Professional Documents
Culture Documents
Bhd
ELEMENT&NO.&1&:&WORK&BELOW&LOWEST&FLOOR&LEVEL
Note:!Allow!10%!profit!and!overhead.
Excavation
1 Excavator!with!operator!and!fuel RM13,000.00!/!26!days
2 Total!cycle!of!excavator!for!reduced!level!and!trench 17!secs/m3
3 Total!cycle!of!excavator!for!pit 24!secs/m3
Removal&of&surplus
5 8!wheelsYlorry!rental!(Including!driver!and!petrol) RM400!/!day!(8hrs)
6 8!wheelsYlorry!capacity 14m3
7 Unloading!time!according!to!lorry's!specification 15mins!/!m3
8 Return!trip 30!mins
Concrete
Material!cost:
1 Ready!mix!concrete!Grade!15! RM!168/!m3
2 Ready!mix!concrete!Grade!25! RM!190/!m3
3 Ready!mix!concrete!Grade!25! RM!199/!m3
Labour&cost&:&
Labour!cost!:!
1 Additional!labour!for!spreading!and!level: 0.60hr/m3!@!RM3.50/hr
2 Additional!labour!working!around!reinforcement: 0.55hr/m3!@!RM3.50/hr
3 Cost!of!vibrator RM!6.30/!1.50m3
Formwork
1 4'!x!8'!x!12mm!@!RM!36.50/!pc RM!36.50/pc
2 Cutting!waste! 15%
3 0.03m3!of!struts!per!m2!for!
sides!of!pad!footing!/!column!stump!/!ground!beam RM!400.00/!m3
4 Allow!4!uses!for!timber!formwork
5 Waste!on!each!use! 10%
6 Nails,!bolts!and!mould!oil! RM!1.50!per!m2
7 4!joiners!and!8!labourers!take!4!hours! Joiners!@!RM!10.63/!hr
to!erect!and!fixing!ALL!formwork Labourer!@!RM!7.50/!hr
Hardcore
1 Hardcore RM!50/!m3
2 Excavator!with!operator!and!fuel RM13,000.00!/!26!days
3 Rate!of!excavator!to!spread!and!level 0.05hr/!m3
4 Unskilled!labour!for!roller! RM!55/!day!(8hrs)
5 Allow!10%!for!compaction
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_WBLFL
!MBina!Construction!Sdn!Bhd
Reinforcement&Bar
Material!cost:
Mild!steel!reinforcement!bar:
1 10mm!diameter!bar!delivered!to!site! RM!2,730.00/!tonne
High!tensile!reinforcement!bar:
2 12mm!diameter!bar!delivered!to!site,!1m@!0.89kg! RM!2,750.00/!tonne
3 16mm!diameter!bar!delivered!to!site,!1m@!1.58kg! RM!2,600.00/!tonne
4 Allow!for!labour!stacking!&!loading! RM!5.00/!tonne
5 Allow!0.66kg!tie!wire!for!each!100kg!of!reinforcement!bar RM!4.50/kg
6 Allow!spacers!@!RM!4.00/!tonne!of!rebar
7 Allow!wastage! 7%
8 Allow!for!rolling!margin! RM!22.00/!tonne
Labour!cost:
1 Team!Y!1!skilled!labourer!and!1!unskilled!labourer! Skilled!labour@!RM82!/day
Unskilled!labour@!RM55!/day
2 Time!analysis!for!100kg!of!reinforcement!bar!
Select 28!mins
Cut 32!mins
Bend 35!mins
Fix 23!mins!
Hoist!twice 7!mins
3 Allow!idling!time! 10%
Fabric&Reinforcement&
Material!cost:
1 A6:!2.61kg/m2!wire!mesh!delivered!to!site RM!75.24!per!pc
(2.20m!x!6.0m)
2 A8:!3.01kg/m2!wire!mesh!delivered!to!site RM!352.44!per!pc
(2.20m!x!6.0m)
3 Allow!spacers,!tie!wire!and!lapping 5%
4 Allow!wastage 5%
Labour!cost:
1 Team!Y!1!skilled!labourer!and!1!unskilled!labourer! Skilled!labour@!RM82!/day
Unskilled!labour@!RM55!/day
2 Unrolling!and!place!over!regular!area 0.25hr!/!100sf
3 Allow!idling!time! 10%
4 Allow!10%!for!profit!and!overhead
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_WBLFL
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)1/A&:&EXCAVATE&TO&REDUCED&LEVEL&
Part&1&:&Excavation
(1) Material&quantity&for&reduced&level = 10m3
(2) &Time&Required
(Total'cycle'of'excavator'is'17'seconds'per'cubic'meter.'Refer'to'Appendix)
Excavation&<1.50m&deep = 10m3&x&(17/60)&hrs/m3
TOTAL = 10m3&x&0.28&hr/m3 2.8 hrs
(3) Labour&and&Plant&Cost
(Combined'cost'as'quotation'given'by'contractor.'Refer'to'Appendix)
Hourly&rate&for&labour&and&plant = RM13,000.00&/&26&days
= RM500.00 per&day
= RM500/8hr RM62.50 /hr
(4) Total&cost&excavation&including&profit&and&overhead
Total&cost& = RM175.00
Add:&Profit&and&overhead&(10%) = RM175.00&x&1.1 RM192.50
Part&2&:&Removal&of&surplus
(No'bulking'factor.'Assuming'site'is'ordinary'soil'and'sand.)
Time&required&(Loading'time'is'factor'into'excavator)
(Return&trip&+&Unloading&time)&x&Idle&Factor = (30&+&15)&x&1.15mins 51.75 mins
(3) Estimate&cost&(Incl.'driver'and'diesel)
RM400&per&day&(8&hrs) = (RM400/(8&x&60))&x&51.75 RM43.13
(4) Total&cost&of&removing&surplus&including&profit&and&overhead
Total&cost& = RM43.13
Add:&Profit&and&overhead&(10%) = RM43.13&x&1.1 RM47.44
Summary
(1) Total&cost&
Excavation&and&removal&of&surplus = RM192.50&+&RM47.44 RM239.94
(2) Unit&rate&(RM/m3)
Total&cost&/&total&qty = RM239.94&/&10m3 RM23.99 /m3
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/1
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)1/B&:&EXCAVATE&PITS&
Part&1&:&Excavation
(1) Material&quantity&for&reduced&level = 4m3
(2) &Time&Required
(Total'cycle'of'excavator'is'24'seconds'per'cubic'meter.
Longer'time'accounted'for'excavating'pit.'Refer'to'Appendix)
(3) Labour&and&Plant&Cost
(Combined'cost'as'quotation'given'by'contractor.'Refer'to'Appendix)
Hourly&rate&for&labour&and&plant = RM13,000.00&/&26&days RM500.00 /day
= RM500/8hr RM62.50 /hr
(4) Total&cost&excavation&including&profit&and&overhead
Total&cost& = RM100.00
Add:&Profit&and&overhead&(10%) = RM100.00&x&1.1 RM110.00
Part&2&:&Removal&of&surplus&
(No'bulking'factor.'Assuming'site'is'ordinary'soil'and'sand.)
Time&required&
(Loading'time'is'factor'into'excavator,'no'need'to'account'for'return'trip)
Unloading&time&x&Idle&Factor = 15&x&1.15 17.25 mins
(3) Estimate&cost
RM400&rental&per&day&(8&hrs) = (RM400&/&(8&x&60))&x&17.25 RM14.38
(Incl.'driver'and'diesel)
(4) Total&cost&of&removing&surplus&including&profit&and&overhead
Total&cost& = RM14.38
Add:&Profit&and&overhead&(10%) = RM14.38&x&1.1 RM15.82
Summary
(1) Total&cost&
Excavation&and&removal&of&surplus = RM110.00+&RM14.38 RM124.38
(2) Unit&rate&(RM/m3)
Total&cost&/&total&qty = RM124.38&/&4m3 RM31.10 /m3
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/2
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)1/C&:&EXCAVATE&TRENCH
Part&1&:&Excavation
(1)& Material&quantity&for&reduced&level = 9m3
(2)& &Time&Required
(Total'cycle'of'excavator'is'17'seconds'per'cubic'meter.
Excavation&<1.5m&deep = 9m3&x&(17/60)&hrs/m3
TOTAL = 9m3&x&0.28 2.5 &hrs
(3)& Labour&and&Plant&Cost
(Combined'cost'as'quotation'given'by'contractor.'Refer'to'Appendix)
Hourly&rate&for&labour&and&plant = RM13,000.00&/&26&days RM500.00 /day
= RM500/8hr RM62.50 /hr
(4)& Total&cost&excavation&including&profit&and&overhead
Total&cost& = RM156.25
Add:&Profit&and&overhead&(10%) = RM156.25&x&1.1 RM171.88
Part&2&:&Removal&of&surplus
(1) Material&quantity&to&cart&away = 9m3
Time&required&(Loading'time'is'factor'into'excavator)
(Return&trip&+&Unloading&time)&x&Idle&Factor = (30&+&15)&x&1.15 51.75 mins
(4) Total&cost&of&removing&surplus&including&profit&and&overhead
Total&cost& = RM43.13
Add:&Profit&and&overhead&(10%) = RM43.13&x&1.1 RM47.44
Summary
(5) Total&cost&
Excavation&and&removal&of&surplus = RM171.88&+&RM47.44 RM219.32
(5) &Unit&rate&(RM/m3)
Total&cost&/&total&qty = RM219.32&/&9m3
= RM24.37 RM24.40 /m3
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/3
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)/2/O&:&SAWN&FORMWORK&TO&SIDES&OF&PAD&FOOTING&
B4(1)/2/P&:&SAWN&FORMWORK&TO&SIDES&OF&COLUMN&STUMP
B4(1)/2/Q&:&SAWN&FORMWORK&TO&SIDES&OF&GROUND&BEAM
(2) Labour&cost
Cost&of&gang&per&hour&
1&carpenter&(joiner)&@&RM&78/day = 78/8 9.75
1&labourer&@&RM&55/day = 55/8 6.88
4&joiners&assisted&by&8&labourers&required&4&hours&to&erect&and&dismantle&all&formwork&to&the&frame&
All&formworks& = (5+14+7)&m2 26
4&hours&are&required&to&fix&and&dismantle&26.00m2&formwork&
Therefore&1&m2&requires&0.15&hr = 4&hr&/&26.00&m2 0.15&hr
(3) Total&cost&including&profit&and&overhead
Material&+&Labour = RM8.67&+&RM14.11 RM22.78
Add:&Profit&and&overhead&(10%) = RM&22.78&x&10% RM2.28
RM25.06
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/4
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)/1/G&:&Hardcore
(2)& Plant&Cost&(with&Operator)
Hourly&rate&for&plant&with&operator = RM13,000.00&/&26&days RM500.00 /day
= RM500/8hr RM62.50 /hr
Hourly&required&x&rate = Hour&x&Rate
Unloading&and&spread&hardcore&at&0.05hr/m3 = 0.05hr/m3&x&RM62.50& RM3.13 /m3
(Refer'to'Appendix)
(3)& Unskilled&labour
Hourly&rate&for&labour = RM55.00&/&8&hr RM6.88 /hr
Spreading&with&roller&at&0.10&hr/m3& = 0.10&hr/m3&x&RM6.88 RM0.69 /m3
(4)& Total&cost&including&profit&and&overhead
Material&+&Plant+&Labour = RM&(55&+&3.13&+&0.69) RM58.82
Add:&Profit&and&overhead&(10%) = RM64.70 /m3
(5)& Convert&cost&in&m3&to&m2
Area&for&1m3 = RM64.70&/m3&x&0.15&m RM9.71 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/5
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)/1/D&:&Reinforced&concrete&work&Grade&15
Concrete&Grade&15&
(1) Material&cost
1m3&of&ready&mix&concrete&Grade&15 = RM168.00 /m3
(2) Place&*&Labour&and&vibrator&
Additional&labour&spreading&and&level = 0.60&x&RM&3.50 RM2.10 /m3
Cost&of&vibrator&per&m3&=&RM&6.30/1.50 = RM&6.30/&1.50 RM4.20 /m3
Total&labour&cost RM8.23 /m3
(3) Total&cost&(RM&/&m3)
Material&+&Labour = RM168.30&+&RM8.23 RM176.53 /m3
(4) Unit&rate&(RM/m2)
(Convert'cost'per'm3'to'm2) = RM&194.18&x&0.05 RM9.71 /m2
B4(1)/1/J&:&Reinforced&concrete&work&Grade&25
Concrete&Grade&25&
(1) Material&Cost
1m3&of&ready&mix&concrete&Grade&25 = RM190.00 /m3
(2) Place&*&Labour&and&vibrator&
Additional&labour&spreading&and&level = 0.60&x&RM&3.50 RM2.10 /m3
Additional&labour&working&around&rebar& = 0.55&x&RM&3.50 RM1.93
Cost&of&vibrator&per&m3&=&RM&6.30/1.50 = RM&6.30/&1.50 RM4.20 /m3
Total&labour&cost RM8.23 /m3
(3) Total&cost&(RM&/&m3)
Material&+&Labour = RM190.00&+&RM8.23 RM198.23 /m3
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/6
MBina&Construction&Sdn&Bhd
B4(1)/2/A&:&Reinforced&concrete&work&Grade&30
Concrete&Grade&30
(1) Material&cost
1m3&of&ready&mix&concrete&Grade&30 = RM199.00 /m3
(2) Place&*&Labour&and&vibrator&
Additional&labour&spreading&and&level = 0.60&x&RM&3.50 RM2.10 /m3
Cost&of&vibrator&per&m3&=&RM&6.30/1.50 = RM&6.30/&1.50 RM4.20 /m3
Total&labour&cost RM8.23 /m3
(3) Total&cost&(RM&/&m3)
Material&+&Labour = RM199&+&RM8.23 RM207.23 /m3
Add:&Profit&and&overhead&(10%) = RM&207.23&x&1.1 RM227.95 /m3
(4) Unit&rate&(RM/m2)
(Convert'cost'per'm3'to'm2) = RM227.95&x0.125&thk RM28.49 /m2
B4(1)/2/B&:&Reinforced&concrete&work&Grade&30
Step'1O3'as'above,'only'differs'in'unit'rate'due'to'thickness'of'bed
(4) Unit&rate&(RM/m2)
(Convert'cost'per'm3'to'm2) = RM227.95&x&0.175m&thk RM39.89 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/7
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)/2/G&*&L&:&&8MM&DIAMETER&HIGH&TENSILE&BAR&REINFORCEMENT
(1) Material&cost
8mm&diameter&high&tensile&rebar& = RM&2,800/tonne 2,800.00 /tonne
delivered&to&site
add:labour&unloading&&&stacking& = RM&5.00/tonne 5 /tonne
wastage&on&rebar&(7%) = RM&2,800&x&7% 196 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100kg&x1000kg&xRM4.50 29.7 /tonne
rolling&margin& = RM&22.00/&tonne 22 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4 /tonne
RM3,056.70 /tonne
(2) Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82/&8 10.25 /hr
1&labourer&@&RM&55/day = 55/&8 6.88 /hr
Gross&total 17.13 /hr
add:&idling&time&(10%) 1.71
Cost&of&labour& RM18.84 /hr
Time&analysis&per&100kg&(10mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
Cost&of&labour = 125&/&60&x&RM&18.84 39.25 /100&kg
RM392.50 /tonne
(3) Total&cost&including&profit&and&overhead
Total&rate&(RM/tonne)
Material&cost& = RM3,056.70 /tonne
Labour&cost
Concretor = RM392.50 /tonne
RM3,449.20 /tonne
(4) Unit&rate&(RM/kg)
Unit&rate& = RM3.80 /kg
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/8
MBina&Construction&Sdn&Bhd
B4(1)/2/C&*&F&:&10MM/12MM&DIAMETER&MILD&STEEL&REINFORCEMENT
(1) Material&cost
10mm/12mm&diameter&mild&steel&rebar&delivered&to&site
= RM&2,750/tonne 2,750.00 /tonne
add:labour&unloading&&&stacking& = RM&5.00/tonne 5 /tonne
wastage&on&rebar&(7%) = RM&2,750&x&7% 192.5 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100kg&x&1000kg&x&RM&4.50 29.7 /tonne
rolling&margin& = RM&22.00/&tonne 22 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4 /tonne
RM3,003.20 /tonne
(2) Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82/&8 10.25 /hr
1&labourer&@&RM&55/day = 55/&8 6.88 /hr
Gross&total 17.13 /hr
add:&idling&time&(10%) 1.71
Cost&of&labour& RM18.84 /hr
Time&analysis&per&100kg&(10mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
Cost&of&labour = 125&/&60&x&RM&18.84 39.25 /100&kg
RM392.50 /tonne
(3) Total&cost&including&profit&and&overhead
Total&rate&(RM/tonne)
Material&cost& = RM3,003.20 /tonne
Labour&cost
Concretor = RM392.50 /tonne
RM3,395.70 /tonne
(4) Unit&rate&(RM/kg)
Unit&rate& = RM3.74 /kg
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/9
MBina&Construction&Sdn&Bhd
B4(1)/2/G&*&L&:&&16MM&DIAMETER&HIGH&TENSILE&BAR&REINFORCEMENT
(1) MATERIAL&COST
16mm&diameter&high&tensile&rebar&delivered&to&site
= RM&2,600/tonne 2,600.00 /tonne
add:labour&unloading&&&stacking& = RM&5.00/tonne 5 /tonne
wastage&on&rebar&(7%) = RM&2,600&x&7% 182 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100kg&x&1000kg&x&RM&4.50 29.7 /tonne
rolling&margin& = RM&22.00/&tonne 22 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4 /tonne
RM2,842.70 /tonne
(2) LABOUR&COST
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82/&8 10.25 /hr
1&labourer&@&RM&55/day = 55/&8 6.88 /hr
Gross&total 17.13 /hr
add:&idling&time&(10%) 1.71
Cost&of&labour& RM18.84 /hr
Time&analysis&per&100kg&(10mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
Cost&of&labour = 125&/&60&x&RM&18.84 39.25 /100&kg
RM392.50 /tonne
(3) Total&cost&including&profit&and&overhead
Total&rate&(RM/tonne)
Material&cost& = RM2,842.70 /tonne
Labour&cost
Concretor = RM392.50 /tonne
RM3,235.20 /tonne
(4) Unit&rate&(RM/kg)
Unit&rate& = RM3.56 /kg
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/10
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&1&*&WORK&BELOW&LOWEST&FLOOR&LEVEL
B4(1)/2/M&:&A6:&2.61kg/m2&to&125mm&SLAB
(1)&MATERIAL&COST
A6:&2.61kg/m2&wire&mesh&delivered&to&site = RM&75.24&per&piece&/&(2.20m&x&6.0m) 5.70 /m2
add:wastage&(5%) = RM&5.70&x&5% 0.285 /m2
allow&spacers,&tie&wire&and&lapping&(5%) = RM&5.70&x&5% 0.285 /m2
RM6.27 /m2
(2) LABOUR&COST
Cost&of&gang&per&hour&
1&skilled&labour&@&RM&82/day = 82/&8 10.25 /hr
1&general&labour&@&RM&55/day = 55/&8 6.88 /hr
Gross&total 17.13 /hr
add:&idling&time&(10%) 1.71
Cost&of&labour& RM18.84 /hr
Time&required&per&m2&(Fabric&reinforcement) = 0.25&hr&/&100&sqft
= 0.25&hr&/&9.3m2
= 0.03&hr&/&m2
Cost&of&labour&per&m2 = Hourly&labour&cost&x&rate
= RM18.84&x&0.03hr/m2 RM0.57 /m2
(3) Total&cost&including&profit&and&overhead
Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity& = RM6.27&+&RM0.57 RM6.84
Add:&Profit&and&overhead&(10%) = RM6.84&x&10% RM2.99
TOTAL&COST RM9.83 /m2
(4) Unit&rate&(RM/kg)
Unit&rate& = RM9.83 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/11
MBina&Construction&Sdn&Bhd
B4(1)/2/N&:&A8:&3.01kg/m2&to&175mm&SLAB
(1)&MATERIAL&COST
A8:&3.01kg/m2&wire&mesh&delivered&to&site = RM&352.44&per&piece&/&(2.20m&x&6.0m) 26.70 /m2
add:wastage&(5%) = RM&26.70&x&5% 1.335 /m2
allow&spacers,&tie&wire&and&lapping&(5%) = RM&26.70&x&5% 1.335 /m2
RM29.37 /m2
(2) LABOUR&COST
Cost&of&gang&per&hour&
1&skilled&labour&@&RM&82/day = 82/&8 10.25 /hr
1&general&labour&@&RM&55/day = 55/&8 6.88 /hr
Gross&total 17.13 /hr
add:&idling&time&(10%) 1.71 /hr
Cost&of&labour& RM18.84 /hr
Time&required&per&m2&(Fabric&reinforcement) = 0.25&hr&/&100&sqft
= 0.25&hr&/&9.3m2
= 0.03&hr&/&m2
Cost&of&labour&per&m2 = Hourly&labour&cost&x&rate
= RM18.84&x&0.03hr/m2 RM0.57 /m2
(3) Total&cost&including&profit&and&overhead
Total&cost&=&total&rate&x&total&quantity& = RM29.37&+&RM0.57 RM29.94
Add:&Profit&and&overhead&(10%) = RM29.94&x&10% RM2.99
TOTAL&COST RM32.93 /m2
(4) Unit&rate&(RM/kg)
Unit&rate& = RM32.93 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(1)/12
!MBina!Construction!Sdn!Bhd
ELEMENT&NO.&2:&FRAME
Note:!Allow!10%!profit!and!overhead.
Concrete
1 ReadyRmixed!concrete!Grade!25 RM!190/m3
2 ReadyRmixed!concrete!Grade!30 RM!200/m3
3 Additional!labour!for!placing!of!concrete!into!beam 0.60hr/m3!@!RM3.50/hr
4 Additional!labour!working!around!reinforcement 0.55hr/m3!@!RM3.50/hr
5 Cost!of!vibrator RM!6.30/!1.50m3
Formwork
1 Plywood!WBP!4'!x!8'!x!12mm!5!ply!(2nd!grade) RM!36.50/pc
2 Allow!for!cutting!waste! 15%
3 0.03m3!of!struts!per!m2!for!the!beams RM!400.00/!m3
4 Allow!4!uses!for!timber!formwork:
5 Waste!on!each!use! 10%
6 Nails,!bolts!and!mould!oil! RM!1.50!per!m2
7 4!joiners!and!8!labourers!take!9.5!hours!to!erect!and!fixing!BEAM! Joiners!@!RM!78/!day
4!joiners!and!8!labourers!to!take!4!hours!to!erect!and!fixing!COLUMN! Labourer!@!RM!55/day
Reinforcement&
Mild!steel!reinforcement!bar:
1 8mm!diameter!bar!delivered!to!site! RM!2,800.00/!tonne
2 10mm!diameter!bar!delivered!to!site! RM!2,750.00/!tonne
High!tensile!reinforcement!bar:
3 10mm!diameter!bar!delivered!to!site! RM!2,750.00/!tonne
4 12mm!diameter!bar!delivered!to!site RM!2,750.00/!tonne
5 16mm!diameter!bar!delivered!to!site RM!2,600.00/!tonne
6 Allow!for!labour!stacking!&!loading! RM!5.00/!tonne
7 Allow!0.66kg!tie!wire!for!each!100kg!of!reinforcement!bar RM!4.50/kg
8 Allow!spacers!@!RM!4.00/!tonne!of!rebar
9 Allow!waste 7%
10 Allow!for!rolling!margin! RM!22.00/!tonne
Labour!cost:
11 Team!R!1!skilled!labourer!(barbender)!and!1!unskilled!labourer!
1!skilled!labour RM82/!day
1!unskilled!labour RM55/!day
12 Allow!idling!time! 10%
13 Time!analysis!for!100kg!of!reinforcement!bar!
Select 28!mins
Cut 32!mins
Bend 35!mins
Fix 23!mins!
Hoist!twice 7!mins
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_Frame
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&2:&CONCRETE&WORK&CALCULATION
B4(2)/1/A:&Concrete&for&beam
(1)&Material&cost RM
Concrete&Gr.25
1m3&of&readyOmixed&concrete&Grade&25 190.00 /m3
(2)&Labour&cost
Place&I&Labour&and&vibrator&
Additional&labour&placing&into&frame& = 0.60&x&RM&3.50 2.10
Additional&labour&working&around&rebar& = 0.55&x&RM&3.50 1.93
Cost&of&vibrator&per&m3&@&RM&6.30/1.50 = RM&6.30/&1.50 4.20
8.23 /m3
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m3)
Material&cost 190.00 /m3
Labour&cost 8.23 /m3
TOTAL&RATE 198.23 /m3
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 198.23&x&6 1,189.38
Add:&Profit&and&overhead&(10%) = 1,189.38&x&10% 118.94
TOTAL&COST 1,308.32
(4)&Unit&rate&(RM/m3)
Unit&rate&=&total&cost&/&total&quantity = 1,308.32/6 218.05 /m3
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/1
MBina&Construction&Sdn&Bhd
B4(2)/1/D:&8mm&diameter&mild&steel&reinforcement&
(1)&Material&cost RM
8mm&diameter&mild&steel&
8mm&diameter&mild&steel&rebar&delivered&to&site = RM&2,800/tonne 2,800.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,800&x&7% 196.00 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
3,056.70 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(8mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 3,056.70 /t
Labour&cost 392.50 /t
3,449.20 /t
Convert&the&rates&to&RM/kg = 3,449.20/1000
TOTAL&RATE 3.45 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.45&x&73 251.85
Add:&Profit&and&overhead&(10%) = 251.85&x&10% 25.19
TOTAL&COST 277.04
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/2
MBina&Construction&Sdn&Bhd
B4(2)/1/E:&10mm&diameter&mild&steel&reinforcement&
(1)&Material&cost RM
10mm&diameter&mild&steel&
10mm&diameter&mild&steel&rebar&delivered&to&site = RM&2,750/tonne 2,750.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,750&x&7% 192.50 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
3,003.20 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(10mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 3,003.20 /t
Labour&cost 392.50 /t
3,395.70 /t
Convert&the&rates&to&RM/kg = 3,395.70/1000
TOTAL&RATE 3.40 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.40&x&100 340.00
Add:&Profit&and&overhead&(10%) = 340.00&x&10% 34.00
TOTAL&COST 374.00
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/3
MBina&Construction&Sdn&Bhd
B4(2)/1/H:&10mm&diameter&high&tensile&reinforcement&
(1)&Material&cost RM
10mm&diameter&high&tensile
10mm&diameter&high&tensile&rebar&delivered&to&site = RM&2,750/tonne 2,750.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,750&x&7% 192.50 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
3,003.20 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(10mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 3,003.20 /t
Labour&cost 392.50 /t
3,395.70 /t
Convert&the&rates&to&RM/kg = 3,395.70/1000
TOTAL&RATE 3.40 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.40&x&250 850.00
Add:&Profit&and&overhead&(10%) = 850.00&x&10% 85.00
TOTAL&COST 935.00
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/4
MBina&Construction&Sdn&Bhd
B4(2)/1/I:&12mm&diameter&high&tensile&reinforcement&
(1)&Material&cost RM
12mm&diameter&high&tensile
12mm&diameter&high&tensile&rebar&delivered&to&site = RM&2,750/tonne 2,750.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,750&x&7% 192.50 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
3,003.20 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(12mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 3,003.20 /t
Labour&cost 392.50 /t
3,395.70 /t
Convert&the&rates&to&RM/kg = 3,395.70/1000
TOTAL&RATE 3.40 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.40&x&270 918.00
Add:&Profit&and&overhead&(10%) = 918.00&x&10% 91.80
TOTAL&COST 1,009.80
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/5
MBina&Construction&Sdn&Bhd
B4(2)/1/K&:&FORMWORK&FOR&BEAM
1)&Material&cost
1m2&of&12mm&sawn&formwork& = RM&36.50&/&(1.22&x&2.44) 12.26 /m2
4'&x&8'&x&12mm&@&RM&36.50/pc
Allow&allowance&for&cutting&(15%) = RM&12.26&x&15% 1.84 /m2
For&sides&of&ground&beam&0.03m3&of&struts&required = RM&400.00/&m3&x&0.03m3 12.00 /m2
Cost&of&timber 26.10 /m2
Allowing&4&uses&cost&per&use& = RM&26.10/&4& 6.53 /m2
Allow&waste&on&each&use&(10%) = RM&6.53&x&10% 0.65 /m2
Nails,&bolts&and&mould&oil&@&RM&1.50/&m2 = RM&1.50 1.50 /m2
Cost&of&reuse&formwork 8.68 /m2
(2)&Labour&cost
Cost&of&gang&per&hour&
1&carpenter&@&RM&78/day = 78/8 9.75 /hr
1&labourer&@&RM&55/day = 55/8 6.88 /hr
One&gang&consists&of&4&joiners&assisted&by&8&labourers&required&9.5&hours&to&erect&and&dismantle&
all&formwork&to&beam
All&formworks&
9.5&hours&are&required&to&fix&and&dismantle&63.00m2&formwork&
Therefore&1&m2&requires&0.15&hr = 9.5/&63.00&m2 0.15&hr /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost 8.68 /m2
Labour&cost 14.11 /m2
TOTAL&RATE 22.79 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 22.79&x&63 1,435.77
Add:&Profit&and&overhead&(10%) = 1,435.77&x&10% 143.58
TOTAL&COST 1,579.35
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/6
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&2:&CONCRETE&WORK&CALCULATION
B4(2)/1/B:&Concrete&for&column
(1)&Material&cost RM
Concrete&Gr.30
1m3&of&readyOmixed&concrete&Grade&25 200.00 /m3
(2)&Labour&cost
Place&I&Labour&and&vibrator&
Additional&labour&placing&into&frame& = 0.60&x&RM&3.50 2.10
Additional&labour&working&around&rebar& = 0.55&x&RM&3.50 1.93
Cost&of&vibrator&per&m3&@&RM&6.30/1.50 = RM&6.30/&1.50 4.20
8.23 /m3
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m3)
Material&cost 200.00 /m3
Labour&cost 8.23 /m3
TOTAL&RATE 208.23 /m3
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 208.23&x&2 416.46
Add:&Profit&and&overhead&(10%) = 416.46&x&10% 41.65
TOTAL&COST 458.11
(4)&Unit&rate&(RM/m3)
Unit&rate&=&total&cost&/&total&quantity = 458.11/2 229.05 /m3
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/7
MBina&Construction&Sdn&Bhd
B4(2)/1/C:&8mm&diameter&mild&steel&reinforcement&
(1)&Material&cost RM
8mm&diameter&mild&steel&
8mm&diameter&mild&steel&rebar&delivered&to&site = RM&2,800/tonne 2,800.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,800&x&7% 196.00 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
3,056.70 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(8mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 3,056.70 /t
Labour&cost 392.50 /t
3,449.20 /t
Convert&the&rates&to&RM/kg = 3,449.20/1000
TOTAL&RATE 3.45 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.45&x&76 262.20
Add:&Profit&and&overhead&(10%) = 262.20&x&10% 26.22
TOTAL&COST 288.42
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/8
MBina&Construction&Sdn&Bhd
B4(2)/1/F:&12mm&diameter&high&tensile&reinforcement&
(1)&Material&cost RM
12mm&diameter&high&tensile
12mm&diameter&high&tensile&rebar&delivered&to&site = RM&2,750/tonne 2,750.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,750&x&7% 192.50 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
3,003.20 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(12mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 3,003.20 /t
Labour&cost 392.50 /t
3,395.70 /t
Convert&the&rates&to&RM/kg = 3,395.70/1000
TOTAL&RATE 3.40 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.40&x&208 707.20
Add:&Profit&and&overhead&(10%) = 707.20&x&10% 70.72
TOTAL&COST 777.92
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/9
MBina&Construction&Sdn&Bhd
B4(2)/1/G:&16mm&diameter&high&tensile&reinforcement&
(1)&Material&cost RM
16mm&diameter&high&tensile
16mm&diameter&high&tensile&rebar&delivered&to&site = RM&2,600/tonne 2,600.00 /tonne
labour&unloading&&&stacking& = RM&5.00/tonne 5.00 /tonne
wastage&on&rebar&(7%) = RM&2,600&x&7% 182.00 /tonne
tie&wire&0.66kg/100kg&@&RM&4.50/kg = 0.66/100x1000xRM&4.50 29.70 /tonne
rolling&margin& = RM&22.00/&tonne 22.00 /tonne
Allow&spacers&at&RM&4.00&per&tonne&of&rebar = RM&4.00/&tonne 4.00 /tonne
2,842.70 /tonne
(2)&Labour&cost
Cost&of&gang&per&hour&
1&barbender&@&RM&82/day = 82&/&8 10.25 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
17.13 /hr
add:&idling&time&(10%) 1.71
18.84 /hr
Time&analysis&per&100kg&(10mm&dia.reinforcement)
Select = 28&mins
Cut = 32&mins
Bend = 35&mins
Fix = 23&mins
Hoist&twice& = 7&mins
125&mins
= 125&/&60&x&RM&18.84 39.25 /100kg
392.50 /tonne
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/kg)
Material&cost 2,842.70 /t
Labour&cost 392.50 /t
3,235.20 /t
Convert&the&rates&to&RM/kg = 3,235.20&/1000
TOTAL&RATE 3.24 /kg
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.24&x&222 719.28
Add:&Profit&and&overhead&(10%) = 719.28&x&10% 71.93
TOTAL&COST 791.21
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/10
MBina&Construction&Sdn&Bhd
B4(2)/1/J&:&FORMWORK&FOR&COLUMN
1)&Material&cost
1m2&of&12mm&sawn&formwork& = RM&36.50&/&(1.22&x&2.44) 12.26 /m2
4'&x&8'&x&12mm&@&RM&36.50/pc
Allow&allowance&for&cutting&(15%) = RM&12.26&x&15% 1.84 /m2
For&sides&of&ground&beam&0.03m3&of&struts&required = RM&400.00/&m3&x&0.03m3 12.00 /m2
Cost&of&timber 26.10 /m2
Allowing&4&uses&cost&per&use& = RM&26.10/&4& 6.53 /m2
Allow&waste&on&each&use&(10%) = RM&6.53&x&10% 0.65 /m2
Nails,&bolts&and&mould&oil&@&RM&1.50/&m2 = RM&1.50 1.50 /m2
Cost&of&reuse&formwork 8.68 /m2
(2)&Labour&cost
Cost&of&gang&per&hour&
1&carpenter&@&RM&78/day = 78/8 9.75 /hr
1&labourer&@&RM&55/day = 55/8 6.88 /hr
One&gang&consists&of&4&joiners&assisted&by&8&labourers&required&4&hours&to&erect&and&dismantle&
all&formwork&to&column
All&formworks&
4&hours&are&required&to&fix&and&dismantle&27.00m2&formwork&
Therefore&1&m2&requires&0.15&hr = 4/&27.00&m2 0.15&hr /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost 8.68 /m2
Labour&cost 14.11 /m2
TOTAL&RATE 22.79 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 22.79&x&27 615.33
Add:&Profit&and&overhead&(10%) = 615.33&X&10% 61.53
TOTAL&COST 676.86
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(Frame)/11
MBina Construction Sdn Bhd
Roof Frame
Material Cost
1 1m3 of timber roof beam including load and stancked on site RM 3360/m3
2 1m3 of timber roof trusses and frame including load and stancked RM 3281/m3
on site
3 1m3 of timber purlin including load and stancked on site RM 3159/m3
4 1m3 of timber fascia board including load and stancked on site RM 3937/m3
5 1m3 of timber battens including load and stancked on site RM 3454/m3
6 Allow cutting wastage 10%
7 Nails required for general construction work 1.5kg/m3 RM 5.00/kg
8 Transportation costs are included in all material cost stated above.
Labour Cost
11 1 gang of carpenter consist of 2 carpenters and 1 unskilled 8 hours/day
labourer.
12 1 carpenter RM90/day
13 1 unskilled labour RM 55/day
Labourer output
14 Output of 1 gang of carpenters including cutting to length, setting 20 hours
out and fixing 1 m3 of timber in roof
15 Scaffolding - unnecessary (3m high can easily reach using stool or
ladder)
Rainwater Goods
Material Cost
1 We proposed to use 420mm x 330mm interlocking coloured roof RM 2.00/pcs
tiles to replace 380mm x 230mm roof tiles.
2 We proposed to use 420mm x 250mm coloured concrete ridge tiles RM 5.00/pcs
to replace 200mm x 200mm ridge tiles.
3 1 No. of Eaves cap (420mm x 250mm) RM 13.00/pcs
4 Wastage for broken tiles 3%
5 Nails (500 nos per bucket) RM 25/bucket
6 Wastage for nails 20%
7 Transportation costs are included in all material cost stated above.
Labour Cost
8 1 gang of roofer consist of 2 roofers and 2 unskilled labourer for 8 hours/day
concrete roof tiles
9 1 gang of roofer consist of 1 roofer and 1 unskilled labourer for 8 hours/day
ridge tiles, hip starter, gutter and flashing
10 1 Roofer RM 83/day
11 1 unskilled labour RM 55/day
Output Data
12 Time required to unload 1000 pieces of tile 15 minutes
13 Time required to lay 1000 pieces of tile 6 hours
14 Time required to fix every 10m of eaves cap 1 hour
15 Time required to fix every 8 meters of half round gutter 1 hour
16 Time required to fix every 8 meters of flashing 1 hour
Tools Cost
17 Allow material cost for small tools (material cost includes roof tiles, 3%
nails and wastage)
18 Scaffolding - unnecessary (3m high can easily reach using stool or
ladder)
ROOF FRAME
B4(3)/1/A: 125mmx250mm ROOF BEAM
Labour cost
Time required to set 1m3 x hourly rate = 20 x 29.38 587.60 RM/m3
b. Total quantity
125 x 250mm x 161 m = (0.125 x 0.25 x 161) 5.031 m3
c. Total Cost
Total cost = qty (m3) x rate (RM/m3) = 5.031 x 4291.10 21588.52
Add: profit and overhead (10%) = 21588.52 x 0.10 2,158.85
TOTAL COST 23,747.37
Labour cost
Time required to set 1m3 x hourly rate = 20 x 29.38 587.60 RM/m3
b. Total quantity
100 x 200mm x 238m = (0.10 x 0.20 x 238) 4.76 m3
c. Total Cost
Total cost = qty (m3) x rate (RM/m3) = 4.76 x 4204.20 20,011.99
Add: profit and overhead (10%) = 20011.99 x 0.10 2,001.20
TOTAL COST 22,013.19
Labour cost
Time required to set 1m3 x hourly rate = 20 x 29.38 587.60 RM/m3
b. Total quantity
90 x 75mm x 225m = (0.09 x 0.075 x 225) 1.52 m3
c. Total Cost
Total cost = qty (m3) x rate (RM/m3) = 1.52 x 4070.00 6,186.40
Add: profit and overhead (10%) = 6186.40 x 0.10 618.64
TOTAL COST 6,805.04
Labour cost
Time required to set 1m3 x hourly rate = 20 x 29.38 587.60 RM/m3
b. Total quantity
150 x 25mm x 46m = (0.150 x 0.025 x 46) 0.17 m3
c. Total Cost
Total cost = qty (m3) x rate (RM/m3) = 0.17 x 4925.80 837.39
Add: profit and overhead (10%) = 837.39 x 0.10 83.74
TOTAL COST 921.13
Labour cost
Time required to set 1m3 x hourly rate = 20 x 29.38 587.60 RM/m3
b. Total quantity
38 x 75mm x 672m = (0.038 x 0.075 x 672) 1.92 m3
c. Total Cost
Total cost = qty (m3) x rate (RM/m3) = 1.92 x 4394.50 8,437.44
Add: profit and overhead (10%) = 8437.44 x 0.10 843.74
TOTAL COST 9,281.18
RAINWATER GOODS
B4(3)/1/F COLOURED INTERLOCKING CONCRETE ROOF TILES
b. Time analysis
Unload 1000 pieces of tiles = 15/60 (minutes) 0.25 hr
Lay 1000 pieces of tiles = 6.00 hr
6.25 hr
b. Time analysis
Unload 1000 pieces of tiles = 15/60 (minutes) 0.25 hr
Lay 1000 pieces of tiles = 6.00 hr
6.25 hr
b. Time analysis
Unload 1000 pieces of tiles = 15/60 (minutes) 0.25 hr
Lay 1000 pieces of tiles = 6.00 hr
6.25 hr
b. Time analysis
1 hour for every 8 m of half round gutter
Time required to fix 28 m gutter = 28/8 3.50 hr
Labour cost to fix 28m = 3.5 x 17.26 60.41
B4(3)/1/J FLASHING
b. Time analysis
1 hour for every 8 m of flashing
Time required to fix 56 m flashing = 56/8 7.00 hr
Labour cost to fix 56m = 7.0 x 17.26 120.82
ELEMENT&NO.&4:&EXTERNAL&BRICKWALL&DATA
Note:!Allow!10%!profit!and!overhead.
Brickwall
1 1m2!Half!brick!thick!wall!requires!59!pieces!of!bricks
2 1m2!One!brick!thick!requires!118!pieces!of!bricks
3 Material!cost!for!cement!and!sand!bricks RM120/600pcs
4 Allow!wastage!for!bricks 5%
5 1m2!Half!brick!thick!wall!requires!0.07m3!mortar
6 1m2!One!brick!thick!wall!requires!0.15m3!mortar
7 Material!cost!for!Ordinary!Portland!Cement!including!unloading! RM14/50kg
8 Material!cost!for!Sand!including!unloading RM35/tonne
9 1m3!of!OPC!=!1420kg
10 1m3!of!Sand!=!1600kg
11 Allow!shrinkage!and!wastage!for!mortar 33.33%
12 Material!cost!for!Exmet! RM5/roll!@!36m
13 Allow!for!wastage!and!overlap!for!Exmet 5%
14 Assume!brickwall!is!3m!high
15 1!gang!of!bricklayers!consist!of!1!bricklayer!and!1!unskilled!labour! 8!hours/day
16 1!bricklayer RM75/day
17 1!unskilled!labour RM55/day
18 Output!of!1!gang!of!bricklayers!including!fixing!Exmet,!DPC!&!Bonding! 120pc/hr
Ties!
DPC
1 Material!cost!for!115mm!wide!DPC RM31/roll!@!53m
2 Material!cost!for!225mm!wide!DPC RM31/roll!@!27m
3 Allow!for!wastage!for!DPC 5%
4 Allow!for!overlapping!for!DPC 15%
Bonding&Ties
1 Material!cost!for!6mm!Diameter!M.S.!Bonding!Ties RM9.50/12m
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_External!walls
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&4:&EXTERNAL&BRICKWALL&CALCULATION
B4(4)/1/A:&HALF&BRICKWALL
(1)&Material&cost RM
Cement&and&Sand&Brick
Cement&and&sand&brick:
RM&120/600&pcs = 120&/&600 0.20 /pcs
1m2&Half&brick&thick&wall&requires&59&pieces&of&bricks
RM&0.20/pc&x&59&pcs = 0.20&x&59 11.80 /m2
Cement&Mortar&Mix&(1:6)
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50&x&14 397.60 /m3
Sand&including&unloading:&
6m3&at&1600kg/m3&at&RM35/tonne = 6&x&1600&/&1000&x&35 336.00 /6m3
Gross&total 733.60 /7m3
Allow&shrinkage&for&mortar&(33.33%) = 733.60&x&33.33% 244.51
1m2&Half&brick&thick&wall&requires&0.07m3&of
mortar&@&RM&139.73 = 0.07&x&139.73 9.78 /m2
Exmet
36m&long,&64mm&wide&coil&of&Exmet&
RM&5/roll&@&36m& = 5&/&36 0.14 /m
Quantity&of&Exmet&required&to&be&placed&at&every&4th&course&of&3m&high&wall
3m&high&/&((0.065m&+&0.010m&)&x&4)& = 3&/&((0.065+0.010)&x&4) 10.00 nos.
Assume&brickwall&is&3m&high.
Total&girth&of&half&brickwall:
55m2&brickwall&/&3m&high& = 55&/&3 18.33 m
18.33m&long&wall&(Half&brick&thick&wall)
18.33m&long&&x&10&nos.&x&RM0.14/m = 18.33&x&10&x&0.14 25.46
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III/(4)/1
MBina&Construction&Sdn&Bhd
(2)&Labour&cost RM
Cost&of&gang&per&hour&
1&bricklayer&@&RM&75/day = 75&/&8 9.38 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
16.25 /hr
1&gang&can&lay&120&bricks&per&hours&including&bonding&ties,&exmet&and&dpc
Cost&of&laying&59&bricks&(1m2)&
RM&16.25&/&120&x&59 = 16.25&x&120&/&59 7.99 /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Cement&and&sand&bricks 12.39 /m2
Cement&mortar&mix&(1:6) 9.78 /m2
Exmet 0.49 /m2
22.66 /m2
Labour&cost
Bricklayer 7.99 /m2
TOTAL&RATE 30.65 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 30.65&x&55 1685.57
Add:&Profit&and&overhead&(10%) = 1685.57&x&10% 168.56
TOTAL&COST 1854.13
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 1854.13&/&55 33.71 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III/(4)/2
MBina&Construction&Sdn&Bhd
B4(4)/1/B:&ONE&BRICKWALL
(1)&Material&cost RM
Cement&and&Sand&Brick
Cement&and&sand&brick:
RM&120/600&pcs = 120&/&600 0.20 /pcs
1m2&Half&brick&thick&wall&requires&118&pieces&of&bricks
RM&0.20/pc&x&118&pcs = 0.20&x&118 23.60 /m2
Cement&Mortar&Mix&(1:6)
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50&x&14 397.60 /m3
Sand&including&unloading:&
6m3&at&1600kg/m3&at&RM35/tonne = 6&x&1600&/&1000&x&35 336.00 /6m3
Gross&total 733.60 /7m3
Allow&shrinkage&for&mortar&(33.33%) = 733.60&x&33.33% 244.51
1m2&One&brick&thick&wall&requires&0.15m3&of
mortar&@&RM&139.73 = 0.15&x&139.73 20.96 /m2
Exmet
36m&long,&64mm&wide&coil&of&Exmet&
RM&5/roll&@&36m& = 5&/&36 0.14 /m
Quantity&of&Exmet&required&to&be&placed&at&every&4th&course&of&3m&high&wall
3m&high&/&((0.065m&+&0.010m&)&x&4)& = 3&/&((0.065+0.010)&x&4) 10.00 nos.
Assume&brickwall&is&3m&high.
Total&girth&of&one&brickwall:
46m2&brickwall&/&3m&high& = 46&/&3 15.33 m
15.33m&long&wall&(One&brick&thick&wall)
15.33m&long&&x&10&nos.&x&RM0.14/m = 15.33&x&10&x&0.14 21.30
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III/(4)/3
MBina&Construction&Sdn&Bhd
(2)&Labour&cost RM
Cost&of&gang&per&hour&
1&bricklayer&@&RM&75/day = 75&/&8 9.38 /hr
1&unskilled&labour&@&RM&55/day = 55&/&8 6.88 /hr
16.26 /hr
1&gang&can&lay&120&bricks&per&hours&including&bonding&ties,&exmet&and&dpc
Cost&of&laying&118&bricks&(1m2)&
RM&16.26&/&120&x&118 = 16.25&x&120&/&118 15.99 /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Cement&and&sand&bricks 24.78 /m2
Cement&mortar&mix&(1:3) 20.96 /m2
Exmet 0.49 /m2
46.23 /m2
Labour&cost
Bricklayer 15.99 /m2
TOTAL&RATE 62.22 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 62.22&x&46 2862.12
Add:&Profit&and&overhead&(10%) = 2862.12&x&10% 286.21
TOTAL&COST 3148.33
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 3148.33&/&46 68.44 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III/(4)/4
MBina&Construction&Sdn&Bhd
B4(4)1/C:&115mm&DPC
(1)&Material&cost RM
115mm&wide&DPC&for&half&brick&thick&wall
RM&31/roll&@&53m = 31&/&53 0.58 /m
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost TOTAL&RATE 0.70 /m
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 0.70&x&24 16.80
Add:&Profit&and&overhead&(10%) = 16.80&x&10% 1.68
TOTAL&COST 18.48
(4)&Unit&rate&(RM/m)
Unit&rate&=&total&cost&/&total&quantity = 18.48&/&24 0.77 /m
B4(4)/1/D:&225mm&DPC
(1)&Material&cost
225mm&wide&DPC&for&half&brick&thick&wall
RM&31/roll&@&27m = 31&/&27 1.15 /m
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost TOTAL&RATE 1.38 /m
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 1.38&x&22 30.36
Add:&Profit&and&overhead&(10%) = 30.36&x&10% 3.04
TOTAL&COST 33.40
(4)&Unit&rate&(RM/m)
Unit&rate&=&total&cost&/&total&quantity = 33.40&/&22 1.52 /m
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III/(4)/5
MBina&Construction&Sdn&Bhd
B4(4)/1/E:&Bonding&Ties
(1)&Material&cost RM
6mm&Diameter&at&450mm&girth
RM&9.50/roll&@&12m& = 9.50&/&12 0.79 /m
450mm&girth = 0.79&x&0.450 0.36 /pc
(2)&Labour&cost
Included&in&brickwork&labour.&
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/nos.)
Material&cost TOTAL&RATE 0.36 /pc
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 0.36&x&160 58.32
Add:&Profit&and&overhead&(10%) = 58.32&x&10% 5.83
TOTAL&COST 64.15
(4)&Unit&rate&(RM/nos.)
Unit&rate&=&total&cost&/&total&quantity = 64.15&/&162 0.40 /nos
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III/(4)/6
MBina Construction Sdn Bhd
Brickwall
1 1m2 Half brick thick wall requires 59 pieces of bricks
2 Material cost for cement and sand bricks RM120/600pcs
3 Allow wastage for bricks 5%
4 2 3
1m Half brick thick wall requires 0.07m mortar
5 Material cost for Ordinary Portland Cement including unloading RM14/50kg
6 Material cost for Sand including unloading RM35/tonne
3
7 1m of OPC = 1420kg
3
8 1m of Sand = 1600kg
9 Allow shrinkage and wastage for mortar 33.33%
DPC
1 Material cost for 115mm wide DPC RM31/roll @ 53m
2 Allow for wastage for DPC 5%
3 Allow for overlapping for DPC 15%
Bonding Ties
1 Material cost for 6mm Diameter M.S. Bonding Ties RM9.50/12m
2 3
1m Half brick thick wall requires 0.07m of
mortar @ RM 188.53 = 0.07 x 188.53 13.20 /m2
Exmet
36m long, 64mm wide coil of Exmet
RM 5/roll @ 36m = 5 / 36 0.14 /m
Reinforcement Bar
5 6mm diameter mild steel bar delivered to site RM2650/tonne
6 Allow for labour stacking & loading RM 5.00/ tonne
7 Allow 0.66kg tie wire for each 100kg of reinforcement bar RM 4.50/kg
8 Allow spacers @ RM 4.00/ tonne of rebar
9 Allow waste 7%
10 Allow for rolling margin RM 22.00/ tonne
11 1 barbender is required RM82/day
13 Allow idling time 10%
Time analysis for 100kg of reinforcement bar :
14 Select 28 mins
15 Cut 32 mins
16 Bend 35 mins
17 Fix 23 mins
18 Hoist twice 7 mins
Formwork
19 Formwork RM16/m2
20 Cutting waste 15%
21 0.03m3 of struts per m2 for the lintols RM400/m3
22 Allow 4 uses for timber formwork
23 Waste on each use 10%
24 Nails, bolts and mould oil RM1.50 per m2
25 1 joiner takes 0.5 hours to erect and fixing all formworks RM78/day
Door Frame
1 900mm x 2400mm x 1.2mm thick electro galvanized metal door
frame RM86/no
2 800mm x 2100mm x 1.2mm thick electro galvanized metal door
frame RM77/no
3 Daily rate for one joiner (8 hours/day) RM90/day
4 Framing a door 3mins/m
5 Hanging a door 3mins/m
6 Screwing bolts and nuts 2mins/m
7 Fixing door frame 2mins/m
8 Allow material cost 5%
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_Door & Ironmongery
MBina Construction Sdn Bhd
Door Leaf
1 900mm x 2400mm x 38mm thick flush door with laminated RM280/no
2 800mm x 2100mm x 38mm thick flush door with laminated RM140/no
3 Daily rate for one joiner (8 hours/day) RM90/day
4 Framing a door 7mins/no
5 Hanging a door 7mins/no
6 Mortising the door for hinges 10mins/no
7 Install cylinder lock 6mins/no
8 Allow for tools 5%
Ironmongeries
1 Solid stainless steel leve handle, mortise lock complete with 6pin
thumbturn cylinder RM35/no
2 102mm x 76mm x 2.0mm thick stainless steel butt hinges RM6.50/no
3 Daily rate for one joiner (8 hours/day) RM90/day
4 Handling for steel butt hinges 6mins/no
5 Fastening bolts and nuts for hinges 6mins/no
6 Handling all ironmongeries 6mins/no
7 Fixing the ironmongeries 6mins/no
8 Allow for tools 5%
Painting
1 One Dulux Maxilite Plus undercoat RM35/7L
2 Two Dulux Gloss Finish finishing coats RM116/5L
3 One undercoast apply on wood surfaces 9.52L/100m2
4 Two finishing coats apply on wood surfaces 5.88L/100m2
5 Allow for wastage 5%
6 Painter rate (8 hours/day) RM76/day
7 Paint undercoat on wood surface 2.5hours/100m2
8 Paint finishing coats on wood surface 2hours/100m2
9 Allow for tools 5%
Door Roller
1 3500mm x 2000mm colourbond roller door RM1400/no
2 Daily rate for one joiner (8 hours/day) RM90/day
3 Handling the roller door 7mins/no
4 Connector roller door 9mins/no
5 Fastened the bolts and nuts 7mins/no
6 Fixing roller door 7mins/no
7 Allow for tools and ladder 5%
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_Door & Ironmongery
MBina Construction Sdn Bhd
REINFORCED CONCRETE
(1) Material cost RM
Concrete Gr.25
1m3 of pre-mixed concrete Grade 25 190.00 /m3
REINFORCEMENT BAR
(1) Material cost
6mm Diameter mild steel
6mm diamter mild steel rebar delivered to site = RM2650/tonne 2,650.00 /tonne
Add:labour unloading & stacking = RM 5.00/tonne 5.00 /tonne
wastage on rebar (7%) = RM 2,650 x 7% 185.50 /tonne
tie wire 0.66kg/100kg @ RM4.50/kg = 0.66/100kg x 1000kg x RM 4.50
29.70 /tonne
rolling margin = RM 22.00/ tonne 22.00 /tonne
Allow spacers at Rm4.00 per tonne of rebar RM 4.00/ tonne 4.00 /tonne
2896.20 /tonne
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/1
MBina Construction Sdn Bhd
FORMWORK
(1) Material cost
1m2 of 12mm sawn formwork
4' x 8' x 12mm @ RM 36.50/pc = RM 36.50 / (1.22 x 2.44) 12.26 /m2
Allow allowance for cutting (15%) = RM 12.26 x 15% 1.84 /m2
For sides of lintol 0.03m3 of struts required = RM 400.00/ m3 x 0.03m3 12.00 /m2
Cost of timber 26.10 /m2
Allowing 4 uses cost per use = RM 26.10/ 4 6.53 /m2
Allow waste on each use (10%) = RM 6.53 x 10% 0.65 /m2
Nails, bolts and mould oil @ RM 1.50/ m2 = RM1.50 1.50 /m2
Cost of reuse formwork 8.68 /m2
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/2
MBina Construction Sdn Bhd
SUMMARY
Unit rate for precast concrete lintel
Concrete + reinforcement + formwork = 6.14 + 0.77 + 6.42 13.33 /m
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/3
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/4
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/5
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/6
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/7
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/8
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/9
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/10
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/11
MBina Construction Sdn Bhd
Estimating (QSB 60504) Coursework 2: Project Tendering Appendix III_(6) Door & Ironmon/12
!MBina!Construction!Sdn!Bhd
ELEMENT&NO.&7:&INTERNAL&WALL&FINISHES&DATA
Note:!Allow!10%!profit!and!overhead.
Cement&and&sand&(1:4)&backings
1 1m3!of!OPC!=!1420kg
2 1m3!of!Sand!=!1600kg
3 Material!cost!for!Ordinary!Portland!Cement!including!unloading! RM14/50kg
4 Material!cost!for!Sand!including!unloading RM35/tonne
5 Allow!shrinkage!and!wastage!for!mortar 33.33%
Ceramic&tiles
6 Size!of!ceramic!tiles!=!200mm!x!300mm!x!7mm!thick
7 Material!cost!for!200mm!x!300mm!x!7mm!thick!ceramic!tiles RM2.30/!piece
8 Allow!wastage!for!tiles 10%
9 Assume!material!cost!for!white!cement!mortar RM2/!m2
10 1!gang!consists!of!1!unskilled!labour!and!1!tiler! 8!hours/day
11 1!unskilled!labour RM55/day
12 1!tiler RM96/day
13 To!mix!1m3!of!cement!mortar!requires!1!hour
14 To!lay!1m2!of!ceramic!tiles!requires!2.5!hours
15 To!do!1m2!of!pointing!requires!1!hour
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_Int.!Wall!Finishes
!MBina!Construction!Sdn!Bhd
ELEMENT&NO.&7:&INTERNAL&WALL&FINISHES&DATA
Note:!Allow!10%!profit!and!overhead.
Cement&and&sand&(1:4)&+&plastering
1 1m3!of!OPC!=!1420kg
2 1m3!of!Sand!=!1600kg
3 Material!cost!for!Ordinary!Portland!Cement!including!unloading! RM14/50kg
4 Material!cost!for!Sand!including!unloading RM35/tonne
5 Allow!shrinkage!and!wastage!for!mortar 33.33%
6 Plasticizer!used!=!0.10kg/!50kg!of!cement RM10/!1kg
7 1!gang!consists!of!2!skilled!labours!and!1!unskilled!labour 8hours/!day
8 1!skilled!labour RM87/!day
9 1!unskilled!labour RM55/!day
10 Coverage!for!20mm!thick!plaster!=!75m2!per!1000kg
Assume!1000kg!refers!to!cement!only
11 To!deliver!and!stack!cement!@!20!numbers!of!50kg!bag!per
hour
12 To!mix!and!apply!100m2!requires!18!hours
Painting
1 One!coat!of!Dulux!Interior!Basecoat!Sealer!at!plaster!surfaces!@!10! RM135.00/!18!litres
litres!per!100m2
2 Two!finishing!coats!of!Dulux!ICI!Maxilite!Trade!Emulsion!paint!at! RM65.00/!18!litres
plaster!surfaces!@!9.52!litres!per!100m2
3 Allow!wastage!for!all!works 5.00%
4 1!painter!(8hours/!day) RM76/!day
5 One!coat!of!basecoat!sealer!at!plaster!surfaces! 6.6!hour!per!100m2
6 Two!finishing!coats!of!emulsion!paint!at!plaster!surfaces 4.5!hour!per!100m2
7 Allow!of!material!cost!for!paint!brush,!accessories!and!other!small! 5%
tools
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_Int.!Wall!Finishes
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&7:&INTERNAL&WALL&FINISHES&CALCULATION
B4(7)/1/A:&BACKINGS
(1)&Material&cost RM
Cement&and&Sand&(1:4)&Backings
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50&x&14 397.60 /m3
Sand&including&unloading:&
4m3&at&1600kg/m3&at&RM35/tonne = 4&x&1600&/&1000&x&35 224.00 /4m3
Gross&total 621.60 /5m3
Allow&shrinkage&and&wastage&for&mortar(33.33%) = 621.60&x&33.33% 207.18
(2)&Labour&cost
Included(in(tiles(labour
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Cement&and&sand&(1:4)&backings = 3.32 /m2
TOTAL&RATE 3.32 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.32&x&95 315.40
Add:&Profit&and&overhead&(10%) = 315.40&x&10% 31.54
TOTAL&COST 346.94
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 346.94&/&95 3.65 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(7)/1
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&7:&INTERNAL&WALL&FINISHES&CALCULATION
B4(7)/1/C:&TILES&FINISHING
(1)&Material&cost RM
Ceramic&Tiles
Number&of&tiles&per&m2 = 1/&(0.20&x&0.30) 17.00 piece
Gross&cost&per&m2&@&RM2.30/&piece = 17&x&2.30 39.10 /m2
(2)&Labour&cost
1&gang&of&labour&consists&of&1&unskilled&labour&and&1&tiler
To&mix&cement&mortar
Unskilled&labour&@&RM55/&day = 55/8 6.88 /hr
Cost&to&mix&1m2 = 6.88&x&1&x&0.020 0.14 /m2
To&lay&ceramic&tiles&and&pointing
Tiler&@&RM96/&day = 96/8 12.00 /hr
Cost&to&lay&and&point&1m2 = 12&x&(2.5&+&1) 42.00 /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Ceramic&tiles = 43.01
White&cement&mortar = 2.00
Labour&cost = 42.14
TOTAL&RATE 87.15 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 87.15&x&95 8279.25
Add:&Profit&and&overhead&(10%) = 8,279.25&x&10% 827.93
TOTAL&COST 9107.18
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 9,107.18&/&95 95.87 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(7)/2
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&7:&INTERNAL&WALL&FINISHES&CALCULATION
B4(7)/1/B:&INSITU&FINISHING
(1)&Material&cost RM
Cement&and&Sand&(1:4)&+&Plasticizer
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50&x&14 397.60 /m3
Sand&including&unloading:&
4m3&at&1600kg/m3&at&RM35/tonne = 4&x&1600&/&1000&x&35 224.00 /4m3
Gross&total 621.60 /5m3
(2)&Labour&cost
1&gang&of&labour&consists&of&2&skilled&labour
and&1&unskilled&labour
2&skilled&labour&@&RM87/&person/&day = 87/&8&x&2 21.75 /hour
1&skilled&labour&@&RM55/&person/&day = 55/8&x&1 6.88 /hour
Labour&gang&hourly&rate 28.63 /hour
Coverage&for&20mm&thick&plaster&=&75m2&per&1000kg
Assume&1000kg&refers&to&cement&only
Cement&per&1m2 = 1000/&75 13.33 kg
Time&required&by&labour
To&deliver&and&stack&13.33kg&cement
20&numbers&of&50kg&bag&per&hour = [&13.33/&(20x50)&x1] 0.013 hour
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(7)/3
MBina&Construction&Sdn&Bhd
(3)&Total&cost&including&profit&and&overhead RM
a.&Total&rate&(RM/m2)
Material&cost
Cement&and&sand&(1:4)&and&plasticizer = 3.47 /m2
Labour&cost = 5.53 /m2
TOTAL&RATE 9.00 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 9.00&x&132 1188.00
Add:&Profit&and&overhead&(10%) = 1,188.00&x&10% 118.80
TOTAL&COST 1306.80
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 1,306.80&/&&132 9.90 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(7)/4
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&7:&INTERNAL&WALL&FINISHES&CALCULATION
B4(7)/1/D:&PAINTING
(1)&Material&cost RM
Paint
1&coat&basecoat&sealer = (135.00/&18)&x&10 75.00 /100m2
2&finishing&coats&emulsion&paint = (65.00/&18)&x&9.52&x&2 68.76 /100m2
143.76 /100m2
Allow&wastage&for&all&works&(5%) = 143.76&x&5% 7.19 /100m2
Cost&per&100m2 = 150.95 /100m2
(2)&Labour&cost
Hourly&rate
Painter&@&RM76/&day = 76/8 9.50
Time&required&to&paint&100m2
1&coat&basecoat&sealer = 6.6 6.6 hour/
100m2
2&finishing&coats&emulsion&paint = 4.5&x&2 9.00 hour/
Total&time&required&to&paint&100m2 15.60 100m2
Total&labour&cost&per&100m2
Hourly&rate&x&Total&time&required = 9.50&x&15.60 148.20 /100m2
(3)&Total&cost&per&1m2&including&profit&and&overhead RM
a.&Total&rate&(RM/m2)
Material&cost
Paint = 1.51 /m2
Allow&for&tools&(5%) = 1.51&x&5% 0.08 /m2
Labour&cost = 1.48 /m2
TOTAL&RATE 3.07 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.07&x&132 405.24
Add:&Profit&and&overhead&(10%) = 405.24&x&10% 40.52
TOTAL&COST 445.76
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 445.76&/&132 3.38 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(7)/5
!MBina!Construction!Sdn!Bhd
ELEMENT&NO.&8:&Internal&Floor&Finishes
Note:!Allow!10%!profit!and!overhead.
Floor&Finishes
Material&Cost:&Cement&and&sand&(1:3)&
1 1m3!of!OPC!=!1420kg
2 1m3!of!sand!=!1600kg
3 Material!cost!for!Ordinary!Portland!Cement!including!unloading! RM!14/50kg
4 Material!cost!for!Sand!including!unloading RM35/tonne
5 Allow!shrinkage!and!waste!for!mortar 33.33%
Material&Cost:&Ceramic&Tiles
6 300mmX300mmX7.5mm!thk!Ceramic!tiles RM2.60/pieces
7 Allow!wastage!for!ceramic!tiles 10%
8 White!Cement RM2.00
Labour&Cost&(m2)
9 1!unskilled!labour!for!cement!&!sand!screed! RM!55/day
10 One$gang$of$labour$consist$of$1$unskilled$and$1$skilled$tiler:
($to$floor)$(8hours/day)
1!unskilled!labour RM55/day
1!skilled!tiler!labour RM96/day
11 One$gang$of$labour$consist$of$1$semi$skilled$and$1$skilled$tiler:
($to$floor$n.e$15$from$horizontal)$(8hours/day)
1!semiskilled!labour RM60/day
1!skilled!tiler!labour RM96/day
12 One$gang$of$labour$consist$of$1$unskilled$and$1$skilled$tiler:
($to$skirting$and$drop)
1!unskilled!labour!each RM55/day
1!skilled!tiler!labour!each RM96/day
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_Int!Floor!Finishes
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/A<'20mm'thk'C&S(1:3)'screedH'to'floor
(1)'Material'cost RM
Cement'and'Sand'(1:3)'Screed'(M2)
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50kg&x&RM&14 397.60 /m3
Sand&including&unloading:&
3m3&at&1600kg/m3&at&RM35/tonne = 3&x&1600&/&1000&x&RM&35 168.00 /3m3
Gross&Total 565.60 /4m3
Allow&shrinkage&and&wastage&for&mortar&(33.3%) = 565.60x&33.33% 188.51
Net&total&for&4m3& 754.11 /4m3
(2)'Labour'Cost
Labour'Cost
To&mix&cement&mortar&
1&Unskilled&labour&@&RM55/day = RM55/8 6.88 /hr
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m2)
Material&cost
Cement&and&Sand&(1:3)Screed = 3.77 /m2
Labour&cost = 0.14 /m2
TOTAL'RATE 3.91 /m2
b.'Total'quantity'(m2)
Quantity = TOTAL'QUANTITY 18.00 /m2
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity = 3.91&x&18 70.38 RM
Add:&Profit&and&overhead&(10%) = 70.38x10% 7.04 RM
TOTAL 77.42 RM
(4)'Unit'rate'(RM/m2)
Unit&Rate=&Total&Cost/&Total&Quantity = RM77.42/18 4.30&RM/m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/1
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/B<C&S(1:3)'as'Backings'screed'with'adshiveH'to'floor
(1)'Material'cost RM
'Cement'and'Sand'(1:3)'as'Backings'screed'with'adshive'
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50kg&x&RM&14 397.60 /m3
Sand&including&unloading:&
3m3&at&1600kg/m3&at&RM35/tonne = 3&x&1600&/&1000&x&RM&35 168.00 /3m3
Gross&Total 565.60 /4m3
Allow&shrinkage&and&wastage&for&mortar&(33.3%) = 565.60x&33.33% 188.51
Net&total&for&4m3& 754.11 /4m3
(2)'Labour'Cost
Labour'Cost
Included(in(tiles(labour
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m2)
Material&cost
Cement&and&Sand&(1:3)Screed = 3.77 /m2
TOTAL'RATE 3.77 /m2
b.'Total'quantity'(m2)
Quantity = TOTAL'QUANTITY 86.00 /m2
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity = 3.77x86 324.22 RM
Add:&Profit&and&overhead&(10%) = 324.22x10% 32.42 RM
TOTAL 356.64 RM
(4)'Unit'rate'(RM/m2)
Unit&Rate=&Total&Cost/&Total&Quantity = RM356.64/86 4.15&RM/m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/2
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/C<C&S(1:3)'as'Backings'screed'with'adshiveH'to'floor:'laid'to'fall'not'exceeding''
15º'from'horizontal
(1)'Material'cost RM
'Cement'and'Sand'(1:3)'as'Backings'screed'with'adshive'
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50kg&x&RM&14 397.60 /m3
Sand&including&unloading:&
3m3&at&1600kg/m3&at&RM35/tonne = 3&x&1600&/&1000&x&RM&35 168.00 /3m3
Gross&Total 565.60 /4m3
Allow&shrinkage&and&wastage&for&mortar&(33.3%) = 565.60x&33.33% 188.51
Net&total&for&4m3& 754.11 /4m3
(2)'Labour'Cost
Labour'Cost
Included(in(tiles(labour
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m2)
Material&cost
Cement&and&Sand&(1:3)Screed = 3.77 /m2
TOTAL'RATE 3.77 /m2
b.'Total'quantity'(m2)
Quantity = TOTAL'QUANTITY 4.00 /m2
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity = 3.77x4 15.08 RM
Add:&Profit&and&overhead&(10%) = 15.08x10% 32.42 RM
TOTAL 16.59 RM
(4)'Unit'rate'(RM/m2)
Unit&Rate=&Total&Cost/&Total&Quantity = RM16.59/4 4.15&RM/m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/3
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/D<C&S(1:3)'as'Backings'screed'with'adshiveH'to'drop:'100mm'high
(1)'Material'cost
'Cement'and'Sand'(1:3)'as'Backings'screed'with'adshive' RM
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg
Sand&including&unloading:& = 1420&/&50kg&x&RM&14 397.60 /m3
3m3&at&1600kg/m3&at&RM35/tonne
= 3&x&1600&/&1000&x&RM&35 168.00 /3m3
Allow&shrinkage&and&wastage&for&mortar&(33.3%) Gross&Total 565.60 /4m3
= 565.60x&33.33% 188.51
Net&total&for&4m3& 754.11 /4m3
Divide&by&parts&of&mix&(1:3)
= 754.11/&4 188.53 /m3
Cost&per&m2
= 188.53&x&0.020x0.100 0.38 /m
(2)'Labour'Cost
Labour'Cost
Included(in(tiles(labour
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m)
Material&cost
Cement&and&Sand&(1:3)Screed
= 0.38 /m
b.'Total'quantity'(m) TOTAL'RATE 0.38 /m
Quantity
= TOTAL'QUANTITY 7.00 /m
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity
Add:&Profit&and&overhead&(10%) = 0.38x7 2.66 RM
= 2.66x10% 0.27 RM
TOTAL 2.93 RM
(4)'Unit'rate'(RM/m)
Unit&Rate=&Total&Cost/&Total&Quantity
= RM2.93/7 0.42&RM/m
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/4
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/E<C&S(1:3)'as'Backings'screed'with'adshiveH'to'skirting:'150mm'high
(1)'Material'cost
'Cement'and'Sand'(1:3)'as'Backings'screed'with'adshive' RM
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg
Sand&including&unloading:& = 1420&/&50kg&x&RM&14 397.60 /m3
3m3&at&1600kg/m3&at&RM35/tonne
= 3&x&1600&/&1000&x&RM&35 168.00 /3m3
Allow&shrinkage&and&wastage&for&mortar&(33.3%) Gross&Total 565.60 /4m3
= 565.60x&33.33% 188.51
Net&total&for&4m3& 754.11 /4m3
Divide&by&parts&of&mix&(1:3)
= 754.11/&4 188.53 /m3
Cost&per&m2
= 188.53&x&0.020x0.150 0.57 /m
(2)'Labour'Cost
Labour'Cost
Included(in(tiles(labour
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m)
Material&cost
Cement&and&Sand&(1:3)Screed
= 0.57 /m
b.'Total'quantity'(m) TOTAL'RATE 0.57 /m
Quantity
= TOTAL'QUANTITY 70.00 /m
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity
Add:&Profit&and&overhead&(10%) = 0.57&x&70 39.90 RM
= 39.90x10% 3.99 RM
TOTAL 43.89 RM
(4)'Unit'rate'(RM/m)
Unit&Rate=&Total&Cost/&Total&Quantity
= RM43.89/70 0.63&RM/m
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/5
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/F<Ceramic'TilesH'to'floor
(1)'Material'cost
Ceramic'Tiles
No.&of&tiles&per&m2 = 1/(0.3x0.3) 11.11 pieces
Gross&cost&per&m2&@RM2.60/&piece = 11.11&x&2.60& 28.89 /m2
add&10%&wastage = RM28.89 2.89 /m2
Net&cost&per/m2 = RM28.89&+&RM2.89 31.78 /m2
(2)'Labour'Cost
Labour'Cost
1(gang(of(labour(consits(of(1(unskilled(and(1(skilled(tiler
To&mix&cement&mortar
Unskilled&labour@RM55/day = RM55/8 6.88 /hour
Cost&to&mix&1m2 = 6.88x1x0.020 0.14 /m2
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m2)
Material&cost
Cement&and&Sand&(1:3)Screed
Labour&Cost 33.78 /m2
= 42.14 /m2
b.'Total'quantity'(m2) TOTAL'RATE 75.92 /m2
Quantity
= TOTAL'QUANTITY 86.00 /m2
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity
Add:&Profit&and&overhead&(10%) = 75.92&x&86 6,529.12 RM
= 6529.12&x&10% 652.91 RM
TOTAL 7,182.03 RM
(4)'Unit'rate'(RM/m2)
Unit&Rate=&Total&Cost/&Total&Quantity
= RM7182.03/86 83.51&RM/m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/6
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/G<'Ceramic'TilesH'to'floor:'laid'to'fall'not'exceeding''15º'from'horinzontal
(1)'Material'cost
Ceramic'Tiles
No.&of&tiles&per&m2 = 1/(0.3x0.3) 11.11 pieces
Gross&cost&per&m2&@RM2.60/&piece = 11.11&x&2.60& 28.89 /m2
add&10%&wastage = RM28.89 2.89 /m2
Net&cost&per/m2 = RM28.89&+&RM2.89 31.78 /m2
(2)'Labour'Cost
Labour'Cost
1(gang(of(labour(consits(of(1(unskilled(and(1(skilled(tiler
To&mix&cement&mortar
Semi&skilled&labour@RM60/day = RM60/8 7.50 /hour
Cost&to&mix&1m2 = 7.50x1x0.020 0.15 /m2
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m2)
Material&cost
Cement&and&Sand&(1:3)Screed
Labour&Cost 33.78 /m2
= 42.15 /m2
b.'Total'quantity'(m2) TOTAL'RATE 75.93 /m2
Quantity
= TOTAL'QUANTITY 4.00 /m2
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity
Add:&Profit&and&overhead&(10%) = 75.93&x&4 303.72 RM
= 303.72x10% 30.37 RM
TOTAL 334.09 RM
(4)'Unit'rate'(RM/m2)
Unit&Rate=&Total&Cost/&Total&Quantity
= RM334.09/4 83.52&RM/m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/7
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/H<'Ceramic'TilesHto'drop:'100mm'high
(1)'Material'cost
Ceramic'Tiles
No.&of&tiles&per&m2 = 1/(0.3x0.3) 11.11 pieces
Gross&cost&per&m2&@RM2.60/&piece = 11.11&x&2.60& 28.89 /m2
add&10%&wastage = RM28.89 2.89 /m2
Net&cost&per/m2 = RM28.89&+&RM2.89 31.78 /m2
(2)'Labour'Cost
Labour'Cost
1(gang(of(labour(consits(of(1(unskilled(and(1(skilled(tiler
To&mix&cement&mortar
Unskilled&labour@RM55/day = RM55/8 6.88 /hr
Cost&to&mix&1m2 = 6.88x1x0.020x0.100 0.01 /m
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m)
Material&cost
Cement&and&Sand&(1:3)Screed
Labour&Cost 3.38 /m
= 4.21 /m
b.'Total'quantity'(m) TOTAL'RATE 7.59 /m
Quantity
= TOTAL'QUANTITY 7.00 /m
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity
Add:&Profit&and&overhead&(10%) = 7.59&x&4.21 53.13 RM
= 53.13x10% 5.31 RM
TOTAL 58.44 RM
(4)'Unit'rate'(RM/m)
Unit&Rate=&Total&Cost/&Total&Quantity
= RM58.44/7 8.35&RM/m
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/8
MBina&Construction&Sdn&Bhd
Element'NO.8'INTERNAL'FLOOR'FINISHES'CALCULATION
B4(8)/1/I<'Ceramic'TilesHto'skirting:'150mm'high
(1)'Material'cost
Ceramic'Tiles
No.&of&tiles&per&m2 = 1/(0.3x0.3) 11.11 pieces
Gross&cost&per&m2&@RM2.60/&piece = 11.11&x&2.60& 28.89 /m2
add&10%&wastage = RM28.89 2.89 /m2
Net&cost&per/m2 = RM28.89&+&RM2.89 31.78 /m2
(2)'Labour'Cost
Labour'Cost
1(gang(of(labour(consits(of(1(unskilled(and(1(skilled(tiler
To&mix&cement&mortar
Unskilled&labour@RM55/day = RM55/8 6.88 /hr
Cost&to&mix&1m2 = 6.88x1x0.020x0.15 0.02 /m
(3)'Total'cost'including'profit'and'overhead
a.'Total'rate'(RM/m)
Material&cost
Cement&and&Sand&(1:3)Screed
Labour&Cost 5.07 /m
= 6.32 /m
b.'Total'quantity'(m) TOTAL'RATE 11.39 /m
Quantity
= TOTAL'QUANTITY 70.00 /m
c.'Total'cost'(RM)
Total&cost&=&total&rate&x&total&quantity
Add:&Profit&and&overhead&(10%) = 11.39&x&70 797.30 RM
= 797.30x10% 79.730 RM
TOTAL 877.03 RM
(4)'Unit'rate'(RM/m)
Unit&Rate=&Total&Cost/&Total&Quantity
= RM877.03/70 12.53&RM/m
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III(8)/9
!MBina!Construction!Sdn!Bhd
ELEMENT&NO.&9:&INTERNAL&CEILING&FINISHES&DATA
Note:!Allow!10%!profit!and!overhead.
Fibrous&Plaster&Ceiling
1 1220mm!x!1830mm!x!12mm!thk!fibrous!ceiling!plasterboard! RM18.50/piece
including!unloading
2 Allow!wastage!for!fibrous!ceiling!plasterboard 10%
3 34mm!metal!furring!including!unloading RM2.40/piece
4 Allow!wastage!for!metal!furring 10%
5 1!gang!consists!of!2!skilled!labours!and!1!unskilled!labours! (8!hours!/day)
6 1!Skilled!labour! RM!90/day
7 1!Unskilled!labour!! RM!55/day
8 Allow!RM5!for!screw RM!5
ASSUMPTION
1 Assume!1!piece!of!plasterboard!require!4!nos!of!metal!furring! (by!supplier)
2 Assume!to!lay!1m2!of!ceiling!plasterboard!requires!0.65!hours (by!book)
3 Assume!to!lay!1m2!of!metal!furring!requires!0.27!hours (by!book)
Paint
1 One!coat!of!basecoat!sealer!at!plaster!surfaces! RM135.00/!18Litres
@!10!litres!per!100m2
2 Two!finishing!coats!of!emulsion!paint!at!plaster!surfaces! RM65.00/!18Litres
@!9.52!litres!per!100m2
3 Allow!wastage!for!all!works 5%
4 1!painter!(8hours/!day) RM76/!day
5 One!coat!of!basecoat!sealer!at!plaster!surfaces!
@!6.6!hour!per!100m2
6 Two!finishing!coats!of!emulsion!paint!at!plaster!surfaces!
@!4.5!hour!per!100m2
7 Allow!of!material!cost!for!paint!brush,!accessories!and 5%
other!small!tools
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_Int.!Ceiling!Fin.
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&9:&INTERNAL&CEILING&FINISHES&CALCULATION
B4(9)/1/A:&FIBROUS&PLASTER&CEILING
(1)&Material&cost RM
Fibrous&Ceiling&Plasterboard&including&unloading
No.&of&1220mm&x&1830mm&x&12mm&thk&plasterboard&per&m2:
= 1&/&(1.22x1.83) 0.45pieces/m2
Gross&cost&per&m2&@&RM18.50/piece:&
= 0.45x18.50 8.33 /m2
Allow&wastage&for&Fibrous&Ceiling&Plasterboard&(10%)
= 8.33&x&10% 0.83 /m2
9.16 /m2
Metal&Furring&including&unloading
No.&of&34mm&metal&furring:&(assume&1&piece&of&plasterboard&require&4&nos&of&metal&furring
= 4&/&(1.22x1.83) 1.79pieces/m2
Gross&cost&per&m2&@&RM2.40/piece:
= 1.79x2.40 4.30 /m2
Allow&wastage&for&metal&furring&(10%)
= 4.30&x&10% 0.43 /m2
4.73 /m2
(2)&Labour&cost
Labour&gang
1&skilled&labour&@&RM90/person/day = RM90/8&x&1 11.25 /hr
1&unskilled&labour&@&RM55/person/day = RM55/8&x&1 6.88 /hr
Labour&gang&hourly&rate 18.13 /hr
Time&required&by&labour
Assumed&to&lay&1m2&of&ceiling&plasterboard&requires&0.65&hours
= 0.65&x&18.13 11.78 /m2
Assumed&to&lay&1m2&of&metal&furring&requires&0.27&hours
= 0.27&x&18.13 4.90 /m2
16.68 /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Fibrous&Ceiling&Plasterboard = 9.16 /m2
Metal&Furring = 4.73 /m2
13.89 /m2
Labour&cost
1&skilled&labour&&&1&unskilled&labour = 16.68 /m2
TOTAL&RATE 30.57 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(9)/1
MBina&Construction&Sdn&Bhd
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 30.57&x&104 3179.28
Allow&sum&of&RM5&for&screw = 5 5.00
Gross&total 3184.28
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 3,502.71&/&104 33.68 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(9)/2
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&9:&INTERNAL&CEILING&FINISHES&CALCULATION
B4(9)/1/B:&PAINTING
(1)&Material&cost RM
Paint
1&coat&basecoat&sealer = (135.00/&18)&x&10 75.00 /100m2
2&finishing&coats&emulsion&paint = (65.00/&18)&x&9.52&x&2 68.76 /100m2
143.76 /100m2
Allow&wastage&for&all&works&(5%) = 143.76&x&5% 7.19 /100m2
Cost&per&100m2 = 150.95 /100m2
(2)&Labour&cost
Hourly&rate
Painter&@&RM76/&day = 76/8 9.50
Time&required&to&paint&100m2
1&coat&basecoat&sealer = 6.6 6.6 hour/
100m2
2&finishing&coats&emulsion&paint = 4.5&x&2 9.00 hour/
Total&time&required&to&paint&100m2 15.60 100m2
Total&labour&cost&per&100m2
Hourly&rate&x&Total&time&required = 9.50&x&15.60 148.20 /100m2
(3)&Total&cost&per&1m2&including&profit&and&overhead RM
a.&Total&rate&(RM/m2)
Material&cost
Paint = 1.51 /m2
Allow&for&tools&(5%) = 1.51&x&5% 0.08 /m2
Labour&cost = 1.48 /m2
TOTAL&RATE 3.07 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.07&x&104 319.28
Add:&Profit&and&overhead&(10%) = 319.28&x&10% 31.93
TOTAL&COST 351.21
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 351.21&/&104 3.38 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(9)/3
!MBina!Construction!Sdn!Bhd
ELEMENT&NO.&10:&EXTERNAL&FINISHES&DATA
Note:!Allow!10%!profit!and!overhead.
Cement&and&sand&(1:4)&+&plastering
1 1m3!of!OPC!=!1420kg
2 1m3!of!Sand!=!1600kg
3 Material!cost!for!Ordinary!Portland!Cement!including!unloading! RM14/50kg
4 Material!cost!for!Sand!including!unloading RM35/tonne
5 Allow!shrinkage!and!wastage!for!mortar 33.33%
6 Plasticizer!used!=!0.10kg/!50kg!of!cement RM10/!1kg
7 1!gang!consists!of!2!skilled!labours!and!1!unskilled!labour 8hours/!day
8 1!skilled!labour RM87/!day
9 1!unskilled!labour RM55/!day
10 Coverage!for!20mm!thick!plaster!=!75m2!per!1000kg
Assume!1000kg!refers!to!cement!only
11 To!deliver!and!stack!cement!@!20!numbers!of!50kg!bag!per
hour
12 To!mix!and!apply!100m2!requires!18!hours
Painting
1 One!coat!of!Dulux!Interior!Basecoat!Sealer!at!plaster!surfaces!@!10! RM135.00/!18!litres
litres!per!100m2
2 Two!finishing!coats!of!Dulux!ICI!Maxilite!Trade!Emulsion!paint!at! RM65.00/!18!litres
plaster!surfaces!@!9.52!litres!per!100m2
3 Allow!wastage!for!all!works 5.00%
4 1!painter!(8hours/!day) RM76/!day
5 One!coat!of!basecoat!sealer!at!plaster!surfaces! 6.6!hour!per!100m2
6 Two!finishing!coats!of!emulsion!paint!at!plaster!surfaces 4.5!hour!per!100m2
7 Allow!of!material!cost!for!paint!brush,!accessories!and!other!small! 5%
tools
Cement&and&sand&(1:4)&screed
1 1m3!of!OPC!=!1420kg
2 1m3!of!Sand!=!1600kg
3 Material!cost!for!Ordinary!Portland!Cement!including!unloading! RM14/50kg
4 Material!cost!for!Sand!including!unloading RM35/tonne
5 Allow!shrinkage!and!wastage!for!mortar 33.33%
6 1!unskilled!labour RM55/!day
7 To!mix!1m3!of!cement!mortar!requires!1!hour
Skim&coat
1 ASG!800!Base!Grey!Skim!Coat!(25kg/!bag)!(Density!1650kg/m3) RM13/!bag
2 Allow!shrinkage!and!wastage!factor 10%
3 1!gang!consists!of!2!skilled!labours!and!1!unskilled!labour (8!hours/!day)
4 1!skilled!labour RM87/!day
5 1!unskilled!labour RM55/!day
6 Assume!1m2!requires!0.24!hour (by!book)
Estimating!(QSB!60504)!Coursework!2:!Project!Tendering Appendix!III_External!Finishes
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&10:&EXTERNAL&FINISHES&CALCULATION
B4(10)/1/A:&INSITU&FINISHING
(1)&Material&cost RM
Cement&and&Sand&(1:4)&+&Plasticizer
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50&x&14 397.60 /m3
Sand&including&unloading:&
4m3&at&1600kg/m3&at&RM35/tonne = 4&x&1600&/&1000&x&35 224.00 /4m3
Gross&total 621.60 /5m3
(2)&Labour&cost
Labour&gang
2&skilled&labour&@&RM87/&person/&day = 87/&8&x&2 21.75 /hour
1&skilled&labour&@&RM55/&person/&day = 55/8&x&1 6.88 /hour
Labour&gang&hourly&rate 28.63 /hour
Coverage&for&20mm&thick&plaster&=&75m2&per&1000kg
Assume&1000kg&refers&to&cement&only
Cement&per&1m2 = 1000/&75 13.33 kg
Time&required&by&labour
To&deliver&and&stack&13.33kg&cement
20&numbers&of&50kg&bag&per&hour = [&13.33/&(20x50)&x1] 0.013 hour
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(10)/1
MBina&Construction&Sdn&Bhd
(3)&Total&cost&including&profit&and&overhead RM
a.&Total&rate&(RM/m2)
Material&cost
Cement&and&sand&(1:4)&and&plasticizer = 3.47 /m2
Labour&cost = 5.53 /m2
TOTAL&RATE 9.00 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 9.00&x&91 819.00
Add:&Profit&and&overhead&(10%) = 819.00&x&10% 81.90
TOTAL&COST 900.90
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 900.90&/&&91 9.90 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(10)/2
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&10:&EXTERNAL&FINISHES&CALCULATION
B4(10)/1/D:&PAINTING
(1)&Material&cost RM
Paint
1&coat&basecoat&sealer = (135.00/&18)&x&10 75.00 /100m2
2&finishing&coats&emulsion&paint = (65.00/&18)&x&9.52&x&2 68.76 /100m2
143.76 /100m2
Allow&wastage&for&all&works&(5%) = 143.76&x&5% 7.19 /100m2
Cost&per&100m2 = 150.95 /100m2
(2)&Labour&cost
Hourly&rate
Painter&@&RM76/&day = 76/8 9.50
Time&required&to&paint&100m2
1&coat&basecoat&sealer = 6.6 6.6 hour/
100m2
2&finishing&coats&emulsion&paint = 4.5&x&2 9.00 hour/
100m2
Total&time&required&to&paint&100m2 15.60 hour/
100m2
Total&labour&cost&per&100m2
Hourly&rate&x&Total&time&required = 9.50&x&15.60 148.20 /100m2
(3)&Total&cost&per&1m2&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Paint = 1.51 /m2
Allow&for&tools&(5%) = 1.52&x&5% 0.08 /m2
Labour&cost = 1.48 /m2
TOTAL&RATE 3.07 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.07&x&91 279.37
Add:&Profit&and&overhead&(10%) = 279.37&x&10% 27.94
TOTAL&COST 307.31
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 307.31&/&91 3.38 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(10)/3
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&10:&EXTERNAL&FINISHES&CALCULATION
B4(10)/1/B:&INSITU&FINISHINGS
(1)&Material&cost RM
Cement&and&Sand&(1:4)&Screed
Ordinary&Portland&Cement&including&unloading:&
1m3&at&1420kg/m3&at&RM14/50kg = 1420&/&50&x&14 397.60 /m3
Sand&including&unloading:&
4m3&at&1600kg/m3&at&RM35/tonne = 4&x&1600&/&1000&x&35 224.00 /4m3
Gross&total 621.60 /5m3
(2)&Labour&cost
To&mix&cement&mortar
Unskilled&labour&@&RM55/&day = 55/8 6.88 /hr
Cost&to&mix&1m2 = 6.88&x&1&x&0.020 0.14 /m2
0.14 /m2
(3)&Total&cost&per&1m2&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Cement&and&sand&(1:4)&screed = 3.32 /m2
Labour&cost = 0.14 /m2
TOTAL&RATE 3.46 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 3.46&x&18 62.28
Add:&Profit&and&overhead&(10%) = 62.28&x&10% 6.23
TOTAL&COST 68.51
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 68.51&/&18 3.81 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(10)/4
MBina&Construction&Sdn&Bhd
ELEMENT&NO.&10:&EXTERNAL&FINISHES&CALCULATION
B4(10)/1/C:&SKIM&COAT
(1)&Material&cost RM
Skim&coat
3mm&thk&ASG&800&Base&Grey&Skim&Coat&(25kg/bag)
Density&1650kg/m3 = 1650&/&25&x&RM13 858.00
Gross&Total 858.00
Allow&shrinkage&and&wastage&for&skim&coat&(10%)
= RM&858.00&X&10% 85.80 /m2
Net&Gross&Total 943.80 /m2
(2)&Labour&cost
Labour&gang
1&skilled&labour&@&RM87/person/day = RM87/8&x&1 10.88 /hr
1&unskilled&labour&@&RM55/person/day = RM55/8&x&1 6.88 /hr
Labour&gang&hourly&rate 17.76 /hr
Time&required&by&labour
Assume&1m2&require&0.24&hour
= 17.76&x&0.24 4.26 /m2
(3)&Total&cost&including&profit&and&overhead
a.&Total&rate&(RM/m2)
Material&cost
Skim&Coat m2 2.83 /m2
Labour&cost
1&skilled&labour&&&1&unskilled&labour 4.26 /m2
TOTAL&RATE 7.09 /m2
c.&Total&cost&(RM)
Total&cost&=&total&rate&x&total&quantity = 7.09&x&36.00 255.24
(4)&Unit&rate&(RM/m2)
Unit&rate&=&total&cost&/&total&quantity = 280.76&/&36 7.80 /m2
Estimating&(QSB&60504)&Coursework&2:&Project&Tendering Appendix&III_(10)/5