ANALISA HARGA SATUAN PEKERJAAN

TAHUN ANGGARAN 2017

NO URAIAN KOEF SAT. HARGA SAT JMH HARGA JMH HARGA JUMLAH
BAHAN UPAH BAHAN UPAH
1 2 3 4 5 6 7(3x5) 8(3x6) 9=(7+8)
1 1 m3 Lapis Permukaan Penetrasi Makadam
A Bahan
Batu Pecah 3-5 Cm 1.1831 m3 185,000.00 218,873.50 218,873.50
Batu Pecah 2-3 cm 0.3697 m3 250,000.00 92,425.00 92,425.00
Batu Pecah (0,5 - 1- 2 ) cm 0.2070 m3 185,000.00 38,295.00 38,295.00
Aspal 82.4000 kg 12,500.00 1,030,000.00 1,030,000.00
B Alat
Dump Truck 0.5917 jam 200,000.00 118,340.00 118,340.00
3-Wheel Roller ( Mesin Gilas ) 0.0609 jam 400,000.00 24,360.00 24,360.00
Alat Bantu 1.0000 ls 15,000.00 15,000.00 15,000.00
C Tenaga
Mandor 0.1218 jam 100,000.00 12,180.00 112,180.00
Pekerja 5.3570 jam 85,000.00 455,345.00 455,345.00
D Jumlah Harga Tenaga, Bahan, dan Alat 1,537,293.50 467,525.00 2,104,818.50
F Harga Satuan Pekerjaan 2,104,818.50
G Harga Satuan Pekerjaan 1 m2 105,240.93
H Dibulatkan 105,000.00

Rekap kebutuhan Material dan HOK


Volume Pekerjaan 11625 m2

No. Material Satuan Jumlah


1 Batu Pecah 3-5 cm m3 13,000
2 Batu Pecah 2-3 cm m3 4,000
3 Batu Pecah (0,5 - 1- 2 ) cm m3 2,000
4 Aspal drum 6,180
5 Dump Truck jam 6,000
6 3-Wheel Roller ( Mesin Gilas ) jam 700
7 Alat Bantu ls 11,000
8 Mandor jam 1,400
9 Pekerja jam 62,000