required by
(a) If the ground is saturated, are the conditions suitable Schedule 3 of the Construction (Design and Management)
for a dewatering system to be used? If so, can Regulations 2007:
battering be adopted without endangering adjoining 1. Is access to and from the workface sufficient and
property? secure?
(b) Is the ground of the type that may ‘boil’ when 2. Are all working faces secure, wedges tight and support
excavation is commenced? material free from damage?
(c) How long will the excavation be open? (If capable of 3. Is there any sign of movement or deflection in the
battering this will be the economical solution, especially support system?
where the excavation has to be open for a long period 4. Is the soil condition as predicted? If not, what action
of time). should be taken?
(d) Where surface water may be a problem, can an 5. Are spoil heaps the correct distance back from the
adequate run-off system be achieved from any cut-off trench edge?
drains or ditches that may be needed? 6. Are pipes, bricks and other materials, plant etc., well
(e) What action is needed to support and safeguard clear of the edge so that there is no risk of falling into
services etc. which cross or are adjacent to the the trench or of vibration causing damage to the
excavation? How will this relate to the support system support?
envisaged? 7. Are the drawings/sketches being properly followed in
(f) Is the position of the works likely to lead to surface installing the support? (This is particularly important in
water pollution? relation to the spacing of walings and struts).
(g) Is the dewatering method likely to lead to a possible 8. Are walings and struts, or proprietary equipment,
pollution threat to ground water or an aquifier? If so supported against falling downward - by hangers,
advice must be sought from an environmental puncheons, lip blocks, etc?
consultant or the Environment Agency 9. Is there any risk of gases, or noxious fumes, getting into
the workings?
When all these questions have been answered, a
decision can be made as to the use of battering, proceeding

8B - 22 June 2007
10. Are regular tests for gases or fumes being carried out? 18. Do gangways or bridges comply with the requirements
(This is particularly important in shafts and tunnels). Is of the CDM - Part 4 and the Work at Height Regulations
ventilation required? 2005 in relation to the provision of safe movement for
11. Has any risk of flooding been properly assessed? pedestrians and vehicles and the prevention of falls.
12. Is resuscitation equipment available and a nominated Have access bridges for plant and vehicles crossing the
person trained to use it? excavation been designed by competent persons?
13. Have all persons been instructed in evacuation 19. Where backfilling is required, are stop blocks in
procedure and the correct rescue procedure to follow if position?
someone is overcome by gases or fumes in the trench? 20. Is there an agreed system of support withdrawal and
14. Have all support materials been checked before have those carrying it out been properly instructed?
installation in the excavation? In particular, are the 21. Where pumping is necessary, is a proper watch being
correct pins provided in the trench struts? kept to make sure that fine material is not being drawn
15. Is the work adequately protected and marked during out from behind the support system?
the day? Is it fenced, or covered, and lit at night? Are 22. Is the water from a pumping process being dumped out
watchmen needed? onto grassland or, if it is being pumped into a water
16. Are operatives wearing safety helmets? Is any other course, aquifier or drain, is there an Environment
protective equipment needed? Agency consent in place and are the conditions being
17. In shafts and tunnels, in particular, is adequate complied with?
lighting provided? Is the temporary lighting system
safe?

Glossary of terms
Batter (or rake) An artificial, uniform steep slope. In Puncheons Vertical props used to support higher
trenching, the angle of batter must be (or props) walings or struts from the ones
less than the angle of repose of the soil. below.
Bitch A fastening of iron or steel used for Runners Vertical timbering, usually approximately
securing heavy timbers which cross each 2.5m to 3m long, 50mm thick and
other. Similar to a dog but with one of its 225mm wide, with the lower ends chisel-
ends at right angles to the other. shaped. Used in unstable ground instead
Chogs (or chocks, Timber blocks used as distance pieces of poling boards and driven in advance
or blocking) or packing, e.g. between a waling and of digging.
the temporary or permanent lining of Side boards Boards, at least 150mm x 38mm,
an excavation. forming the sides of a heading.
Cleat A block of timber fixed to a member to Side trees Timbers, at least 225mm x 75mm, which
prevent the movement of other abutting support the head trees and side boards
timbers. in a heading.
Dog A fastening of iron used for spiking large Sills Timber, at least 225mm x 75mm, laid
timbers together and having both ends across the bottom of a heading or trench
bent down and pointed. and carrying at its ends the feet of the
Folding wedges Wedges used in pairs, overlapping each side trees.
other and driven in opposite directions in Soldier piles Vertical supports holding horizontal
order to hold or force apart two parallel (or H piles) sheeting or walings in place. They are
surfaces. secured by struts across the excavation
Foot block A timber pad used to spread a load from or by ground anchor tie backs.
a ground prop or side tree. Steel sheet piling Steel sheets, capable of being inter-
Hanger A steel rod or bolt sometimes used locked, driven to the full required depth
(or tie rod) instead of lacings between successive before digging begins. Normally used
frames to take their weight and prevent in loose, soft or waterlogged soil.
movement of the timber. Sheeting is either tied back, strutted
Head trees Horizontal timbers, at least 225m x across the width of the excavation, or
75mm, in the roof of a heading, which used with raking shores or in cantilever.
rest on the side trees and support the This type of sheeting can be re-used
head boards. many times.
Lacings Vertical timbers spiked to the sides of Steel trench sheets A lightweight form of steel sheet pile (see
struts and walings, tying them together to above), which has largely replaced
carry the weight of the lower frames as timber poling boards and runners in
excavation proceeds. support work.
Lip (lipping block, A short length of timber fixed and spiked Stretchers (or liners) Timbers, at least 150mm x 38mm, driven
or lipping piece) to the top of a strut, and projecting between the ends of opposing members
sufficiently beyond its end so as to rest on of a frame to lock them in position and
a waling. It supports the weight of the strut spiked to members against which they
while wedges are being driven. rest.
Pinchers Pair of poling boards, strutted apart Struts Horizontal members in compression
across a trench, to support the excavated which resist the thrust from the sides of an
faces where the ground is good. excavation.
Poling boards Timbers, 1m to l.5m long, 32mm to 50mm Walings Horizontal members supporting poling
thick and usually 225mm wide, or boards, runners, vertical sheeting or
equivalent steel sheeting, placed vertically soldiers.
in an excavation to support the sides.

June 2007 8B - 23
CHECKLIST FOR GROUNDWORKS METHOD STATEMENTS
Groundworks method statements should – Duration of work.
normally include the following so far as is – Details of the precautions to be taken to prevent collapse
relevant in the circumstances :- of the sides of the excavation e.g. battering or support. If
– Name and address of the groundworks contractor. support is proposed this should include details of the
– Name and address of the site to which the method system to be used.
statement relates. – Details of access/egress to and from the bottom of the
– Names of the supervisor/foreman and appointed safety excavation plus any crossings over the excavation.
adviser and arrangements for monitoring the work. – Details of any fencing around the open excavation.
– Description of the works to be carried out including – Details of plant and equipment to be used together with
confirmation that the site has been visited and due confirmation that all necessary records will be provided
account taken of surrounding conditions, access, etc. on site.
– Details of the personnel to be used and their training/ – Method of storing and dispensing fuel oil including
experience. precautions to prevent pollution of groundwater.
– Details of PPE to be provided to personnel. – Quantity of petrol to be stored on site and method of
– Sequence of operations detailing method of dealing with storage.
specific hazards. – If any roadworks are involved, the name of the supervisor
– Details of methods of locating and avoiding any existing trained in accordance with the New Roads and Street
underground services, whether or not their presence is Works Act 1991.
known.
– Details of Environment Agency consent conditions in
relation to any likely impact of the works on surface Note :-
water, ground water or an underlying aquifier. An additional method statement will be required for any
work involving entry into confined spaces e.g. sewer
For all excavation works :- connections.
– Nature of the soil and moisture conditions. This checklist is intended to aid the production and
– Measures taken to check for toxic contaminants in the approval of method statements. It is not an exhaustive list of
ground. every possible issue that may need to be addressed for any
– Dimensions of the excavation. given task.
– Method of excavation. Refer to Section 1 for general information on method
– Proximity of services or structures. statements.

8B - 24 June 2005
REFERENCE SOURCES
Legislation National Joint Council for the Building Industry:
The Water Resources Act 1991 “Site Safe and You”: A pocket booklet on all aspects of
Management of Health and Safety at Work Regulations 1992 site safety, which includes a checklist for work in
Construction (Design and Management) Regulations 2007 excavations and with excavation plant.
Work at Height Regulations 2005
Lifting Operations and Lifting Equipment Regulations 1998
Provision and Use of Work Equipment Regulations 1998 Training Courses
The Groundwater Regulations 1998 Construction Industry Training Centre
Bircham Newton
Nr. Kings Lynn
British Standards Norfolk
CP 2004 Foundations
BS 4074 Specification for metal props and struts
Construction Health & Safety Group
BS 5268 Code of Practice for the structural use of timber
John Ryder Training Centre
BS 5930 Code of Practice for site investigations
St. Anne’s Road
BS 6031 Code of Practice for earthworks
Chertsey
Surrey
Guidance
Construction Industry Research and Information
Association:
Training aids
Construction Health and Safety Group slide/tape
Technical Note 95: “Proprietary trench support systems”
programmes
(2nd Edition 1982). An illustrated summary which includes
tabulations of each system’s characteristics and
capabilities. CIRIA
Report 97: “Trenching practice” (1983). A guide to safe video:
practice in the design and use of temporary support for Trenching - Good Practice
trenches not deeper than 6m.
Timber Research and Development Association:
Environment Agency
“Timber in excavations” (1981). A guide to assist site
Building a cleaner future
staff and planners to assess site conditions and to choose
appropriate support for trenches, shafts and headings.
“Simplified rules for the inspection of second-hand timber All of the above reference material is available from:
for load bearing use” (1981). A valuable pocket guide Construction Industry Publications Ltd.,
showing how to assess the value of second-hand timber. 17 Gatelodge Close, Round Spinney,
Health and Safety Executive: Northampton NN3 8RJ.
HSE Leaflet CIS 8 Safety in excavations Tel: 0870 078 4400
Guidance Booklet HS(G)47: Avoiding danger from Fax: 0870 078 4401
underground services e-mail sales@cip-books.com

June 2007 8B - 25
This page is intentionally blank

8B - 26 June 2005

You might also like