You are on page 1of 3

Item Descripción Und.

Metrado Precio S/ Parcial S/


01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

1.01 OBRAS PROVISIONALES


01.01.01 CASETA DE GUARDIANIA glb 1.00 5,794.72 5,794.72
1.02 TRABAJOS PRELIMINARES
01.02.01 TRAZO Y REPLANTEO INICAL m2 171.30 8.50 1,456.05
2 EQUIPOS DE PROTECCION PERSONAL
2.01 EQUIPO DE PROTECCION PERSONAL glb 1.00 8,850.00 8,850.00
3 MOVIMIENTO DE TIERRAS 11,114.61
3.01 EXCAVACION MASIVA CON MAQUINARIA m3 83.70 23.07 1,930.96
3.02 EXCAVACION DE ZANJA PARA CIMIENTOS m3 8.19 400.23 3,277.88
3.03 EXCAVACION PARA ZAPATAS m3 10.54 560.32 5,905.77
4 CONCRETO SIMPLE 5,052.90
4.01 CONCRETO SOLADO MEZCLA 1:10 CEMENTO-HORMIGON e=0.10 m. m2 2.38 123.84 294.74
4.02 CONCRETO CICLOPEO PARA CIMENTACION 1:10 + 30% P.G. m3 8.13 585.26 4,758.16
5 CONCRETO ARMADO 447,110.83
5.01 ZAPATAS 12,537.73
05.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 m3 14.28 717.18 10,241.33
05.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 395.25 5.81 2,296.40
5.02 VIGA DE CIMENTACION 6,094.26
05.02.01 CONCRETO EN VIGA DE CIMENTACIÓN f'c=210 kg/cm2 m3 4.57 867.07 3,962.51
05.02.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 366.91 5.81 2,131.75
5.03 SOBRECIMIENTO ARMADO 14,745.87
05.03.01 CONCRETO EN SOBRECIMIENTO f'c=210 kg/cm2 m3 5.61 1,414.48 7,935.23
05.03.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 366.24 5.81 2,127.85
05.03.03 ENCOFRADO DE SOBRECIMIENTO h=0.30 m m2 29.88 156.72 4,682.79
5.04 PLACAS 14,323.82
05.04.01 CONCRETO EN PLACAS f'c=210 kg/cm2 m3 4.98 1,027.63 5,117.60
05.04.02 ENCOFRADO DE PLACAS m2 51.47 136.69 7,035.43
05.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 373.63 5.81 2,170.79
5.05 COLUMNAS 73,836.86
05.05.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 16.37 1,800.96 29,481.72
05.05.02 ENCOFRADO COLUMNAS m2 206.76 136.69 28,262.02
05.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 2,769.90 5.81 16,093.12
5.06 VIGAS 164,845.89
05.06.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 35.85 1,006.15 36,070.48
05.06.02 ENCOFRADO DE VIGAS m2 734.82 154.18 113,294.55
05.06.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 PARA VIGAS kg 3,542.53 4.37 15,480.86
5.07 TANQUE ELEVADO 18,675.57
05.07.01 CONCRETO TANQUE ELEVADO f'c=175 kg/cm2 m3 2.48 1,780.71 4,416.16
05.07.02 ENCOFRADO TANQUE ELEVADO m2 61.41 214.86 13,194.55
05.07.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 183.28 5.81 1,064.86
5.08 CISTERNA 6,270.90
05.08.01 ENCOFRADO DE CISTERNA m2 8.82 144.04 1,270.43
05.08.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 172.24 5.81 1,000.71
05.08.03 CONCRETO EN CISTERNA f'c=210 kg/cm2 m3 2.25 1,777.67 3,999.76
5.09 ESCALERAS 18,031.50
05.09.01 ENCOFRADO EN ESCALERA m2 7.83 252.26 1,975.20
05.09.02 CONCRETO ESCALERAS f´c=210 kg/cm2 m3 7.54 1,531.33 11,546.23
05.09.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 776.26 5.81 4,510.07
5.1 LOSAS ALIGERADAS 94,327.92
05.10.01 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA m2 282.55 134.57 38,022.75
05.10.02 LOSA ALIGERADA f'c= 210 kg/cm2 m3 24.77 923.65 22,878.81
05.10.03 LADRILLO PARA TECHO DE h=0.20 m und 2,402.00 9.80 23,539.60
05.10.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,701.68 5.81 9,886.76
5.11 LOSAS MACIZAS 23,420.51
Item Descripción Und. Metrado Precio S/ Parcial S/
05.11.01 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 3.57 117.65 420.01

05.11.02 LOSA MACIZA f'c= 210 kg/cm2 m3 20.16 1,027.66 20,717.63


05.11.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 392.92 5.81 2,282.87
6 MUROS Y TABIQUES
6.01 MUROS DE TABIQUERIA m2 61.10 57.50 3,513.25
7 BARANDAS
7.01 BARANDA DE FIERRO EN ESCALERA ML 29.68 206.12 6,117.64
8 PARAPETOS
8.01 PARAPETOS m2 47.90 68.81 3,296.00
9 VIDRIOS
9.01 VIDRIO SEMIDOBLE (3 mm.) p2 73.70 81.73 6,023.50
10 PUERTAS
10.01 PUERTAS DE MADERA CEDRO DE TABLEROS REBAJADOS DE 4.5 mm und 11.00 203.94 2,243.34
11 INSTALACIONES SANITARIAS 62,189.86
11.01 RED DE AGUA 9,321.71
11.01.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 20.00 96.30 1,926.00
11.01.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 O 1/2" ML 33.10 66.23 2,192.21
11.01.03 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 O 3/4" ML 10.91 66.94 730.32
11.01.04 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1" ML 14.04 83.25 1,168.83
11.01.05 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 O 1¼" ML 10.63 87.99 935.33
11.01.06 CODO PVC SAP PARA AGUA DE 1/2" X 90° und 15.00 132.66 1,989.90
11.01.07 TEE PVC SAP PARA AGUA DE 1/2" und 7.00 54.16 379.12
11.02 RED DE DESAGUE 43,061.00
11.02.01 RED DE DISTRIBUCION TUBERIA 4" pto 66.49 46.47 3,089.79
11.02.02 RED DE DISTRIBUCION TUBERIA 2" ML 101.91 86.91 8,857.00
11.02.03 SALIDA DE DESAGUE EN PCV 4" ML 9.00 434.79 3,913.11
11.02.04 SALIDA DE DASGUE DE PVC 2" und 12.00 417.48 5,009.76
11.02.05 SALIDA DE VENTILACION PVC 2" und 20.00 408.13 8,162.60
11.02.06 SUMIDERO DE 2" DE BRONCE und 9.00 416.72 3,750.48
11.02.07 REGISTRO ROSCADO DE BRONCE 4" und 14.00 416.15 5,826.10
11.02.08 CAJAS DE REGISTRO DE DESAGUE 12" x 24" und 2.00 433.48 866.96
11.02.09 INODORO ONE PIECE ARTICO BLANCO und 9.00 232.28 2,090.52
11.02.10 LAVATORIO INDIGO + PEDESTAL und 9.00 141.88 1,276.92
11.02.11 URINARIO und 2.00 108.88 217.76
11.03 SOBRECIMIENTO 9,807.15
11.03.01 SUMINISTRO E INSTALACION INODORO TANQUE BAJO DE LOSA pza 9.00 424.08 3,816.72
11.03.02 SUMINISTRO E INSTALACION LAVATORIO DE LA LOSA C/PEDESTAL pza 7.00 421.81 2,952.67
11.03.03 SUMINISTRO E INSTALACION DE URINARIO ACADEMY BLANCO STANDAR, INC FLUXOMETRO pza 4.00 759.44 3,037.76

12 SALIDAS PARA ALUMBRADO, TOMACORRIENTE, FUERZA Y SEÑALES DEBILES 6,314.77


12.01 SALIDAS PARA ALUMBRADO 2,330.17
12.01.01 SALIDA PARA BRAQUETE pto 1.00 49.45 49.45
12.01.02 SALIDA PARA BOMBILLOS pto 17.00 43.86 745.62
12.01.03 SALIDA PARA FLUORESCENTES pto 35.00 43.86 1,535.10
12.02 SALIDA PARA INTERRUPTORES 1,328.17
12.02.01 INTERRUPTOR UNIPOLAR SIMPLE pto 10.00 41.70 417.00
12.02.02 INTERRUPTOR BIPOLAR SIMPLE pto 17.00 43.79 744.43
12.02.03 INTERRUPTOR TRIPOLAR SIMPLE pto 3.00 55.58 166.74
12.03 SALIDA PARA TOMACORRIENTES 2,656.43
12.03.01 TOMACORRIENTE MONOFASICO pto 18.00 34.02 612.36
12.03.02 TOMACORRIENTE TRIFASICO pto 18.00 35.62 641.16
12.03.03 SALIDA PARA TELEFONO pto 7.00 73.99 517.93
12.03.04 SALIDA PARA INTERCOMUNICADOR pto 1.00 40.02 40.02
12.03.05 SALIDA DE FUERZA pto 2.00 68.23 136.46
12.03.06 CAJA DE PASO 10X10CM und 10.00 70.85 708.50
Item Descripción Und. Metrado Precio S/ Parcial S/
13 CANALIZACIONES Y TUBERIAS 1,582.92

13.01 TUBERIA PVC-SAP ELECTRICA DE 20 mm ML 444.59 3.38 1,502.71


13.02 TUBERIA PVC-SAP ELECTRICA DE 25 mm ML 21.62 3.71 80.21
14 CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS 3,385.05
14.01 ALAMBRE TW 2.5 mm2 ML 1,070.02 2.68 2,867.65
14.02 ALAMBRE THW 4 mm2 ML 66.56 3.74 248.93
14.03 ALAMBRE TW 6 mm2 ML 53.37 3.21 171.32
14.04 ALAMBRE DESNUDO THW 6 mm2 ML 27.06 3.59 97.15
15 TABLEROS 626.44
15.01 TABLERO GENERAL pza 1.00 336.72 336.72
15.02 SUBTABLERO pza 2.00 144.86 289.72
16 DISPOSITIVOS DE MANIOBRA Y PROTECCION 345.1
16.01 INTERRUPTOR TERMOMAGNETICO und 10.00 34.51 345.1
17 INSTALACION PUESTA A TIERRA 764.78
17.01 POZO PUESTA A TIERRA und 1.00 764.78 764.78
18 EQUIPO ELECTRICO Y MECANICO 1,346.24
18.01 ELECTROBOMBA und 2.00 673.12 1,346.24
19 ACCESORIOS 1,414.12
19.01 FLUORESCENTES T8 und 35.00 29.31 1,025.85
19.02 BOMBILLOS und 16.00 21.31 340.96
19.03 BRAQUETES und 1.00 47.31 47.31
COSTO DIRECTO 555,939.80
GASTOS GENERALES 13.2741% 7,425.50
UTILIDADES (10%) 55,593.98
SUBTOTAL 618,959.28
IGV (18%) 111,412.67
TOTAL 730,371.96

SON: SETECIENTOS TREINTA MIL TRESCIENTOS SETENTA Y UNO CON 96/100 SOLES