Construction: Completion Certificate Not Issued ☒ لم يتم إصدار شهادة إتمام العمل:مرحلة اإلنشاء
Maintenance Period: Completion Certificate Issued ☐ تم إصدار شهادة اتمام العمل:مرحلة ما بعد االنشاء
Post Construction: Completion Certificate Issued and Maintenance Period Expired ☐ تم اصدار شهادة اتمام العمل وانتهت فترة الصيانة:مرحلة ما بعد االنشاء
Structures: ☒ ☐ 0 B المنشئات
A: Acceptable. Assets are in suitable B: Acceptable with comments. Assets are C: Unacceptable. Assets are not in suitable
condition for handover based on the findings acceptable pending resolution of comments. condition for handover.
and limits of this inspection.
األصول في حالة مناسبة للتسليم وذلك: مقبول.أ األصول في حالة: مقبول مع وجود مالحظات.أ األصول في حالة غير مناسبة للتسليم: غير مقبول.أ
وفقاً لمحتويات هذا التقرير مقبولة ولكن القرار يعتمد على المالحظات
For comments see following Snag List Cover Sheet and Snag List
لالطالع على المالحظات يرجى مراجعة قائمة العيوب وتعليمات الموقع
Project No.: QS016-P01 رقم المشروع Project Name: Bypass from Rawdat Rashed اسم المشروع
1. Name of Staff Present at Inspection (Ashghal/PMC/Consultant/Contractor/Sub Contractor) بيانات الموظفين الذين حضروا اثناء التفتيش
Debonding from concrete substrate and cracking of joint sealant due to possible workmanship issues are found on most of the retaining wall movement joints.
Weep holes were clogged and closed by backfill materials around the existing utility service manholes (Ooredoo).
Poor soil compaction on the manhole embankment was evident.
Cleaning and removal of waste materials on the drain channel between retaining wall and reinforced embankment.
3. Safety Critical / Urgent Issues المشاكل العاجلة \ حرجة تؤثر على السالمة
Project No.: QS016-P01 رقم المشروع Project Name: Bypass from Rawdat Rashed اسم المشروع
1 22/02/2018 All throughout the wall Debonding from concrete substrate Click here to enter text. ☐
and cracking of joint sealant on most
of the joints.
Removal of defective sealant and
cleaning / preparation of concrete
substrate prior to reapplication of joint
sealant shall be observed in most
priority. Replacement of sealant would
include not only those exposed ones
but also those joints covered with
backfill material.
2 22/02/2018 Along the wall Weep holes were clogged and closed Click here to enter text. ☐
by backfill materials around the
existing utility service manholes
(Ooredoo).
Exposed weep holes shall be cleared
with any clogging debris and
appropriate drainage system shall be
provided that would not obstruct
movement of water as well as
undermine the stability of the
embankment.
3 22/02/2018 Soil near manholes Poor soil compaction on the manhole Click here to enter text. ☐
embankment was evident. Top soil
was loose and presence of waste
debris were found.
Correct compaction and reinstatement
procedure shall be undertaken.
4 22/02/2018 Soil near manholes Waste materials can be seen all Click here to enter text. ☐
throughout the drain channel
perimeter between retaining wall and
reinforced embankment. Presence of
vegetation is also evident.
Removal of waste materials and
vegetation shall be done to permit
good surface drain movement.
End of Snag