You are on page 1of 2

INDUSTRIAL CADRE FOR OPERATION AND MAINTENANCE

Project No:PRJ-17096
Project Title: Chemanol-R202 A/B Piping Fabrication
START DATE 15-Jan-18 TODAY DATE 25-Feb-18
PROJECT
OWNER ACTUAL ACTUAL PERCENT
S/N ACTIVITY NAME START DATE FINISH DATE START DATE FINISH DATE COMPLETE
1 Pre-Fabrication Preparation FP 15-Jan-18 17-Jan-18 0%
2 Prepare and Issue Fabrication Drgs and Cutting Plan FP 17-Jan-18 17-Jan-18 0%
3 Material Issue, Bending, Rolling, Machining, Cutting FP 18-Jan-18 18-Jan-18 0%
4 Fitup, Fitup Inspection, Welding, Welding Inspection FP, QCD 19-Jan-18 25-Jan-18 0%
5 Sand Blasting & Painting FP, QCD 18-Jan-18 27-Jan-18 0%
6 Mob of Equipment and Spools to site QCD 28-Jan-18 29-Jan-18 0%
7 Erection and Completion of Site Welds FP 30-Jan-18 12-Feb-18 0%
8 Prep'n&Closing Punch List and Old NCR's FP, QCD 13-Feb-18 15-Feb-18 0%
9 10% RT of Welded Joints QCD 19-Feb-18 25-Feb-18 0%
10 Final Inspection and Hydrotest QCD 19-Feb-18 23-Feb-18 0%
11 Subm'n of Project Docs & QA/QC Dossier QCD 25-Feb-18 25-Feb-18 0%
12 Sign of QHSE Feedback and Job Completion Frm QCD 25-Feb-18 25-Feb-18 0%
Note: Above Planned Schedule is considering Day&Night-2 Shift per day
Manpower(Workshop): Supervisor(Mumtaz)-1 No, Fabricator-6 No's, Welder- 7 No's, Fitter-6 No's, Rigger-2 No's, Helper- 9 No's
INDUSTRIAL CADRE FOR OPERATION AND MAINTENANCE
Project No:PRJ-FP-181..
Project Title: SABIC-UNITED Pipe Spool Fabrication and Installation(CS SA106)
START DATE − TODAY DATE −
PROJECT
OWNER ACTUAL ACTUAL PERCENT
S/N ACTIVITY NAME Days START DATE FINISH DATE COMPLETE
1 Procurement of materials PRC,FIN 0%
2 Pre-Fabrication of Pipe Spools FP 2 0%
3 Radiographic Testing of all 10% joints FP 1 0%
4 Sandblasting & Painting of Spools at Shop 1 0%
5 Mobilisation of prefabricated spools to site FP 1 0%
6 Blinding and Isolation FP 1 0%
7 Erection of Scaffolding FP 1 0%
8 Assembly and Erection of Spools at site FP 3 0%
9 Radiographic Testing of all 100% joints QCD 1 0%
10 Pipes Paint Touchup FP 1 0%
11 Final Visual Inspection as per Isometric and Drawings FP,QCD 1 0%
12 Deblinding FP 1 0%
13 Housekeeping and Handover ALL 1 0%
14 QA/QC Dossier Submission QCD 3 0%
15 Sign of QHSE Feedback and Job Completion Frm FP,QCD 1 0%
Total No's of Days 19
Abbrevations: PRC-Procurement Department; FIN-Finance Department; QCD-Quality Control Department;