You are on page 1of 12

ENGINEERING, PROCUREMENT AND CONSTRUCTION(EPC) WORKS AND

SERVICES FOR JURONG ISLAND MARKETING TERMINAL PROJECT, SINGAPORE.

SYSTEM NO : Potable Water

TESTPACK:
CIWE-JIMT-P-002

Main P & ID :JIMT-C02-C-17-20038 Rev 4

Type of Test : HYDRO TEST

Test Pressure : 130.5 Psi

DesignTest Pressure : 87 Psi

Test Medium : Water

Contractor : CIWE

PROJECT : JIMT LOCATION : Office south


CIWE-JIMT PROJECT
PIPEWORK PRE-TEST CHECK LIST Page 1 of 1

SYSTEM: Potable water PROJECT : JIMT

MAIN P&ID No: JIMT-C02-C-17-20038 REV: 4 LOCATION : Office south

TEST PACK No: CIWE-JIMT-P-002


YES N/A NO
1. Check that all NDE / PMI / and PWHT requirements are as specified, have been
met and recorded.
Welding Inspector : Date :
2. Check that the bores of all orifice flanges have been ground smooth.
3. Pipework internal cleaning confirmed.
4. Check Isometrics are latest revisions and agree with Testpack Specification Sheet
5. Check isometrics against the P&ID.
6. Check pipe slopes conform to P&ID / Isometrics requirements.
7. Check that the correct bolts and gaskets are installed at all mechanical joints.
8. Check that all vents and drains are installed (Submit for permission to add vents
and drains for testing as required).
9. Check all pipe and fittings for correct schedule and material type.
10. Check that temporary lifting lugs are welded to correct specification and NDE tested.
11. Check valve materials - use spec. ref. in piping material specification.
12. Check that branch reinforcement is correct.
13. Check sealant on screwed connections is as per specification.
14. Check that all pressure connections are installed correctly as per specification.
15. Check for correct flow direction through filters and strainers, traps, check valves
globe valves and control valves.
16. Check orifice valve tap orientation.
17. Check that orifice flanges have required upstream and downstream 'clearances'
18. Check all orifice taps have been seal welded and unused tapped holes have been
plugged and seal welded.
19. Check that all pipe supports are completely installed as per drawings and pipe
support standards / specs and schedules - additional supports may be
required - refer to standard drawings.
20. Check that all temporary pipe supports have been removed.
21. Check springs supports are in position and all pre-test checks have been done
and gags are in or springs are locked.
22. Check that all the necessary test spades have been installed correctly.
23. Check that all valves, sprinkler heads, rossettes, nozzles and other equipment that
could be damaged by testing are identified, removed or isolated, on the test package.
24. Check test medium for conformity to requirements.
25. Check pressure gauge calibration correct.

26. Mechanical Supervisor to verify flange alignment to rotating equipment


prior to test.
Mechanical Supervisor : Date :
Remarks: No test breaks are allowed against welded isolating valves without Client approval.

For and on behalf of NAME Signature Date


CIWE
PMC
SPC
CIWE-JIMT PROJECT
TEST BLIND LIST Page: 1 of 1
TEST PACK NO: CIWE-JIMT-P-002
Test Rev
Blind Iso Dwg. Size of Removed CIWE PMC
No. blind Sign Sign Remarks
1 PW-6001-1R1-8" 0 8"
PW-5401-1R1-8"
2 0 8"

For and on behalf of NAME Signature Date


CIWE
PMC
SPC
CIWE-JIMT PROJECT
PIPING PUNCH LIST PAGE 1 of 1

SYSTEM No. : Potable water PROJECT : JIMT

TEST PACK No. : CIWE-JIMT-P-002 PIPE SPEC : Potable water Pipe Spool

PUNCH LIST COMPLETION


DESCRIPTION OF REMEDIAL WORKS
Item Initiator CAT CIWE PMC SPC
(DISCIPLINE)
DATE SIGN DATE SIGN DATE SIGN

Cat "A" - Punch Items must be repaired/completed or corrected before (pressure) testing can take place

Cat "B" - Punch Items may be repaired, completed/corrected after (pressure) testing, but before Reinstatement Acceptance
`

CIWE-JIMT PROJECT
PIPING TEST PACK APPROVAL TO TEST Page: 1 of 1

SYSTEM NO:
### Potable water PROJECT : JIMT

TEST PACK No.: CIWE-JIMT-P-002 LOCATION : Office south

EFD No.:
###

1. PMC ENGINEERING REVIEW


There are no outstanding Engineering issues that prevent this line from being tested.

NAME: POSITION:

DATE: SIGNATURE:

2. PMC CONSTRUCTION REVIEW


All items on Pipework Pre-Test Check List have been examined and completed.
All category A Punch List items have been rectified.
The system has been set-up for testing as per requirements.

NAME: POSITION:

DATE SIGNATURE:

REMARKS

COMPLETED BY

COMPANY

SIGNATURE

NAME

DATE
CIWE-JIMT PROJECT
PRESSURE TEST REPORT
SYSTEM: Potable water PROJECT : JIMT

TEST PACK No: CIWE-JIMT-P-002 LOCATION : Office south

P & ID No. JIMT-C02-C-17-20038 Rev : 4

ISO Drawing No. See Attached Sheets (pipe line release inspection record)
DESIGN DATA TEST DATA
Ambient Temperature 30°C Ambient Temperature 31°C

Test Pressure 130.5 Psi Test Pressure 130.5 Psi

Design Pressure 87 Psi Holding Time 30 Mins

Fluid Water Testing Medium Water

Service Temperature 19.4°C - 36.6°C Testing Temperature


Applicable Documents Pressure gages used give ID No. C1-2701-01
1 SAC/PL17/2505 &
Document No. : Calibration Cert. No & Date
27.10.2017
Pressure gages used give ID No. NA
2
Calibration Cert. No & Date

Pressure gages used give ID No. NA


3
Calibration Cert. No & Date

Comments/Remarks Pressure Checked During Holding Time


P (If Required)
130.5 Psi No Gage ID. Date Time Reading Signature

87 Psi 30 minutes 1 C1-2701-01 15.12.2017 14.00 Hrs 0 Psi


2 C1-2701-01 15.12.2017 14.13 Hrs 60 Psi
3 C1-2701-01 15.12.2017 14.30 Hrs 100 Psi
0 4 C1-2701-01 15.12.2017 14.35 Hrs 130.5 Psi
5 C1-2701-01 15.12.2017 15.05 Hrs 130.3 Psi
t0 t1 t2 t3 t4 t5 t6 T

We confirm that the pressure test results as noted above correct and conform to the project requirements.

For and on behalf of Name Signature Date

CIWE

PMC

SPC
CIWE-JIMT
PIPE LINE TEST RELEASE
INSPECTION RECORD
SYSTEM No. : Potable water PROJECT : JIMT
PAGE NO.: 1 of 1
TEST PACK No: CIWE-JIMT-P-002 LOCATION : Office south
Checked by CIWE Checked by CIWE CHECKED BY PMC CHECKED SRC
P&ID NO.: JIMT-C02-C-17-20003

CHECK ITEMS
S/N ISO DWG NO. REV NO LINE NO. RESULT
VALVE BLIND SPACER VENT DRAIN SUPPORT GASKET NDE

1 PW-5401-1R1-8 0

2 PW-6001-1R1-8 0
Exception List Issued Yes No E/L No
CIWE-JIMT PROJECT
TEST PACK CONTENTS Page: 1 of 1

AREA: Office south PROJECT : JIMT

SYSTEM:
### Potable water TEST PACK NO: CIWE-JIMT-P-002

LOCATION : Office south ###

Tick Box if Included

1. Pipework Pre-Test Checklist

2. Test Blind List

3. Piping Punch List

4. Piping Test Pack Approval To Test

5. Pressure Gauge Calibration Certificates

6. Pressure Test Report

7. Line List

8.Approved Isometric Drawing

9. Piping & Instrument Diagram

10.Pipe Line Welding Pack

11. Equipment Erection Report

12. Material Certificate

You might also like