2013-14 Q.NO.-3(b') for this prb.

]
012-13-->Q.NO.-2(b)[Sir you can refer
2013-14--> Q.NO.-3(b) & Q.NO.-3(b')
2014-15--> Q.NO.-4a(ii)
2014-15 ---> Q.NO.-2(a) [i have solved this problem and sent the solution to your
whatsapp no. please just check the correctnesss of this solution]

A sewage treatment plant of capacity 12500 m3/day is to be designed to treat incoming BOD of
210 mg/l and TSS concentration of 400 mg/l to the level of outlet BOD as 30 mg/l and TSS 50
mg/l respectively. Design the following units while ensuring to meet the above effluent quality.
i) Primary sedimentation tank, ii) Aeration tank and iii) Secondary clarifier.

A UASB sewage treatment plant is to be set up to treat 10 MLD flow. The incoming BOD is 250
mg/l. By assuming suitable upflow velocity and other design conditions, calculate the number of
UASB reactors required, volume and HRT of each reactor.