Professional Documents
Culture Documents
ML 2014 (23) Management was not able to Create a committee consisting of Comply with the audit recommendations Management January onwards Partially No Inventory Committee Management has ordered the
conduct its annual physical two or more employees designated Property Officer 2015 Implemented was created Property Officer to prepare the
count of PPE; accordingly, by the agency head, to take charge Inventory Plan.
the preparation and of the inventory taking which shall
submission of the include the property officer or RPCPPE for 2014 has been
corresponding RPCPPE custodian to be witnessed by the submitted
were not undertaken, Agency Auditor.
causing difficulty in
determining whether all
properties recorded in the
book exists and whether all
properties physically existing
Require the concerned Property and
are duly recorded in the
Supply Officers to prepare detailed
books, thus completeness,
inventory action plan that is
accuracy and existence of
understood and accepted by all the
the PPE account balance of
members of the Inventory
P25,749,782.20 could not be
Committee and take into
ascertained
consideration the timing of the
counting to enable the Inventory
Committee to complete the activity
within the scheduled date and
submit the RPCPPE on or before Page 1 of 45
January 31 of the ensuing year
corresponding RPCPPE
were not undertaken,
causing difficulty in
determining whether all
properties recorded in the
book exists and whether all
properties physically existing
Require the concerned Property and Agency Action Plan
are duly recorded in the
Supply Officers to prepare detailed Reason for
books, thus completeness,
inventory action plan that is Status of Partial/Delay/Non
Ref. accuracy
Auditand existence of
Observation Audit Recommendations Target Implementation Action taken/Action to be taken
understood and accepted by all the Person/Dept. Implementation implementation, if
the PPE account balance of Action Plan
members of the Inventory Reponsible applicable
P25,749,782.20 could not be
Committee and take into From To
ascertained
consideration the timing of the
counting to enable the Inventory
Committee to complete the activity
within the scheduled date and
submit the RPCPPE on or before
January 31 of the ensuing year
Page 2 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
Impose a deadline for the
submission of the RPCPPE so that
reconciliation of the physically
inventoried properties with the
accounting records can be done and
that discrepancies noted, if any, can
be immediately corrected
ML 2014 (34) The balances of Office Instruct the Accountant and the Comply with the audit recommendations Accountant January onwards Ongoing The Supply Officer is still in the
Supplies Inventory per books Supply Officer to reconcile the Supply Officer 2015 process of obtaining RIS' and
of the Accounting Unit and difference of P349,735.75 in the preparing Inventory reports for the
per records of the Supply Office Supplies Inventory years without reports
Unit has a discrepancy of
P349,735.75; likewise, a
monthly report prepared by Create an Inventory Committee to Reconciliation on-going
the Supply Unit on the conduct the physical count of the
Inventory of Supplies and inventories every six months and
Materials was not in submit the RPCI to the Office of the
accordance with the Auditor on or before July 31 and
Instructions C and D on page January 31 of each year
138, MNGAS, Volume II,
thus, the accuracy and
validity of the book balance
of P455,810.72 of the Office
Supplies Inventory is
doubtful
ML 2014 (42) Reimbursements of Instruct the personnel processing Comply with the audit recommendations Bookkeeper January onwards Fully Implemented The Accounting unit has submitted
travelling expenses of some the claims to oblige all claimants to Accountant 2015 the required documentary
officers and employees comply with the documentary requirements on April 28, 2015
totaling P251,342.82 were requirements pursuant to COA
not duly supported with basic Circular 2012-001 dated June 14,
documents contrary to 2012
Section 28, MNGAS, Volume
I and COA Circular No.
2012-001 dated June 14,
2012, thus lack of proper
evidence to validate and
establish regularity of the
claim
Page 3 of 45
Reimbursements of
travelling expenses of some
officers and employees
totaling P251,342.82 were
not duly supported with basic
documents contrary to Agency Action Plan
Section 28, MNGAS, Volume Reason for
I and COA Circular No. Status of Partial/Delay/Non
Ref. Auditdated
2012-001 Observation
June 14, Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
2012, thus lack of proper Reponsible applicable
evidence to validate and From To
establish regularity of the
claim
Page 4 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (50) Appropriate accounts Chief, Financial and Management Comply with the audit recommendations Bookkeeper January onwards Fully Implemented The Bookkeeper has adjusted and
prescribed under the revised Division should adjust and reclassify Accountant 2015 reclassified the said accounts to
government chart of these accounts to their proper their proper accounts
accounts were not used in accounts
recording various
transactions totaling
P37,000.91 contrary to
Section 112 of PD 1445,
resulting to misstatements of
the affected accounts
ML 2014 (57) The correctness and Instruct the Accountant to exert best Comply with the audit recommendations Accountant January onwards Ongoing The Accountant has acquired a
reliability of the financial effort to analyze/review and account 2015 copy of the Financial Statements
statements (FS) of the BLGF for the significant balances of of LOGOFIND from the project
as of December 31, 2014 is P8,965,240.88 in the LOGOFIND accountant
uncertain due to the doubtful project; and
existence of inventories and To coordinate with the former
depreciated property, plant project accountant while effecting
Effect any adjustment, if any, and
and equipment appearing in the transferring and closing of
close the balances by transferring it
the FS of the Local balances
to the General Fund of the BLGF
Government Finance
books of accounts for fair
Development (LOGOFIND)
presentation in the FS as prescribed
Project with total debit and
under Paragraph 27, PPSAS,
credit amount of
Volume I and Section 73.a of the
P8,965,240.88, in violation
MNGAS, Volume I
with Paragraph 27, PPSAS,
Volume I, and Section 73.a
of the MNGAS, Volume I
ML 2014 (64) The BLGF outstanding Instruct the Accountant and the Accountant January onwards Ongoing The Supply Offcer in coordination
balance of the Due from Supply Officer to regularly Supply Officer 2015 with the Accountant is in the
NGAs - Procurement coordinate with the PS for the process of obtaining records to
Service (PS) amounting to periodic reconciliation of their help with the reconciliation of
P219,536.04 as of records and to adjust any accounts with DBM-PS
December 31, 2014 differed discrepancy that may be uncovered
from the records of the PS of
P246,608.45 by P27,072.41
due to non-reconciliation of
both agencies’ records
Page 5 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (72) Management failed to take Review cash management program Exert all efforts to maximize budget utilization Management January onwards Not Implemented Management commented that they
full advantage of the funds and adhere strictly to the provision Accountant 2015 have been diligently and efficiently
received during the year, of Paragraph No. 2 of DBM Circular managing its cash program in
contrary to DBM Circular Letter No. 2011-15 dated December Budget Officer accordance with the rules and
Letter No. 2011-15, thus, the 26, 2011 on the optimum utilization regulations. The issuance of the
unused Notice of Cash of available NCA and require the National Budget Circular No. 551
Allocation (NCA) totaling concerned officials/personnel to dated January 2, 2014, amends the
P13,006,244.30 or 15.20 per submit promptly all claims for DBM Circular Letter 2011-15 which
cent of the total NCAs payment with complete provides that “NCAs to cover the
received for CY 2014 documentation 2nd semester requirements for
operations was reverted regular budget shall be subject to
the submission of FARs/Budget
Accountability Reports (BARS) as
Auditor’s Rejoinder: The of end of June 30 and consistent
funds on hand could have with the DBCC-approved MDP.
been used to pay existing
obligations since BLGF
financial position as at year- On the reverted amount of
end showed existing P13,006,244.30, this comprises
obligations of P3,248,452.12. Personnel Services for funded
Management must have positions of employees who availed
been confused with the use of the retirement option under the
of the NCA and allotment Rationalization Plan of the BLGF.
Thus, resulting to an unused cash
for Personnel Services.
Page 6 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
The amount reverted cannot be
used for the payment of unpaid
obligations since said obligations or
services were not yet delivered nor
rendered
ML 2014 (83) The practice of recording Stop the practice of charging directly Exert all efforts to comply with the audit Bookkeeper January onwards Not Implemented Management
purchases of supplies and to Other Supplies and Materials recommendations Accountant 2015 commented that
materials as outright Expense all purchases of supplies supplies purchased
expense resulted in the and materials not paid out of the from outside suppliers
understatement of Other PCF for fair presentation of the were recognized
Supplies and Materials Supplies and Materials Inventory immediately as expense
Inventory; and account in the Statement of to simplify journal
overstatement of Other Financial Position. entries because these
Supplies and Materials items were immediately
Expense issued to end-users
upon delivery and
supported with
corresponding RSMI
ML 2014 (90) The Accounting Unit and the Accountant and the Supply Officer to Exert all efforts to comply with the audit Accountant January onwards Partially Impracticability of Stock Cards are now being
Supply Unit do not maintain maintain properly the SLC and the recommendations Supply Officer 2015 Implemented maintaining two similar maintained by the Supply Officer
the Supplies Ledger Card SC for each item of the supplies ledger cards
(SLC) and Stock Card (SC), inventories
respectively, for each item of
Office Supplies
received/issued resulting to
difficulty of reconciling the
balances recorded in the
Accounting Unit and the
Supply Unit
Page 7 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (96) Submission of reports such The Accountant should submit the The Management through the Administrative Accountant January onwards Fully Implemented The Cash and Accounting Unit has
as (a) Disbursement Report of Disbursements and Division (Admin) and Financial and Management Cashier 2015 already registered to the weAccess
Records with all paid Report of Collections together with Division (FMD), shall register to the we Access facility of the Landbank of the
vouchers and supporting all the paid vouchers and supporting facility of the Land Bank of the Philippines to be Philippines
documents and Liquidation documents evidencing the able to immediately print the Bank Statements
Reports; (b) Report of transactions regularly to the Audit and enable them to prepare and submit the
Collections with Team within ten (10) days from date Bank Reconciliation Statements on time
corresponding issued Official of receipt of said documents
Receipts; (c) Trial
Balances/Financial Submit Financial Reports regularly
Statements; and (d) Bank in compliance with Section 71 of the
Reconciliation Statements, Manual on NGAS
were delayed, thus, deter us
to a timely examination and Submit Bank Reconciliation
audit of the transactions and Statement regularly in compliance
communication of the results with Section of COA Circular No. 96-
thereof 011 dated October 2, 1996
ML 2014 (104) The purposes and Oblige the Inventory Committee to Exert all efforts to comply with the audit Supply Officer January onwards Fully Implemented Supply Officer has submitted RPCI
usefulness of the Report on prepare and finalize immediately the recommendations 2015 for July 31 and January 31 of 2015
the Physical Count of RPCI for submission to the Auditor to the Auditor
Inventories (RPCI) are not on or before July 31 and January 31
attained due to non- of each year as prescribed under
submission of the said report Section 65 of the MNGAS, Volume
within the required period in II; and
violation of Section 65 of the
Manual on the NGAS, Impose a deadline to all concerned
Volume II on the submission of the RPCI so
that reconciliation of the physical
inventories with the accounting
records can be done and that
discrepancies noted, if any, can be
corrected promptly
Page 8 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (109) The Collecting Officer does Instruct the Collecting Officer to Comply with the audit recommendations Cashier January onwards Fully Implemented Management commented that
not maintain Cash Receipts update her records by 2015 participants to the CPD courses
Record (CRR) for cash accomplishing the prescribed Cash requires sending registration
collections and deposits, Receipts Register in accordance through email to the Training
thus, monitoring of with Section 38 of the MGAS, for Management Staff at
accountability at any given proper monitoring of her collections tms.blgf.gov.ph. Once the training
period could not be easily and deposits in order to team acknowledges the
determined determine/establish easily the registration, participants are
running cash balance at any point in required to deposit their payments
time through Land Bank of the
Philippines (LBP). The Official
Receipt is issued to the participant
in the venue during the training. In
this case, the Cashier was not able
to keep track immediately those
who have paid and relied only on
the Bank Statements provided by
the LBP, hence, encounter difficulty
in maintaining an updated CRR
ML 2014 (117) The AO has not Accountable Officer should prepare Comply with the audit recommendations Cashier January onwards Fully Implemented The RAAF are already submitted
prepared/submitted the and submit the Report of Management 2015 by the Cashier.
monthly Report of Accountability of Accountable Forms
Accountability for monthly to the concern offices to The management has designated
Accountable Forms (RAAF) comply with Sec. 445 of GAAM, another employee to the Cash
Volume II, and Sec. 68 of MNGAS, Section to assist the Cashier
Volume II, to check the existence
and completeness of used and
unused accountable forms on hand
Page 9 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (125) The insurance coverage of Property Officer should Secure Comply with the audit recommendations Property Officer January onwards Fully Implemented Management commented that they
BLGF properties, with net immediately property insurance for 2015 are in the process of disposing
book value of P7,859,800.92 the properties which were not Office Furniture and Fixtures and
was inadequate due to the included in the insurance coverage Other Properties. The renovated
non-renewal of the insurance as required under RA No. 656 and office of the BLGF is furnished by
of its properties (except for COA Circular 92-390 dated the DOF. They opined that it is no
motor vehicles) as required November 17, 1992 longer necessary to insure the
under RA No. 656 and COA properties which are to be disposed
Circular 92-390. Likewise, Property Officer should ensure that
there was no updated all insurable assets as reported in
Inventory Report of PPE the updated RPCPPE duly verified
submitted to the General by the Auditor are adequately
Insurance Fund of the covered/insured with GSIS
Government Insurance
System (GSIS) as basis for
the insurance coverage,
thus, posing risks on non-
indemnification of the total
value of assets and
properties in case of loss
Page 10 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (136) The Agency’s Acting Concerned personnel of the Comply with the audit recommendations Accounting Unit January onwards Fully Implemented Management immediately acted on
Property Officer and the Administrative and Finance Division 2015 the recommendation and in the
Supply Officer were not should immediately secure fidelity process of securing all the
bonded, thus, government bond insurance for the Acting necessary documents for the
properties were not Property Officer and the Supplies, bonds application of the AOs
protected in case of based on the Revised Schedule of
improper or unauthorized Premium Rates or Annex C of
use or misapplication thereof Treasury Circular No. 02-2009 dated
August 6, 2009 to properly
safeguard the agency’s fund and
properties
ML 2014 (144) An Official Receipt or Comply with the BIR and LTFRB Comply with the audit recommendations Management January onwards Fully Implemented The OIC-Executive Director in his
Taximeter Issuing Receipt regulations to always ask from the 2015 Memorandum dated May 15, 2015
were not attached for the taxi taxi driver/s an OR/TIR for the directed to all officers/employees
fares claimed by some reimbursement of taxi fare as this is that reimbursement of taxi fares
employees for their travel a requirement for the reimbursement without submitting the ORs /TIR as
from their residence to of traveling expenses since this is required by the BIR and LTFRB
airport and vice versa but considered as an official function. rules and regulations, will be
instead used a Otherwise, taxi fares without TIR disallowed effective May 7, 2015
Reimbursement Expense should be disallowed in audit
Receipt (RER) which is not
in accordance with COA
Circular No. 2004-006 dated
September 9, 2004 and
Revenue Regulations No.
17-2006 dated September 6,
2006
Page 11 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (151) The airline ticket/fare in the Adhere strictly with Section 73, Comply with the audit recommendations Management January onwards Partially Management Exert all efforts to adhere strictly to
amount of P8,257.00 Book VI of the Revised 2015 Implemented commented that while Section 73, Book VI of the Revised
incurred by the Deputy Administrative Code of 1987 and the the Bureau is exerting Administrative Code of 1987 and
Executive Director for policy of BLGF as embodied in the all efforts to conform the policy of BLGF
Administration who was Training Manual System Guidebook with the rules and
invited by the PHALTRA on charging the Traveling Expense regulations of the
President to grace the 81st of the invited officers to act as existing travel policies
National Convention and resource persons/subject matter of Resource Persons, it
Seminar Workshop of all experts is sometimes inevitable
local government treasurers that transportation
and assessors and to deliver expenses are not
a message was charged to shouldered by the
the account Travelling recipient agency. In the
Expenses - Local in violation case of Deputy
of Section 73, Book VI of the Executive Director for
Revised Administrative Code Administration, her
of 1987 and the policy plane fare was not
statement of BLGF as shouldered by the
embodied in its Training PHALTRA, as certified
Management System by the attached
Guidebook Certification, hence her
ticket was purchased by
the Bureau
ML 2014 (157) Airline tickets for P99,568.00 Direct the concerned officers and Comply with the audit recommendations Concerned January onwards Fully Implemented Management commented that
of some officers/employees employees who booked their airline Officers and 2015 during the bookings made, there
were booked through private tickets through private firms to Employees was no advice that bookings have
companies rather than explain/justify. Likewise, the to be made directly with airlines
booking directly with the practice of booking airline fares companies. The memorandum
airlines companies which through a private firm should be itself does not provide a legal basis
resulted in a higher stopped and refrained from to avoid to support this Observation.
rates/fares as compared to suspensions/disallowances Moreover, there is no conclusive
the officers/employees who proof given that the BLGF was put
booked directly with the in a disadvantageous position
airlines/bus, thus, when it bought the ticket from the
disadvantageous to the travel agencies.
government
Page 12 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
It is not always the case that the
airline companies give lower rates
than accredited travel agencies.
The latter are given slots with lower
rates. Such that, if a buyer can
luckily avail of these slots, there is
a possibility that he/she will pay
smaller amount.
ML 2014 (163) The Agency’s GAD Plan and GAD Plan and Budget should Comply with the audit recommendations Admin January onwards Fully Implemented Management has adhered with the
Budget (GPB) for the year always be in accordance with the GAD Focal Person 2015 recommendation
2014, was not endorsed by applicable guidelines and activities
Philippine Commission on in support to GAD focused program
Women (PCW) to the approved and properly endorsed by
Department of Budget and PCW to the DBM as required under
Management (DBM) as Section 28 of GAA to determine
required under Section whether the GAD Accomplishment
12.2.1 of the PCW-NEDA- Report is compliant with the
DBM Joint Circular No. endorsed GAD Plan and Budget
2012-01, thus, the GAD
Accomplishment Report
(AR) submitted could not be
determined whether the
activities could be
considered sufficient
compliance or aligned with
said requirement
Page 13 of 45
Agency Action Plan
Reason for
Status of Partial/Delay/Non
Ref. Audit Observation Audit Recommendations Person/Dept. Target Implementation Action taken/Action to be taken
Action Plan Implementation implementation, if
Reponsible applicable
From To
ML 2014 (170) The amount allocated for Allocate at least five percent of their Comply with the audit recommendations January onwards Fully Implemented GAD Focal Person has adhered
Gender and Development budget for GAD programs as 2015 with the recommendation, used
(GAD) programs for CY provided for under Section 28 of the attribution method in the
2014 was only GAA for FY 2014 in order to carry- preparation of the GAD Plan
P3,033,296.80 instead of the out all projects that were identified
amount required under and to be GAD related GAD Activities were conducted
Section 28 of the GAA which
is P3,223,450.00 or five
percent (5%) of the total
budget of the Agency. As
such, the benefits that could
be derived by the
beneficiaries on GAD
program and activities were
not fully achieved
Agency Sign-off:
Armi M. Advincula
Director II, AFMS
Note: Status of Implementation may either be (a) Fully Implemented, (b) Ongoing, (c) Not Implemented, (d) Partially Implemented, or (e) Delayed
Page 14 of 45
Actual Implementation
Status of Date REMARKS
Date of Follow-up
Implementation
From To
Page 15 of 45
Actual Implementation
Status of Date REMARKS
Date of Follow-up
Implementation
From To
Page 16 of 45
Actual Implementation
Status of Date REMARKS
Date of Follow-up
Implementation
From To
Page 17 of 45
Actual Implementation
Status of Date REMARKS
Date of Follow-up
Implementation
From To
Page 18 of 45
Actual Implementation
Status of Date REMARKS
Date of Follow-up
Implementation
From To
Page 19 of 45
Bureau of Local Government Finance
8F EDPC Building, BSP Complex, Roxas Boulevard, Manila
Target Status of
Ref. Audit Observation Audit Recommendations Person/Dept.
Action Plan Implementation Implementation
Reponsible
From To
ML 2014 (29) The Other Supplies Inventory Supply Officer should submit the Instruct the Supply Officer to Supply Officer January onwards Fully
account is overstated by required RSMI’s to the comply with the audit 2015 Implemented
P61,182.00 which pertains to Accounting Unit for the recommendation
supplies that had been issued in immediate adjustment of the
2011 but not yet recorded in the account.
books during that year and still
not yet recorded in 2014.
ML 2014 (23) Management was not able to Create a committee consisting of Comply with the audit Management January onwards Partially
conduct its annual physical count two or more employees recommendations Property Officer 2015 Implemented
of PPE; accordingly, the designated by the agency head,
preparation and submission of to take charge of the inventory
the corresponding RPCPPE were taking which shall include the
not undertaken, causing difficulty property officer or custodian to
in determining whether all be witnessed by the Agency
properties recorded in the book Auditor.
exists and whether all properties
physically existing are duly
recorded in the books, thus
completeness, accuracy and
existence of the PPE account
balance of P25,749,782.20 could
not be ascertained
in determining whether all
properties recorded in the book
exists and whether all properties
physically existing are duly
recorded in the books, thus
completeness, accuracy and
existence of the PPE account Require the concerned Property
balance of P25,749,782.20 could and Supply Officers to prepare
not be ascertained detailed inventory action plan
that is understood and accepted
by all the members of the
Inventory Committee and take
into consideration the timing of
the counting to enable the
Inventory Committee to
complete the activity within the
scheduled date and submit the
RPCPPE on or before January 31
of the ensuing year
ML 2014 (34) The balances of Office Supplies Instruct the Accountant and the Comply with the audit Accountant January onwards Ongoing
Inventory per books of the Supply Officer to reconcile the recommendations Supply Officer 2015
Accounting Unit and per records difference of P349,735.75 in the
of the Supply Unit has a Office Supplies Inventory
discrepancy of P349,735.75;
likewise, a monthly report
prepared by the Supply Unit on
the Inventory of Supplies and
Materials was not in accordance
with the Instructions C and D on
page 138, MNGAS, Volume II,
thus, the accuracy and validity of
the book balance of P455,810.72
of the Office Supplies Inventory is
doubtful
likewise, a monthly report
prepared by the Supply Unit on
the Inventory of Supplies and
Materials was not in accordance
with the Instructions C and D on
page 138, MNGAS, Volume II,
thus, the accuracy and validity of Create an Inventory Committee
the book balance of P455,810.72 to conduct the physical count of
of the Office Supplies Inventory is the inventories every six months
doubtful and submit the RPCI to the
Office of the Auditor on or
before July 31 and January 31 of
each year
ML 2014 (42) Reimbursements of travelling Instruct the personnel Comply with the audit Bookkeeper January onwards Fully
expenses of some officers and processing the claims to oblige recommendations Accountant 2015 Implemented
employees totaling P251,342.82 all claimants to comply with the
were not duly supported with documentary requirements
basic documents contrary to pursuant to COA Circular 2012-
Section 28, MNGAS, Volume I and 001 dated June 14, 2012
COA Circular No. 2012-001 dated
June 14, 2012, thus lack of proper
evidence to validate and establish
regularity of the claim
ML 2014 (50) Appropriate accounts prescribed Chief, Financial and Comply with the audit Bookkeeper January onwards Fully
under the revised government Management Division should recommendations Accountant 2015 Implemented
chart of accounts were not used adjust and reclassify these
in recording various transactions accounts to their proper
totaling P37,000.91 contrary to accounts
Section 112 of PD 1445, resulting
to misstatements of the affected
accounts
ML 2014 (57) The correctness and reliability of Instruct the Accountant to exert Comply with the audit Accountant January onwards Ongoing
the financial statements (FS) of best effort to analyze/review and recommendations 2015
the BLGF as of December 31, account for the significant
2014 is uncertain due to the balances of P8,965,240.88 in the
doubtful existence of inventories LOGOFIND project; and
and depreciated property, plant
and equipment appearing in the
FS of the Local Government
Finance Development
(LOGOFIND) Project with total
debit and credit amount of
P8,965,240.88, in violation with
Paragraph 27, PPSAS, Volume I,
and Section 73.a of the MNGAS,
Volume I
2014 is uncertain due to the
doubtful existence of inventories
and depreciated property, plant
and equipment appearing in the
FS of the Local Government
Finance Development
(LOGOFIND) Project with total Effect any adjustment, if any, and
debit and credit amount of close the balances by
P8,965,240.88, in violation with transferring it to the General
Paragraph 27, PPSAS, Volume I, Fund of the BLGF books of
and Section 73.a of the MNGAS, accounts for fair presentation in
Volume I the FS as prescribed under
Paragraph 27, PPSAS, Volume I
and Section 73.a of the MNGAS,
Volume I
ML 2014 (64) The BLGF outstanding balance of Instruct the Accountant and the Accountant January onwards Ongoing
the Due from NGAs - Supply Officer to regularly Supply Officer 2015
Procurement Service (PS) coordinate with the PS for the
amounting to P219,536.04 as of periodic reconciliation of their
December 31, 2014 differed from records and to adjust any
the records of the PS of discrepancy that may be
P246,608.45 by P27,072.41 due uncovered
to non-reconciliation of both
agencies’ records
ML 2014 (72) Management failed to take full Review cash management Exert all efforts to maximize budget Management January onwards Not
advantage of the funds received program and adhere strictly to utilization Accountant 2015 Implemented
during the year, contrary to DBM the provision of Paragraph No. 2 Budget Officer
Circular Letter No. 2011-15, thus, of DBM Circular Letter No. 2011-
the unused Notice of Cash 15 dated December 26, 2011 on
Allocation (NCA) totaling the optimum utilization of
P13,006,244.30 or 15.20 per cent available NCA and require the
of the total NCAs received for CY concerned officials/personnel to
2014 operations was reverted submit promptly all claims for
payment with complete
documentation
Auditor’s Rejoinder: The funds on
hand could have been used to pay
existing obligations since BLGF
financial position as at year-end
showed existing obligations of
P3,248,452.12. Management
must have been confused with
the use of the NCA and allotment
ML 2014 (83) The practice of recording Stop the practice of charging Exert all efforts to comply with the Bookkeeper January onwards Not
purchases of supplies and directly to Other Supplies and audit recommendations Accountant 2015 Implemented
materials as outright expense Materials Expense all purchases
resulted in the understatement of of supplies and materials not
Other Supplies and Materials paid out of the PCF for fair
Inventory; and overstatement of presentation of the Supplies and
Other Supplies and Materials Materials Inventory account in
Expense the Statement of Financial
Position.
ML 2014 (90) The Accounting Unit and the Accountant and the Supply Exert all efforts to comply with the Accountant January onwards Partially
Supply Unit do not maintain the Officer to maintain properly the audit recommendations Supply Officer 2015 Implemented
Supplies Ledger Card (SLC) and SLC and the SC for each item of
Stock Card (SC), respectively, for the supplies inventories
each item of Office Supplies
received/issued resulting to
difficulty of reconciling the
balances recorded in the
Accounting Unit and the Supply
Unit
ML 2014 (96) Submission of reports such as (a) The Accountant should submit The Management through the Accountant January onwards Fully
Disbursement Records with all the Report of Disbursements and Administrative Division (Admin) and Cashier 2015 Implemented
paid vouchers and supporting Report of Collections together Financial and Management Division
documents and Liquidation with all the paid vouchers and (FMD), shall register to the we
Reports; (b) Report of Collections supporting documents Access facility of the Land Bank of
with corresponding issued Official evidencing the transactions the Philippines to be able to
Receipts; (c) Trial regularly to the Audit Team immediately print the Bank
Balances/Financial Statements; within ten (10) days from date of Statements and enable them to
and (d) Bank Reconciliation receipt of said documents prepare and submit the Bank
Statements, were delayed, thus, Reconciliation Statements on time
deter us to a timely examination
and audit of the transactions and
communication of the results
thereof
Submit Financial Reports
regularly in compliance with
Section 71 of the Manual on
NGAS
ML 2014 (104) The purposes and usefulness of Oblige the Inventory Committee Exert all efforts to comply with the Supply Officer January onwards Fully
the Report on the Physical Count to prepare and finalize audit recommendations 2015 Implemented
of Inventories (RPCI) are not immediately the RPCI for
attained due to non-submission submission to the Auditor on or
of the said report within the before July 31 and January 31 of
required period in violation of each year as prescribed under
Section 65 of the Manual on the Section 65 of the MNGAS,
NGAS, Volume II Volume II; and
ML 2014 (117) The AO has not Accountable Officer should Comply with the audit Cashier January onwards Fully
prepared/submitted the monthly prepare and submit the Report recommendations Management 2015 Implemented
Report of Accountability for of Accountability of Accountable
Accountable Forms (RAAF) Forms monthly to the concern
offices to comply with Sec. 445
of GAAM, Volume II, and Sec. 68
of MNGAS, Volume II, to check
the existence and completeness
of used and unused accountable
forms on hand
Designate the custody,
safekeeping and disbursing of
other cash advances to other
qualified Officers/Employees so
that the Collecting/Disbursing
Officer could perform her duties
and responsibilities satisfactorily.
The management may also
add/assign qualified personnel
to assist the Cashier
ML 2014 (125) The insurance coverage of BLGF Property Officer should Secure Comply with the audit Property Officer January onwards Fully
properties, with net book value of immediately property insurance recommendations 2015 Implemented
P7,859,800.92 was inadequate for the properties which were
due to the non-renewal of the not included in the insurance
insurance of its properties (except coverage as required under RA
for motor vehicles) as required No. 656 and COA Circular 92-390
under RA No. 656 and COA dated November 17, 1992
Circular 92-390. Likewise, there
was no updated Inventory Report
of PPE submitted to the General
Insurance Fund of the
Government Insurance System
(GSIS) as basis for the insurance
coverage, thus, posing risks on
non-indemnification of the total
value of assets and properties in
case of loss
Auditor’s Rejoinder: While it is Property Officer should ensure
true that the subject disposable that all insurable assets as
properties may no longer be reported in the updated RPCPPE
required to be insured with the duly verified by the Auditor are
GSIS, this does not mean that adequately covered/insured with
Management should wait for GSIS
their properties to be considered
disposable first before these are
to be insured with the GSIS
because this is required under RA
No. 656.
ML 2014 (136) The Agency’s Acting Property Concerned personnel of the Comply with the audit Accounting Unit January onwards Fully
Officer and the Supply Officer Administrative and Finance recommendations 2015 Implemented
were not bonded, thus, Division should immediately
government properties were not secure fidelity bond insurance
protected in case of improper or for the Acting Property Officer
unauthorized use or and the Supplies, based on the
misapplication thereof Revised Schedule of Premium
Rates or Annex C of Treasury
Circular No. 02-2009 dated
August 6, 2009 to properly
safeguard the agency’s fund and
properties
ML 2014 (144) An Official Receipt or Taximeter Comply with the BIR and LTFRB Comply with the audit Management January onwards Fully
Issuing Receipt were not attached regulations to always ask from recommendations 2015 Implemented
for the taxi fares claimed by some the taxi driver/s an OR/TIR for
employees for their travel from the reimbursement of taxi fare as
their residence to airport and vice this is a requirement for the
versa but instead used a reimbursement of traveling
Reimbursement Expense Receipt expenses since this is considered
(RER) which is not in accordance as an official function.
with COA Circular No. 2004-006 Otherwise, taxi fares without TIR
dated September 9, 2004 and should be disallowed in audit
Revenue Regulations No. 17-2006
dated September 6, 2006
ML 2014 (151) The airline ticket/fare in the Adhere strictly with Section 73, Comply with the audit Management January onwards Partially
amount of P8,257.00 incurred by Book VI of the Revised recommendations 2015 Implemented
the Deputy Executive Director for Administrative Code of 1987 and
Administration who was invited the policy of BLGF as embodied
by the PHALTRA President to in the Training Manual System
grace the 81st National Guidebook on charging the
Convention and Seminar Traveling Expense of the invited
Workshop of all local government officers to act as resource
treasurers and assessors and to persons/subject matter experts
deliver a message was charged to
the account Travelling Expenses -
Local in violation of Section 73,
Book VI of the Revised
Administrative Code of 1987 and
the policy statement of BLGF as
embodied in its Training
Management System Guidebook
ML 2014 (157) Airline tickets for P99,568.00 of Direct the concerned officers and Comply with the audit Concerned January onwards Fully
some officers/employees were employees who booked their recommendations Officers and 2015 Implemented
booked through private airline tickets through private Employees
companies rather than booking firms to explain/justify. Likewise,
directly with the airlines the practice of booking airline
companies which resulted in a fares through a private firm
higher rates/fares as compared to should be stopped and refrained
the officers/employees who from to avoid
booked directly with the suspensions/disallowances
airlines/bus, thus,
disadvantageous to the
government
ML 2014 (163) The Agency’s GAD Plan and GAD Plan and Budget should Comply with the audit Admin January onwards Fully
Budget (GPB) for the year 2014, always be in accordance with the recommendations GAD Focal 2015 Implemented
was not endorsed by Philippine applicable guidelines and Person
Commission on Women (PCW) to activities in support to GAD
the Department of Budget and focused program approved and
Management (DBM) as required properly endorsed by PCW to
under Section 12.2.1 of the PCW- the DBM as required under
NEDA-DBM Joint Circular No. Section 28 of GAA to determine
2012-01, thus, the GAD whether the GAD
Accomplishment Report (AR) Accomplishment Report is
submitted could not be compliant with the endorsed
determined whether the GAD Plan and Budget
activities could be considered
sufficient compliance or aligned
with said requirement
ML 2014 (170) The amount allocated for Gender Allocate at least five percent of Comply with the audit January onwards Fully
and Development (GAD) their budget for GAD programs recommendations 2015 Implemented
programs for CY 2014 was only as provided for under Section 28
P3,033,296.80 instead of the of the GAA for FY 2014 in order
amount required under Section to carry-out all projects that
28 of the GAA which is were identified and to be GAD
P3,223,450.00 or five percent related
(5%) of the total budget of the
Agency. As such, the benefits
that could be derived by the
beneficiaries on GAD program
and activities were not fully
achieved
Reason for
Partial/Delay/Non Actual Implementation Date
Action taken/Action to be taken Date of Follow-up Status of Implementation REMARKS
implementation, if
applicable
From To
The Supply Officer has submitted Copy received.
the required RSMI to the Accounting
Division and to the Auditing Office.
Adjustments were already made by
the Accounting Division on January
2015 December 31,
Fully Implemented June 2, 2015 2015
No Inventory Committee was Management has ordered the No Inventory Committee was created
created Property Officer to prepare the thus no deatiled inventory action plan
Inventory Plan. was submitted to the Auditor. No
physical inventory was conducted for the
year 2015 as of the date. Imposition of
deadline for the submission of RPCPPE is
still ongoing.
Not Implemented
still ongoing.
Not Implemented
Ongoing
Not implemented
Fully Implemented
The Bookkeeper has adjusted and The Bookkeeper has adjusted and
reclassified the said accounts to reclassified to the account Accountable
their proper accounts Forms, Plates and Stickers Inventory but
failed to create Drugs and Medicines
Inventory account thus account is still
misstated and unadjusted.
Partially Implemented
Ongoing
To coordinate with the former
project accountant while effecting Ongoing
the transferring and closing of
balances
Ongoing
Management commented
that supplies purchased from
outside suppliers were
recognized immediately as
expense to simplify journal
entries because these items
were immediately issued to
end-users upon delivery and
supported with
corresponding RSMI
Not Implemented
Impracticability of Stock Cards are now being Stock Cards and Supplies Ledger Cards
maintaining two similar maintained by the Supply Officer are now being maintained but not yet
ledger cards updated as of date.
Partially Implemented
The Cash and Accounting Unit has The management has now registered to
already registered to the weAccess the eMDS system of Landbank to provide
facility of the Landbank of the easier and faster access to bank
Philippines statements and reports.
Fully Implemented
Fully Implemented
Management commented that
participants to the CPD courses
requires sending registration
through email to the Training
Management Staff at
tms.blgf.gov.ph. Once the training
team acknowledges the registration,
participants are required to deposit
their payments through Land Bank
of the Philippines (LBP). The Official
Receipt is issued to the participant
in the venue during the training. In
this case, the Cashier was not able
to keep track immediately those
who have paid and relied only on
the Bank Statements provided by
the LBP, hence, encounter difficulty
in maintaining an updated CRR
Fully Implemented
Fully Implemented
Not implemented
The OIC-Executive Director in his
Memorandum dated May 15, 2015
directed to all officers/employees
that reimbursement of taxi fares
without submitting the ORs /TIR as
required by the BIR and LTFRB rules
and regulations, will be disallowed
effective May 7, 2015
Fully Implemented
Fully Implemented
It is not always the case that the
airline companies give lower rates
than accredited travel agencies. The
latter are given slots with lower
rates. Such that, if a buyer can
luckily avail of these slots, there is a
possibility that he/she will pay
smaller amount.
Fully Implemented
Fully Implemented
GAD Activities were conducted