You are on page 1of 202

The Pennsylvania State University

The Graduate School

College of Earth and Mineral Sciences

INTEGRATED DATA ENVIRONMENT FOR ANALYSIS AND


CONTROL OF ENERGY CONSUMPTION (IDE-ACE) IN SURFACE
COAL MINING

A Dissertation in

Mining Engineering

by

Dragan Bogunovic

© 2008 Dragan Bogunovic

Submitted in Partial Fulfillment

of the Requirements

for the Degree of

Doctor of Philosophy

December 2008

i
The dissertation of Dragan Bogunovic was reviewed and approved* by following:

Vladislav Kecojevic
Associate Professor of Mining Engineering
Dissertation Adviser, Chair of Committee

R. Larry Grayson
Professor of Energy and Mineral Engineering

Maochen Ge
Associate Professor of Mining Engineering

Dongwon Lee
Associate Professor of Information Sciences and Technology

Yaw D. Yeboah
Professor of Energy and Mineral Engineering
Head of the Department of Energy and Geo-Environmental Engineering

*Signatures are on file in Graduate School.

ii
ABSTRACT

The U.S. mining industry consumes a significant amount of energy, primarily diesel fuel

and electricity. A recent study by the U.S. Department of Energy indicates the energy

consumption of about 1,246 trillion Btu (365 billion kWh) annually. The continuous

global increases in energy demand, energy prices as well as the environmental impact

relating to CO2 emissions represent a substantial challenge for the industry.

Currently, coal mines use state-of-the-art technology integrated into sophisticated

systems that monitor production and equipment performance in real-time. However,

frequent data acquisition results in multiple, unrelated, data storages simultaneously

inducing an industry-wide problem of being data rich and information poor.

This dissertation presents the results of research work on the development of an

integrated data environment system for analysis and control of energy (IDE-ACE)

consumption in a surface coal mining operation.

The IDE-ACE is able to provide answers to the crucial questions of when, where, and

how much energy is being used in the mining production chain. A high energy consumer

(equipment) can be isolated by the integrated analytical processes and data recorded in a

centralized database. The system integrates additional features that utilize the existing

real-time data sources in order to optimize equipment working parameters, lower

production costs, and reduce energy consumption and CO2 emission. A case study on an

operating surface coal mine is carried out to demonstrate the practical application of the

developed system. The methodology developed in this dissertation can be used as a

benchmark for calculation of energy consumption in surface coal mining. Additionally,

the results of the study indicate that a case study mine is likely to benefit in energy

savings of approximately quarter million dollars on the annual basis.

iii
TABLE OF CONTENTS

List of Tables …….……………………………………………………….………………….. vii

List of Figures ……..…………………………………………………………………….……. viii

List of Equations …..…………………………………………………………………………. xii

List of Symbols ……...………………………………………………………………….…..… xiv

Acknowledgment …………………………………………………………………………..… xvi

Dedication ……………………………………………………………………………………. xvii

Chapter 1

1 INTRODUCTION................................................................................................................... 1

1.1 Background ............................................................................................................................. 1

1.2 Problem Statement .................................................................................................................. 4

1.3 Scope of Work......................................................................................................................... 8

Chapter 2

2 LITERATURE REVIEW ...................................................................................................... 10

Chapter 3

3 IDE-ACE METHODOLOGY DEVELOPMENT ................................................................ 20

iv
3.1 Introduction ........................................................................................................................... 20

3.2 Proposed Technical Approach .............................................................................................. 20


3.2.1 Hardware Requirements for IDE-ACE......................................................................... 23
3.2.2 Phase I – Process Analysis ........................................................................................... 24
3.2.3 Phase II - Design .......................................................................................................... 26
3.2.4 Phase III – Development .............................................................................................. 43
3.2.4.1 Integrated Database Block – IDB ........................................................................ 43
3.2.4.2 Database Management Block – DMB ................................................................. 49
3.2.4.3 Data Analysis Tool – DAT .................................................................................. 51
3.2.4.3.1 CO2 Analysis – Emission from the Coal ......................................................... 74
3.2.4.3.2 CO2 Analysis – Emission from the Liquid Fuels............................................. 76
3.2.4.3.3 The Performance Indicator (PI) ....................................................................... 77
3.2.4.3.4 Operator Performance Evaluation - Analytical Hierarchical Process ............. 79
3.2.4.3.5 Statistical Analysis and Model Development .................................................. 87
3.2.4.4 Web Reporting Block – WRB ............................................................................. 88
3.2.5 Phase IV – Testing........................................................................................................ 91
3.2.6 Phase V – Deployment ................................................................................................. 91

Chapter 4

4 THE IDE-ACE IN APPLICATION – RESULTS AND DISCUSSION .............................. 92

4.1 Introduction ........................................................................................................................... 92

4.2 Data Collection...................................................................................................................... 93

4.3 Dragline Experiment ............................................................................................................. 95

4.4 Data Management Block - Interface Infrastructure ............................................................. 102

4.5 Reporting System Block – Interface Infrastructure ............................................................. 116

4.6 Data Analysis Block – Interface Infrastructure ................................................................... 122


4.6.1 Design of Experimental Tool (DET) .......................................................................... 124
4.6.2 Dragline Data Analysis Tool (DDAT) ....................................................................... 127

v
4.6.2.1 Data Retrieval .................................................................................................... 128
4.6.3 Data Analysis.............................................................................................................. 130

4.7 Data Analysis – Mobile Equipment .................................................................................... 145

4.8 Data Analysis - CO2 Emission ............................................................................................ 148

4.9 Data Analysis – Energy Summary ...................................................................................... 150

4.10 Electricity Consumption/Productivity Model Development ........................................... 152


4.10.1 Significant Variables .............................................................................................. 152
4.10.2 Models Building ..................................................................................................... 154
4.10.2.1 Criterion Selection Procedure ............................................................................ 156
4.10.3 Model Validation ................................................................................................... 161

4.11 Diesel Fuel Consumption Model .................................................................................... 167

4.12 Chapter Summary ........................................................................................................... 170

Chapter 5

5 SUMMARY AND CONCLUSIONS.................................................................................. 172

5.1 Summary ............................................................................................................................. 172

5.2 Recommendations for Further Research ............................................................................. 177

6 REFERENCES .................................................................................................................... 178

vi
LIST OF TABLES

Table 2-1: Energy Requirements for a 9,967 ton/day Hypothetical Interior Surface Coal Mine ......... 12

Table 2-2: Energy Requirements for a 27,778 ton/day Hypothetical Western Surface Coal Mine....... 13

Table 3-1: The Relationships Arithmetic .............................................................................................. 40

Table 3-2: The Load Factor Guide (Cat, 2007) ..................................................................................... 53

Table 3-3: Fuel Consumption Based on The Load Conditions (Cat, 2007) .......................................... 54

Table 3-4: Fixed Carbon Content (Stefanko, 1983) .............................................................................. 75

Table 3-5: Numerical Scale for Comparative Judgment of Indicators .................................................. 81

Table 3-6: The Overall Weights Resulting from the Pairwise Comparison .......................................... 86

Table 3-7: Review of Technologies and Tools for IDE-ACE Development......................................... 90

Table 4-1: Summary of the Results ....................................................................................................... 96

Table 4-2: The Analysis of CO2 Results ............................................................................................. 135

Table 4-3: Summary Statistics for Models (Minitab Output).............................................................. 154

Table 4-4: Models and Summary of Statistics for Three Energy Models ........................................... 160

Table 4-5: Regression Results Based on Model-Building and Validation Data Sets – Model 1 ........ 164

Table 4-6: Regression Results Based on Model-Building and Validation Data Sets – Model 2 ........ 165

Table 4-7: Regression Results Based on Model-Building and Validation Data Sets – Model 3 ........ 166

Table 4-8: Regression Results Based on Model-Building and Validation Data Sets – Diesel Fuel

Consumption .............................................................................................................................. 169

vii
LIST OF FIGURES

Figure 3-1: Methodology for IDE-ACE Development ................................................................. 22

Figure 3-2: Communication Among the System Elements ........................................................... 23

Figure 3-3: Schematic Overview of the Coal Extraction Process (P&H, 2003) ............................ 28

Figure 3-4: Common Coal Extraction Process (SME, 1992) ......................................................... 29

Figure 3-5: A General Relational Database Model – RDM........................................................... 33

Figure 3-6: Structure of Inherited Data Sources ............................................................................ 35

Figure 3-7: An Example of Using Preliminary Field List to Identify Table List .......................... 36

Figure 3-8: An Example of the Final Table List ............................................................................ 37

Figure 3-10: An Example of Table and Its Elements for IDE-ACE .............................................. 39

Figure 3-11: The Table Relationship Matrix ................................................................................. 40

Figure 3-12: An ER Relationship Diagram Developed in Microsoft VISIO Case Tool................ 42

Figure 3-13: An Example of SQL Query ....................................................................................... 44

Figure 3-14: The Fuel Extractor .................................................................................................... 45

Figure 3-15: Existing Data Sources in MS Excel .......................................................................... 46

Figure 3-16: The Primary Key Converter ...................................................................................... 47

Figure 3-17: The Overview of Tables in the SQL Server Management Studio ............................. 48

Figure 3-18: The Diagram Fuel Consumption in IDE-ACE Database .......................................... 49

Figure 3-19: Fuel Consumption Ranges ........................................................................................ 56

Figure 3-20: Logic Flow of Determining High Energy Consumer ................................................ 57

Figure 3-21: The Initial Screen for the Experiment ....................................................................... 60

Figure 3-22: The Screen Located in the Dragline Cab .................................................................. 60

Figure 3-23: The Single Report for Operator Performance for One Experimental Target ............ 61

Figure 3-24: The Dragline Cycle Phases ....................................................................................... 62

viii
Figure 3-25: The Form to Gather Data in the Fill Phase ............................................................... 64

Figure 3-26: The Form to Gather Data in the Hoist and Swing Phase .......................................... 65

Figure 3-27: The Form to Gather Data in the Return and Positioning Phase ................................ 66

Figure 3-28: Cycle Detection (Accuweigh, 2003) ......................................................................... 67

Figure 3-29: Payload Weight (Accuweigh, 2003) ......................................................................... 67

Figure 3-30: The Relationship Between the Fill Time SQL and Measured Fill Time................... 69

Figure 3-31: Search Algorithm for the Best Fill Factor ................................................................. 73

Figure 3-32: The Performance Indicator – Graphical Analysis ..................................................... 78

Figure 3-33: The Hierarchy Diagram – Top-Down Approach ...................................................... 80

Figure 3-34: The Pairwise Comparison Algorithm........................................................................ 82

Figure 3-35: Comparison Matrix for Operator Assessment for the “Selected Time Frame”

Criterion. ............................................................................................................................... 85

Figure 3-36: Comparison Matrix for Operator Assessment Based on “Annual Basis” Criterion.. 85

Figure 3-37: The IDE-ACE Web Portal ........................................................................................ 89

Figure 4-1: Typical Cross-Section of the Mine ............................................................................. 93

Figure 4-2: Production Versus Different Cycle Times, Overall Time and Fill Factors ................. 98

Figure 4-3: Production Versus Fill Distance and Fill Speed ......................................................... 99

Figure 4-4: Production Versus Energy Required to Fill the Bucket ............................................ 100

Figure 4-5: The Summary of Experimental Results .................................................................... 101

Figure 4-6: User Interface - Windows Navigation Diagram........................................................ 103

Figure 4-7: The Main Screen of IDE –ACE System ................................................................... 104

Figure 4-8: The Equipment Manager Screen. .............................................................................. 105

Figure 4-9: The Truck Production Manager Screen .................................................................... 106

Figure 4-10: The Scheduled Hours and Delays Manager ............................................................ 109

Figure 4-11: The Delay Category/Code Manager........................................................................ 110

ix
Figure 4-12: The Liquid Fuel and Electricity Allocation Forms ................................................. 111

Figure 4-13: The Employee Manager Form ................................................................................ 113

Figure 4-14: The Energy Manager ............................................................................................... 113

Figure 4-15: The History of Energy Prices .................................................................................. 114

Figure 4-16: The Road Condition Manager ................................................................................. 115

Figure 4-17: The Fuel Consumption Report ................................................................................ 117

Figure 4-18: Graphic Descriptive Statistics ................................................................................. 118

Figure 4-19: Electricity Consumption Report .............................................................................. 119

Figure 4-20: Production by Trucks Report .................................................................................. 121

Figure 4-21: The Dragline Analysis Tool (DET)......................................................................... 124

Figure 4-22: The Design of Experiment Form............................................................................. 125

Figure 4-23: The Experimental Target Form ............................................................................... 126

Figure 4-24: The DDAT Form – Data Retrieval Objects ............................................................ 128

Figure 4-25: The DDAT Form – Data Analysis Objects ............................................................. 130

Figure 4-26: The Chart Form ....................................................................................................... 132

Figure 4-27: The Normalized Form ............................................................................................. 132

Figure 4-28: The Average Values Form ...................................................................................... 133

Figure 4-29: The Summary Form ................................................................................................ 133

Figure 4-30: The CO2 Emission Form ......................................................................................... 134

Figure 4-31: Chart With Percentage Value of Change in CO2 Emission and Number of Buckets

............................................................................................................................................. 136

Figure 4-32: The Operators Performance Tool ............................................................................ 137

Figure 4-33: The Operators Evaluation for Selected Time Period .............................................. 141

Figure 4-34: The Operators Evaluation Extrapolated on an Annual Basis .................................. 141

Figure 4-35: The Operator Evaluation Based on the Minimum Unit Cost .................................. 142

x
Figure 4-36: The Boom Stress Report ......................................................................................... 144

Figure 4-37: The Pivot Chart Analysis Tool ................................................................................ 146

Figure 4-38: The Fuel Consumption Analysis Tool .................................................................... 147

Figure 4-39: The CO2 Emission Report ....................................................................................... 148

Figure 4-40: CO2 Emission from Facility .................................................................................... 149

Figure 4-41: The DOE Report ..................................................................................................... 151

Figure 4-42: The Correlation Matrix Between Variables ............................................................ 155

Figure 4-43: The Best Subset Regression Method....................................................................... 156

Figure 4-44: The Stepwise Regression Method ........................................................................... 157

Figure 4-45: Minitab Output for Regression Analysis – Model 1 ............................................... 158

xi
LIST OF EQUATIONS

FCmin  FCmax
AVFC i  (3-1) ....................................................................................... 54
2

CFCi  AVFC i  WH
(3-2)............................................................................................. 55

CFCi 1
FFCi  CFCi  (3-3) ........................................................................................ 55
2

y  1.749x  0.5204 (3-4) ................................................................................................ 68

BP  SF
FF  % (3-5)................................................................................................. 70
V  MD

EC DCS
EC  (3-6) ...................................................................................................... 70
CF  3,600

 n ( FF )
  n ( FF )

 (i)   P(i) /  P(i)   E ( j ) /  E ( j ) (3-7) ........................................................... 72
 i 1   j 1 
FD
BL  (3-8) ............................................................................................................. 72
L

 44 
CO 2  TC  FC    [t ] (3-9) ................................................................................... 74
 12 

ELC  44 
CO 2   FC    [t ] (3-10) ................................................................. 75
  EC  0.5862  12 

CO2  FL  CF [t ] (3-11) ......................................................................................... 76

 44 
CC  0.99     0.0022
 12   t 
CF   gal  (3-12) .............................................................. 76
2000  

xii
 1 x y z
1 / x 1 p q 
A (3-13).................................................................................... 81
1 / y 1 / p 1 r
 
1 / z 1 / q 1 / r 1

ES  w1  s1  w2  s 2  ...  wn  s n (3-14) .............................................................. 84

n
ES   wi  si (3-15)................................................................................................. 84
i 1

Y= Β0 + Β 1X1 + Β 2X2 + Β 3X3 + Β 4X4 + Β 5X5 + Β 6X6 ( 4-1) .................................................................. 153

Y= Β 0 + Β 1X1 + Β 2X2 + Β 3X3 + Β 4X4 + Β 5X5 (4-2) ..................................................................... 153

( SSEr  SSEf ) /( p  q)
F*= (4-3) ................................................................................. 153
SSEf /(n  p)
Y = 11.9 - 2.77 PI + 0.238 FT + 0.0317 HR - 0.0341 CT (4-4) ....................................................... 158

Y = 0.201 - 0.000823 CT + 0.00395 FT + 0.000615 HR - 0.0414 PI (4-5) ........................................... 159

Y = 4067 - 48.4 CT + 44.9 + BKT - 3.61 HR (4-6) .......................................................................... 159

 (Y i  Yˆi ) 2
MSPR  i 1
(4-7)................................................................................. 163
n
Y = 654 + 0.0306 PR + 8.59 HR (4-8) .................................................................... 168

xiii
LIST OF SYMBOLS

Average Fuel Consumption AVFC


Bucket Length L
Bucket Load BL
Bucket Payload BP
Calculated Fuel Consumption CFC
Carbon Content CC
Conversion Factor CF
Data Analysis Component DAC
Data Analysis Tool DAT
Data Management Component DMC
Database Management Block DMB
Difference Between a Production and Energy Consumption 
Drivers & Control Systems DCS
Electricity Consumed by Equipment ELC
Electricity Consumption E
Energy Consumption EC
Entity-Relationship ER
Evaluation Score ES
Fill Distance FD
Fill Factor FF
Final Fuel Consumption FFC
Fix Carbon Content FC
Foreign Key FK
Graphical User Interface GUI
Integrated Data Environment for Analysis and Control of Energy Consumption IDE-ACE
in Surface Coal Mine
Load Factor LF
Local Area Network LAN
Material Density MD
Maximum Fuel Consumption FCmax

xiv
Minimum Fuel Consumption FCmin
Normalization Form NF
Open Database Connectivity ODBC
Performance Indicator PI
Primary Key PK
Production P
Programmable Logical Controller PLC
Relational Database Management RDBM
Relational Database Model RDM
Reporting System Component RSC
Structured Query Language SQL
Thermal Efficiency of Power Plant η
Total Amount of Coal TC
Total Fuel Consumption TFC
Unified Modeling Language UML
Unit-less Energy Consumption Recorded in the DCS Database ECDCS
Vehicle Information Management System VIMS
Visual Basic for Application VBA
Volume of the Bucket V
Web Reporting Block WRB
Wireless Local Area Network WLAN
Working Hours WH

xv
Acknowledgment

I would like to express my sincere thanks to my advisor, Professor Vladislav Kecojevic,

for his tireless support and guidance. He has always provided me with useful ideas,

suggestions, and encouragement through the completion of this dissertation. With his

experience, knowledge, high standards in research, and financial support, he helped me to

rapidly overcome the research obstacles and finish this project.

I am also grateful to my thesis committee members, Professors R. Larry Grayson,

Maochen Ge, and Dongwon Lee whose precious comments helped me to improve the

research.

I thank the Department of Energy and Mineral Engineering for continued financial

support through the years of my PhD studies. My special thanks to Robert Byers for his

friendship, assistance and professionalism while I was working as the departmental IT

assistant.

I express gratitude to the people in the mining company providing me their data, which I

used for this research.

Finally, I would like to thank all my colleagues and friends from the department for their

collaboration and friendship.

xvi
Dedication

To my wife, brother and parents.

xvii
Chapter 1

1 Introduction

1.1 Background

The mining industry is a vital part of the U.S. economy and comprises the production of

coal, metal, and non-metal minerals. Globally, the U.S. is one of the main consumers and

producers of mineral commodities. Almost 23.5 tons annually per person of different

materials must be mined from U.S. land (DOE, 2004). Furthermore, in the course of a

lifetime, each American will use approximately 1,750 tons of minerals, metals, and fuels

(DOE, 2002). Coal as the low-cost energy source is used to generate the largest portion of

the nation’s electricity supply. According to the U.S. Energy Information Administration

(EIA, 2007) coal was used to generate 51.1 and 50.4 percent of electricity in 2005 and

2006, respectively. The United States is endowed with the largest coal reserves in the

world, and EIA (2007) estimates that recoverable reserves are about 268 billion tons. On

the basis of the current production rate of 1.1 billion tons per year, the U.S. has more than

240 years of coal.

The U.S. mining industry provides essential raw material for electricity generation,

production of cement, agricultural lime, the construction industry, electronics, asphalt,

medicine and many more. In other words, mining is and will remain a viable part of the

economy for many years (Kubach, 2004).

1
Mining involves three basic processes including (1) Material Extraction; (2) Materials

transport and Handling, and (3) Beneficiation and Processing. Primarily, these operations

have to be performed respecting the health and safety of miners the environment, and

economic viability of operations. The economic viability is associated with an energy

cost which is one of the largest components of the operating costs. The energy sources in

mining operations are diesel fuel, electricity, natural gas, coal, and gasoline, with

participation in total energy consumption of 34%, 32%, 22%, 10%, and 2%, respectively

(DOE, 2007). In surface coal mining, the electricity and diesel fuel are the most frequent

energy sources, while the most significant energy consumers are draglines, shovels,

trucks, belt conveyors, crushers, and bulldozers. According to the Mining Industry

Energy Bandwidth Study (DOE, 2007a) current energy consumption in the mining

industry is approximately 1,246 trillion Btu. It ranks as the sixth nationwide energy-

consuming industry in the fuel and electricity category (Pallegrino et al., 2005).

Historically, energy conservation in the mining industry is one of the highest priorities.

Great progress has been made in the rational use of energy during the last three decades.

Ever since 1973, industry in general has been reducing its consumption of energy in order

to offset substantial increases in energy cost. Early studies carried out during the 1980s

show a trend of extensive usage of electricity for trolley-assisted trucks, in-pit crushers,

and belt conveyor systems (Rixen, 1981 and Chadwick, 1982).

During the 1990s there has been phenomenal growth in computing and communication

technology, which has transformed the mining industry from what was once an intensive

labor and highly dangerous occupation to a highly technological industry. These

2
advances in technology development were key to the mining industry’s profitability and

sustainability (NMA, 1998).

Today, in reaching for simultaneous goals of cleaner and more energy-efficient

processes, the industry continuously reduces the costs of production. Initiative for energy

reduction in mining processes is accepted worldwide. The South African Department of

Minerals has set a goal to reduce current energy consumption by 15% by 2015 (Van Der

Merwe, 2007). Recently, a similar approach was established for Canadian open-pit

mines. The Mining Association of Canada (2005) provides comprehensive benchmarking

for energy consumption in mining operations based on measurements collected from

seven Canadian mines.

In an effort to make more efficient use of America’s domestic energy and mineral

resources, the U.S. Department of Energy used to fund research and development

projects related to energy efficiency in mining. As a result, several studies (DOE 2007,

2007a, 2007b, 2006, 2004, 2004a, 2003, 2002, EIA 2001) have been published. The

studies reveal the benchmarks, methods for calculating the energy consumption, and

ideas for energy saving.

The DOE’s Mining Industry of the Future (IOF) program encouraged partnerships

between private industries, Federal government, and academia to strengthen the mining

position in the U.S. economy by providing new ideas and process improvements (DOE,

2004). One of the major objectives of the IOF strategy is to increase energy efficiency in

mining by reducing energy requirements and operational cost, and improving

productivity (Mosser, 2007; DOE, 2004b). Cooperatively, the Department of Energy and

3
National Mining Association identified specific mineral commodities that require

significant energy in extraction and preparation processes (DOE, 2002). Due to lack of

“real” field data about energy consumption, the DOE has developed a methodology to

determine the energy requirements for eight of the most important commodities that

require a significant amount of energy for extraction. These results have been used to

extrapolate energy requirements for another fifty commodities produced in the U.S.

However, the methodology used for calculation has numerous uncertainties in developing

these estimates, e.g., the ratio of mineral handled per unit of production, material

characteristics, mine region, etc. An additional problem represents a lack of data on

energy consumption from operating mines. Mining companies consider these data as

confidential and often they are not willing to release them to the “outside world.”

1.2 Problem Statement

The goal of consuming less energy per ton of ore extracted remains one of the key

objectives of the mining industry. A DOE study (2007a) revealed that the mining industry

consumes about 1,246 TBtu/year of energy (3,414 Btu =1kWh). Taking into account an

average electricity price for the industrial sector of 6.25 ¢/kWh, the total cost of energy

consumed in U.S. mining is $22.81 billion. The coal industry alone consumes about 485

TBtu/year which translates to $8.88 billion per year.

According to a number of researchers and available publications (Rixen, 1981; DOE,

2002; MAC, 2005), including a recently published document Mining Industry Energy

4
Bandwidth Study (DOE, 2007), the Material Extraction and Handling, and Beneficiation

and Processing are the processes where most of the energy is being used as well as the

processes where a significant amount of energy can be saved. Surprisingly, the total

savings of 53% of current energy consumption can be achieved through investments in

state-of-the-art equipment and various R&D projects (DOE, 2007). However, the

percentage of energy savings requires additional validation since the methodology used

for the calculation relies on estimation of crucial variables (production and equipment

employed) and does not count for material properties, geometry of mine and many other

variables. These uncertainties emphasize the need for development of a new calculation

method which is based on real data from specific mining processes.

Reducing energy consumption in industry, in general, requires an effective energy

management system (Van Der Merwe, 2007). A number of researchers including Bush et

al. (2002), Dessureault (2007), and Harney (2007) concluded that successful energy

saving requires an endeavor to create a system that will be able to provide the answers to

the questions of when, where, and how much energy is being used in the mining

processes?

In other technologically advanced industries, the application of Information Technologies

(IT) and Information Systems (IS) allows managers and engineers to control the

production chain as an integrated process as an alternative to management of isolated

processes. The IS provides the framework that Harney (2007) considers as vital for

efficient utilization and savings of energy in any mining operation. The author underlines

that reduction in energy costs is feasible through accurate measurement of energy

consumption, identification of high-energy consumption units, awareness of how

5
production affects energy usage, maintaining the records about energy consumptions on a

regular basis, and by conveying information to everyone who has influence on energy

consumption. In other words, significant energy cost savings are attainable by treating the

energy as an asset instead of a non-manageable expense. Management of energy

resources requires an integrated information system capable of recording the changes in

energy consumption. The changes have to be recorded on a regular basis as either real-

time or near real-time (Bush et al., 2002). Once the data about energy consumption

becomes available, benchmarking usage and establishing performance goals can be

accomplished.

Most of the modern mining operations use several databases to continuously accumulate

data. Data are collected either automatically (real time) or manually (near-real time). The

manually collected data are usually stored in different databases (MS Access, MS SQL,

MySQL, Oracle, etc.), spreadsheet tables (MS Excel) or paper-based reports. Additional

data source that makes data management more challenging is the existence of automated

systems such as DCS (by Drives & Controls Services, Inc) or VIMS (Vehicle

Information Management System by Caterpillar). These systems store raw data at

permanent locations, while the software supplied as an integral part of the automated

system generates default reports. Any analysis that goes beyond the reports provided by

the system manufacturer requires knowledge of information technology (IT) and database

management. The lack of IT-skilled personnel at the mines would mean that the data

from the likely useful databases becomes useless in the data warehouse. An example

situation is the DCS database which records data about energy consumption, while the

software delivered from the manufacturer provides the reports for production only. As

6
more data is being collected through the mining production chain, the mines are facing

the problem seen in other high technologically advanced industries: “being data-rich

while information poor.”

Even though the mining industry strives to seek adequate solutions for high energy

consumption, thorough results are not presented. The complexity of the mineral

extraction process defines two problems that the mining industry has not solved yet: (1)

difficulties in a management process caused by a variety of stochastic processes, and (2)

dissonance in information flow from places where energy is purchased to the auditing

unit.

An integration of data sources by developing an Information Model (IM) for a generic

coal mining process and an associated software application for data management might

help in the endeavor to reduce energy consumption in coal mining. Based on the

experience of other industries that also have disintegrated production processes, the

application of Information Technology (IT) and development of an Information System

(IS) becomes the preferred approach in the attempt to solve the problem of high energy

consumption in the mining industry.

7
1.3 Scope of Work

The major scope of this work is to:

 Develop the Integrated Data Environment for Analysis and Control of Energy

Consumption (IDE-ACE) in surface coal mining;

 Develop technology and methodologies that would be incorporated in the IDE-

ACE to isolate high energy consumers based on integrated analytical processes

and data recorded in a centralized database;

 Create a novel methodology capable of utilizing the production and energy

consumption data recorded by the DCS system in order to optimize equipment

working parameters and achieve reduction in electricity consumption.

Through this research the following research questions will be addressed:

1. Does the system have potential to provide a matrix for energy savings

recognizable by DOE and applicable for wider usage in the coal mining

industry?

2. What is the difference in unit energy consumption between results obtained by

the DOE methodology and the methodology suggested in this research?

8
3. Does the suggested Information System provide the answer to one of the crucial

problems in the mining industry, high energy consumption? If so, what are the

overall benefits after the system has been integrated into a mine, and how can

the benefits be quantified?

4. Assuming that development of an Information System is an acceptable

approach to record and measure the production vs. energy consumption; what

methodology would be acceptable to use along with the Information System in

order to reduce energy consumption by optimizing working parameters without

replacing the equipment or requesting significant capital investment?

9
Chapter 2

2 Literature Review

In simple terms the mining industry is a complex interaction of disintegrated processes in

which significant amount of energy is consumed. The first step in an attempt to reduce

energy consumption is to identify the opportunities for energy savings. These

opportunities necessitate an energy management program with accurate and frequently

updated data sources. Even though the energy consumption data is partially collected

through the mining production chain, reliable information about energy consumption is

still not available. The major reason for a lack of reliable data comes from the fact that

mining companies do not make energy consumption data publicly available. Usually, this

type of information is considered to be confidential. Due to the lack of real data on

energy requirements the “SHERPA Mine Cost Estimation Model” (by Western Mining

Engineering, Inc.) is widely accepted as the methodology to calculate energy

requirements for the mining industry in most of DOE’s documents.

The purpose of the SHERPA software is to estimate operating costs for mining

operations. The minimum input data requires only an approximate production rate and

haul distances for ore and waste (Western Mining Engineering, 2007). However, the

selection of input data has to be performed by an estimator who understands the mining

production chain, and particularly equipment requirements for a given production rate.

SHERPA does not consider the variability in mining operations defined through the rock

(soil) properties, mining methods, size of equipment, customer requirements, geology of

the ore body, geography, transportation requirements, or many other factors. These

10
uncertainties as well as the questionable validity of SHERPA’s database, which may be

caused by minimal hardware requirements (386 processor, 2.5 Mb hard disk, and DOS

operating system), emphasize a need for development of a new generic methodology

specific to coal mining operations.

Historically, most of the publications regarding energy consumption and savings in the

mining industry have come from the U.S. Department of Energy (DOE), but only two

documents DOE (2002) and DOE (2007) provide quantitative data for energy

requirements in the mining industry.

DOE (2002) revealed the data for energy requirements on mining and beneficiation

processes for eight of the most important commodities (Coal; Potash, Soda Ash and

Borate; Iron; Copper; Lead and Zinc; Gold and Silver; Phosphate Rock; and Limestone).

These commodities are produced in the eastern, interior, and western mining regions of

the U.S. Focusing on the coal mining industry, the document provides data on energy

requirements calculated using SHERPA methodology for “hypothetical” surface coal

mine in the interior and western U.S. Analysis of these data shows discrepancies

generally categorized as (1) calculation errors, and (2) inappropriate and inconsistent

equipment selection. For example, the total unit energy requirement by all units for the

“hypothetical” western mine whose production is 27,778 ton/day is 55,359 Btu/ton, while

the total unit energy requirements by all units in the case of the “hypothetical” interior

mine with production of 9,967 ton/day is 77,317 Btu/ton. Based on these numbers, the

mine that has nearly three times larger capacity employs equipment that consumes about

28% less energy. Moreover, regarding equipment selection neither mine reports the use

of a dragline, even though it is (1) widely used as the overburden prime mover in surface

11
coal mining operations, and (2) recommended for small distances (70 ft.) i.e. for strip

mining in general. A summary of equipment used for both “hypothetical” mines, along

with remarks (designated by the shaded areas) that are used to point to unjustifiable and

inconsistent equipment selection are provided in Tables 2-1 and 2-2.

Table 2-1: Energy requirements for a 9,967 ton/day Hypothetical Interior Surface Coal Mine

Energy Consumption
Number Daily Sngl. Unit All Units All units All Units
Unit (Btu/ton) (Btu/hour) (Btu/day) (Btu/ton)
of units hrs/unit
1 2 3 4 5 6 7
Bulldozer 2 14 7,190 10,200,000 143,000,000 14,400
Front-end Loaders 5 14 5,110 18,200,000 255,000,000 25,550
Hydraulic Shovel 1 9.38 3,860 4,100,000 38,500,000 3,860
Rear Dump Truck 11 14 2,330 18,200,000 255,000,000 25,630
Rotary Drills 2 14 1,130 1,610,000 22,600,000 2,260
Service Trucks 2 14 477 679,000 9,500,000 953
Pumps 2 14 466 663,000 9,280,000 931
Bulk Trucks 2 13.58 462 679,000 9,220,000 925
Water Tankers 1 2.94 443 1,500,000 4,420,000 443
Pick-up Trucks 8 14 291 1,660,000 23,200,000 2,330
Graders 1 0.56 35 619,000 347,000 35
Total 58,200,000 770,000,000 77,300
Real total 21,794 58,110,000 770,067,000 77,317

12
Table 2-2: Energy requirements for a 27,778 ton/day Hypothetical Western Surface Coal Mine

Energy Consumption
Number Daily Sngl. Unit All Units All units All Units
Unit
of units hrs/unit (Btu/ton) (Btu/hour) (Btu/day) (Btu/ton)
1 2 3 4 5 6 7
Bulldozer 7 20 1,680 16,300,000 327,000,000 11,800
Cable Shovel 4 20 2,490 13,900,000 277,000,000 9,980
Rear Dump Truck 11 20 2,370 33,200,000 724,000,000 26,000
Rotary Drills 2 20 813 2,260,000 45,200,000 1,630
Service Trucks 2 20 293 813,000 16,300,000 586
Pumps 2 20 332 923,000 18,500,000 665
Bulk Trucks 2 20 293 813,000 16,300,000 586
Water Tankers 1 20 1,080 1,500,000 30,000,000 1,080
Pick-up Trucks 8 20 149 4,140,000 82,800,000 2,980
Graders 1 1.2 52 1,220,000 1,460,000 52
Total 78,000,000 1,540,000,000 55,400
Real total 9,552 75,069,000 1,538,560,000 55,359

In June 2007, the Department of Energy released a second document that provides energy

bandwidth in the mining industry (DOE, 2007). The document indicated statistics for

energy consumed in the mining industry and total energy saving opportunities that exist

in the industry if the current processes are improved by implementing more energy-

efficient practice and by using advanced technologies. As opposed to the previous DOE

study (2002), this report focuses on the average energy consumption of similar equipment

types to estimate the potential for energy savings. The equipment is grouped into

categories based on their processes (e.g., digging, blasting, material handling, crushing,

etc.) within different mining industries (Coal, Metal, and Non-Metal). Again, the data for

energy requirements are either calculated by the SHERPA methodology or have been

inherited from Energy and Environmental Profile of the U.S. Mining Industry (DOE,

2002). An additional weakness of the document is a significant number of ambiguities in

13
the numbers provided in the tables and figures. For example, the number for energy

saving provided in the tables does not match the numbers presented in the charts.

Nonetheless the document shows a methodology to indicate energy saving opportunities

and according to the results the greatest reduction for the mining processes can be

actualized in the coal and metal mining industries. The saving opportunities are

categorized in two groups: (1) Best Practice Energy Savings Opportunity, which results

from investment in state-of-the-art technologies or opportunities existing today that have

not been fully implemented in mine operations; and (2) R&D Energy Savings

Opportunity, which is saving after R&D achieves substantial improvements in the energy

efficiency. The definition of these opportunities, however, is based on subjective

assumptions and in the case of best practice energy savings is described as “…determined

from a variety of sources describing mining operations that use significantly less energy

compared to typical operations.” Similarly, the numbers for R&D energy savings

opportunity are “… derived from researchers' estimates of practical efficiency

improvements.”

In summarizing the two most relevant documents used as the references for energy

consumption in coal mining, it becomes obvious that both have (1) weakness in

methodology and equipment selected to determine energy consumptions, and (2)

variation in numbers as well as numerous subjective assumptions used to derive the

overall conclusions for energy requirements.

An accurate measurement and recording of energy consumption is a key for energy

improvements (Harney 2007; Bush et. al, 2002). Successful energy management has to

14
provide information on how much energy is been consumed by some equipment at any

given time. A method that was successfully used in other, technologically advanced

industries, to integrate the production chains into one system and improve energy

efficiency, was application of Information Technology (IT). An integrated perspective of

the Mining Value Chain with enterprise–wide application of information technology (IT)

ensures the ability of every mining process to improve energy consumption, land, capital

and labor. IT offers enormous potential for the mining industry and makes opportunities

to create new values (Sarak, 2007).

Recently, the mining industry has started with implementation of advanced IT

technologies (e.g., truck dispatching system, GPS system, etc.) which are typically multi-

software and multi-vendor. Those advances, however, create issues that mining

professionals have to deal with. According to Dessureault (2007), the first issue comes

from inconsistency of data recorded in a variety of mining processes. This problem

induces a common expression “drowning in data, starving for the information.” The

second issue introduced by Dessureault (2007) is nonexistence of an industry information

model that can be used to integrate available data into one system. Finally the author

emphasized the significance of IT literacy in mining professionals. Mining professionals

are not usually well educated in effective use and management of IT, yet, they are most

qualified to understand the physical processes behind the data generated.

Morgan (2005) also supports the idea of a common Information Model (IM) for the

mining industry. The IM defines how things are identified and what information about

those things is needed by the business. Well designed IM is a key component for the

design of a centralized database. This database should be able to accept information from

15
multiple sources, as well as to provide an access for different applications (e.g., Microsoft

Office or data query tools). The centralized database that hosts multiple data sources is

called the data warehouse. In general, the data warehouse provides the raw data used for

analysis by utilizing different software tools and data-mining techniques.

Dessureault (2007) further provides importance of data mining and data warehousing in

the mining industry. The author reminds about the variety of system control techniques

such as Just-In-Time (JIT) inventory, Flexible Manufacturing systems (FMS), and Total

Quality Management (TQM). These systems are used in advanced manufacturing and

processing, and they are an integral part of the Information System. Application of a

custom-designed IS or some different data analysis tools allows analysis of raw data

retrieved from a data warehouse by applying standardized business rules and data-mining

techniques. The example of data mining was explained by utilizing the SQL Server 2005

Business Intelligence Studio as a tool to analyze a large database (1.5 Terabyte of data).

With the data-mining algorithms integrated into the software package, the author was

able to distinguish the trends among the datasets retrieved from the database. Utilizing a

series of a neural network and linear regression data-mining module, which is part of

SQL Server 2005 Business Intelligence Studio, the author managed to build regression

models for diesel fuel consumption. These models were more accurate than models

created by conventional regression analysis using monthly averages as the dataset.

Besides numerical results, the SQL 2005 Server provides a graphical representation of

data. The importance of the graphical analysis comes from the fact that datasets are

extensively large and numerical analysis only is not a convenient way to understand the

underlying trends among the variables. This example clearly states that application of IS

16
in combination with a data warehouse is an appropriate tool for energy management and

identification of areas/equipment with high energy use.

Expansion in the volume of data available in all business sectors of the mining industry

and computer applications in the mining industry have inspired many authors to conduct

research focused mainly on improving productivity and cost performance (Grayson,

1989; Grayson, 1992; Galiev et al., 1997; Lee, 1999; Dessureault, 1999; Morgan, 2005;

Sarkka and Pukkila, 2007; Swords et al., 2007; Dessuerault, 2007; Ersoy and Celebi,

2007).

Besides, numerous research work has been performed internationally in areas related to

the application of Information Systems in the mining industry (Akhmedov et al. 2001;

Kolonja et al., 2002; Ersoy and Celeby 2007; Mundaca, 2007). The overall goal of these

systems is to improve processes and reduce the operating costs. However, these systems

are not designed to manage energy consumption of all production units at a mine site, yet

they recognize Information Systems as a key for productivity improvements in mines

(Dessureault, 2004).

Besides the IT component, an Information System for energy management has to be able

to deal with the complexity of mining processes. Emphasizing the importance of energy

consumption control, Simic et al. (1998) listed the principal factors that have influence on

energy consumption. These factors are: (1) natural; (2) technological; and (3)

organizational. The authors created a model for analysis and monitoring of energy

consumption composed of four blocks: (1) the analytic block for structural design; (2) the

analytic block for project design; (3) correction for the technological block; and (4) the

17
block for an existing technological process. The significance this model is an analysis of

all mining stages and the energy required to achieve the goals in those stages. Analysis

shows that energy saving in mining processes is attainable, yet only through an analytic

approach that includes technical, technological, design and organizational issues. In

conclusion the authors stated that the overall solution for the energy-saving process is

complex, and it requires a new approach seeks for entire system optimization. However,

the system optimization cannot be performed globally. Improvements in order to reduce

energy consumption are possible only by acting on a particular element of the system

(Staniak and Franca, 1996). In addition to equipment optimization and processes

improvements, (Coito et al, 2005) qualified the opportunities in management/personnel

structure that have influence on energy efficiency. The improvements in areas such as

limited capital investment, production concerns, and availability of information could

greatly improve energy consumption.

In summary, it appears that previous research does not systematically identify when,

where, and how much energy is being used through the mining processes. Moreover, the

existing methodology for energy benchmarking in the mining industry is based on

numerous assumptions, while the information systems developed so far do not provide a

mechanism to reduce energy consumption utilizing available data sources.

Therefore the main objective of this research is to develop an Integrated Data

Environment composed of an Information System, which is a tool to accurately record

day-to-day production/energy consumption activities, and sets of methodologies that are

able to control energy consumption based on analysis of existing data sources. The

18
Integrated Data Environment should provide a method to control energy allocation that

can be adapted and used by DOE and across the mining industry.

19
Chapter 3

3 IDE-ACE Methodology Development

3.1 Introduction

The objective of this research was to develop an Integrated Data Environment applicable

for application in the coal mining industry. Generally, the research was developed in two

phases: (1) data collection at a mine site, and (2) computer data analysis. The data were

collected at a surface coal mine, operated by one of the largest North American coal

companies. The computer analysis and system development was performed at The

Pennsylvania State University. The development of the Integrated Data Environment

included a variety of methods applied in Information Technology, Operations Research,

and Computer Programming. Detailed insight into the suggested methodology is

explained in following chapter.

3.2 Proposed Technical Approach

The proposed methodology is inspired by successful examples in other industries where

integration of existing, decentralized data creates an Integrated Data Environment (IDE).

The IDE includes Information Management and Data Analysis in a secure environment

for both internal (intranet) and external (Internet) users, while making data available only

for authorized personnel. However, while the processes are similar, the production chains

for mining cannot be adopted from other industries since the processes and equipment

20
used in mining are unique which requires development of a particular solution. This task

incorporated the sets of methodologies, software, and analysis tools into the Integrated

Data Environment for Analysis and Control of Energy Consumption (IDE-ACE) in

Surface Coal Mining. The IDE-ACE development has a basis in the technological

processes and data recorded at a surface coal mine operated by one of the largest United

States coal companies. Figure 3-1shows the concept of the IDE-ACE that was developed

through this research. The development of IDE-ACE was organized into five phases:

Data Collection and Analysis, Design, Development, Testing, and Integration.

21
Figure 3-1: Methodology for IDE-ACE development

22
3.2.1 Hardware Requirements for IDE-ACE

The development of an Integrated Data Environment is a complex, multistep process that,

besides a software component, requires a computer network infrastructure. The

information system infrastructure necessitates a design of a LAN (Local Area Network)

including the computer servers and other active and passive network components. The

design and operation of the IDE-ACE required two servers. One is a centralized database

server hosting the Microsoft SQL Database and the second, Web server, hosting the web-

based application. The web application has a permanent connection with the database

server, allowing remote access to the centralized database. Figure 3-2 shows a simplified

example of the hardware requirement for the IDE-ACE system.

Users

Work Station
Work Station

Printer

LAN NETWORK

ROUTER
INTERNET
SQL DATABASE SERVER WEB SERVER

WLAN NETWORK

Network Administrator

ON DRAGLINE SQL DATABASE

Figure 3-2: Communication among the system elements

23
However, the example of a network in Figure 3-2 shows three servers. Two servers (SQL

database and WEB) are in a LAN network. The third server, located on the dragline,

establishes a connection with the SQL database through a wireless network (WLAN).

Transfer of data between those two servers is performed on a regular basis; however, this

connection is not permanent. It changes based on the circumstances and a delay between

two consecutive updates which is managed by the network administrator.

3.2.2 Phase I – Process Analysis

Phase I provided a broad picture of the processes from which data were to be collected.

The development of information systems requires active participation of developers and

the end users (Merle, 1995). For the analysis stage, one of the most valuable sets of

information is accumulated through interviews (Davis and Yen, 1999). For the IDE-ACE

the initial information was gathered through a series of interviews with mine management

and collection of historical data from the company. The purpose of the interview was to

clarify details about inherited, historical data (legacy and paper databases) and

information about the way the organization uses its data. Interview subjects were mine

management personnel and mine employees (operations, maintenance, accounting, etc.).

A goal from the mine visit was to collect enough data for further analysis. Also, these

interviews revealed important facts used for the development of a general coal mining

model. The expectations to get data in some of the following forms were successfully

accomplished.

24
 Access database (.mdb);

 Excel spreadsheets (.xls);

 Text documents (.doc, .txt, etc.);

 Paper-based forms used for day-to-day application; and

 Electrical power invoices and fuel supply records.

Besides the physical data sources, the interviews provided information related to the

following questions:

 How is the coal mining production chain organized?

 How are the data gathered during a shift, day, or month?

 Who is responsible for data input?

 Does the organization record energy consumption? If so, how do they do that?

 What type of reporting system (for energy consumption and production) does
mine management already have?

25
3.2.3 Phase II - Design

In the Design Phase the electronic information collected at the mine as well as the

information from the interviews conducted with mine personnel were used to determine

the relationships among operational processes in both a quantitative and qualitative

manner. The result of this phase was a conceptual framework for a surface coal mining

process designed with standard, data modeling language. The data modeling language

uses graphical notation to describe a system thereby creating its abstract model.

Actually, development of an information system begins by modeling of business

processes that it encounters for activities in a particular production segment. The business

processes usually have a hierarchical structure with basic processes at the top separated

on several sub-processes. The sub-processes are related to different organizational units.

For practical purposes, different tools are available for model development. The tools

used for development have a common name CASE (Computer–Aided System

Engineering), while the methodology that is usually adjoined is CADM (Case Application

Development Method). The methodology contains the following stages:

1. Business environment understanding;

2. Business processes identification;

3. Modeling of the steps in the business processes;

4. Business processes analysis;

5. Redesign; and

6. Testing of redesigned solutions.

26
The design phase encounters, also, a data-mapping process. In other words, the data

mapping designs a connection among the elements of the system in order to incorporate

data sources into a single, integrated data environment. The data-mapping process is a

common practice in a software design engineering, and it is frequently incorporated with

other IT methodologies.

The data-mapping process has been used in IDE–ACE to establish a connection and

develop a basis for a Relational Database Model (RDM). The basis of the IDE-ACE is in

the common surface coal mining process. This process has several interrelated production

stages. For the purpose of this research, the common process is named as a general one

because it is based on the strip coal mining method. The general coal extraction process is

given in Figures 3-3 and 3-4. Figure 3-3 shows an overview of the coal extraction process

including drilling and blasting operations. However, the coal mine used for IDE-ACE

development is not using drilling and blasting operations; therefore, this segment could

not be included in the model. Figure 3-4 shows the structure chart that has a basis on the

processes from Figure 3-3. The analysis of data sources revealed information about the

number of equipment engaged in production, the type of fuel that the equipment uses,

production achievements, etc.

27
Figure 3-3: Schematic overview of the coal extraction process (P&H, 2003)

28
Figure 3-4: Common Coal Extraction Process (SME, 1992)

As mentioned, the surface coal mining process is similar for the majority of surface coal

mining operations, particularly in U.S. interior and western coal mining. Similarity in the

29
extraction process comes from discontinuous mining systems which are mainly employed

in the U.S. surface coal mining industry. Process affects both the coal and overburden

where the shovels, trucks and draglines remove excavated material.

On the other hand, existing alternatives for the coal and overburden removal are a

continuous mining extraction. In this scenario the prime movers are the bucket wheel or

chain excavators, while the material handling is performed by conveyor belts. However,

the continuous mining systems are mostly in application in Europe and Australia.

The mechanical extraction method unifies seven stages merged into a unique production

chain. These stages are: (1) topsoil removal; (2) sub-soil removal; (3) drilling and

blasting; (4) truck and shovel excavation; (5) dragline operations; (6) coal loading and

haulage; and (7) reclamation (P&H, 2003).

Topsoil removal is the phase of removing the material on either stockpiles or immediate

haulage on the spoil sides. Topsoil removal and reclamation processes are highly

correlated. The reclamation process is regulated by law, and each mine has to comply

with the remedy plan that is approved by authorities prior to mine opening.

The drilling and blasting operation is an optional process, and it depends on mine rock

properties. For example, if a coal seam is underneath a hard rock, the drilling process

followed by blasting operations will take place. The overburden at the mine that is used

as the model for IDE-ACE development is a soft material; consequently no drilling and

blasting operations are required.

30
Either blasted or directly excavated, an overburden is removed from a place by shovels

and trucks. The same equipment is also used for coal excavation and haulage to the

stockpiles or the power plant. From the economics point of view, the capital and

operating costs for the shovel and trucks are extremely high. The cost per cubic yard of

material excavated by shovel-truck operations is as much as three times more than in the

case of a dragline (Lund, 2007).

Dragline operations are very productive and mainly employed for overburden removal in

strip mining operations. Its application depends upon the geology and rock properties at

the mine. As the primary energy source, a dragline uses electricity. Because of the

powerful motors integrated into the machine, draglines consume a tremendous amount of

electricity, simultaneously making significant electricity bills. Based on similar research

(Staniak and Francia, 1996) an improvement in some of the phases of the dragline cycle

likely will make savings in electricity consumption of up to 15%. However, to make

improvements it is necessary to recognize the spots in the production chain where

improvements can be applied. This action requires a variety of experiments to be

performed.

The analysis of data from a mine reveals the links among the elements of the surface

mining system. Also, the analysis recognizes the spots in the systems that, if improved,

will result in energy reduction and potential improvement in overall equipment

productivity. For that reason, data mapping becomes an important segment in the

methodology developed for the IDE-ACE system.

31
Regarding the energy consumption, the analysis of data gathered from the mine revealed

that some variables in the model are not related. For instance, a relationship between the

diesel consumption of trucks and production was not established. However, the analysis

of unrelated datasets indicated that if the intersection between a pair of datasets exists, a

relationship between them is likely to be established. The summary of this design phase

provided the inputs for the subsequent stages in IDE-ACE development.

In general, the process followed by data mapping is the development of a relational

database model (RDM). The relational databases are frequent in the software

development engineering. They provide a convenient tool for management of large

datasets.

The integration process defines data elements (columns in the tables) and relates them to

other data elements (in different tables). For modeling purposes, the CASE tool,

Microsoft Visio 2007 was used. The MS Visio 2007 supports a standard data modeling

language - Unified Modeling Language (UML) and Entity-Relationship (ER) diagrams.

The UML has the purpose to define the system’s use cases (i.e. how the system will be

used by end users) and software components (define front-end user interface). The ERs

are used to design a Relational Database Model.

The Relational Database Model (RDM) developed in this study sets a keystone for the

IDE-ACE. Ever since 1969 when E.F. Codd introduced the RDM for the first time, it

became a popular data-management method. The RDM provides simplified data

manipulation, data integration and analysis through data visualization. The model

presents a storage mechanism for unification of available data. In a relational database the

32
relations are, basically, the tables in which particular records are stored. Each table

(relation) is composed of tuples (records) and attributes (fields). In the table each record

is designated by a uniquely defined field also known as the primary key (PK). In the case

of RDM, relationships are categorized as: (1) One-to-One; (2) One-to-Many; and (3)

Many-to-Many. Two tables will be related, by some of these relationships, sharing at

least one of the fields. Figure 3-5 shows a schematic view of the relational database

model.

Equipment

Fuel Production

Shift Crew Seam

Figure 3-5: A general relational database model – RDM

Regardless of the size and its complexity, the database design requires consistency from

the beginning through the end of the development process. A well defined framework for

a database secures a higher level of autonomy in the later stages of the process. In other

words spending less time in the development process increases a risk of facing problems

with the database through operational application (Hernandez, 1997).

33
A database design process starts analyzing the information inherited from a mine. The

first step requires a transformation of paper-based data sources into electronic form. A

stage that follows relates an existing data source and recognizes logical relationships.

These relationships provide input parameters for centralized database development. A

system that currently exists at a mine is an interaction of disintegrated and robust files.

With this system in place it becomes time costly when information retrieval is requested.

The implementation of a centralized database reduces the time to retrieve information

necessary in the decision-making process. Figure 3-6 shows a structure of inherited data

from the mine. The figure indicates that data stored in the Access Database and those

recorded in the Excel spreadsheets are not related. Therefore, the information for

production and energy consumption are not available without additional data handling.

Besides, the data-handling scenario requires a person skillful to perform this type of

analysis.

The analysis of data with the system at a mine becomes even more challenging when the

paper-based data is necessary to correlate with the electronically stored data sources.

This, as well as the continual increment in volume of automatically generated data,

imposes the application of the RDM as a practical solution.

34
DATA SOURCE

PAPER BASED LEGACY


DATABASE DATABASE

Access Excel
Database Spreadsheet

Electricity consumption

Equipment data

Fuel consumption
Production
Equipment availability
Employee
Equipment inventory

Lube consumption

Delay

Rainfall

Figure 3-6: Structure of inherited data sources

Hernandez (1997) provides the rules for successful integration of available data sources.

The comprehensive database development includes the following stages: (1) Analysis of

the existing database; (2) Creating data structures; (3) Determining and establishing table

relationships; (4) Determining and defining business rules; and (5) Reviewing data

integrity.

The analysis of existing data sources follows a process of defining the data structure. This

is a crucial step in the database design that identifies the subjects from the interviews and

legacy databases. The following example outlines a citation from one of the interviews

performed at mine.

35
“…. Most of the equipment is supplied by diesel fuel on the field. The diesel fuel
distribution is done by two fuel trucks. End dump trucks are refilled on the parking lots
close to the pit, while the bulldozers, easy miner and other equipment located on the
benches has been refilled on the spot. We have also fuel pumps where the light vehicles
and small utility trucks are refilled.”

The subjects in the sentences above (equipment, diesel fuel, fuel trucks, etc.) indicate

potential fields for the database tables. The process of creating the data structure

continues with defining a list of subjects, which in the post-filtering processes establishes

a list of preliminary fields. Figure 3-7 shows an example of a preliminary field list and

the subjects associated with it.

Figure 3-7: An example of using preliminary field list to identify table list

The remaining process aggregates the subjects from the field list to the final table list

(Figure 3-8) that was used for the overall database design.

36
Final Table List

Name Type Description

Equipment Data Mechanized equipment used in the coal and overburden


extraction process, as well as the equipment supporting
the production. It contains information required to
identify a particular piece of equipment.

Employee Data A person hired by the company to provide a service for


the jobs that he is qualified for.

Figure 3-8: An example of the final table list

The relational database design has an additional important process which makes RDMs

unique. The process is called data normalization and requires steps for efficient structure

of data in the tables. Two reasons validate the normalization. First, it eliminates

redundancy of data (i.e., recording the same data in more than one table), and the second,

normalization establishes data dependency (i.e., storing only related data in tables).

In general, data normalization is a standardized procedure, widely accepted in the

database developer community. The normalization has five stages commonly recognized

as 1NF (first normal form), 2NF, 3NF, 4NF, and 5NF, which is rarely in application.

Contrary, Hernandez (1997) emphasizes the 1NF and 2NF normalization form for the

basic database design.

An additional feature distinctive for the RDM is the concept of the primary key (PK). The

primary key is a column in the table that uniquely identifies the table and the records in

the database schema (database structure). The primary key ensures the referential

integrity of the database and, coupled with the foreign key (FK), establishes the

37
relationships among the tables. The PK is either a meaningful number (e.g., VIN vehicle

identification number) or is generically created by the DBMS (database management

system). The primary key has to:

 Uniquely identify each record in the table;

 Contain unique values;

 Cannot be null;

 Cannot be a multiplied field;

 Contain a minimum number of fields necessary to define uniqueness;

 Cannot be optional in whole or in part; and

 Directly identify the value of each field in the table.

Figure 3-10 shows an example of the steps in the database development where the PK

was associated with the field list in the table equipment. The naming convention for the

field names in the IDE-ACE database is standardized. The first three capital letters

describe the table to which fields belong (Figure 3-9), while the remaining segment is a

dedicated name. The field, field, has a descriptive purpose and in more detail explains the

field name. The lasting field, key¸ has been used to mark the primary and foreign keys.

38
Figure 3-10: An example of table and its elements for IDE-ACE

The last, but the most challenging segment in the design phase is a relationship

determination. The relationship is a corner stone in the database development

(Hernandez, 2003). The relationship establishes the link between a pair of tables that are

logically related to each other. Also, the relationship helps to further refine the table

structures and minimize redundancy. To overcome a difficulty of making a relationship, a

table matrix methodology was used. The concept of the relationship matrix is similar to a

pairwise comparison that has wide application in multi-criteria analysis. The relationship

matrix is composed of tables across the top, and then down the left side of the matrix

(Figure 3-11). The names in the matrix have to be in some order. The process of

relationship determination begins by selecting a table on the left and the table across the

top. If it exists, an appropriate type of relationship must be entered in the matrix. The

official relationships among the tables were created by applying the rules in Table 3-1.

39
Table 3-1: The relationships arithmetic

Relationship – Row Operator Relationship – Column Official relationship

1:1 + 1:1 1:1

1:1 + 1:N 1:N

1:N + N:1 M:N

The overall relationship matrix developed for the purpose of this research is given in

Figure 3-11.

Figure 3-11: The table relationship matrix

40
The ultimate goal of the design stage was to create an entity relationship (ER) diagram.

The ER diagram is a database model designed with the purpose to help a process of

physical database development. ERs are frequently used in software engineering for

creating the conceptual data model of physical systems. These models are the first stage

in the information system design, and they are used to describe information flow within a

database. Various computer-aided software engineering (CASE) tools, aggregate with

different types of notation standards, have been used for an ER design. For this research,

Barker’s notation was adopted. Among the database developers, this notation is popularly

known as a “Crow’s Foot.” The name comes from the symbols at the end of the

relationship lines. The symbols determine a cardinality (maximum) and modality

(minimum) numbers of entity occurrences in a relationship. An example of the ER

diagram used in IDE-ACE design is given in Figure 3-12.

41
Figure 3-12: An ER relationship diagram developed in Microsoft VISIO CASE tool

The IDE-ACE database design was performed on a Microsoft SQL Server 2005 platform.

The MS SQL server has advantages over the MS Access database system in improved

reliability, better performance, reduced network traffic, and scalability. This is

particularly important when the real-time monitoring system, such as DSC database,

becomes a part of the Integrated Database Block IDB. An additional preeminence of SQL

over MS Access is support for the databases where the number of records exceeds 50,000

(Express Technology, 2002).

The version of the SQL Server database used for this research was free of charge. The

version was released for educational purposes and as such lacks advanced features

42
available in Microsoft SQL Server 2005. The shortage of those features was overcome by

utilizing custom codes developed in Visual Basic for Application (VBA) and the

import/export options among the Access, Excel, and SQL platforms.

3.2.4 Phase III – Development

This was the most challenging phase in IDE-ACE design (Figure 1, phase 3). It included

development of the following sub-components: (1) Integrated Database Block – IDB; (2)

Database Management Block – DMB; and (3) Web Reporting Block – WRB.

3.2.4.1 Integrated Database Block – IDB

The IDB amalgamates multi-data sources into a unique SQL Server environment. The

physical development of IDB was supported by ER diagrams created in the Design

Phase. The tables (entities), fields, primary keys (PK), foreign keys (FK), and other

elements for the database schema in this stage are physically implemented on the SQL

server platform. Furthermore, the data from the multiple sources (Access, Excel, paper,

and DCS) were incorporated into the Integrated Data Environment. Once the data was

imported, the SQL queries (Figure 3-13) were used for data retrieval from the new

database. The fundamental static queries were converted in dynamic queries during the

software development stage. As stated earlier the design of a system such as IDE-ACE

blends a variety of methodologies and techniques for data storage into an integrated data

environment.

43
SELECT EQUIPMENT.EQPserial, SUM(PRODUCTION_TRUCKS.PROTtons) AS
total
FROM PRODUCTION_TRUCKS INNER JOIN
EQUIPMENT ON PRODUCTION_TRUCKS.EQPnumber =
EQUIPMENT.EQPnumber
WHERE (PRODUCTION_TRUCKS.PROTDate
BETWEEN CONVERT(DATETIME, '2006-01-01 00:00:00', 102)
AND CONVERT(DATETIME, '2006-12-31 00:00:00',102))
GROUP BY EQUIPMENT.EQPserial
HAVING (EQUIPMENT.EQPserial = N'171')

Figure 3-13: An example of an SQL query

Data-cleaning and data-processing techniques are used to prepare data. These processes

verify that existing data values are correct and ready to be implemented into the new

database. The purpose of data cleaning is to eliminate the errors and redundancy, increase

data reliability, and ensure data consistency. A necessity for data cleaning is especially

required when integrating heterogeneous data sources (Rahm and Hond Dai, 2000; Kan

and Tan, 2008). The heterogeneity of the data sources, in this research, results from a

variety of sources (Excel, Access, and paper based) allocated prior to data integration.

The integration should satisfy several aspects. The most important is a detection and

removal of major errors and inconsistencies from the data sets. To perform this task

Rahm and Hond Dai (2000) recommend an application of either commercial or custom-

made tools in order to minimize (eliminate if possible) manual data inspection. The

mapping functions for data cleaning along with other data transformation should be

specified in a declarative way and be reusable for other data sources. Removing the “bad”

data from available data sources helps in keeping the new database clean from garbage,

thereby providing reliable and accurate information.

44
Applying the data-cleaning and filtering techniques for this research resulted in

development of a custom VBA (Visual Basic for Application) software tool. This VBA

approach was used because data sources are either in Microsoft Excel or Access formats.

A custom-made toolbar was integrated into Excel and reused for data extraction. A macro

(Fuel Extractor, Figure 3-14) extracts the fuel consumption data from the inherited Excel

spreadsheet (Figure 3-15).

The macro allows a user to input relative coordinates of the first cell in the Excel table

containing the raw fuel consumption data, followed by the number of days in a particular

month and the first day for which a record exists in a spreadsheet. This is an iterative

process and has to be performed for every spreadsheet available.

Figure 3-14: The fuel extractor

45
Figure 3-15: Existing data sources in MS Excel

The process followed by the data extraction is data cleaning. Data cleaning is performed

together with a schema-related data transformation. The clean data matches the

conclusions from the design phase and complies with the standards defined by the ER

diagrams. For data conversion an additional macro, Primary Key Converter (PKC),

(Figure 3-16) was developed. The PKC assigns a unique VIN number to every piece of

equipment existing in the datasets. Due to a large number of data records, this process

was automated to minimize errors.

46
Figure 3-16: The primary key converter

Successful accomplishment of data cleaning provided the input parameters for data

integration into the SQL Server 2005 environment. The integration was performed

utilizing the ODBC (Open Database Connectivity) connectivity and Microsoft Access.

The ODBC presents an interface for accessing data in a heterogeneous environment. It

has application in both relational and non-relational database management (RDMB)

systems. The ODBC connectivity alleviates a need for learning multiple application

programming interfaces, focusing the developer’s efforts on the primary problem –

system development.

Utilizing the ODBC data integration, the tables were imported into the SQL server

environment. Figure 3-17 shows the tables imported into the database and SQL Server

Management Studio.

47
Figure 3-17: The overview of tables in the SQL Server Management Studio

The SQL Server Manager allows modeling of SQL database diagrams. The SQL

diagrams provide developers with a graphical overview of relations among the tables.

The diagrams can reflect the system in whole or only particular segments. Figure 3-18

shows an example of a SQL database diagram where relationships among the tables and

appropriate data types are presented. A completion of the IDE-ACE database

infrastructure initiated the following stage in IDE-ACE development - Database

Management Block.

48
Figure 3-18: The diagram fuel consumption in IDE-ACE database

3.2.4.2 Database Management Block – DMB

The development phase continued by designing the Graphical User Interface (GUI) and

the Data Analysis Tool (DAT). The aim of DMB is to provide an interaction with end

users in both error-free data entry and intuitive data analysis.

Graphical User Interface (GUI)

A graphical user interface consists of menus, buttons, textboxes, calendar controls, and

other options designed with a purpose of providing a front-end application. Therefore, the

goal of the GUI is to allow user-friendly database management. The IDE-ACE integrates

an error-free data entry through the mechanisms that monitor values entered in particular

49
fields. For example, a system prevents a user from entering a dragline production in a

field for entering the number of steps that the dragline made. This and many other data

validations are organized through pop-up message interaction. The development of the

GUI was performed in the MS Access and MS VBA environments. Utilizing the

advantages of ODBC connectivity, MS Access was connected on the back-end of the

SQL database. Since the SQL database resides on the server, the front-end application

can be deployed through a local network in a required number of instances. The final

version of the IDE –ACE is a stand-alone application, allowing the setup on any

windows-based computer system. This is accomplished utilizing the Access 2007

Runtime Library. The runtime library allows users to run the IDE-ACE on a computer

without having MS Access 2007 preinstalled.

The graphical user interface of the IDE-ACE system includes three essential components:

(1) Data Management Component - DMC; (2) Reporting System Component - RSC; and

(3) Data Analysis Component - DAC.

The Data Management Component - DMC provides data entry into the IDE-ACE

database. This part includes data input for the equipment, production, energy

consumption, employee management, and miscellaneous data input such as energy price,

production delays, rainfall, road conditions, coal/overburden seams as well as the work

codes and shift management.

The Reporting System Component - RSC provides feedback by interacting with the

system user. The user has an option to choose from among different variables and

generate custom reports. Chapter 4 provides more details on this subject.

50
The Data Analysis Tool – DAT provides an analytical tool to improve existing mining

processes by optimizing current working parameters in dragline operations and pointing

to a high diesel fuel consumer. The DAT has the goal to convert data into useful

information and convey that information to the managers. This is the most challenging

part in the development and includes the application of different methodologies. These

methodologies are explained separately in the following segment of the chapter.

3.2.4.3 Data Analysis Tool – DAT

The DAT introduces (1) a methodology for analyzing diesel fuel consumption, and (2) an

original methodology for energy savings on a dragline. The electricity saving is achieved

by optimizing the dragline fill factor through the analyses of data recorded in the DCS

database. This database records vital information for prime movers (dragline and electric

shovel). Common statistical methods are employed for analysis of available data sources.

Also, a regression analysis was used to determine significant relationships among the

variables having an influence on energy consumption. One of the benefits that the system

provides is a comparison of existing energy consumption data with the estimations

provided by DOE.

The calculation and analysis of real diesel fuel consumption is based on the records from

database, retrieving the data for: (1) fuel consumption, (2) production, and (3) equipment

time utilization. The result of such analysis is compared against the data provided by the

equipment manufacturer (nominal fuel consumption). The difference between those

numbers (real fuel consumption versus nominal fuel consumption) designates the high

51
energy consumer. A further step in the fuel reduction process aggregates the service and

maintenance plan and as such goes beyond the scope of this dissertation.

More detailed analysis in order to determine “the high fuel consumer” is provided later in

the chapter. The equipment employed at the mine is mainly produced by Caterpillar.

Caterpillar’s handbook (CAT, 2007) provides nominal fuel consumption data for any

piece of equipment. The nominal fuel consumption is determined based on the load

factors (LF) that can be: (1) low, (2) medium, or (3) high. In general, the LF is a function

of rolling resistance, hauling time, road conditions, etc.

Table 3-2 shows a detailed overview of load factors for the equipment available in the

IDE-ACE database. The medium load factor is recognized at the mine providing the data

for this research.

52
Table 3-2: The load factor guide (CAT, 2007)

LOAD FACTORS
LOW MEDIUM HIGH

Large amount of Normal load and haul Long haul time with
idling. Short to time. Varying load and frequent adverse
medium hauls on well haul road conditions. grades. Continuous
Trucks

maintained level haul Some adverse grades. use on very poorly


roads. Minimum total Some high rolling maintained haul
resistance. resistance roads with high
rolling resistance.

Considerable idling or Production dozing, Steady ripping,


travel with no load. pulling scrapers, most shuttle pushloading
pushloading. and downhill dozing.
Bulldozers

Agricultural drawbar Agricultural drawbar


work at full throttle but work at full throttle,
EQUIPMENT

not always lugging engine lugged to


engine. Some idling max. power most of
and some travel with the time. Little or no
no load. idling or travel in
reverse.

Finish grading, light Average road Ditching, fill


Motor Graders

maintenance, road maintenance, road mix spreading, spreading


travel. work, scarifying, snow base material,
plowing. ripping, heavy road
maintenance, snow
plowing.

Most utility, urban Most residential sewer Most pipeline


Excavators

applications in sandy applications in natural applications in hard


loam. Digging less bed clay. Digging 60- rocky material.
than 50% of the daily 85% of the daily work Digging 90-95% of
work schedule. Scrap schedule. Most log the daily work
handling applications. loading applications schedule.

53
For the analysis, the real fuel consumption was compared against the fuel consumption

that equipment might consume if working in low, medium, or high load conditions. For

every piece of equipment, the CAT handbook provides ranges of fuel consumption values

and these values are recorded in the IDE-ACE database. Table 3-3 shows an example of

fuel consumption ranges for the truck CAT 784C.

Table 3-3: Fuel consumption based on the load conditions (CAT, 2007)

Equipment LOW Medium High


[gal/hour] [gal/hour] [gal/hour]

Min Max Min Max Min Max


CAT 784C
14 21 21 29 29 38.5

Simultaneously, by querying the database, an “on the fly” calculation estimates the fuel

consumption. An average value of nominal fuel consumption is recognized as the

multiplier for this calculation. Averaging the fuel consumption is justified by the ranges

of values provided in the CAT handbook. The average fuel consumption value is

calculated as follows:

FCmin  FCmax
AVFC i  (3-1)
2

Where, AVFCi (gallons/hour) is the average fuel consumption, i is one of the load factors

(low, medium, or high), FCmin is the minimum fuel consumption for a given load factor

(gallons/hour), and FCmax is the maximum fuel consumption for a given load factor

(gallons/hour).

54
The average fuel consumption is further multiplied by the number of working hours that

the equipment has accumulated over a time period. The result of multiplication is the

calculated fuel consumption (CFC) for selected time frame and load factor i.

CFC i  AVFC i  WH (3-2)

The last calculation preceding the fuel consumption comparison adjusts the CFC.

Namely, the equipment with the real fuel consumption was evaluated based on the load

factor of the next larger CFC. For example, let us assume a truck consumes 11,000

gallons of diesel over a time period. Further, let us assume that calculated values (CFC)

indicate the fuel consumption for the low load factor of 6,000 gallons and the medium

load factor of 12,000 gallons. As a result, the equipment consuming 11,000 gallons will

be categorized as the medium consumer because the real fuel consumption is closer to the

value for medium load factor. The mechanism of calculation for this analysis has a

formal definition in:

CFCi 1
FFCi  CFCi  (3-3)
2

Where, FFC is final fuel consumption used for the comparison, CFC is calculated fuel

consumption, and i load factor.

55
The equation (3-3) applied on the three load factors eventually defines the low, medium,

and high fuel consumption ranges. Figure 3-19 illustrates these ranges and the positions

of calculated fuel consumptions (CFCi) within the ranges.

LOW RANGE MEDIUM RANGE HIGH RANGE

CFClow CFCmed CFChigh

Figure 3-19: Fuel consumption ranges

The fuel consumption analysis explained above has a comparative purpose only. It relies

on the assumption of average working/road conditions and it is exclusively used with the

purpose of allocating potentially high energy consumers. However, further analysis has to

confirm or decline initial assumptions. In an effort to determine the high energy

consumer, the algorithm in Figure 3-20 was developed and integrated in the IDE-ACE

code.

56
START

Retrieve data for selected fleet and time frame

Retrieve data for nominal fuel consumption


and calculate the average value AVFC

Set initial parameters

multiplier=AVFC(i)
multiplier_counter=1
equipment_counter=1
equipment_total=n

i - avg. fuel consumption for low, medium,


and high load factor
i=1,2,3

Calculate the fuel consumption for AVFC(i)


using a working hours that equipment
accumulated in a selected time frame

TFC(i)=AVFC(i)*WH

Compare the real fuel consumption for


selected time frame and equipment against the
calculated values from the previous step

NO

Add the equipment in the NO


Real cons.>Calculated cons. YES
category i+1

NO

Select next equipment in the fleet for the


same multiplier AVFC(i)

equipment_counter>n

YES

multiplier_counter=3

YES

END

Figure 3-20: Logic flow of determining high energy consumer

57
The Database Management Block designed for analysis and optimization of dragline

operations was developed in three steps.

Step 1 – Field trip and data collection at mine site. This step included designing the

experiment and developing a set of procedures to collect data from a dragline. Also,

software tools were designed for data collection and comparison against the data recorded

in the DCS database.

Step 2 - Analysis of data to establish the relationships among the variables having

the influence on energy consumption. The result of this process was the development of

a methodology and algorithm for semi-automated data analysis to achieve “the best

bucket fill factor” from the data recorded in the DCS database.

Step 3 – Integration of results from Step 2 into the Search Algorithm for the Best

Fill Factor and design of Data Management Block. The algorithm was originally

developed for this research and it is based on the general search algorithm widely used in

the computer science.

58
Step 1 – Field trip and data collection at mine site

Introduction to Experiment

The coal mine used for the data collection is located in southern part of the United States.

(Due to confidentiality reasons, the name and accurate location of the mine will not be

revealed; however, general information about the mine and geology are provided.) There

are nine coal seams in total with thicknesses ranging from 12” to 60”. The top three

seams are not minable because of low coal quality. This region of the U.S. is

characterized by high amount of rainfalls. The mine has complex geology and a

significant amount of annual rainfall (6 ft). The mine produces approximately 3.5 million

tons of coal per year. The operation utilizes diverse mining equipment: Dragline Marion

8200, electric shovel P&H 2800, Caterpillar end dump trucks CAT 785 and 789B (with

payloads of 180 and 200 t, and respectively); bulldozers CAT D11, D10, and D6; as well

as the Huron easy-miner and various auxiliary equipment.

The experiment was performed with the objective of measuring the dragline cycle time in

order to evaluate the bucket fill factor versus the dragline energy consumption and

productivity. For the testing purposes a custom application for data collection was

developed (Figure 3-21).

59
Figure 3-21: The initial screen for the experiment

This data collection application was used for data acquisition directly from the dragline

cab by observing and recording the information from the screen located in front of the

dragline operator (Figure 3-22).

Figure 3-22: The screen located in the dragline cab

60
Included in this objective was the task of analyzing gathered data and generating a report

(Figure 3-23). The results from these reports are stored in the spreadsheets and used for

subsequent statistical analysis.

Figure 3-23: The single report for operator performance for one experimental target

The objective of the experiment also included the data comparison between surveyor-

recorded data, and data retrieved from the DCS database. For every experiment target, the

required comparison was performed. The experiment targets were defined as 70%, 80%,

85%, 90%, and 100% fill factors of the 82 yd3 bucket with 15% swell factor and an

61
average density for all burdens of 1.6 t/yd3. For practical purposes the targets were

redefined as pounds of overburden in the dragline bucket. The weights in the bucket were

179,722 lb., 182,539 lb., 193,948 lb., 205,375 lb., 228,174 lb., respectively. Throughout

the experiments the operators were challenged to achieve the weights indicated above.

While digging, the operators were in position to keep the pace of weight in the bucket

while focusing on the number being displayed on the screen.

Analyzing the results, the best fill factor for running the experiment was obtained. The

objective of the best fill factor was to maximize the average production and minimize

energy consumption during the load phase of the overall dragline cycle (Figure 3-24).

Positioning

Return
Time

Dump

Hoist and Swing

Loading Advance
(Dragging)

0 Operation

Figure 3-24: The dragline cycle phases

Two additional constrains were considered in this experiment. One of the constrains

limits the fill time in the range of 16-18 seconds (GBI, 2000). The other constrain

(Dragline Productivity Center, 2001) recommends that the dragline bucket in soft and dry

62
material should be filled in up to three buckets lengths. Practically, if the bucket length is

20 ft., a dragline operator should disengage a bucket when it reaches 60 ft.

An additional goal in the experiment includes the comparisons of the numerical targeted

fill factors with those described in words. For this experiment the words “Fill as Best as

Possible” and “No Dozing Effect” were identified as targets. Such information provides

visual indications about the moment when to stop the fill and start the hoist phase. For

instance, if the optimum numeric fill factor has a targeted value of 80% (193,948 lb), and

the “No Dozing Effect” has a target corresponding fill factor of 81%; the operator should

have a visual perception about the optimum weight in the bucket. This concept cannot be

accepted as the general rule and the visual perception has to be adjusted according to the

measurement provided on the screen in a dragline cab. Supporting results and discussion

for this experiment setup are provided in Chapter 4.

Experimental procedure

The cycle time measurement was initialized from the moment the bucket was positioned

on the ground and the operator started the digging phase. The experiment trials were

conducted measuring the different sub cycle times. For experiment purposes, the overall

cycle time is the sum of the following sub times: (1) fill time; (2) swing time – full; (3)

swing time – empty. When not digging in the regular condition (e.g. front cut), a dump

time of 5 seconds was added to the swing time-full. The sub-time 5 second time is the

average value resulting from the experiment.

63
The fill time is a segment of the overall dragline cycle time. It is measured from the

moment when the bucket touches the ground and the digging phase begins, until the

moment a drag payout phase starts. As soon as the operator started to fill the bucket the

first time stamp was recorded. The second time stamp was recorded when the operator

started to hoist the bucket, i.e., when the drag payout phase starts. The difference between

these two time stamps determines the bucket loading time per cycle.

The form in Figure 3-25 was designed to record not only the loading time, but also the

material weight, volume, and dump height used for the later bucket fill factor calculation.

The loading time that was ranging between 16-22 seconds allowed the surveyor enough

time to enter required data in the form.

Figure 3-25: The form to gather data in the fill phase

In the experiment, the swing time-full equals the maximum value of drag payout, hoist,

and swing time. The reason being is that all these phases in the dragline cycle operators

are performed simultaneously. Moreover, some of them are not even possible to perform

64
without simultaneously running two or more activities. The swing full phase ends when

the material from the bucket is dumped on the spoil. In the case when a hoist phase ends

before a swing phase (swing limited situation), the application provides an option to take

the time stamp at that particular moment (Figure 3-26).

Figure 3-26: The form to gather data in the hoist and swing phase

Similarly, the swing time-empty starts the moment the boom begins the movement

toward the high wall and ends once a bucket touches the ground. This phase also

accounts for several single phases being performed at the same time (swing empty, drag

in, positioning, and lowering). In the event where the swing phase ends earlier than the

lowering phase, the form in Figure 3-27 allows recording of the end of swing phase. This

usually occurs when the operator tries to position the bucket on the high wall and/or

when digging the maximum depth. In either case, the dragline operates in a hoist-limited

condition.

65
Figure 3-27: The form to gather data in the return and positioning phase

As the surveyor gathers the data in a dragline, the DCS system simultaneously records

new events in the SQL database. The system integrated in a dragline has sets of PLCs

(Programmable Logical Controller) that sample 20-50 times per second and store 20

parameters per cycle in the database. The records in the database are average values of

measurements taken in the single dragline cycle. The data flow from the moment when

the cycle starts until the moment the data is being stored in the database has three steps:

(1) Cycle Detection, (2) Payload Weight, and (3) Write to Database. (Accuweigh, 2003).

The DCS system starts to measure and record the events for the new cycle the moment a

material in the bucket is dumped (Figure 3-28). The PLC system initiates the weighting

material procedure at the moment the material in the bucket is heavy enough to invoke

the system trigger (Figure 3-29); however, the actual loading time begins earlier, i.e., at

the moment the bucket is first dragged through the waste material, finishing when the

bucket is ready to be hoisted (Dragline Productivity Center, 2001).

66
Figure 3-28: Cycle detection (Accuweigh, 2003)

Figure 3-29: Payload weight (Accuweigh, 2003)

67
Analysis of the “Weight on rope vertical component with drag/crowd influence”

component of Payload Weight algorithm implies a need for comparing the results stored

in the DCS database with the real (in-situ) measurements. This comparison has an

explanation in a delay existing between the loading time recorder by DCS system and the

real fill time recorded by the surveyor.

Step 2 – Data Analysis

The bucket fill factor, together with the cycle time, is one of the crucial parameters that

determine the dragline’s optimal production for a given bucket size and the mechanical

properties of material.

As mentioned, the difference in the bucket loading time measurements existing between

the DCS and in-situ measurement requires statistical analysis in order to establish a

relationship between measurements. The regression analysis of variables Fill Time SQL

(predictor, x) and the Measured Fill Time (response, y) resulted in following equation

with R2=0.7279.

y  1.749x  0.5204 (3-4)

This equation was used as the correction equation for the SQL time retrieved from the

database and it is implemented into software code of the IDE-ACE system. This

correction means that every fill time recorded in the database will be adjusted on the real

fill time. The regression analysis was performed using MS Excel and Minitab statistical

software. Figure 3-30 shows the relationship between the measured load time and the

SQL load bucket time.

68
Fill Time SQL vs. Measured Fill Time

35

30
y = 1.749x - 0.5204
Measured Fill Time [sec]

25 R2 = 0.7279

20
Fill time
Linear (Fill time)
15

10

0
- 5 10 15 20
Fill Time SQL [sec]

Figure 3-30: The relationship between the Fill Time SQL and Measured Fill Time

The experiment was performed in the multi-seam environment. The seams are dissimilar

in their material properties and this variability was used to advantage to develop a model

potentially applicable for many surface coal mines. In other words, application of the

system developed for the multi-seam coal extraction can easily be adjusted for single-

seam operations. Based on the experiment setup, when varying the bucket fill factor,

different production capacities, and accompanying energy consumptions were obtained.

Deeper insight into the DCS database schema and the records available in the database

indicates that the system records energy consumption in the digging phase only. Due to

this fact, the energy consumption for the remaining phases of the overall dragline cycle

was accepted as a constant value.

The main focus in this experiment was related to the relationships between the energy

consumption and production rates. However, more details on the experiment results and

discussion are provided in Chapter 4.

69
The Equation 3-5 brings into relationship the variables to calculate the targeted fill factor

(FF).

BP  SF
FF  % (3-5)
V  MD

Where: BP is bucket payload [t], SF is swell factor, V is volume of the bucket [yd3], and

MD is material density [t/yd3].

The IDE-ACE integrates conversion of unit-less numbers recorded in the DCS database

into the standardized unit, kWh. Namely, the DCS system records the information

provided from the PLSs in the raw format. That format has to be adjusted in order to

measure the electricity consumption in kWh. For this purpose, the DCS manufacturer

provides a conversion coefficient. The conversion coefficient is not a unique number,

therefore the calculation has to be adjusted for different applications. To alleviate this

variability in the conversion coefficients, the IDE-ACE has integrated interaction with the

system users, allowing adjustment of the coefficient values. This feature compensates for

variability and allows the system to be relevant to different surface coal mines. For

conversion of unit-less numbers into kWh the following equation was used.

EC DCS
EC  (3-6)
CF  3,600

Where: EC is energy consumption [kWh], ECDCS is unit-less energy consumption

recorded in the DCS database, CF is a conversion factor provided from the system

manufacturer.

70
As mentioned, the conversion factor differs from one DCS system to another. In order to

evaluate the electricity consumption the IDE-ACE system user needs to contact the DCS

manufacturer and inquire about the information for the particular dragline. The data the

manufacturer needs to be supplied with are the dragline model, the name of mine, and the

name of the company running the mine. The replay from the DCS Company contains a

single number that has to be entered in the IDE-ACE and used for the conversion.

Step 3 – Integration of Results into Algorithm

This step summarizes the analysis of the experimental results in order to establish the

relationships among the variables and the results. The main focus is on the relationship

between the energy consumption and the production rate. This relationship designates

two functions: production, f1(x) and electricity consumption, f2(x). The maximum

difference between those functions f1(x)-f2(x) in characteristic points (targeted fill factors

on the x – axis) designates the best fill factor for given conditions. This maximum

difference is distinguished as the delta () and it is used for further model (IDE-ACE)

development and data analysis.

A calculation for delta includes several steps. The process starts by normalizing the

results recorded for both electricity consumption and production in the SQL database.

The normalization justifies different orders of magnitude of electricity consumption and

production rates. The order of magnitude for the production rate is 3, while the order of

magnitude for the energy consumption is 6. Respecting this difference, the numbers have

to be normalized and transformed into values between 0 and 1. Upon normalization, the

71
difference between the production and electricity consumption () is calculated. The

process of normalization is defined by equation (3-7):

 n ( FF )
  n ( FF )

 ( i )   P ( i ) /  P ( i )   E ( j ) /  E ( j ) (3-7)
 i 1   j 1 

Where: i=1,2,…n(FF); j=1,2,…n(FF); n(FF) is a number of targeted fill factors, P(i) is a

production for i-th targeted fill factor; E(j) is an electricity consumption for j-th targeted

fill factor.

As the experiment showed, the maximum delta is not the only constrain being considered

to evaluate the best fill factor. The fill time and bucket lengths constrain are also

integrated into the analysis and algorithm development. As a calculated value, the bucket

length is a function of the fill distance and bucket length. The bucket length is a technical

detail accepted from the manufacturer, while the fill distance is the experimental

outcome. The number of bucket lengths is calculated utilizing the formula:

FD
BL  (3-8)
L

Where: BL is number of buckets [unit-less number], FD is a fill distance [ft.], and L is a

bucket length [ft.].

All three constrains (delta, fill time, bucket lengths) are integrated in the search algorithm

for the Best Fill Factor (Figure 3-31).

72
START

Design an experiment and select


targeted fill factors FF

Input data from experiment sheet.


Retrieve Production P(i) and Energy E(i)
data into arrays P(i) and E(i)

Normalization

 n( FF)
  n( FF)

 (i)  P(i) / P(i)  E( j) / E( j)
 i 1   j 1 
i=1,2,... FF j=1,2,…FF
NO n(FF) – number of targeted fill factors

Store (i) into array_delta

i>FF

YES
Fill Factor for criteria MAX difference
Store FF*( ) in final_array
FF*( )=MAX (i)

Retrieve fill time and FF from database

NO
i>n(FF)
and
16<FT<18

YES
Store Fill Factor for criteria Fill Time into
array_filltime

FF*(FT)=MIN(array_filltime) Store FF*(FT) in final_array

Retrieve bucket length and FF from


database

NO

i>n(FF)
and
3≤BL<4

YES

Store Fill Factor for criteria Bucket


Length into array_bucketlength

FF*(BL)=MIN(array_bucketlength) Store FF*(BL) in final_array

The Best Fill Factor, FF*


END
FF*= MAX (final_array)

Figure 3-31: Search algorithm for the best fill factor

73
3.2.4.3.1 CO2 Analysis – Emission from the Coal

In this research, the CO2 emission is expressed in terms of tons of CO2 emitted from the

weight of the coal being burned in a power plant in order to generate electricity and

supply equipment at the mine. Estimation for the CO2 emission is also performed for the

facilities (maintenance and office buildings) located at the mine site.

The calculation for CO2 emission has basis in the combustion process of fixed carbon

content that is restrained in a volume of coal. Carbon dioxide forms during a coal

combustion process when one atom of carbon (C) reacts with two atoms of oxygen (O),

(C+O2 CO2). Since the atomic weight of carbon is 12 and that of oxygen is 16, the

atomic weight of carbon dioxide is 44. Therefore, the equation used for CO2 calculation

(Nevers, 1995) is defined as:

 44 
CO 2  TC  FC    [t ] (3-9)
 12 

Where: TC is a amount of coal for which one calculates the CO2 emission [t], FC is a

fixed carbon content that coal contains [%/100], 44/12 is ratio of molecular weight of

CO2 to the molecular weight of carbon C. The values of fixed carbon content are

provided in Table 3-4.

74
Table 3-4: Fixed carbon content (Stefanko, 1983)

Coal Fixed Carbon Component Btu value [Btu/lb]

Anthracite 86% - 98% >15,500

Bituminous 45% - 86% 10,500 - 15,500

Sub bituminous 35% - 45% 8,300 - 13,000

Lignite 25% - 35% 4,000 - 8,300

The fixed carbon content used for calculations in this research is 32.5%. It was calculated

based on the coal quality specified in Btu per lb of coal. The coal from the mine has an

average value of 5,200 Btu per pound.

Additional calculation to determine the amount of CO2 emitted from the electrical

equipment was performed. The process converts the electricity consumption in kWh to

the amount of coal burned at the power plant that supplies the mine with the electricity.

This calculation accounts for power plant efficiency, Btu value of coal burned, carbon

content for the coal, and conversion factors. A calculation of the amount of CO2 from the

equipment running on electricity uses following formula:

ELC  44 
CO 2   FC    [t ] (3-10)
  EC  0.5862  12 

Where: ELC is the amount of electricity consumed by equipment [kWh], η is the thermal

efficiency of power plant, 0.5862 is a conversion factor used to convert Btu/lb into

kWh/t, EC is energy content of the coal (5,200 Btu); FC is a fixed carbon content

[%/100], and 44/12 is the ratio of molecular weight of CO2 to the molecular weight of

carbon C.

75
3.2.4.3.2 CO2 Analysis – Emission from the Liquid Fuels

Similar to the carbon content in a coal, the liquid fuels contain carbon residue (Speight,

1999). The carbon dioxide emission from the liquid fuels (FL in gallons) is a product of

the fuel amount (FL) and the conversion factor (CF).

CO2  FL  CF [t ] (3-11)

The conversion factor varies based on the fuel type. According to the EPA (2005), the

diesel fuel conversion factor is 0.0112; the gasoline has a value of 0.0097. These factors

are calculated based on the carbon residue (carbon content) in one gallon of diesel or

gasoline fuel. The carbon content for the diesel is 2,798 grams, and for the gasoline it is

2,421 grams (EPA, 2005). The oxidation factor for all oil and oil products is 0.99.

Practically, this means that 99% of fuel burns out while 1% remains un-oxidized. The

conversion factors for the CO2 emission for liquid fuels are calculated based on the

formula:

 44 
CC  0.99     0.0022
 12   t 
CF   gal  (3-12)
2000  

Where: CC is carbon content for the fuel [g], 0.99 is oxidation factor, 44/12 is ratio of

molecular weight of CO2 to the molecular weight of carbon C.

76
3.2.4.3.3 The Performance Indicator (PI)

The Performance Indicator (PI), in this research, is being used as a reliable variable for

various evaluation processes. The importance of the performance indicator resulted from

analysis of data collected through the experiment.

The PI is an indicator of an operator’s efficiency in terms of electricity use and

productivity for a given electricity input. In general, the performance indicator is either

positive (+) or negative (-), (Figure 3-32). The negative performance indicates that an

operator spends more energy which produces an overburden. In other words, the specific

energy consumption in terms of [kWh/t] is negative. To determine the PI, the input

variables required are the energy consumption and the production rate records

accumulated over the time frame when the operator worked. The energy consumption in

the digging phase is the electricity that an operator spends during the digging phase of the

overall dragline cycle.

The PI calculation requires several steps and the process is based on the normalization

procedure and the difference between production and energy consumption. The PI sign

designates the operators qualified for the succeeding steps in the process of determining

the best operator respecting the optimal energy consumption. Therefore, an analysis of an

operator’s performance can be performed graphically and mathematically. An example of

the graphical analysis is demonstrated in Figure 3-32.

77
Figure 3-32: The Performance Indicator – graphical analysis

Figure 3-32 illustrates the energy consumption and production rates among the operators.

The operators are displayed on the x-axis while the y-axis contains both the normalized

energy and production rates. The positive difference between the production and energy

consumption designates the energy efficient operators. The case with the negative PI is

opposite. Therefore, the negative difference points out, in terms of energy, the most

inefficient operators over the selected time frame.

A mathematical calculation of the performance indicator is based on the normalization of

energy and production rates. (This process of normalization was explained in detail in

previous parts of the IDE-ACE methodology discussion). Once the data is normalized,

the algebraically calculated difference between the production and electricity

consumption determines the sign of PI. The cardinality of the PI set is determined by the

number of the operators with positive (+) PIs.

78
A constrain that further diminishes the cardinality of PI set is based on the number of

working hours an operator accumulated over a selected time frame. An accumulated

number of hours that is less than one standard deviation eliminates the operator from

further analysis. More detailed explanation for this type of analysis follows in the next

segment of theses.

3.2.4.3.4 Operator Performance Evaluation - Analytical Hierarchical Process

The operator performance assessment is an important issue in many industries and

professions. For the assessment, the multiple criteria analyses are usually adopted

(Bernold et al., 2002; Johannes et al., 2007; GBI, 2001). Also, different methodologies

are applied to estimate the operator performance. The analytic hierarchy process (AHP) is

a method for dealing with problems that involve the consideration of multiple criteria

simultaneously. AHP was developed by Thomas L. Saaty (1980) and ever since it has

been modified and adjusted for a variety of applications. In spite of some shortcomings

(Dyer, 1990; Ramananthan and Ganesh, 1995), the literature shows that the analytic

hierarchy process has been successfully applied in the practice.

The AHP has been applied to problems for many disciplines. In the surface mining

industry, it is widely accepted for solving problems in equipment selection,

environmental impact, and decision-making processes (Komljenovic and Kecojevic,

2006; Bascetin, 2004; Bascetin, 2006; Bascetin, 2003; Herzog and Bandopadhyay, 1996).

One advantage of the AHP is that it provides a comprehensive and logical analysis of

problems for which considerable uncertainty exists (Komljenovic and Kecojevic, 2006).

79
The essence of this process is a decomposition of complex problem into segments and

development of a hierarchy with the objective (goal) at the top, and criterions, sub

criterions, and alternatives at the bottom (Pohekar and Ramachandran, 2004; Bascetin,

2004). The hierarchy diagram in Figure 3-33 shows a decomposition of problem in this

research. The N Operators is an alternative that changes depending on the time frame for

which an evaluation is running. For example, selecting the best dragline operator over a

period of one day gives the alternative of four operators. Similarly, running the analysis

over a one-month time frame gives the alternative of 12 or more operators.


GOAL

Select the best dragline operator


CRITERIA

Unit Unit energy Working Annual Annual


Fill time Cycle time Angle
Production consumption hours Production Cost
[s] [s] [deg.]
[t/h] [kWh/t], [h] [t] [$]
ALTERNATIVES

N N N N N N N N
Operators Operators Operators Operators Operators Operators Operators Operators

Figure 3-33: The hierarchy diagram – top-down approach

Going further in the process, the criteria at a given hierarchy level are compared in pairs

assessing their relative importance. This process is called pairwise comparison. For this

comparison, Saaty developed the scale ranging from 1-9. The values 2, 4, 6, and 8 are

80
used to determine compromise values of importance. Table 3-5 shows the levels of

comparison and assigned descriptions.

Table 3-5: Numerical scale for comparative judgment of indicators

Level Description

1 Equal importance

3 Moderately more important

5 Strongly important

7 Very Strongly Important

9 Extremely more important

Based on this level one makes a judgment and assigns relative weights to the criterion

(indicator). For this process, the pairwise comparison method necessitates the application

of a comparison matrix. The formal representation of this matrix is as follows:

 1 x y z
1 / x 1 p q 
A (3-13)
1 / y 1 / p 1 r
 
1 / z 1 / q 1 / r 1

Saaty (1990) explains several different approaches to calculate the relative weights

utilizing the pairwised comparison. The method averaging over normalized columns to

estimate eigenvalues of the matrix is used for the purposes of this research. It consists of

steps defined through the algorithm shown in Figure 3-34. The result is a weight with a

value between 0 and 1. Totaling the individual scores from this analysis gives a score

equal to 1; otherwise the calculation of weights is not valid.

81
STEP 1

Calculate the sum of each column.

STEP 2

Normalize the elements in each column by


dividing the column sum. Add normalized
elements to each row.

STEP 3

Divide the row total (Step 2) by the number


of criteria compared.

STEP 4

Calculate relative weights for criteria


judgments from other experts (if more
people analyzing data).

STEP 5

Calculate the final score (FS).


FS=Relative weight*Score

Figure 3-34: The pairwise comparison algorithm

The pairwised comparison technique was applied in order to obtain the weights of the

criteria used for operator performance assessment. These weights are further employed to

calculate the evaluation score that is used to determine the best operator. Eight criteria

have been used to assess dragline operator performance. These criteria are:

82
1. Fill time [s] - the time that operator needs to fill the bucket with the material;

2. Cycle time [s] - the total time required to complete full dragline cycle (fill

time, swing with full bucket, dump, swing with empty bucket, and positioning

the bucket);

3. Angle [deg.] – defined as the average angle over a one-hour period. The angle

is measured from the moment the operator starts swing with full bucket until

the end of the dump phase;

4. Working hours [h] - specifies the total number of hours an operator worked

in selected time period;

5. Unit production [t/h] - designates the production that an operator achieved

over a one-hour period;

6. Unit energy consumption [kWh/t] - designates the electricity consumption

per ton of overburden, over a one-hour time frame, in the digging phase of the

overall dragline cycle;

7. Annual Production [t] - an extrapolated value calculated from unit

production and the cycle time.

8. Annual Cost [$] - appoints an extrapolated value resulted from the annual

production and unit electricity cost [¢/kWh].

The operator assessing process contains three categories: (1) assessment for the selected

time frame, (2) assessment on an annual basis, and (3) minimum cost. These categories

are assimilated in the IDE-ACE as optional buttons available on demand.

83
The assessment for the selected time frame utilizes the top six criteria listed above, while

the assessment on an annual basis integrates all criteria. The assessment according to

minimum cost [$/t] does not use the criteria weights; however, it evaluates the

performance based on the cost of electricity that an operator spent removing the total

amount of overburden over a one-hour time frame. The ranking of the scores starts in

deseeding order, pointing to the least expensive operator.

Again, it is important to mention that the operators with negative performance indicators

and less working hours than one standard deviation are disqualified from the evaluation.

The weights calculated by the pairwised comparison are further used to determine the

overall evaluation score, which is used as the criterion to evaluate an operator’s

performance. The evaluation score (ES) is calculated as follows:

ES  w1  s1  w 2  s2  ...  w n  sn (3-14)

n
ES   w i  s i (3-15)
i 1

Where: w is the weight for each criterion, s is the score for each option, and n is number

of criteria used for the evaluation.

Applying AHP and pairwised comparison on this research, reveals two comparison

matrixes. The first matrix is for the assessment based on the criterion “selected time

frame” (Figure 3-35), while the second is for the assessment using the “annual basis”

criterion (Figure 3-36).

84
Table 3-6 shows a comprehensive list of weights and the name convention used in the

method of establishing operator performance.

Criteria A B C D E F
A 1.00 5.00 7.00 7.00 5.00 5.00
B 0.20 1.00 0.33 7.00 7.00 7.00
C 0.14 3.00 1.00 7.00 7.00 5.00
D 0.14 0.14 0.14 1.00 5.00 7.00
E 0.20 0.14 0.14 0.20 1.00 7.00
F 0.20 0.14 0.20 0.14 0.14 1.00

Figure 3-35: Comparison matrix for operator assessment for the “selected time frame” criterion.

Criteria A B C D E F G H
A 1.00 5.00 5.00 7.00 5.00 5.00 5.00 5.00
B 0.20 1.00 0.33 7.00 7.00 7.00 7.00 7.00
C 0.20 3.00 1.00 7.00 7.00 5.00 5.00 5.00
D 0.14 0.14 0.14 1.00 5.00 7.00 7.00 7.00
E 0.20 0.14 0.14 0.20 1.00 7.00 5.00 5.00
F 0.20 0.14 0.20 0.14 0.14 1.00 5.00 5.00
G 0.20 0.14 0.20 0.14 0.20 0.20 1.00 1.00
H 0.20 0.14 0.20 0.14 0.20 0.20 1.00 1.00

Figure 3-36: Comparison matrix for operator assessment based on “annual basis” criterion.

Some of the spaces in the above matrixes are filled with predetermined values while other

spaces have to be filled in by an analyst. The predetermined values are located in the

main diagonal of (A, A), (B, B), etc., and have the value 1. The analyst assigns the values

only for half of the remaining spaces because the second half is used for the reverse

comparison, and must be reciprocals of the first half. The relative importance of the

85
criteria is the analyst’s arbitrary decision influenced by personal experience and expertise

in the field.

Table 3-6: The overall weights resulting from pairwised comparison

Scores
Criterion Description Selected Time Frame Annual basis
A Unit Production [t/h] 0.42 0.32
B Unit Energy [kWh/t] 0.18 0.18
C Fill Time [s] 0.21 0.19
D Cycle Time [s] 0.09 0.12
E Angle [deg.] 0.07 0.08
F Working hours [h] 0.03 0.06
G Annual Production [t] 0.03
H Annual Cost [$] 0.03
∑ 1.00 1.00

The last operator performance category developed through the IDE-ACE system focuses

on the maximum stresses on the dragline boom. Among the other reasons that justify

design of this tool, the latter two are identified as the most important.

1. Correlation between the best operators, and the operators producing the maximum

stress;

2. The boom lifetime expansion.

Not all DCS systems are coupled with strain gages used to measure the stresses;

therefore, the maximum stresses category is an optional feature included in the IDE-ACE

system.

86
3.2.4.3.5 Statistical Analysis and Model Development

Having indicated a system of data collection and processing, the following is to perform

the analysis of the results and to establish correlations among the variables. Regression

analysis is a statistical tool widely accepted for investigating relationships among

variables. Particularly for this research, a linear multiple regression analysis is used to

analyze the data from the database and build the forecasting models. Both the model

building and model validating processes are performed with data stored in the centralized

IDE-ACE database and accumulated over the period April – July of 2007. The

forecasting models developed through this research focuses on:

 Productivity in terms of cost per ton[$/t];

 Energy Efficiency [kWh/t];

 Productivity in terms of tons per hour [t/h];

 Diesel Fuel Consumption [gal].

The regression analysis is a useful tool in a variety of applications; however, if a model

includes statistically insignificant variables, the forecasting results might be misleading.

The final mark on a regression analysis is validation of the “best model” using different

criteria (R2, R2adj, Mallows C-p, reduction of variance). If the initial regression analysis

neglects the statistical significance of the model, a variety of remedy measures are

available (e.g. centering the variables). Besides which, the regression model might

include interaction, higher order terms or even both. In any case, the analysis and

discussion chapter documents the development of regression models.

87
The regression analysis for this research was performed using the Minitab statistics

software package. This package allows for both simple and multiple linear regressions,

and the multiple linear regression appears to be a useful tool for the mathematical

description of data associated with any real-world process. For the multiple regression,

the stepwise (forward and backward selection, and backward elimination), as well as the

best subset methods were used. The final “best” model resulted from one of the formerly

mentioned techniques. The results and conclusions are provided in chapter 4.

3.2.4.4 Web Reporting Block – WRB

One of the advantages of Information Management Systems is to provide data access via

intranet or Internet. In e-commerce or banking applications this is very a disseminating

means to convey information to the end-user. From the IDE-ACE point of view this will

make energy consumption/production reports available to any authorized user. The

database access privileges will be defined through user groups. To meet the objective of

this research, ASP.NET is the programming language of choice. (The ASP.NET is a free

technology that allows designers to create dynamic web applications. ASP.NET is part of

the Microsoft.NET platform and the Internet Information Service (IIS).) The ASP.NET

application will reside in a Dynamic Link Library (DLL) on the server. When a user

sends a request to the server, DLL interprets a code and sends HTML back to the user

(Darie and Ruvalcaba, 2006). A combination of ASP.NET (dynamic part) and HTML

(static - visual part) Web pages will result in the overall Dynamic pages shown in Figure

3-37.

88
Figure 3-37: The IDE-ACE web portal

The connection between ASP.NET code and HTML pages was performed in Microsoft

Expression Web. Similar to the Access VBA environment, all text in MS Expression

Web is color-coded, which makes navigation through the program code very convenient.

Finally, ASP.NET allows database connectivity, making it an excellent tool for data

89
retrieval through the customized SQL queries. (SQL is a standard language used to

create, modify, and maintain databases.) For the purpose of this research, a query for data

retrieval (SELECT statement) will be used to convey information through the ASP.NET

application. The maintenance and modification of the database will be performed through

the Database management Block (DMB).

To summarize, the Development Phase and its three stages, the IDB, DMB, WRB are

developed using the technologies presented in Table 3-7.

Table 3-7: Review of technologies and tools for IDE-ACE development.

Block Technology Tool

IDB Relational Database -MS SQL 2005 Express Edition

DMB Windows Based Application -Visual Basic for Application (VBA)


- MS Access 2007
- MS Access 2007 Runtime Library

WRB ASP.NET and HTML -Microsoft Expression Web

90
3.2.5 Phase IV – Testing

The testing phase starts as soon as the IDE-ACE graphic user interface is finished. This

phase reveals remaining bugs in the code and tunes up the system outputs. (The input is

historic data obtained from the company.) The testing phase required more frequent

interaction between the mine management and the Pennsylvania State University. More

tight collaboration will be necessary to adjust and validate the results using the new sets

of data.

3.2.6 Phase V – Deployment

The last stage in the process is deployment of the Integrated Data Environment for

Analysis and Control of Energy Consumption (IDE-ACE) in surface coal mining. This

phase includes training for employees who will use the system and present the

advantages that IDE-ACE provides.

Finally, the development phase will evaluate the system in real application and “on-the-

fly “resolve unexpected issues.

91
Chapter 4

4 The IDE-ACE in Application – Results and Discussion

4.1 Introduction

The development process was the most demanding task in the IDE-ACE design. Included

in this task was the development of the Integrated Database Block (IDB), Database

Management Block (DMB), and Web Reporting System (WRB). Relying on the software

technologies discussed in Chapter 3, the specific methodology for the IDE-ACE system

was developed. The most beneficial outcomes of the integrated data environment were its

data recording, reporting, and analysis potential. The near real-time data availability

endows mine managers with flexibility in evaluating the energy consumption/production

issues soon after they occur. The results and discussion of this process, as well as the

benefits of this system, are outlined in this chapter. Furthermore, the chapter addresses

the application of regression statistics in order to develop the linear regression models.

The models show the correlation among the most significant variables as predictors, with

specific electricity consumption, and specific production as the response variables.

The IDE-ACE was developed to provide support to the operations managers in the

analysis and control of energy consumption (ACE). By integrating the multiple data

sources in a unique environment, the managers are in a position to make better and

timelier decisions in an attempt to reduce the energy consumption. An existing energy

crisis and serious environmental issues related to carbon dioxide emissions make the

energy-saving ideas even more significant.

92
4.2 Data Collection

The data used for this research originate from a surface coal mine located in the southern

region of the United States. Generally speaking, the multiple production chains of the

mine result from the complex geology of the coal seams and are aggravated by intense

weather conditions (6 ft. of rainfall). Regardless of this complexity, the mine produces,

on an annual basis, approximately 3.5 million tons of coal and about 42 million tons of

overburden. A typical cross-section of the mine is illustrated in Figure 4-1. The

production is organized on the shift basis. On the shovel-truck operations, the operators

work two eight-hours shifts. On the dragline operations, the operators also work two

twelve-hour shifts.

Figure 4-1: Typical cross-section of the mine

In general, the equipment operators are divided into the crews. One supervisor is

associated with every shovel-truck crew, but the supervisors are not in charge for the

dragline operation. For this operation, immediate responsibility is associated with the

shift coordinators. The shift coordinators are also qualified to supervise the shovel-truck

93
operation, and in the management hierarchy structure the shovel-truck supervisor reports

to the shift coordinators.

Among their other duties, the shovel-truck supervisors are responsible for recording the

daily production rate after every shift. (The MS Access database keeps the records for the

daily production rates.)

A measurement of energy consumption is scheduled on a daily and monthly basis. A

consumption of liquid fuels is recorded on the daily basis. The total amount of diesel fuel

consumed by a piece of equipment is noted daily in the Excel spreadsheet. On the other

hand, the electricity consumption is recorded on a monthly basis and currently no

electronic records are available for it. Moreover, only the accounting department keeps

the paper-based records (monthly receipts) for electricity consumption.

The mine management have organized the current data recording system by utilizing the

multiple Excel spreadsheets, the Access database, and paper-based records. However,

these data are not related, though the useful back information and the analytical tools are

not available.

For the development and the testing purposes of the IDE-ACE system, the mine

management provided the production, diesel fuel consumption, and electricity data

accumulated over one year (January – December of 2006). In addition, the data recorded

over a period of five months (April 2007 – August 2007) by the DCS system were also

available. However, due to a confidentiality agreement, some of the results in this

analysis are not revealed.

94
4.3 Dragline Experiment

In addition to cycle time the bucket fill factor is one of the crucial parameters that

determines the optimal dragline production for the given bucket size and properties of

material. The goal in this experiment was to determine the changes in the electricity

consumption and production rate by varying different bucket fill factors. The illustrations

provided in this analysis focus on a single seam, however, the analysis for the remaining

two seams was performed in a similar fashion.

Table 4-1 shows a summary of results for experiments performed on a single seam.

Besides the raw information such as production, energy consumption, fill factor, etc., the

table also contains the data calculated based on the literature recommendations.

Descriptive statistics and graphical data analysis confirmed the relationships among the

variables, which were adopted for the search algorithm development. As previously

mentioned, the experiment was performed on three seams, however, one of the seams is a

mixture of the virgin and re-handled material, and the analysis of results for this

compound seam have shown some discrepancies. These discrepancies disqualified the

seam from further consideration. The results from the other two seams confirm

consistency and they are used to determine the pattern in data changes.

95
Table 4-1: Summary of the results

96
Figure 4-2 shows the relationships between the production, cycle time, and the targeted

fill factors. (The targeted fill factors are given along the x-axis.) Also, both y-axes are

occupied. One of them displays the time, while the other shows achieved production rate.

The fill time is particularly important because it is the only segment of the overall cycle

time influenced by the operator performance. The swing times for both empty and full

buckets are more or less a function of the digging geometry associated with the particular

digging pattern.

Further analysis includes the average angle and the overall cycle time. Integrating all

constrains, one is able to distinguish the optimum targeted fill factor, which in this

example was 80%.

Two bars on the far right side in Figure 4-2 provide the results for the “in words” defined

fill factors. Comparing the results with the “in words” defined fill factor, “No Dozing”

shows correlation with 80% targeted fill factor. The result of analysis indicates that the

targeted 80% fill factor presents the optimal value for this seam. Therefore, even if only

visually observing the bucket, the operator should meet the optimal fill factor and

disengage the bucket once the material in front of the bucket starts to move. Further,

restrain from disengaging the bucket results in a so-called “dozing effect”, which

consequently increases electricity consumption and reduces the productivity.

97
Figure 4-2: Production versus different cycle times, overall time and fill factors

The chart in Figure 4-3 illustrates production versus fill distance and fill speed. Again,

along the x-axis, the targeted fill factors are presented, while the y-axis contains only the

production [t/h]. Likewise, to conclusion from the previous chart, the chart in Figure 4-3

infers that the optimal fill factor is achieved for the targeted 80% fill factor. For this

target, the fill distance of 65 ft., and the fill speed of 260 fpm are recorded. The argument

supporting this conclusion confirms the recommendation of three bucket lengths to fill

the bucket (Dragline Productivity Center, 2001). The bucket length for the dragline used

in the experiment is 21 ft., which divided by the fill distance gives approximately 3.1

bucket lengths.

98
Production vs. Fill Distance and Fill Speed - D SEAM

350 6000
Fill Distance [ft] Fill Speed [fpm] Production [t/h] 79% Achieved Average Fill

5,044
300
292 4,939 5000
4,816 291 4,818 279
272 289 4,732 4,638
91% 83% 260
269
4,258
250
76% 70% 82% 78%
79%
4000

Production [t/h]
200

3000

150
110

104
2000
100
81 81
71 69
65

1000
50

0 0
100% 90% 85% 80% 70% Best Fill No Dozing
Targeted Fill Factor [%]

Figure 4-3: Production versus Fill Distance and Fill Speed

The chart in Figure 4-4 provides the relationship between the energy required to fill the

bucket and the production achieved over a one-hour period. Similar to the previous

charts, this one also displays the production on one of the y-axes. The other y-axis

contains the energy required to load the bucket. The units for the production are tons per

hour [t/h], while the energy to load the bucket does not contain the units. Namely, the raw

energy consumption data recorded in the database are unit-less and require additional

calculation to be converted in kWh. This conversion is explained in the remaining part of

IDE-ACE methodology.

99
Production vs. Fill Energy - D SEAM
450,000 6,000
Energy to Fill Production 79% Achieved Average Fill Factors

400,000 385,390
5,044
4,939
4,816 4,818 5,000
4,732 4,638
350,000
332,106
4,258 319,712

302,391
300,000 4,000
Energy Load Bucket [Ws]

Production [t/h]
250,000 232,015
229,293
222,843
3,000
91% 79%
83% 76% 70% 82% 78%
200,000

150,000 2,000

100,000

1,000

50,000

0 0
100% 90% 85% 80% 70% Best Fill No Dozing
Targeted Fill Factor [%]

Figure 4-4: Production versus Energy required to fill the bucket

The result available on every one of three charts indicates the achieved average fill factor.

This number provides the fill factor that the operators actually achieved for some of the

targeted fill factors. For example, running the dragline for a one-hour period, the operator

achieved, on average a fill factor of 88%, while the target was the fill factor of 85%. This

implies that the average material weight in the bucket was about 5,820 lbs. more than the

operators were expected to get.

Evaluating the results achieved for 80% and 100% fill factors, a decrease in the overall

dragline cycle time of 14 seconds in favor of 80% fill factor was noticed. The 100% fill

factor was evaluated because the experience from the on-site research indicated that most

100
of the operators tend to fill the bucket as best as possible, making this fill factor a

common practice.

Assuming the same results for the targeted fill factor over a period of one year, i.e., 8,760

scheduled hours, and 69% availability, the production for the targeted 80% fill factor will

be 28,683,425 tons, while the production for the targeted 100% fill factor will be

28,287,792 tons. The general data used for this comparison, along with the results from

the analysis, are provided in Figure 4-5.

General data
Dragline: Marion 8200
Bucket capacity: 82 cyd
Scheduled hours: 8,760 hours/year
Overall Utilization: 69%

Data verification

100 % FF 80 % FF

Cycle time 80 sec Cycle time 66 sec


Production/cycle 104 tons Production/cycle 87 tons
Annual Production 28,287,792 t/year Annual Production 28,683,425 t/year
Energy Consumption 385,390 unitless Energy Consumption 229,293 unitless

 Production Difference: 395,633 tons/year 

Figure 4-5: The summary of experimental results

Even though the material weight in the bucket for the 100% fill factor is about 16%

larger, the production on an annual basis is smaller at 395,633 tons or 1.4%. At the same

time, removing the overburden with the 80% fill factor reduces the energy consumption

to about 36%.

101
The overall conclusion from the experiments conducted for the given seam is that the

optimal production was satisfied for the targeted fill factor of 80%. The achieved fill

factor of 76%, average distance of 65 ft. (3.1 bucket lengths), and the fill time of 15

seconds corresponds to targeted fill factor. At the same time, the energy requirement to

fill the bucket was optimal.

4.4 Data Management Block - Interface Infrastructure

The software development stages are defined as follows: information collecting

requirements, developing the design, debugging, and testing. The downside of the

process is the design of the software and visualization (design of GUI) of its components.

Decisions must be made to determine the logical connections and communication among

the system components. For larger projects, design of software is a team effort; however,

for smaller projects the design is usually left up to the system developer. In either case,

experiences show that no matter how good the rest of a system is, if an ineffective GUI is

built the end users will not like it (Ambler, 2004).

The communication among the components integrated in the IDE-ACE is given in the

user interface (UI) flow diagram (Figure 4-6) or windows navigation diagrams (Page-

Jones, 2000).

102
IDE – ACE
Open Button Open Button
Application

Open Button

Data Management Block - DMB Reporting System Block - RSB Data Analysis Block - DAB

Equipment
☼☼

Equipment Dragline
☼☼ ☼☼

☼☼
☼☼
☼☼
Production

Truck Design
Liquid Fuel Electricity ☼☼
Experiment

☼☼
☼☼

Dragline
☼☼
Data Analysis
☼☼
Energy Equipment Equipment
☼ Selection Selection ☼☼ Operator
Front End Loader Performance

Liquid Fuel
☼ ☼
Dozer Hours ☼☼
Print Report
☼☼
Print Report




Basic Report Advanced Report
Electricity
☼ ☼
Scheduled Hours ☼☼
Preview Report
☼☼
Preview Report

☼☼ Selected
☼ Delays Time Frame
☼☼
☼☼
Charting Charting
Miscellaneous
☼☼
☼☼
☼☼ Annual Basis
☼☼
Report by Month Report by Month
☼ ☼☼ Fuel ☼☼ Minimum
Energy Location Fuel ☼☼ Cost
☼ ☼☼
Send Report Send Report
☼ Report
☼☼ Fuel ☼☼ Minimum
☼ Price
Delay ☼

Web Cost
Production
☼☼
☼☼ Fuel Access

☼☼
☼ Type
Rainfall
☼☼

Mobile Equipment
☼☼

☼☼
Delay ☼☼ Delay Dragline
☼ Category Report Shovel/Trucks
Horizons ☼☼
Pivot Chart Table
Delay
☼☼ Production Production
Code ☼☼ ☼☼ ☼☼

Work Codes Truck Fuel Consump.
Report Report ☼☼
Analysis
☼☼
☼ Dragline Crew
Shift ☼☼ ☼☼
Print Report
Crew Performance
☼☼
☼ Performance ☼☼
Horizon ☼☼ Preview
Road Conditions ☼☼ Supervisor Report
☼☼ Performance
Material ☼☼
Charting

Production
☼☼
CO2 Emission
☼☼

☼☼
Diesel

Miscellaneous
☼☼ ☼☼
Energy Price ☼☼
Electricity

☼☼
Gasoline
☼☼ Delay List

Energy Summary
☼☼

☼☼ Employee List
LEGEND ☼☼
Print Report
☼☼ Open Button ☼☼
Preview Report
☼ Add, Save, Delete, and Records Navigate Buttons ☼☼
Send Report

Figure 4-6: User interface - windows navigation diagram

103
When a user opens the IDE-ACE, the interface (Figure 4-7) shows the main screen,

which is organized in three blocks. Clicking on a button opens different modules of the

system and simultaneously establishes and maintains the connection with the database as

long as the form is opened.

Figure 4-7: The main screen of IDE –ACE system

Generally, the three blocks (DMB, RSB, and DAB) in Figure 4-7 enable navigation

through the entire system. From the system application point of view, the shift

supervisors and personnel employed to complete the data-entering process will frequently

be using the Data Management Block. Deeper insight into the structure of this block

(Figure 4-6) provides the overview of available utilities. The major advantage of the

DMB block is its centralized data management, i.e., every input, change, or data removal

from the database is performed in this block. The inputs, for example, include equipment

management, daily energy purchases, production rates, prices changes, delays, etc.

Figure 4-8 shows the equipment management screen. The IDE-ACE is designed to be

applied on different mines; therefore, the first time a user will primarily have to record

104
the equipment data in the database. The given screen allows input of essential

information for the equipment that is the subject of the reports and analysis tools

available in the IDE-ACE system. The information that user has to enter are provided by:

 Equipment Manufacturer (VIN number, Manufacturer, Model, Type, Tires,


Fuel Consumption Data)
 Internal Organization Policy (Serial Number, Date of delivery, Fleet, Fleet
Name)
 Required by the System Design (Energy Type, Equipment Purpose)

Figure 4-8: The equipment manager screen.

Once the equipment is in the database, the user clicks on the Production button, which

launches the form in Figure 4-9. The screen shows the details organized in tabulated

forms: Trucks, Dragline, Front End Loaders, Dozer Hours, Scheduled Hours, and

Delays. Each of these forms will be discussed next in some detail. The elements on each

form are the objects (the term “object” is commonly recognized in the object-oriented

programming) and further in the discussion the elements on the forms will be referred to

as the “objects”.

105
Figure 4-9: The truck production manager screen

The results from the data mapping bring out the relations between the processes of the

mining production chain. The processes are modeled through the IDE-ACE system,

allowing that every detail that constitutes the production chain will be recorded in the

database. The form in Figure 4-9 captures the information for the shift, the truck, the

loader, the horizon, the haul location, the truck cycles, the production in tons, and the

operator running the particular equipment during a shift. Indicated information, along

with the records for the diesel consumption, allow for quantification of the truck

operator’s performance. However, this feature of the system is currently unavailable

because the mine management does not have such data recorded at present.

Consequently, this data will be available once the system becomes integrated in the mine

business environment.

Besides the truck production records, the IDE-ACE database stores the data for the front

end loaders and dragline production rates. Separate forms have been developed with the

purpose of keeping the production records for these two equipment categories up to date.

106
The front end loader is a multi-purpose piece of equipment. It is used as the

loading/haulage equipment on distances up to 1,000 ft. For a scenario where a loader is

being used to move the coal from the stock piles to the hopper, an appropriate form was

developed. The operator running a loader keeps the record of production by completing

the daily sheet that a supervisor at the end of the shift uses to enter data in the IDE-ACE.

This form allows mine management to keep records for the wheel loader production

when working as the haulage equipment.

A similar form was designed to keep records for the changes in a dragline production.

The supervisors have to complete this form with the data recorded by the dragline

operators at the end of the shift. The data are summary statistics that operators have

displayed on the computer screen in the dragline’s cab.

The key to operational success on a mine site lies in providing accurate, real-time,

guidance information important to those who operate the machine (Leica, 2006). The

mine-supplied data for this research uses a state-of-the art GPS dozer guidance system.

This system accurately displays the grade and elevation at the benches while

simultaneously providing the operators with vital information required to achieve better

coal recovery and to reduce the costs for auxiliary operations. The guidance system

communicates with the mine design software (Carlson Software), which measures and

keeps the records of the bulldozer production rates (volumes of the material pushed).

However, the information missing was the number of hours that dozers have been

working on a particular seam. To record this information an appropriate form was

developed.

107
Even though, the IDE-ACE for this case study was developed for the multi-seam

operations, it can be easily adjusted for the single-seam operations by managing the

Horizons through the Horizons Management Form, which is available in the

Miscellaneous segment of the DMB. (The “horizon” is described as the seams from

which either coal or overburden has been produced.)

The delays in the production due to equipment failures, weather conditions, or any other

reason, are something that an operations manager wishes to record as accurately as

possible. Having accurate records for production delays allows for a faithful overview of

productivity, a pro-active maintenance approach, and an application of other activities for

reducing unscheduled equipment downtime.

Figure 4-10 outlines the remaining two forms available in the Production Manager.

These forms record the shift-scheduled hours and any type of delays that occurred during

the shift. The form Scheduled Hours records the hours during which a machine is

expected to operate, while the form Delays records the delays that occurred during the

scheduled time frame. The difference between these two times determines the equipment

productivity. The overall equipment productivity is a function of the calendar, scheduled,

available, and operating hours.

108
Figure 4-10: The scheduled hours and delays manager

Two objects, Delay Code and Delay Category, manage the available and operating hours.

The available hours remain when the hours for mechanical and electrical delays are

deducted from the scheduled hours. Similarly, the operational hours remain when the

operational delays are deducted from the available hours. Hence, the operating hours are

the times when the equipment actually works, i.e., produces.

The delay code and delay category are managed through the Miscellaneous segment of

the IDE-ACE system. The operational delay, i.e., Delay Category (Figure 4-11)

recognizes:

109
1. Off – Shift: Equipment was not planned to operate and maintenance was

performed;

2. On-shift: Hours for which Operations had intentions to operate equipment but

could not because it was down for maintenance;

3. Idle: Non-maintenance delay during which the equipment is not running;

4. Operational: Non-maintenance delay occurring while equipment is operating.

Figure 4-11: The delay category/code manager

When it is adopted, the delay code system used in this case study is established by the

mine providing the data; however, the delay manager allows for the changes and

110
adjustments to other mines by simply adding the new delay categories and the codes in

empty database. Problems interrupting smooth data entry into the database are overcome

by looking at the set of existing delay codes provided in a report.

The integrated perspective of the IDE-ACE ensures data capture at a deep level in the

mining production chain. An integration of data using the IDE-ACE reporting and

analysis tools provides answers to the crucial questions: when, where, and how much

energy is being used to achieve a production. More importantly, management gets an

insight into whether the equipment uses more energy than specified. The Data Analysis

Block brings out more details on this subject. Nevertheless, this analysis requires detailed

information by recording daily energy consumption. The input of data into database is

enabled through the forms Liquid Fuels Allocation and Electricity Allocation (Figure 4-12).

Figure 4-12: The liquid fuel and electricity allocation forms

111
The liquid fuel allocation form reveals that some of data are missing. This inexistence is

caused by the fact that some information have never been recorded. Because of that, a

detailed analysis of diesel fuel consumption at this point is unavailable. Once the system

is installed and data is recorded, the reports will provide information on who the operator

was for a particular shift, how much diesel fuel a piece of equipment has consumed, who

the fuel delivery employee was, and what delivery truck was used. That information is

the source for detailed analysis on the diesel fuel consumption. With such reports, the

managers will be able to control the fuel consumption and make decisions in order to cut

the expenses for the diesel fuel.

Figure 4-12 further shows the electricity consumption manager. The design of the

manager allows daily input of changes recorded by the electricity meter. By entering the

data in the system, a user chooses one of the electricity meters. The mine in this case

study uses a single electricity meter to measure the electricity consumption on the

dragline, electric shovel, pumps, and the facility. The version of IDE-ACE used for this

case study was adjusted for a particular situation and it recalculated the electricity

consumption based on the percentages provided from the mine.

The Employee Manager (Figure 4-13) allows recording of information valuable for the

detailed reporting system. The form shows basic information for the employee, such as

ID, employee name, his or her position, address, and other general data.

112
Figure 4-13: The employee manager form

The Data Management Block was developed with the purpose of centralized data input

and management. The Energy Miscellaneous Data Manager (Figure 4-14) is a feature

implemented in the application enabling the centralized input for energy management.

Figure 4-14: The energy manager

113
The forms are developed with the purpose of managing the prices, the fuel locations, and

the fuel type being applied at any mine site. The diesel, gasoline, and electricity are the

only energy sources used at the mine from this case study. However, the natural gas and

the coal are also implemented in the system as options for other use cases. In this

example, the diesel fuel is distributed either on the stationary pumps, or by the fuel

trucks. The gasoline is distributed only on the stationary pumps and is mainly used for the

pickup trucks and other utility vehicles.

The fuel price manager form is a unique segment in the application that allows the user to

add new prices or make changes to the existing ones. The changes in this form affect the

results in the report and the analysis blocks of the IDE-ACE. Every new entry in the

database makes the price history list and allows convenient overview of changes. The

prices in Figure 4-15 have been entered for demonstration purpose only. Zeros recognized

on the form means that the price on given date was not changed.

Figure 4-15: The history of energy prices

114
The remaining forms in the miscellaneous segment of the DMB accomplishes a work of

recoding the changes in Rainfall, Horizon, Work Codes, Shift and Road Conditions, but

only the form, “road conditions” (Figure 4-16), will be explained in some detail.

Figure 4-16: The road condition manager

Recording the road condition during the first several months after the IDE-ACE

integration in the mine business environment has experimental purposes. The trial period

will assess the feasibility of continuing with its application.

In either case, the idea of recording the changes in the road conditions on the shift basis is

to correlate those data with the fuel consumption data. The reality that wet road

conditions affect fuel consumption is well known; however, focusing on a particular mine

to determine the rate of fuel consumption change as a function of the road conditions is

not available yet. Justification of this idea in the real application will provide the

managers with information on whether to adjust the road maintenance procedures or

115
continue with an existing practice. It is expected that the procedure will be beneficial,

particularly in the regions reached with the rainfall.

4.5 Reporting System Block – Interface Infrastructure

The Reporting System Block (RSB) was designed to support reliable back-information

converted from the data stored in the database residing on the database server. With this

approach, all relevant information is available immediately after the data is entered in the

database. The data update is scheduled at the end of every shift, so that system provides

near real-time back information. The changes in the energy prices, horizons, shifts, and

equipment created in the DMB affect all reports available in the RSB. While the focus in

this research is on the energy reporting system, the production reports will be available

also.

One object frequently integrated in the IDE-ACE interface is a date selector. Utilizing

this object, a user determines the time frame (start date – end date) for generating a report

for the fuel consumption.

While adding new piece of equipment in the database, a user has to input the fleet to

which a particular piece of equipment belongs. The fleet is important because along with

the date frame, it makes the key required to generate a report for particular equipment. In

the case study, the end dump trucks belong to fleet 170, the bulldozers to fleet 130, etc.

After confirming the fleet and time frame, the IDE-ACE system starts a calculation by

comparing the dates between the fuel consumption and energy price tables. The

116
algorithm sets the initial fuel price as equal to the price on the start date; if no fuel price is

found on the start date, the initial price is set to equal the first preceding price available in

the price table. Another scenario, frequently expected, is when the start date succeeds the

last date available in the price table. When faced with this scenario the algorithm takes

the last energy price from the database and calculates the fuel costs. The whole

calculation process happens in a few seconds and the user is able to follow the progress

by watching the progress bar on the screen.

The Fuel Consumption Report (Figure 4-17) shows the summary statistics for the fuel

consumption and the fuel cost for the equipment belonging to fleet 170 from the time

frame of January 1 to December 31 of 2006.

Figure 4-17: The fuel consumption report

117
The same report also illustrates the carbon dioxide emission by a single piece of

equipment and the total amount of CO2 emitted by the fleet. The summary further

indicates the total and average fuel consumption per fleet as well as the overall cost of the

fuel. The report provides printing, previewing, and charting options. The monthly report

(Figure 4-18) for fuel consumption, in both numerical and graphical forms, is accessible

at touch of a button. The x-axis on the chart contains the time frame in months, while the

y-axis contains the diesel consumption in gallons. The numbers allocated at top of the

bars indicate the total diesel consumption for particular month.

Figure 4-18: Graphic descriptive statistics

The IDE-ACE system also has convenient and straight forward process of summarizing

electricity consumption. Typically, a user selects the time frame and the equipment, hits

118
the confirmation button, and reads, prints, or sends the comprehensive report via e-mail

to a corporate office (Figure 4-19).

Figure 4-19: Electricity consumption report

Prior to data integration this type of report did not even exist. Secondary to the time-

intensive process of manually checking the paper records stored in the accounting

department and creating the comprehensive report.

The electricity consumption report provides the results stored in a few variables. The

variable “unit energy” is the amount of electricity consumed by a piece of equipment

over a one-hour time period. The total electricity and the total hours are values manually

entered in the DMB. Calculating the difference between the total hours for two

consecutive months defines the “monthly hours” variable.

119
The variables “total cost” [$/month] and “unit price” [$/h] are calculated values based on

the total hours and the total electricity consumption that both the equipment and the

facility have accumulated over one month.

The last variable available in the report (Figure 4-19) is the amount of carbon dioxide

emitted from the power plant in order to generate the amount of electricity that particular

equipment or facility has used on the monthly basis. If the equipment (e.g. the water

pumps) does not have an integrated gage to measure the number of hours, the IDE-ACE

notifies a user that some of the results may not be available on the report.

Besides descriptive statistics, the report includes a graphical analysis of electricity

consumption. The example in Figure 4-19 depicts a chart showing the electricity

consumption for a dragline over a period of one year. The variable time is presented

along the x-axis, while the y-axis keeps the values of consumption in kWh.

Along with the fuel consumption reports, mine management is also interested in the

production reports. The production reports and analysis tools are not as detailed as the

fuel consumption reports. The production reporting system generates the reports most

frequently required for day-to-day operations. The design and type of reports were

determined by interviews with mine managers and analysis of the legacy databases. A

more detailed production reporting system is planned for development after IDE –ACE

implementation in the mine environment.

The currently developed reporting system provides feedback for the shovel trucks and the

dragline production rates. Both reports are explained in some details. The manager

chooses between the shovel trucks or dragline productivity reports.

120
The Shovel-Truck Production Report differentiates the reports (Figure 4-20) according to

these categories: Truck, Loader, Horizon, and Material. For either of these categories, the

summary report shows the production rate for the coal and the overburden, including all

trucks over a selected time frame.

Figure 4-20: Production by trucks report

Along with production rates, the managers are interested in getting the crew performance

feedback. This feedback is vital for sustaining production improvements. By running the

Crew Performance tool, a manager determines the best crew over a selected time period.

This information helps in making the decision to juggle the operators among the crews.

For example, a low-performance operator can gain on his or her productivity if working

with a more successful crew member.

121
Two additional reports available in the IDE-ACE system are the Equipment and

Miscellaneous reports (Figure 4-7). The equipment report allows convenient navigation

through the equipment-related data stored in the database. The miscellaneous report

generates a summary for the energy price, the delay list, and the employee list. These

reports have a more or less similar level of detail, so information other than that presented

above will not be provided.

4.6 Data Analysis Block – Interface Infrastructure

The Data Analysis Block (DAT) in particular, addresses the application of the data

mining and the novel algorithms developed in this research. All in endeavor to resolve

some of the contemporary issues with data excess in the surface coal mining industry.

The DAT is the most comprehensive segment developed in this research. It desegregates

a complexity of algorithms and analytical tools in a user-friendly, analytical-reporting

mechanism to control energy consumption in surface coal mines. Simultaneous with

analysis functions, it assesses the operator’s performance in the near real-time. The

results are provided as a windows form or a hard copy report.

Bearing in mind all that has been mentioned previously; the remaining pages of this

chapter show analysis of interfaces and the discussions of results. Again, due to

confidentiality reasons some of the results will not be provided. (However, appropriate

explanations in these cases are provided.)

122
In general, the DAT consists of four options. Each option provides analysis and reports

for a particular type of equipment or fuel type. Choosing one at a time, a user can select

Dragline, Mobile Equipment, CO2 emission, or Energy Summary.

The dragline data analysis tool models the dragline experiment procedure in order to

determine the best fill factor and to analyze operator performance.

The mobile equipment tool assesses the diesel fuel equipment in order to pinpoint the

high fuel consumers.

The CO2 emission tool summarizes the emission of carbon dioxide released from burning

three primarily used types of fuel in the mine.

The energy summary tool provides the comparison between the energy consumption

estimated by DOE for a “hypothetical” mine, and the real energy consumption. This

segment of the data analysis tool provides an explicit answer to one of the research

questions” What is the difference in the unit energy consumption between results

obtained by the DOE methodology and methodology suggested in this research? In order

to evaluate the real energy consumption, the segment also assumes collaboration among

academia, the mining industry, and the DOE. Application of IDE-ACE in this scenario

requires that a mine supply a periodic report on its energy consumption to DOE as the

compensation for this free-of-charge system integration. If this scenario happens, it is

expected that recognition of IDE-ACE by DOE might help to change the attitude of the

society towards the mining industry.

123
4.6.1 Design of Experimental Tool (DET)

The Dragline Performance Analysis Tool consists of three options (Figure 4-21). First,

the Design Experiment Tool allows a user to repeat the dragline experiment procedure to

determine the best fill factor.

Figure 4-21: The dragline analysis tool (DET)

This is a two-step process. The first step includes a design of the experiment with the aim

of defining the target fill factors that dragline operators attempt to achieve in randomly

selected one-hour time frames. The second step is retrieval and storage of data from the

DCS database. Data retrieval follows the optimization procedure that utilizes the novel

algorithm (Search the Best Fill Factor algorithm) suggested in the methodology.

Prior to operator beginning the experiment, a manager initiates the Design Experiment

form (Figure 4-22) and fills in the required fields.

124
Figure 4-22: The design of experiment form

A click on the “Set Target Fill Factors” button checks for the inputs, and if no error is

reported, the manager continues with the design by setting the targeted fill factors. The

interaction between a person and the system is organized with pop-up message boxes

(Figure 4-22) wherein a user has to enter required information. The code behind the form

verifies the data entry. If, for example, a manager wishes to set more than seven fill

factors, the system responds with a warning message. Otherwise, the process runs

smoothly until all targeted fill factors are entered in the system. The confirmation

message indicates that the results are ready for distribution to the dragline operators.

The design of the experiment results in the Experiment Target Report (Figure 4-23). All

experiments are permanently stored in the database or erased by running the “Clear

Database” procedure. To make the experiment reusable, the manager has an option to

create the report with the existing results in the database.

125
Figure 4-23: The experimental target form

Finally, every dragline operator receives a hard copy of the experiment target report and

during a shift, attempts to hit the targeted weights in the bucket. It is the operator’s

arbitrary decision when to start the experiment; however, the experiment has to be

performed during the production process, i.e., when the dragline works in the front cut

mode. The indication of material weight the operator sees on the screen located in the

dragline cab. The time that the operator enters in the report must be recorded from the

clock located on the computer screen in the cab because it is synchronized with the clock

on the database server. The operator’s role finishes at the end of the shift when he or she

turns in the experiment target report to the shift coordinator, who then forwards this

document to the manager.

126
4.6.2 Dragline Data Analysis Tool (DDAT)

Having the experiment target report in hand; the manager opens the Dragline Data

Analysis Tool (DDAT). The tool has two basic functions: (1) to retrieve data from

integrated environment and (2) to analyze retrieved data. These two functions are related

processes in the endeavor to determine the best fill factor. The data retrieval is a two

layered procedure. In the first layer, the DDAT queries the database, performs the

calculation, and stores the data temporary in the arrays. This calculation includes

correction equations (Chapter 3) to adjust DCS records to the exact values. The algorithm

integrated in the second layer permanently stores the results from the arrays into

database, making them available for further analysis.

Typically, the dragline analysis procedure starts by determining the date from the DCS

database in order to extract the production and energy consumption records. Besides

these two datasets, the cycle time, fill time, operator name, and the time stamps are also

extracted. Both the data retrieval and the data analysis are performed using the same

form, yet different data entries, designated by the shaded areas in the succeeding two

figures, are required. Figure 4-24 emphasizes the fields that the manager needs to fill up

when entering the data from the experiment target report.

127
Figure 4-24: The DDAT form – data retrieval objects

4.6.2.1 Data Retrieval

Starting from the top left corner of the screen, a manager initiates the data retrieval by

adjusting the date when an experiment took a place. The following action sets the time

when the operator attempted to achieve the targeted fill factor. The time format is

hh:mm:ss (e.g. 14:35:16 – military time), and for user convenience can be entered either

by typing on the keyboard, or using the up/down arrows. It is important to recall that the

events in the DCS database are recorded in GMT (Greenwich Mean Time), and so the

difference with respect to the local time zone must be adjusted. For example, if the

128
experiment took a place at 13:35:30 hour, the manager has to add five hours (assuming

that a mine is located in the U.S. central time zone) on top of the time recorded by

dragline operator.

To reduce typos, seven typical fill factors (70%, 75%, 80%, 85%, 90%, 95%, and 100%)

are predefined and integrated in the combo box. A user selects one fill factor per

iteration. If an atypical fill factor was targeted in the experiment, its value can be

manually entered.

Finally, the bucket length, the seam on which the dragline was working during the

experiment, the operator’s name and the dragline’s serial number also have to be entered

in the form.

When given a data entry a user confirms by clicking the button, Retrieve Data, initiating

a procedure in the code that checks for errors on the form; if all entries are correct the

algorithm retrieves the data from the DCS database. Simultaneously, the algorithm

records the current results in the table and displays partial information on the screen in

the Current Results area. The current results are limited on: 1) production for the selected

time, 2) production per hour, 3) energy to load the bucket (dimensionless unit from the

database), 4) average fill time, 5) average cycle time, 6) fill distance, and 7) number of

bucket lengths.

Even without running the analysis of retrieved data, the average fill time (recommended

to be 16-18 s) and the number of bucket lengths (recommended to be 3-4 bucket lengths)

infers the preliminary conclusion concerning the tested fill factor. For example, the

iteration in Figure 4-24 shows that 100% fill factor with the fill time of 21.08 s, and the

129
5.26 bucket lengths is unlikely candidate for the best fill factor. Nevertheless, the result in

the data analysis segment will confirm or deny this assumption.

4.6.3 Data Analysis

The same form (Figure 4-25) used for the data retrieval carries the data analysis process.

Since the analysis requires more frequent communication with a user than the data

retrieval process, the interaction is performed by merging the pop-up input boxes in the

GUI. In the boxes a user enters: 1) database conversion number, 2) number of dragline’s

unscheduled days, 3) the power plant thermal efficiency, and 4) average Btu/lb for a coal

burning in a power plant that supplies a mine with electricity.

Figure 4-25: The DDAT form – data analysis objects

130
Likewise, as with the data retrieval procedure, a manager running the analysis sets the

start and end dates, i.e., time frame. The time frame ranges from one day, up to the entire

dataset available in the database. The data analysis segment relies on the data extracted

from the DCS system and temporarily recorded data in the IDE-ACE database. These

reside in the table as long as the user accumulates the results from the experiments and

restrains from wiping the table. Cleaning the table is irreversible action, so user

confirmation is required to accomplish this action.

The system’s feature of storing the results from multiple experiments reduces a margin of

error in an effort to determine the best fill factor. An increase in the number of

experiments stored in the database increases the validity of the overall best fill factor.

Utilizing the IDE-ACE system, the operation management continually measures the fill

factors and determines the best fill factor as the material properties change.

The data analysis outcome is organized in seven tabulated forms. Each of these forms is

next discussed in some details.

1) Chart form – graphically displays the results of the normalization process. It

points on three variables:

(i) Energy that dragline consumed in the digging phase of the overall dragline

cycle over a period of time,

(ii) Production that dragline operators achieved over the same period of time,

(iii) Delta stands for a difference between two functions, the energy and

production rate.

131
Figure 4-26: The chart form

2) Normalized form – gives numerical results from the normalization process.

Again, the normalization process standardizes the values for production and

energy consumption to be in the range between 0 and 1. The ranking on the list is

based on the maximum difference between normalized production and electricity

consumption. The first number on the list induces the best fill factor for running

an analysis.
3)

Figure 4-27: The normalized form

3) Average Form – provides the mean values for the energy consumption (unit-less

number) and the total production (lb) during selected time frame.

132
Figure 4-28: The average values form

4) The tabs, Best Fill Factor and The Worst Fill Factor, graphically visualize the

extremes in the fill factor determined for the running experiment. These forms do

not show any analysis other than a fast summary of the results displayed on a

user-friendly manner.

5) Summary Form – provides detailed overview of the results that the operators

achieved during the experiments. The summary integrates the results only for the

time frame defined on the form. The report holds the statistics for every operator

who participated in the experiment by summarizing the achievements in terms of

date, targeted fill factor, production, energy, fill time, cycle time, fill distance, and

the number of buckets.

Figure 4-29: The summary form

133
6) CO2 Emission Form – holds the data for the CO2 emission during digging phase

of the dragline cycle. The report also indicates crucial details in terms of

electricity consumption in kWh, the amount of coal that has to be burned in the

power plant in order to generate the amount of electricity used for digging the

phase. A given quantity of coal reveals the amount of CO2 emitted in the

atmosphere. Besides this, the report also indicates the number of buckets per hour

and the cost of energy per bucket. The costs of electricity on the hourly and

annual basis are also provided in Figure 4-30.

Figure 4-30: The CO2 emission form

The statistical analysis of the results from Figure 4-30 coupled with the best fill factor

(80%) induces the numbers provided in Table 4-2.

134
Table 4-2: The analysis of CO2 results

Buckets per Estm. annual # of CO2 % change in % change in


FF
hour buckets [t/year] CO2 buckets
70 47 284,068 3,252 0.93 0.90
* 80 52 314,288 3,498 1.00 1.00
85 44 265,936 3,786 1.08 0.85
90 44 265,936 4,339 1.24 0.85
100 43 259,892 5,033 1.44 0.83
* the best fill factor for selected experiment

A comparison of percentage change in CO2 emission against the reaming fill factors

indicates continual increment starting from 85% fill factor. The same conclusion holds

for the percentage of change in the number of buckets. The most extreme increase

occurred for a targeted 100% fill factor when the CO2 emission increased from 3,498 t to

5,033 t on an annual basis. This represents an increase of 44% in CO2 emission with

simultaneous reduction of 17% in the number of buckets (production). This example


80% is the best fill factor for given
confirms the hypothesis that it is not worth spending extra time in the digging phase to

get additional percentage in the bucket fill factor. Moreover, this same practice induces a

double detriment: increased environmental impact and reduced production.

Eventually, the example records a decrease in CO2 emission of 7% for the fill factor of

70%. This is, for sure, a benefit from an environmental standpoint; however, this fill

factor reduces the number of buckets (production) for 10% or 30,220 buckets.

The final conclusion of analysis confirms that an 80% fill factor is optimal for the mine

used in this case study. This conclusion is, graphically justified in the chart in Figure

4-31. The full line indicates the trend in the percentage of CO2 change, while the dotted

line indicates the trend in the percentage of change for the number of buckets. Starting

135
from 70% to 80% fill factor, chart indicates approximately the same rate of change. A

minor change is noticeable for 70%, where decreased environmental impact induces

decrease in the production rate. However, the trend for both lines continuing from 80%

significantly changes; indicating that an operator who is spending more time in the

digging phase negatively affects both CO2 emission and the production rate. Eventually,

this implies extra expenses on the electricity, and likely expected carbon tax bills.

Percent of change in CO2 and # of buckets on annual basis


1.60
1.40
Percent of change [%]

1.20
1.00
0.80
0.60
0.40
0.20
-
50 60 70 80 90 100 110
Targeted Fill Factor [%]

% change in CO2 % change in buckets

Figure 4-31: Chart with percentage value of change in CO2 emission and number of buckets

The remaining dragline analysis tool is the Operator’s Performance (OP) (Figure 4-32).

The OP tool evaluates the production rate and the energy consumption for every operator

working over a selected period of time. In addition, the tool allows analysis of single or

all production seams at once. Along with a given tabulated summary, the tool contains

four comprehensive reports ranking the operators based on the multi-attributes decision

136
methods. More particularly, the analytical hierarchy process (AHP) was used for

validating an operator’s performance. Furthermore, the minimum energy requirement for

the digging phase of the dragline cycle, i.e., energy efficiency, and the maximum stresses

on the boom are distinguished as two additional criteria for an operator’s evaluation.

Figure 4-32: The operators performance tool

Generally, the OP enables the basic and advanced reports. These two are explained in

more detail further in the chapter.

1) Basic report briefly summarizes an operator’s performance, providing the fast

facts of eleven resulting variables about the production and energy consumption,

including all operators working over selected period of time.

137
2) Advance report provides a detailed summary of production and energy

consumption performance for all operators working over a selected period of

time. The advanced report aggregates the results from the basic report and totals

the number of variables on eighteen.

Both the basic and advanced reports use the same GUI to set the time frame and the seam

for running analysis. Besides the time frame and the seam, the advanced report requires

input for the bucket volume, specific gravity, swell factor, and the annual working hours.

A user confirms a given input by clicking the calculator button; which launches the

algorithm to check for the errors in the input boxes. If no error is reported, the results are

displayed on the screen; otherwise, a user gets a message describing the error and the

variable that produced the error.

Once the results are displayed on the screen, a user continues interaction with the system

by either glimpsing the results on the screen and focusing the candidates for the best

operator, or more likely, by running the Analyze Operators Performance tool. For user

convenience, four fully automated analytical mechanisms that rank the operators have

been developed:

1. Selected Time Frame – explicitly measures an operator’s performance as

calculated over a selected period of time, based on the data from the DCS

database. The method uses the most significant variables, and utilizing the

AHP (analytical hierarchy processes) processes, calculates the overall

evaluation score. The evaluation score is a criterion for the final operator’s

138
ranking. The largest evaluation score determines the best operator over a

period of time.

2. Annual Estimation – is similar to the analysis for a selected time frame,

but includes an additional two variables: (1) extrapolated values for the

annual production, and (2) the annual electricity costs. The extrapolated

values result from a calculation based on the mean values of the cycle

time, average bucket weight, projected number of hours the dragline will

operate over the year, and the electricity price. These extrapolated values

are included in the AHP process, which results in the new evaluation

score. As in the previous case, the largest evaluation score determines the

best operator over a period of time.

3. Minimum unit cost – ranks evaluated operators based on the productivity

in terms of $/t. The operator with the minimal cost per unit produced holds

the top position on the rank list. The list is not result of the multi-criteria

analysis, yet the simple ranking is used to determine the best operator.

4. Boom stress report – evaluates the operators based on the stresses induced

on the dragline boom during the production cycles. This report includes

operators who load the boom with the stresses greater than 90% of the

average maximum stresses. This limit recommends a dragline

manufacturer with the purpose of evaluating the likelihood of replacing

the existing bucket with the larger model.

Back in Chapter 3, the Performance Indicator (PI) was introduced. After recognizing its

importance, the PI has been excessively used for the analytical purposes. The PI was

139
developed based on the results from the dragline experiment and it represents an

important criterion not only for the evaluation purposes, but also for the model

development process. (More on the PI’s importance, from the regression analysis

standpoint, is included in the remaining segment of this chapter.)

When faced with the report in Figure 4-32, a manager instantly recognizes the operators

with the negative (-) performance indicator. Immediately, these operators are eliminated

from further discussion and the manager continues evaluating the results looking at the

set of criteria: the unit costs [$/t], unit energy cost [$/h], unit energy [kWh/t], average

cycle time, average fill time, average bucket weights, average angle, and the unit

production rate. Consequently, the evaluation of criteria becomes a challenging task that

is alleviated by the analysis tools available in the IDE-ACE.

After running the analysis tools for the time frame between Jun 1, 2007 – Jun 31, 2007,

the “D Seam” and being given the working parameters for dragline (bucket volume of 82

yd3, specific gravity of 1.53 t/yd3, swell factor of 1.2, and 6,044 hours on the annual

basis), the results in Figures 4-33 and 4-34 indicate that operator J is “the best” operator

in both categories (selected time frame and annual estimation). This implies that operator

J, running the dragline with optimal amount of specific energy [kWh/t], maximizes the

production rate. The experience shows that operators ranked on these two lists do not

match constantly for the same input data. For example, during July of 2007, operator D

had the best evaluation score over the selected time frame; however, the values

extrapolated on the annual basis show Operator E as the one with the best evaluation

score. The report indicates better productivity of about 3%, or 590,323 lb compared with

operator D.

140
Figure 4-33: The operator’s evaluation for selected time period

Figure 4-34: The operator’s evaluation extrapolated on an annual basis

The commercial benefit of this system is also apparent from the results shown in Figure

4-32. Namely, the analysis for the minimum unit cost indicates that operator B is the least

expensive operator. The operator achieved a cost of 0.0109 $/t, or extrapolated on an

annual basis, $257,587.00. The same report reveals the efficiency for Operator I, who, as

one of the best workers in the mine; achieved a cost of 0.0171 $/t, or extrapolated on an

annual basis, $478,498. The difference gives $222,913 variation in the electricity costs

for digging phase only. Assuming two scenarios, where all operators perform like these

two, the annual savings based on the total electricity purchase is about 23%. A similar,

141
but less favorable example (data from July, 2007, Seam D) indicates a savings of about

15%.

Emphasizing the economic aspect of the dragline operations, the IDE-ACE system

incorporates a report (Figure 4-35) where the priority has the least expensive operator. In

this example, the positive Performance Indicator corresponds to the operators with

minimum unit costs; however, this is not the rule when evaluating the operators

respecting this criterion.

Figure 4-35: The operator evaluation based on the minimum unit cost

Comparing the operator performance over a selected period of time and based on the

annual basis with the minimum unit cost, shows that Operator B is the least expensive

operator, i.e., $0.0109 per each ton of material removed. Assuming the same production

rate over a year, this operator will spend $257,585 and remove in total 23,571,948 t of

material. On the other hand, the reports in Figures 4-33 and 4-34 indicate that Operator J

142
was the most productive. His unit energy consumption was 0.188 kWh/t i.e. 0.0122 $/t,

which places him in the third position it the minimum unit cost report. However, on an

annual basis, this operator produces 27,387,701 t, which is equivalent to $334,787. The

results imply that Operator J produces about 14 percent more than Operator B, increasing

the electricity bill for $77,202. Additional analysis and evaluation of the production

schedule plan has to be performed in order to justify whether the increase in production

of 14% is worth $77,202.

The most recent analytical tool integrated in the IDE-ACE system points to the operator

that maximizes the stress on the dragline boom. This feature is developed to justify

likelihood of replacing the existing bucket with the larger model. The advantage of this

scenario is that the operator will more quickly fill the same weight of material in the

bucket, while simultaneously reducing the digging time. Consequently, a decrease in

electricity consumption, which implies an increment in the productivity, is likely to

happen. An additional reason that validates the stress monitoring system is the increase of

the dragline boom lifetime. Hasell (2008) summarizes the results from research

performed at the mine and indicates that operating the dragline with up to 90% of the

average maximum stress will increase the boom lifetime for 37%. Hasell further explains

that the numbers recorded in the DCS database are unit-less, just as in the case of the

electricity consumption. Therefore, the report illustrated in Figure 4-36 does not contains

the units.

143
Figure 4-36: The boom stress report

The algorithm integrated in the code behind the report retrieves only the operators

exceeding 90% of the maximum boom stress. The values for the maximum (max) and

minimum (min) stress are measured by strain gages integrated on the left and right side of

the boom. The dragline experiment was performed over a period of 43 days in order to

determine that the best fill factor did not include the boom stress monitoring segment;

therefore, the detailed analysis and correlation with energy consumption is omitted from

this research.

As a state-of-the art machine, a dragline performs diverse procedures in day-to-day

operations. The most intensive energy operation is the digging phase, where based on the

experiment, about 30% of total electricity was spent. This number came from the total

amount of electricity consumed by the dragline over a period of time, and the results from

IDE-ACE. The results from analysis indicate that savings in average of 19% is attainable

144
during the best practice application. This percentage of savings came from the analysis of

data for months of June and July of 2007.

The results encourage application of the IDE-ACE system as the analytical-control tool in

order to optimize dragline performance and reduce electricity consumption. Future

application of the system will confirm its usefulness. The initial response from the

managers at the mine in this case study confirms the potential that the system has.

4.7 Data Analysis – Mobile Equipment

Another comprehensive segment of the IDE-ACE system considers the analysis and

control of equipment running on the diesel fuel. The segment integrates the algorithm to

recognize the high energy consumers. As previously mentioned, the algorithm is based on

the manufacturer recommendation for the equipment running in low, medium, and high

load conditions (Chapter 3). The details from this analysis, to some extent, are provided.

Another segment integrated in the mobile equipment analysis tool is the Pivot Chart

Analysis. The pivot chart is powerful data analysis tool that enables data visualization.

Pivot charting is a straightforward process, and for this analysis not many explanations

are provided. Briefly, by utilizing this feature, a mine manager can disaggregate the

liquid fuel consumption on a daily basis for every piece of equipment running at the

mine. The graphical features visualize the data displaying the equipment that manager

have selected. Figure 4-37 shows an example of a pivot chart displaying the data for a

fleet of end dump trucks.

145
Confidential information

Figure 4-37: The pivot chart analysis tool

From an analysis standpoint, the Fuel Consumption Analysis provides back information

about the high-energy consumer. By running this analysis tool, the mine managers are

able to identify the equipment that potentially consumes more fuel than a manufacturer

recommended. Figure 4-38 shows an example of the diesel fuel consumption for fleet 170

over a one-year period. The analysis is performed by comparing the real with the

recommended fuel consumption. A detailed calculation method, along with its algorithm,

is provided in Chapter 3. The key indicators (color coded asterisks) focus on the

equipment belonging to particular fuel consumption category. The least favorable

scenario occurs when a manager notices a red asterisk (*) beside the particular

equipment. The example in Figure 4-38 points out three potentially high fuel

consumption trucks. Analyzing the results, truck 171 actually consumed 71,442 gallons

of diesel fuel during 2006 year. The consumption that the manufacturer specified for

146
maximum load conditions and the given number of working hours is 61,290 gallons.

Therefore, this truck consumes about 15% more diesel than recommended and it is

certainly a high fuel consumer.

Similarly, trucks 180 and 182 are also designated as the high-energy consumers. This

case shows that the fuel consumption is less, yet close to the maximum value provided by

the manufacturer. Therefore, this equipment is labeled as the high-energy consumer.


Confidential information

Figure 4-38: The fuel consumption analysis tool

147
4.8 Data Analysis - CO2 Emission

As mentioned earlier in the research, the mine in the case study uses three types of fuels:

diesel, gasoline, and electricity. For each of the categories, the IDE-ACE provides the

calculation and summarizes the results about CO2 emission. The calculation is based on

the fuel consumption over a period of time (liquid fuels) and the amount of coal burned in

a power plant supplying a coal mine with electricity (electrical equipment). Typically, a

user needs to choose one of the available fuels and continue the process by selecting the

fleet and the time frame. The confirmation of the entries generates the report in Figure 4-39.
Confidential information

Figure 4-39: The CO2 emission report

148
The report shows that the total CO2 emission from front end trucks over a period from

January 1 – December 31 of 2006. Besides the gas emission, the report indicates the total

amount of fuel that the fleet has consumed.

A similar report indicating the emission of CO2 from the coal burned to generate the

electricity for the facilities (main building, maintenance building) is illustrated in Figure

4-40. The figure also shows the chart with the electricity consumption from where it is

noticeable that the facility consumes more electricity over the summer time than during

the winter season. The pick in the electricity consumption, i.e., CO2 emission, is in July

when the average temperature for that region of the United States reaches the maximum

value (Weather, 2008).

Figure 4-40: CO2 emission from facility

149
On the importance of accurate CO2 emission, records indicate the world-wide carbon tax

initiative. The carbon tax (CO2 tax) is a tax on the carbon dioxide emission from burning

the fossil fuels. The idea proposes an additional tax that a company will have to pay for

using equipment running on fossil fuels. The climate change activists and the Carbon Tax

Center (CTC 2008) suggest the prices for a carbon tax ranging from $10 to $15 per ton of

carbon dioxide emitted.

For example, the coal mining company used in this case study, only from the most energy

consuming equipment, emits about 70,000 t of CO2 on an annual basis. Nearly 47%, is

from the coal burned in the power plant to generate the electricity supplying the

equipment. Assuming that the carbon tax is set on $10 per ton, the company will have to

pay $700,000 annually. If a carbon tax becomes reality, the results from dragline

optimization will have a double effect. The first benefit will be an immediate decline of

electricity consumption, i.e., reduced electricity bill. The second benefit will result from a

decrease in CO2 emission from the power plant. In this particular case, both benefits total

about a quarter million dollars or 27% in total savings from the electricity point of view

when comparing 80% and 100% fill factors.

4.9 Data Analysis – Energy Summary

The energy summary report is a custom feature of the IDE-ACE system. The idea of this

report is to supply the DOE with accurate information about the energy consumption of a

surface coal mine. This feature calculates the energy consumption and compares it with

150
the energy consumption estimated by DOE (DOE, 2002). DOE has provided the

information that a “typical” interior surface coal mine consumes about 77,000 Btu/t on

the annual basis. The specific energy that has been consumed at a mine from the case

study equals 10,871 Btu/t, without energy from the gasoline. Assuming that energy from

the gasoline equals the total energy consumed at mine, the overall energy consumption

per ton of material moved equals approximately 20,000 Btu/t. Finally, comparison of

DOE’s estimates with the real energy consumption, including the gasoline component,

reveals that the real fuel consumption is about 3.85 times less than what the DOE had

stated.

In the future, assuming that DOE supports this project and surface coal mine X agrees to

supply DOE with the data for the specific energy consumption. The IDE-ACE generates

a report in Figure 4-41 and a user, by clicking the button, sends the report via e-mail to a

corresponding person in DOE. The report includes the total production and the total

energy consumption for both shovel/trucks and dragline operations.

Confidential information Confidential information

Figure 4-41: The DOE report

151
4.10 Electricity Consumption/Productivity Model Development

The purpose of this analysis is to examine and model the energy consumption and the

production rates commissioning the process in terms of several possible explanatory

variables. Three models:

Model 1: Productivity [$/t];

Model 2: Energy Efficiency [kWh/t];

Model 3: Productivity [t/h].

were fitted to numerous combinations of the explanatory and dependant variables. In

order to determine the relationships and significant variables, statistical tests must be

performed. The procedure for one of the models is described in detail, while the rationale

for the remaining two models is identical.

4.10.1 Significant Variables

The results of dragline experiment confirmed the importance of the performance

indicator (PI) variable. However, in order to use this variable as one of the predictors, the

statistical tests have to be carried out to prove this assumption. The variables from the

experiment: cycle time (β1), fill time (β2), bucket weight (β3), angle (β4), hours (β5) are

included for the model development. A sixth variable, Performance Indicator (PI) (β6)

was used to define a full regression model. As the last variable entered in the model, the

PI was statistically tested to confirm its significance. The PI is a categorical (qualitative)

variable and as such requires a dummy variable to be used for a model development. The

152
dummy variables are the indicator variables and take the values 0 and 1. They are also the

only way to quantify the qualitative variable.

For the testing purposes the initial full model (equation 4-1)

Y= β0 + β 1x1 + β 2x2 + β 3x3 + β 4x4 + β 5x5 + β 6x6 (4-1)

is reduced on the model given in equation (4-2).

Y= β 0 + β 1x1 + β 2x2 + β 3x3 + β 4x4 + β 5x5 (4-2)

To test statistical significance the F test (Equation 4-3) with hypotheses H0: β6=0 and Ha:

β6≠0 was performed.

( SSEr  SSEf ) /( p  q)
F*= (4-3)
SSEf /(n  p)

Where: SSEr is the sum of square error for the reduced model, SSEf is the sum of square

error for the full model, p is total number of variables in the full model, and p is total

number of variables tested.

Prior to the regressing analysis, a t-paired test was performed on the predictor variables.

The test of hypotheses H0: μ1 μ2 = 0 and Ha: μ1 μ2 ≠ 0 confirmed equality of the

means with α=0.05, and confidence interval of 95%.

153
For the calculation of SSEr and SSEf the MINITAB software was used and the results for

all three models are presented in Table 4-2.

The test was performed sampling 26 data from the population; therefore, the assumption

for the normality of data is satisfied.

Table 4-3: Summary statistics for models (Minitab output)

MODEL 1 [$/t] MODEL 2 [kWh/t] MODEL 3 [t/h]


m 1 1 1
df 25 25 25
SSE(reduced) 0.000035258 0.0082875 386047
SSE(full) 0.000019051 0.0038007 373337
MSE(full) 0.000000762 0.000152 14933

F* 21.268613137 29.518421053 0.851135070


Area 0.999898 0.999988 0.63495
p-value 0.000102 0.0000120 0.36505

Based on the p-values and α=0.05, the Performance Indicator (PI) shows statistical

significance for models 1 and 2. However, the p-value for the model 3 is greater than α;

therefore, the null hypotheses cannot be rejected. In other words, the PI does not have a

statistical significance; therefore, the regression analysis for the model 3 will be

performed with the variables in the reduced model (Equation 4-2).

4.10.2 Models Building

Analyzing data and building the model is a multistep process. The procedure in this

research will be provided in some detail.

154
The correlation among the variables is the one of the tests required prior to the model

development. The correlation test measures the association between variables and ranges

from minus one (perfect negative correlation) to plus one (perfect positive correlation). A

correlation of zero means there is no relationship between variables. Testing for the

correlation between the variables was performed using Minitab and results indicated that

high correlations were not present. Only two pairs (fill time, cycle time; and angle, cycle

time) with moderately high correlations are noted (Figure 4-42). The same conclusion

results after running the matrix plot test.

Results for: Model Building_table.MTW

Correlations: cycle_time, fill_time, bucket, angle, hours, PI

cycle_time fill_time bucket angle hours


fill_time 0.615
bucket 0.093 0.113
angle 0.827 0.395 0.101
hours 0.035 0.022 -0.088 -0.206
PI -0.227 -0.449 0.235 -0.182 0.022

Figure 4-42: The correlation matrix between variables

Multicollinearity is another procedure required prior to the model building.

Multicollinearity means that some predictors are correlated with other predictors. The

variance inflation factors (VIF) are used to test the multicollinearity. If VIF is greater

than 10 the regression coefficients are poorly estimated (Kutner, et al., 2004). The

maximum VIF of 1.9 in all three models indicates that multicollinearity is not an issue

with variables used for the models.

155
4.10.2.1 Criterion Selection Procedure

This step determines the “best” model based on selected coefficients. Several methods

exist and most of them are integrated into statistical software. Minitab has integrated four

methods: Forward Selection, Backward Selection Stepwise Selection, and All Subset

Methods. Since a detailed description of regression methods is common knowledge and

appears in many statistics textbooks, this research does not cover them in depth.

However, the Minitab outputs obtained for all methods integrated in the software are

aggregated in Figures 4-43 and 4-44, respectively.

Best Subsets Regression: $/1000t versus cycle_time, fill_time, ...

Response is $/1000t

c
y f
c i
l l
e l b
_ _ u a h
t t c n o
i i k g u
Mallows m m e l r P
Vars R-Sq R-Sq(adj) C-p S e e t e s I
1 71.1 70.3 17.6 1.0414 X
1 34.3 32.7 88.1 1.5687 X
2 76.4 75.2 9.3 0.95156 X X
2 75.4 74.1 11.3 0.97244 X X
3 80.4 78.9 3.6 0.87825 X X X
3 77.4 75.6 9.4 0.94378 X X X
4 81.4 79.4 3.7 0.86806 X X X X R2 & C-p criteria
4 80.7 78.7 5.0 0.88345 X X X X
5 81.7 79.1 5.2 0.87369 X X X X X
5 81.5 79.0 5.5 0.87684 X X X X X
6 81.8 78.7 7.0 0.88336 X X X X X X

Figure 4-43: The best subset regression method

156
Backward elimination Forward Elimination Stepwise
Alpha-to-Remove: 0.1 Alpha-to-Enter: 0.25 (forward and backward)
Alpha-to-Enter: 0.15
Alpha-to-Remove: 0.15
Step 4 4 3
Constant 10.42 11.91 10.42
cycle_time -0.034
T-Value -1.38
P-Value 0.177
fill_time 0.180 0.238 0.180
T-Value 3.13 3.37 3.13
P-Value 0.003 0.002 0.003
bucket
T-Value
P-Value
angle
T-Value
P-Value
hours 0.032 0.031
T-Value 2.86 2.79
P-Value 0.007 0.008
PI -2.80 -2.77 -2.80
T-Value -9.14 -9.13 -9.14
P-Value 0.000 0.000 0.000
S 0.878 0.868 0.878
R-Sq 80.45 81.40 80.45
R-Sq(adj) 78.90 79.39 78.90
Mallows 3.6 3.7 3.6

Figure 4-44: The stepwise regression method

Based on the results from the criterion selection analysis, the “best” model accepted to

describe a behavior of unit electricity cost is given in equation 4-4. The initial two

models, defined in terms of unit production [$/t] and unit energy consumption [kWh/t],

are redefined in production and electricity consumption per 1,000 tons. This adjustment

came from absolute values of regression coefficients, which for the unit energy

consumption have small values (e.g. 0.0119).

157
Model 1 – Productivity in terms of cost per ton [$/t]:

Y = 11.9 - 2.77 PI + 0.238 FT + 0.0317 HR - 0.0341 CT (4-4)

Where: Y is the response variable indicating the cost per 1,000 t [$/1000t], PI is the

performance indicator, FT is a fill time [s], HR is the total number of hours [total time],

and CT is a cycle time [s].

The results from the Minitab analysis; with statistics for every predictor variable in the

model, 1 are provided in Figure 4-45.

Regression Analysis: $/1000t versus cycle_time, fill_time, hours, PI

The regression equation is


$/1000t = 11.9 - 0.0341 cycle_time + 0.238 fill_time + 0.0317 hours - 2.77
PI

Predictor Coef SE Coef T P VIF


Constant 11.909 1.679 7.09 0.000
cycle_time -0.03406 0.02473 -1.38 0.177 1.6
fill_time 0.23759 0.07044 3.37 0.002 1.9
hours 0.03173 0.01111 2.86 0.007 1.0
PI -2.7745 0.3039 -9.13 0.000 1.3

S = 0.868057 R-Sq = 81.4% R-Sq(adj) = 79.4%

Analysis of Variance

Source DF SS MS F P
Regression 4 122.023 30.506 40.48 0.000
Residual Error 37 27.880 0.754
Total 41 149.904

Source DF Seq SS
cycle_time 1 9.518
fill_time 1 44.784
hours 1 4.901
PI 1 62.820

Figure 4-45: Minitab output for regression analysis – Model 1

158
Utilizing the same procedure the remaining two models were developed. Again, the

model 2 has included all variables as the Model 1. However, the model 3 includes only

three predictors (cycle time, weight of martial in the bucket, and hours). The variable

Performance Indicator (PI) is missing from the model because the test of the variables did

not provide enough evidence to reject the null hypothesis, i.e., the variable was not

significant. The overall models 2 and 3 are provided in equations 4-5 and 4-6.

Model 2 – Energy Efficiency [kWh/t]

Y = 201 - 0.823 CT + 3.95 FT + 0.615 HR - 41.4 PI (4-5)

Where: Y is the response variable indicating electricity consumption per 1,000 t

[kWh/1000t], PI is performance indicator, FT is a fill time [s], HR is the total number of

hours [total time], and CT is a cycle time [s].

Model 3 – Productivity in terms of tons per hour [t/h]

Y = 4067 - 48.4 CT + 44.9 + BKT - 3.61 HR (4-6)

Where: Y is the response variable indicating hourly production [t/h], CT is a cycle time

[s], BKT is weight of material in the bucket [t], and HR is the total number of hours [total

time].

159
The summary statistics for all three models are provided in Table 4-3.

Included in the table are: the number of predictor variables in the model (n), sample

variance (S), F-test value, coefficients of determination (both R2 and R2adj,), as well as the

Mallow C-p.

Table 4-4: Models and summary of statistics for three energy models

Model n S F R2 R2adj M-Cp


$/1000t 4 0.868 40.48 81.4% 79.4% 3.7

kWh/1000t 4 0.013 41.50 81.8% 79.8% 3.6

t/h 3 122.63 145.21 92.0% 91.3% 2.2

The models 1, 2, and 3 were developed with the intent to validate the specific cost and

energy consumption per ton (i.e. 1,000 tons), as well as the dragline productivity. With a

system such as IDE-ACE, which is integrated in the mine environment, the models are

unlikely to be used; however, based on the statistics they provide a reliable tool for

forecasting one of the three response variables. The models are useful for estimating an

operator’s performance in terms of energy consumption and productivity. The same

analysis is available to validate crew performance.

The challenges with these models come with the data retrieval from the database.

Namely, two models contain the dummy variable (performance indicator), which is the

result of calculation using data stored in the database. The third model (productivity) can

be adopted for application without data retrieved from the database, yet the

160
measurements for required predictor variables are necessary. The issue with the data

retrieval can be bridged querying the database from some of the software (Excel,

Minitab, etc.) containing that feature.

In either case, based on the historic data, the manager can forecast future performance

and manage production achievements.

4.10.3 Model Validation

The model validation procedure has the purpose of checking the “best” regression model

against an independent variable. The validation procedure essentially uses independent

set of data and checks for the model predictive ability.

For the model validation, the data set was split based on the dates. The validation

procedure uses the data from the second half of April, May, June, and July of 2007, that

was recorded in the DCS database. The number of observations available for the model

validation purposes was forty-two.

The literature reports a variety of methods used for model validation purposes. The three

most frequently used methods are (Neter et al., 1996):

 Validation using the new data. This method checks for consistency in the

regression coefficients by comparing the results from the model building and the

model validation data sets. The presence of consistency provides strong support

161
that the selected model is applicable under broader circumstances than those

related to the original data.

 Reestimation of all “good” models derived from the model building data set with

the new data. This means that if the “best” model from the new data set is the

same as the “best” model from the model building data set, then a conclusion

about the model efficiency is confirmed.

 Calibration of the predictive capability of the selected (“best”) regression model.

The overall regression model is the one that “best” describes the behavior of a

given data set. For a different set of random outcomes, the analysis may likely

result with different models in terms of predictor variables. A means of measuring

predictive capability of the selected the “best” model is to use this model to

predict each case in the new data set and then calculate the mean squared

predictor error (MSPR). The concluding inference about the model considers a

difference between the mean square error (MSE) of the selected regression model

and MSPR. If the MSPR is fairly close to the MSE then the selected “best” model

provides an appropriate indication of the predictive ability of the model.

Otherwise, MSPR is an indicator of how well the selected regression model will

predict in the future.

For the regression analysis performed in this research, the reestimation and model

calibrations were performed. The reestimation procedure with the new data set confirmed

the same “best” models as in the model building data set.

162
For the model calibration method, the data from the validation model were imported in

the model building set and using Minitab features, these values were fitted in the

regression models. The results are the predicted values (PFITS) further used with the

validation dataset to calculate the mean square error predicted (MSPR) (Equation 4-7).

 (Y
i 1
i  Yˆi ) 2
MSPR  (4-7)
n

Where, Yi is the value of the response variable in the i-th validation case, Yhat is the

predicted value for the i-th validation case based on the model–building data set; n is

number of cases in the validation data set.

The same procedure was performed for all three models and the results are provided in

Table 4-5. The same table contains the coefficient of determination (variability) for both

the model-building and model validation dataset, as well as the coefficients of

correlation. Table 4-5 also points on the difference between estimated standard deviations

and some other statistics pertaining to the fitted model.

163
Table 4-5: Regression Results Based on Model-Building and Validation Data Sets – Model 1

Statistics Model-building Model-validation


data set data set
b0 11.909 10.189
s{b0} 1.679 2.033
bCT -0.03406 -0.05415
s{bCT} 0.02473 0.30093

bFT 0.23759 0.34206


s{bFT} 0.07044 0.06296

bHR 0.03173 0.02594


s{bHR} 0.01111 0.01216

bPI -2.7745 -1.7544


s{bPI} 0.3039 0.3057

SSE 27.88 28.51


MSE 0.754 0.771
MSPR - 1.580
R2 81.4% 76.3%
R2adj 79.4% 73.7%
r 0.902

Model: Y = 11.9 - 2.77 PI + 0.238 FT + 0.0317 HR - 0.0341 CT

164
Table 4-6: Regression Results Based on Model-Building and Validation Data Sets – Model 2

Statistics Model-building Model-validation


data set data set
b0 201.49 194.03
s{b0} 25.28 30.01
bCT -0.8229 -1.1843
s{bCT} 0.3742 0.4565
bFT 3.954 4.9206
s{bFT} 1.061 0.9293
bHR 0.6146 0.4643
s{bHR} 0.1673 0.1794
bPI -41.397 -28.342
s{bPI} 4.576 4.513

SSE 6323.7 6211.0


MSE 170.9 167.9
MSPR - 369.6
R2 81.8% 77.3%
R2adj 79.8% 74.8%
r 0.904

Model: Y = 201 - 0.823 CT + 3.95 FT + 0.615 HR - 41.4 PI

165
Table 4-7: Regression Results Based on Model-Building and Validation Data Sets – Model 3

Statistics Model-building Model-validation


data set data set
b0 4066.5 3665.0
s{b0} 385.0 315.7
bCT -48.354 -42.846
s{bCT} 2.761 4.272
bBKT 44.897 43.978
s{bBKT} 3.659 2.702
bHR -3.610 -1.558
s{bHR} 1.575 1.825
SSE 571446.0 627151
MSE 15038 16504
MSPR - 15038
R2 92.0% 89.0%
R2adj 91.3% 88.1%
r 0.959

Model: Y = 4067 - 48.4 CT + 44.9 BKT - 3.61 HR

166
The correlation coefficients r, ranging from 0.902 to 0.959, between dependant and fitted

variables indicate strong correlation and justifies application of the models. The same

conclusion can be reached by comparing the coefficient of determination in the validation

data explained by the model with the coefficient of determination of the regression

model.

The results in Tables 4-5, 4-6, and 4-7 indicate that the MSPRs of the validation set are

close to the MSE of the regression model. The fact that the MSE is larger than MSPR

indicates that the model’s describing behavior of the model-building dataset better than

data in the model validation dataset. The difference in the coefficients of determination

confirms this conclusion.

4.11 Diesel Fuel Consumption Model

Another model developed in this research explains the behavior of diesel fuel

consumption for the end dump trucks. The procedure for the model development is

similar to the formerly explained, so the rationale that follows is brief in details providing

the crucial statistics to justify the model.

The variables selected for the model development resulted from the pre-analysis

procedures. The initial model with four predictor variables (production, working hours,

engine power, and truck payload) is reduced on two predictors. The truck payload

predictor was eliminated from the analysis due to perfectly positive correlation with the

engine power. Running all the regression methods (Forward Selection, Backward

Selection Stepwise Selection, and All Subset Methods) using Minitab removed the engine

167
power from further analysis and confirmed that only the production and total number of

hours that equipment has accumulated are statistically significant.

Further analysis revealed that multicolinearity is not an issue, which is adjusted by a

small VIF factor of 1.2. In addition, the correlation of 0.438 supports the decision to

accept these two predictor variables for the model building. The model that is suggested

for prediction of diesel fuel consumption is formulated as follows:

Y = 654 + 0.0306 PR + 8.59 HR (4-8)

Where, Y is the response variable for the diesel fuel consumption [gal], PR is the

production rate [t], HR is the number of hours truck operated [total hours].

For validation purposes, the totals of the fuel consumption for three months for every

truck in the fleet was used. The summary of results for both model-building and model

validation is illustrated in Table 4-8.

168
Table 4-8: Regression results based on model-building and validation data sets – diesel fuel

consumption

Statistics Model-building Model-validation


data set data set
b0 653.9 941.4
s{b0} 591.1 755.9
bPR 0.030561 0.034258
s{bPR} 0.002764 0.004556
bHR 8.591 8.558
s{bBR} 1.660 1.795
SSE 30370721 48221521
MSE 1047266 1662811
MSPR - 24008577
R2 88.3% 82.5%
R2adj 87.5% 81.3%
r 0.423

Model: Y = 654 + 0.0306 PR + 8.59 HR

The statistics from the previous table indicate unbiased values between corresponding

coefficients. However, a relatively large difference between the MSE and MSPR required

application of remedial measures on the data set. The result from these measures was not

significantly different when running the analysis with original data set. For that reason,

the reestimation of all “best” models with the new data set was performed. The result

confirmed that a given model with two predictor variables and fuel consumption as the

responses can be used for the fuel prediction purposes.

Significance of this model comes from the fast and easy estimation of the fuel

consumption based on the historic data recorded on the daily/shift basis. The model

169
necessitates two predictor variables and with 87.5%, explains the changes in the

variability of data. Collecting data is not technologically challenging as in the case of the

previously mentioned three models. The production rates and the hours are the most

frequently recorded data at any mine, regardless of its IT development.

4.12 Chapter Summary

This chapter introduced the application of an integrated data environment for analysis and

control of energy consumption (IDE-ACE) in surface coal mining. It also provided an

overview and discussion of the results appearing on the reports. The data are obtained

from a surface coal mine located in the southern region of the United States. Based on the

production processes at the mine, the general surface mining model was developed. The

analytical processes integrated in the IDE-ACE code calculate the optimal bucket fill

factor. A comparison of electricity consumption that a dragline consumes for 80% fill

factor with the electricity consumed when operators attempt to fill 100% bucket shows

significant improvements in financial savings and environmental issues.

Financial average savings of about 19% on the dragline electricity bill is likely to occur,

contradicting the commonly held assumption among the operators that the bucket has to

be fully loaded to achieve better productivity. Working with a fill factor of 80% reduces

the environmental impact in terms of CO2 emission. The example provided shows

reduction of 44% or 1,535t.

170
Operator performance, calculated based on the multicriteria analysis determines the best

operator based on the optimal electricity consumption. As opposed to performance

indicators that use multiple criteria analysis for calculation, the minimum electricity

consumption ranks the operators according to the minimum electricity consumed during

the digging phase.

The maximum stress on the dragline, a secondary benefit of IDE-ACE, is evaluated also.

Running this tool over period of time is expected to expand the lifetime of the dragline

parts, adding further savings. However, the savings are not measurable as in the case of

electricity consumption, but in the long run the additional benefits are likely.

The additional benefits of the fill factor optimization were confirmed during ten month

production period. The mine deploying the IDE-ACE system confirmed a 6% (Mongeon,

2008) improvement in the dragline productivity. This achievement in production

pragmatically justified methodology developed in this research. Once the IDE-ACE

becomes applied on regular basis, its full potential will be evaluated.

171
Chapter 5

5 Summary and Conclusions

5.1 Summary

Industrialization, increasing wealth in emerging markets, and globalization are some of

the reasons for rising worldwide energy demand. Officials claim that in the next twenty

years demand for energy will be more than 50% greater than is today. Strategies to

mitigate rising energy demand include a variety of alternatives, such as increasing

production of fossil fuels, building nuclear power plants, and investigating the potential

of renewable energy sources. The real application of these alternatives requires

significant capital investment and time. The alternative immediately available is energy

savings and improvements in the management of existing energy sources. The energy

crisis is a global problem and all industries have to participate in the endeavor to make

positive changes. Sustainable development of the mining industry necessitates

fundamental changes in energy awareness, energy conservation, and energy efficiency.

Reduction in energy consumption is unlikely unless mine management starts benefiting

from modern IT coupled with the data sources available at a mine. The research carried

out here shows that diversity of the data sources available at a mine can be integrated into

a unique data environment and be successfully applied in an effort to reduce energy

consumption. The literature review as well as the onsite research have shown that mining

personnel typically do not have the IT background necessary to override the problem of

172
being data rich while information poor. Therefore, this demanding task requires

fundamental changes in the mining enterprises including the active participation of

academic and government institutions.

This chapter presents the main conclusions and results from the research done for this

dissertation. The objective of this dissertation was to develop a methodology for the

Integrated Data Environment for Analysis and Control of Energy Consumption in

Surface Coal Mining. Included in this objective was the design of information system

tools that incorporate available data sources into an integrated data environment managed

from different locations in order to convert data into useful information. The information

system developed in this research incorporates a novel methodology that is capable of

utilizing the production and energy consumption data recorded in the DCS database in

order to optimize dragline working parameters and reduce electricity consumption. Along

with the effort to indicate where, when and how much energy for a given production is

being used, this novel methodology is the focus of this dissertation and the main

contribution made by the author. Successful accomplishment of the dissertation

objectives called for research focused on the:

 Analysis and identification of existing data sources;

 Interviews with mine management in order to identify the existing data

management systems and recognize particular processes assigned with the mining

production chain;

 Research focusing the available data management systems and the technologies

that accommodate the needs of the mining business environment;

173
 Defining the conceptual framework for a novel methodology adjusted for

application in surface coal mines;

 Designing the experimentation procedures in order to measure equipment

performance and recognize the patterns within the datasets;

 Utilizing multi-criteria analysis for developing the IT tools for operator

performance metrics; and

 Integration of the system in the mine business environment.

The development of the methodology had five phases described in detail in Chapter 3.

The first three phases are crucial for the IDE-ACE development because they synthesized

the analytical-experimental procedures designed for this research. The fourth and

especially the fifth phase are the system validation procedures required for the IDE-ACE

integration in the mine business environment. The methodology developed in the

research has the potential to be applied to any mine that uses the DCS dragline

production monitoring system.

The IDE-ACE system integrated in a mine environment allows convenient navigation

through the energy consumption and production records, allowing management personnel

to overcome the problems of misleading information. Chapter 4 explains the IDE-ACE

information system, focusing the most significant improvements that a specific coal mine

can expect utilizing this system over time. The example of the best fill factor shows the

benefits in electricity savings, which simultaneously decreased the environmental impact.

174
Difficulties in achieving absolute and permanent optimality in surface coal mining is

challenging task since many variables influencing the production change over time.

Application of a system such as IDE-ACE allows convenient correction of the bucket fill

factor whenever changes occur. Moreover, the IDE-ACE system analyzes the diesel fuel

consumption and, based on the integrated algorithms, pinpoints the equipment that

consumes more fuel then the manufacturer recommends. The high energy consumer

becomes the subject of further analysis and the maintenance personnel have to investigate

the reasons for that consumption.

The analytical hierarchy process was used to evaluate the dragline performance and

determine the best operator over a selected period of time. Also, the regression analysis

carried out with the data recorded over a period of January - December 2006 and April –

July 2007 resulted in models for the electricity and diesel fuel consumption, as well as the

dragline productivity. The analysis proved the statistical significance of the performance

indicator (PI) variable used for energy consumption models. The models developed

indicate a high coefficient of determination that ranges from 81.4% to 88.3%.

The observations and conclusions on the application of the Integrated Data Environment

for Analysis and Control of Energy consumption in surface coal mining can be

summarized as follows:

 The methodology and system developed in this research make the basis for the

energy recording and the analysis of energy consumption in the surface coal

mining industry which, based on the results, provide more accurate information

then the DOE methodology does. The application of the system utilizing the field

175
data shows that the specific energy consumption is about four times less that the

consumption provided by DOE.

 The benefits that system provides are recognized in the real mine environment

and the feedback from manages will provide the material for the further

improvements of the IDE-ACE system.

 The algorithm developed in this research effectively implemented into the IDE-

ACE system shows the benefits of lower production cost, diminished

environmental impact (reduced CO2 emission), reduced waste of energy,

improved dragline productivity and boom life time;

 The experimental procedure developed through the research and integrated into

the data-driven mining decision-support system furnishes managers with the tools

for continual measurement of bucket fill factor with the purpose of improving the

production/energy consumption achievements;

 The reporting segment provides answers to the questions of when, where, and

how much energy is consumed by equipment over any period of time;

 The algorithm integrated in the system isolates the high energy consumer

(equipment);

 The dragline performance tool carries an analysis of the operators’ efficiency,

reaching the goal of either minimum or optimum energy consumption over a

given time period;

 Running the IDE-ACE system in the real production environment will record
more data and allow further analysis and control of energy consumption in surface

coal mines.

176
5.2 Recommendations for Further Research

The analysis and control of energy consumption in the mining industry in general has

tremendous beneficial potential. Systems such as IDE-ACE are rarely designed at once in

a full scale. Usually, these systems grow over time until all disintegrated segments

become a part of a unique data environment. The potential of the data sources at a surface

coal mine is great for reducing energy cost. Further research can now be conducted on

electric shovels and trucks. The DCS database used as the source of data for the dragline

experiment also records the productivity for an electric shovel. Preliminary analysis

indicated that the methodology developed in this research, with small modifications,

could potentially be applied for the electric shovel. However, any further conclusion

necessitates further experimentation in order to evaluate shovel performance and

potentially reduce electricity consumption. Assuming that results from the experiment

justify the optimization algorithm, the application of IDE-ACE can be extended to the

electric shovels. This will round the entire process, and the DCS database can be used as a

reliable data source in reducing the energy consumption in surface coal mines.

Similar research is suggested in order to utilize the data sources that Caterpillar’s Vehicle

Information Management System (VIMS) offers. With the current energy crisis,

utilization of the VIMS database is increasingly significant. Again, experimentation prior

to any data analysis is recommended. It is expected that the results of experiments

performed with the electric shovel and the end-dump trucks will provide firm conclusions

and suggest the algorithms that can be programmed and integrated into existing an IDE-

ACE system.

177
6 References

Accuweigh, 2003, “Accuweigh production monitoring system”, Drivers & Control


Services, Texas, USA.
Available at: http://www.drivesandcontrols.com/.

Akhmedov, A. D., Ereumin, I. D., Jusupov, K. K., Galiyev, S. and Jaxibayev, K. A.,
2001, “Information system of operative management of mining-transport complex
work on open-pits”, Mine Planning and Equipment Selection, Science Pub Inc, pp.
1106-1112.

Ambler, W. S., 2004, “Agile model – driven development with UML 2.0”, Cambridge
University Press, New York, USA, p 545.

Bascetin, A. 2003, “A decision supporting system for optimal equipment selection in


open pit mining: analytical hierarchy process”,
Available at: www.istanbul.edu.tr/eng/jeoloji/library/dergi/dl/?cilt16-s2-syf(1-12).

Bascetin, A., 2004, “An application of the analytic hierarchy process in equipment
selection at Orhaneli open pit coal mine”, Mining Technology: IMM Transactions
section A, Maney Publishing, Vol. 113, No. 3, pp 192-199.

Bascetin, A., 2006, “A decision support system using analytical hierarchy process
(AHP) for the optimal environmental reclamation of an open-pit mine”,
Environmental Geology, Vol. 53, pp. 663-672.

Bernold, E. L., Lloyd, J., Vouk, M., 2002, “Equipment operator training in the age of
Internet2”, 19th International Symposium on Automation & Robotics in Construction,
Washington DC, USA, Sep. 23-25.

Bush, V., Killingsworth, T. G., and Ruffel, E. P., 2002, “Leveraging your energy
management reduces: application for the mining industry”, SME Annual Meeting
2002, SME, Preprint 02-042.

CAT Inc., 2007, “Caterpillar performance handbook”, Caterpillar Inc., Peoria,


Illinois.

Carbon Tax Center, 2008, Carbon Tax Center, New York,


Available at: http://www.carbontax.org

178
Coito, F., Powell, F., Worrell, E., Price,. L., and Friedmann, R., 2005, “Case study of
California cement industry”, Proceedings 2005 ACEE Summer Study on Energy
Efficiency in Industry, American Council for an Energy-Efficient Economy,
Washington DC.

Chapple, M., 2008, “Database normalization – basics”,


Available at: http://databases.about.com/od/specificproducts/a/normalization.htm

Chadwick, J., 1982, “Saving energy in mining – 1,001 ways to go”, World Mining,
April 1982, pp. 38-43.

Darie, C. and Ruvalcaba, Z., 2006, “Build your own ASP.NET web Site using C# &
VB”, Sitepoint, Australia, p 689.

Davis, S.W., Yen, C.D., 1999, “The information system consultant’s handbook”,
CRC Press, New York, p 765.

Department of Energy, 2002, “Energy and environmental profile of U.S. Mining


Industry”, Department of Energy, Washington DC.
Available at: www1.eere.energy.gov/industry/mining/pdfs/cover.pdf

Department of Energy, 2004, “Energy Use, Loss and Opportunities Analysis: U.S.
Manufacturing & Mining”, Department of Energy, Washington DC. p 169.

Department of Energy, 2004a, “Mining industry of the future - fiscal year 2004
annual report”, Department of Energy, Washington DC.
Available at: www.netl.doe.gov/KeyIssues/mining/mining_fy2004.pdf.

Department of Energy, 2004b, “Mining energy analysis”, Department of Energy,


Washington DC, p 6.

Department of Energy, 2003, “National energy modeling system: An overview 2003”,


Department of Energy, Washington DC.
Available at: www.eia.doe.gov/oiaf/aeo/overview/index.html.

Department of Energy, 2006, “Annual energy outlook 2006”, Department of Energy,


Washington DC.
Available at:
http://www.scag.ca.gov/rcp/pdf/publications/1_2006AnnualEnergyOutlook.pdf .

Department of Energy, 2007, “Mining industry roadmap for crosscutting


technologies”, Department of Energy, Washington DC.
Available at: http://www1.eere.energy.gov/industry/mining/pdfs/ccroadmap.pdf.

Department of Energy, 2007a, “Mining industry bandwidth study”, Department of


Energy, Washington DC, p 42.

179
Department of Energy, 2007b, “Annual coal report 2006”, Department of Energy,
Washington DC.
Available at: http://www.eia.doe.gov/cneaf/coal/page/acr/acr.pdf .

Dessureault, S., Scobe, M., Dunbar, S., 1999, “Intelligent production Management in
Mining Systems”, Proc. 2nd Int. Conf. On Intelligent Processing and Manufacturing of
Materials, Soc. Adv. Mat. Proc. Eng., Honolulu, July 1999.

Dessureault, S., 2004, “Justification techniques for information technology


infrastructure in mining”, Mining Technology, Vol. 113 (4), pp. 257-262.

Dessureault. S., 2007, “Data mining, mining data: energy consumption modeling”,
Proceedings of 33rd International Symposium on Application of Computers and
Operations Research in the Mineral Industry, Magri (editor), 2007, Santiago, Chile,
pp. 451-457.

Dragline Productivity Center, 2001, “Dragline operators’ manual”, Dragline


Productivity Center, Southern Illinois University Carbondale, p 89.

Dyer, J. S., 1990, “Remarks on the analytical hierarchy process”, Management


Science, Vol. 36, No. 3, pp. 249-258.

Environmental Protection Agency, 2005, “Average carbon dioxide emission resulting


from gasoline and diesel fuel”, Office of Transportation and Air Quality, Washington
DC.
Available at: http://www.epa.gov/oms/climate/420f05001.htm.

Energy Information Administration, 2001, “Coal market module of national energy


modeling system”, Energy Information Administration, Washington DC.
Available at: http://tonto.eia.doe.gov/ftproot/modeldoc/m060(2001).pdf.

Energy Information Administration, 2007, “Annual coal report 2006”, Department of


Energy, Washington DC.
Available at: http://www.eia.doe.gov/cneaf/coal/page/acr/acr.pdf.

Ersoy, M., Celebi., N., 2007, “A management information system for a Turkish coal
mine”, Proceedings of 33rd International Symposium on Application of Computers
and Operations Research in the Mineral Industry, Magri (editor), Santiago, Chile,
Santiago, pp 171-178.

Express Technology, 2002, “What is the advantage of Microsoft SQL Server over
Access?”, Express Technology, Fairhope, Alabama.
Available at: www.netl.doe.gov/KeyIssues/mining/mining_fy2004.pdf.

180
Galiev, S., Z., Akhmedov, D.S., Dzhaksibaev A., K., 1997,“The methods of
monitoring and management of mining operations at open-pits via modeling”, Mine
Planning and Equipment Selection, Strakos, Kebo, Frana and Smutny (editors),
Balkema, Rotterdam.

GBI Ground Breaking Innovations, 2001, “Understanding and Improving Dragline


Productivity, Australia
Available at:
http://gbi.net.au/Secure/Dragline%25Course/Case%20Studies%204-8.pdf.

Grayson, R, L., Wang, Y. J., 1989, “Integrated approach to mine production and cost
management”, SME transactions, Society for Mining, Metallurgy and Exploration,
vol.286, pp. 1988-1903.

Grayson, R, L., Nutter, R, S., 1992, “The mine management support system”, 23rd
Application of Computers and Operations Research in the Mineral Industry, Kim
(editor), Tucson, USA, pp. 825-836.

Hallsel, B., 2008, Personal communication.

Harney, D., 2007, “Measuring and controlling energy utilization”, SME Annual
Meeting 2007, SME, Littleton, Colorado, preprint 07-110.

Herzog, D., Bandopadhyay, S., 1996, “Ranking of optimum beneficiation method via
the analytical hierarchy process”, Proc. 26th. Int. Symp. Appl. Computer Mine
Planning, SME/AIME, pp. 323-329.

Hernandez, M.J., 1997, “Database design for mere mortals”, Addison-Wesley


Developers Press, p 440.

Hernandez M. J., 2003, “Database design for mere mortals”, Addison-Wesley


Developers Press, p 662.

Johannes, B., Salnitski, V., Soll, H., Rauch, M., Geoters, K., Maschke, P., Stelling,
D., Eisfeldt, H., 2007, “Pefrofmance assessment in a flight simulator test – Validation
of space psychology methodology”, Acta Astronautica, No 60, pp 379-382.

Kan, M., Tan, Y., 2008, “Record matching in digital library”, Communication of the
ACM, Association of Computing Machinery, Vol 5, No 2.
Komljenovic, D., Kecojevic, V., 2006, “Multi-attribute selection method for mining
trucks”, SME Transactions, Society of Mining Metallurgy, and Exploration, Vol.
320, pp. 94-104.

Kubach, C., 2004, “Will mine survive the eco terrorist attack?”,
Available at: www.mine-engineer.com.

181
Kutner, M. H., 2004, “Applied linear regression models”, McGraw-Hill/Irwin, p.710.

Kolonja, B., Stankovic, R., and Vukovic, F., 2000, “Production information system”,
Mine Planning and Equipment Selection, Balkema, Roterdam, pp. 821-825.

Laica Geosystems, 2006, “Leica DozerNav Plus, high precision GPS dozer
guidance”, Leica Geosystems AG, Switzerland, p. 6.

Lee, Y. T., 1999, “An overview of information modeling for manufacturing systems
integration”, NISTIR 6382, NIST, Gaithersburg, MD

Lund, V., 2007, Personal communication.

Merle, P. M., 1995, “Analysis and design of business information systems”, prentice-
Hall, Inc, New Jersey, p 781.

Mining Association of Canada (MAC), 2005, “Benchmarking the energy


consumption of Canadian open-pits mines”.
Available at http://oee.nrcan.gc.ca/publications/industrial/mining/open-pit/.

Mundaca, L., 2007, “Real time performance management platform in the north
division of CODELCO Chile”, Proceedings of 33rd International Symposium On
Application of Computers and Operations Research in The Mineral Industry, Magri
(editor), 2007, Santiago, Chile, pp. 399-401.

Mosser, M., 2007, “Energy-efficient technology for mining”, National Technology


Laboratory, Department of Energy, Washington DC.
Available at: www.utahmining.org/mike%20mosser%20energy%20efficiency.ppt

Merwe, Van Der C., 2007, “Mining industry challenged to cut energy consumption
15 % by 2015”.
Available at: http://www.miningweekly.co.za/article.php?a_id=109736

Morgan, C., 2005, “Creating a common information model for the mining and
mineral industry”, Proceedings of 32rd International Symposium on Application of
Computers and Operations Research in the Mineral Industry, Taylor and Francis, pp.
21-27.

Mongeon, p., 2008, Personal communication

National Mining Association, 1998, “The future begins with mining”,


Available at: http://campus.mst.edu/iac/iof/industies/MINING/mining_vision.pdf.

National Mining Association, 1998, “CO2: A pollutant?”, ”,


Available at: http://www.nma.org/about_us/publications/pub_co2_pollutant.asp.

182
Nevers, N. D., 1995 "Air pollution control engineering”, McGraw-Hill, New York, p.
506.

Page-Jones, M., 2000, “Fundamentals of object-oriented design in UML”, Dorset


House, New York, USA, p 458.

Pallegrino, J., Quin, J., Thekdi, A., and Justiano, M., 2005, “Energy use, loss and
opportunities analysis for U.S. manufacturing and mining”, 2005 ACEEE Summer
Study on Energy Efficiency in Industry, American Council For Energy Efficient
Economy, Washington DC, p 76.

P&H MinePro, 2003, “Peak performance practices: Excavator selection”,


Harnischfeger Corporation, P&H MinePro Services, Milwaukee, Wisconsin.

Pohekar, S.D., Ramachandar, M., 2004, “Application of multi-criteria decision


making to sustainable energy planning- A review”, Renewable & Sustainable Energy
Reviews, Vol. 8, pp. 365-381.

Ramananthan, R., Ganesh, L. S., 1995, “Using AHP for resource allocation
problems”, European Journal of Operational Research, Vol. 80, pp. 410-417.

Rahm, E. Hong Hai, D., 2000, “Data cleaning: problems and current approaches”,
University of Leipzig, Germany
Available at: http://homepages.inf.ed.ac.uk/wenfei/tdd/reading/cleaning.pdf .

Rixen, W., 1981, “Energy saving ideas for open pit mining”, World Mining, June
1981, pp. 84-86.

Saaty T. L., 1980, “The analytic hierarchy process: Planning priority setting
resource allocation”, McGraw-Hill international Book, Co., New York

Saaty, T. L., 1990, “Decision making for leaders: The analytic hierarchy process in a
complex world”, RWS Publication, Pittsburgh, p 292.

Sarkka, P. Pukkila, J., 2007 “Intelligent mine and its implementation”, Proceedings
of 33rd International Symposium on Application of Computers and Operations
Research in the Mineral Industry, Magri (editor), 2007, Santiago, Chile, pp. 197-207.
SME, 1992, “SME mining engineering handbook”, Society for Mining Metallurgy,
and Exploration, Inc., Littleton, Colorado.

Speight, G. J., 1999, “The chemistry and technology of petroleum” Marcel Dekker, p.
918.

Staniak, K., and Franca, Jr J., 1996, “Energy saving in long distance conveyors –
novel idler technology”, Mine Planning and Equipment Selection, Balkema,
Roterdam, pp. 479-486.

183
Stefanko, R., 1983, “Coal mining technology: Theory and practice”, Society for
Mining Metallurgy, p 410.

Simic, D. R., Kecojevic, J. V., Gomilanovic, R. M., 1998, “Energy consumption


control in opencast coal mining”, Mine Planning and Equipment Selection 1998,
Singhal (editor), Balkema, Rotterdam, pp. 41-45.

Sarak, C., 2007, “Mining value chain – from an IT perspective”, Proceedings of 33rd
International Symposium on Application of Computers and Operations Research in
the Mineral Industry, Magri (editor), 2007, Santiago, Chile, pp. 179-187.

Swords, B., Coyle, E., Norton, B., 2008, “An enterprise energy-information system”,
Applied Energy, Vol. 85, pp. 61-69.

Weather, 2008, Data available at: http://www.weather.com/.

Western Mining Engineering, 2007, “SHERPA software for mine cost estimating –
open pit version”,
Available at: http://www.westernmine.com/westernmine/sherpa.htm.

184
VITA

DRAGAN BOGUNOVIC

Place and Date of Birth: Virovitica, Croatia, January 29, 1976


Education
The University of Belgrade, Belgrade, Serbia, B.S., 2002, Mining Engineering
The University of Belgrade, Belgrade, Serbia, M.S., 2005, Mining Engineering
The Pennsylvania State University, University Park, PA, USA, PhD, 2008, Mining
Engineering

Employment Summary
2006 – present, The Pennsylvania State University, Graduate Assistant
2007, North American Coal Corporation, Summer Internship, Database Design,
Production Improvements
2002-2005, The University of Belgrade, Belgrade, Serbia, Research Assistant

Peer Reviewed Publications


Bogunovic, D., Kecojevic, V., 2007, “Artificial screen for reducing seismic vibration
generated by blasting”, Environmental Geology, Vol. 53, No. 3, pp. 517-525.

Papers Presented at Technical Conferences and Professional Meetings


Bogunovic, D., Kricak, L., Kecojevic, V. (2007). Modeling an Artificial Screen for
Reducing Seismic Vibration“Modeling an artificial screen for reducing seismic
vibration” Proceedings of the 33rd Annual Conference on Explosives and Blasting
Technique, Nashville, TN. International Society of Explosives Engineers, pp. 127-135.
Kricak, L., Bogunovic, D., Teodorovic, Z., 2008,“Sequential Blasting Initiation System
With RF Control (SBIS–RF)”. Proceedings of the 34th Annual Conference on Explosives
and Blasting Technique, New Orleans, LA, International Society of Explosives Engineers
Kricak, L., Bogunovic, D. Majstorovic, J., Krunic, P.,2005, “Programmable initiations
system for electric detonator networks”, VIII th Open Pit and Underwater Mining
Conference, Sunny beach resort, Bulgaria.
Kricak, L., Matic, N., Krunic, P., Bogunovic, D., 2004,“System for recording and analysis of
seismic vibrations – VIBRAREC”, European Conference of Natural Constructin Materials
and Coal, Sarajevo, Bosnia and Herzegovina.
Kricak, L., Purtic, N., Bogunovic, D., 2002, “Application of Bickford Primadet® Nonel
System on Metal and Non Metal Mines”, III International Exhibition and Conference STONE
02, Arandjelovac, Serbia (In Serbian).

185

You might also like