You are on page 1of 151

-1-

HOUSING BOARD HARYANA FARIDABAD

TENDER DOCUMENTS

FOR

WORK FOR THE CONSTRUCTION OF 128 TYPE-A & 64 TYPE-B FLATS (STILT
AT G F+8 STOREY) INCLUDING INTERNAL PUBLIC HEALTH SERVICES,
INTERNAL ELECTRICAL INSTALLATIONS ,COMMON AREA, ROAD WORK,
WATER SUPPLY, SEWERAGE SYSTEM, LANDSCAPING &
HORTICULTURE,RAIN WATER HARVESTING AND BOUNDARY WALL IN
SECTOR-56-56A (GH) FARIDABAD (For Serving/ Ex- Defence And Para-Military
Personnel Of Haryana) (Pocket 1.56 Acre.)

Contractor Witness Executive Engineer


-2-

HOUSING BOARD HARYANA CONSTRUCTION DIVISION FARIDABAD


TENDER NOTICE
Online E-tenders are hereby invited by the undersigned for and on behalf of Housing Board
Haryana for the work mentioned below from the contractors currently enlisted in the
appropriate category with any State Government, Centre Government, MES and Public Sector
Undertaking.

Name of work Approx. value Earnest Tender Time limit


(in Rs.) money document fee &
e-service fee
(Non-
refundable)
WORK FOR THE 210527072/-
Rs. 500000/- 20000.00 + 27 months
CONSTRUCTION OF 128 Rs.1000 for e-
TYPE-A & 64 TYPE-B tendering
DWELLING UNITS (STILT
AT GF+8 STOREY)
INCLUDING INTERNAL
PUBLIC HEALTH SERVICES,
INTERNAL ELECTRICAL
INSTALLATIONS ,COMMON
AREA, ROAD WORK,
WATER SUPPLY,
SEWERAGE SYSTEM,
LANDSCAPING &
HORTICULTURE, RAIN
WATER HARVESTING AND
BOUNDARY WALL IN
SECTOR-56-56A (GH)
FARIDABAD (For Serving/ Ex-
Defence And Para-Military
Personnel Of Haryana) (Pocket
1.56 Acre.)

Contractor Witness Executive Engineer


-3-

1. Date and time of downloading of tender document and preparation of BID w. e .f


22.06.2018 after 1300 Hrs.
2. Expiry date and time of submission of Technical Bid/ price BID online upto 06.07.2018 upto
1500 Hrs.
3. Date of submission of Technical envelop physically along with proof of online earnest
money, tender document fee and e-services fee upto 06.07.2018 upto 1500 Hrs.
4. Date of opening of technical envelop on 06.07.2018 at 1530 Hrs.
5. The bidder will submit EMD, Tender Documents Fee and E-service Fee online upto
04.07.2018.
6. Date of opening financial/ price bid will be intimated separately after sort listing of technical
bid.
7. The bidders can download the tender documents from the portal:
https.haryanaeprocurement.gov.in. Earnest money deposit and tender document fee have to
be deposited online.
8. Contractors shall have to pay the e-service fees of Rs1000/- in form of online favour of
‘Society of IT initiative funds for e-governance’ payable at Chandigarh.
9. Detailed tender documents with other detail & conditions is available on website
http://etenders.hry.nic.in and http://www.hbh.nic.in
10. Housing Board Haryana reserves the right to reject any or all tender without assigning any
reason.

For and behalf of


Housing Board Haryana
Sd/-
(S.K Garg)
Executive Engineer
Housing Board Haryana
Construction Division
Faridabad.
Ph 0129- 2276030.

Contractor Witness Executive Engineer


-4-

INDEX

S.NO. DESCRIPTION PAGE NO.


1. LIST OF ENCLOSURES TO BE SUBMITTED BY 5
TENDERER IN TECHNICAL ENVELOPE (TE)

2. SCHEDULE OF KEY DATES & GENERAL 6


INSTRUCTIONS OF E-TENDERING

3. GENERAL RULES AND DIRECTION FOR THE 10-17


CONTRACTORS

4. FORM A TO H 18-23

5. PERCENTAGE RATE TENDER AND CONTRACT FOR 26-27


WORKS

6. TENDER FOR WORKS 28

7. CONDITIONS OF CONTRACT 29-45

8. LIST OF APPROVED MAKE OF VARIOUS ITEMS 46-47

9 TECHNICAL CONDITIONS, IMPORTANT 48-49


SPECIFICATIONS AND MODE OF MEASUREMENTS
FOR ELECTRICAL WORKS

10. TECHNICAL CONDITIONS & IMPORTANT 49-53


SPECIIFICATIONS
11. ADDITIONAL CONDITIONS 54-66

12. LABOUR REGULATIONS & FAIRWAGES CLAUSE 67-70

13. GURANTEE TO BE EXECUTED BY CONTRACTORS IN 71


RESPECT OF WATER PROOFING

14. SCHEDULE OF SPECIFICATION OF ITEMS, 73-135


QUANTITIES, RATES SCHEDULE OF SPECIFICATION
OF ITEMS, QUANTITIES, RATES

15. External of the work External development such as boundary 136-149


wall, water supply & sewerage, Road, Rain water harvesting,
Landscaping, Lift, Fire & fighting & solar system for
construction of 128 No Type-’A’ (Stilt + 8 storey & 32 No
Type- ‘B’ Stilt +8 storey) Sec-56-56A Faridabad(1.56 Acre)
(PART-B)
16. COST OF DNIT 150

17. BOQ 150

Contractor Witness Executive Engineer


-5-

List of enclosures to be submitted by the tenderer. Technical Envelop "TE"

1. Earnest Money (proof be attached)

2. Tender document fee and e-services fee (proof be attached)

3. Downloaded tender documents containing terms & conditions duly stamped


and signed by authorized representative of the firm be uploaded on line.

4. Deviations form terms and conditions if any.

5. Documentary evidence regarding qualifications criteria.

i. Proof of processing the Labour License form Labour Department,


Government of Haryana.
ii. Performance certificate duly attested for successfully carrying out similar job
as prescribed in DNIT.
iii. Turnover certificate approved and audited by the Chartered Accountant.
iv. PAN Number/ TAN Number.
v. Profile of the company including Partners & Bio-Date of the top officials of
the company.
vi. Details of Arbitration/ Litigation case under process, if any.

6. Authority letter in the name of Authorized Person who have signed the Tender
Document/ Price Bid on behalf of the contractor of the company.

7. All performs ie. A to H duly filled and signed complete in all respect and be
uploaded on line.

8. Enlistment of the contractor.

9. Bid capacity duly calculated as per formula given in the DNIT duly signed by the
agency.

10. Any other documents which are required in fulfillment of eligibility criteria as per
condition of tender document.

Contractor Witness Executive Engineer


-6-

Schedule of Key dates and General Instructions for e-tendering

i) Date and time of downloading of tender document and preparation of BID w.e.f
22.06.2018 at 1300 Hrs.

ii) Expiry date and time of submission of Technical Bid/Price BID online upto 06.07.2018
at 1500 Hrs.

iii) Date of Submission of Technical envelop physically as well as online along with proof of
online payment of earnest money, tender document fee and e-services fee upto
06.07.2018 upto 1500 Hrs.
iv) The bidder will submit EMD, Tender Documents Fee and E-service Fee online upto
04.07.2018.
v) Date of opening of technical envelop on 06.07.2018 at 1530 Hrs.
vi) Date of opening financial/price bid will be intimated spartanly after scrutining of
technical bid.
vii)The Bidders can download the tender documents from the Portal:
https://haryanaeprocurement.gov.in. Earnest Money Deposit and Tender document Fee
have to be deposited through online.

viii) Contractors shall have to pay the e- Service Fees of Rs.1000/- online in favour of
‘Society for IT initiative fund for e-Governance” payable at Chandigarh. However,
the details of EMD, tender document fee and e-service fee are required to be
filled/provide. Scan copies at the time of the online bid preparation stage, the bidders are
required to keep the EMD, tender document fee and eservice fee details ready
beforehand.
ix) Detail tender documents with other detail & conditions are available on website
https://haryanaeprocurement.gov.in.

The Bidders can submit their tender documents (Online) as per the dates mentioned in the
key dates:-

Key Dates

Expiry
Sr. Start date
Department Stage Bidder’s Stage date and
No. and time
time
Tender Document 22.06.2018
06.07.2018
1 - Download and Bid
1500 Hrs.
Preparation & submission 1300 Hrs.
online submission of Tender 22.06.2018
2 - document fee, EMD and E- 04.07.2018
Service fee etc. 1300 Hrs.
Technical
06.07.2018
3 envelope - -
1530 Hrs.
opening

Scrutining of
Will be intimated separately after short-listing of technical
Technical bids &
bid.
4 Opening of
Financial/ Price
Bid

Contractor Witness Executive Engineer


-7-

Important Note:

1) The bidders have to complete ‘Bid Preparation & Submission’ stage on scheduled of date & time
as mentioned above. If any bidder failed to complete his/her aforesaid stage in the stipulated
online time schedule for this stage, his/her bid status will be considered as ‘bids not submitted’.

2) Bidder must confirm & check his/her bid status after completion of his/her all activities for e-
bidding.
3) Bidder can rework on his/her bids even after completion of ‘Bid Preparation & submission
stage’ (Bidder Stage), subject to the condition that the rework must take place during the
stipulated time frame of the Bidder Stage.

Instructions to bidder on Electronic Tendering System

These conditions will over-rule the conditions stated in the tender documents, wherever
relevant and applicable.

1. Registration of bidders on e-Procurement Portal:-

All the bidders intending to participate in the tenders processed online are required to get
registered on the centralized e-Procurement Portal i.e. https://haryanaeprocurement.gov.in.
Please visit the website for more details.
2. Obtaining a Digital Certificate:

2.1 The Bids submitted online should be encrypted and signed electronically with a Digital
Certificate to establish the identity of the bidder bidding online. These Digital
Certificates are issued by an Approved Certifying Authority, by the Controller of
Certifying Authorities, Government of India.

2.2 A Digital Certificate is issued upon receipt of mandatory identity (i.e. Applicant’s PAN
Card) and Address proofs and verification form duly attested by the Bank Manager / Post
Master / Gazetted Officer. Only upon the receipt of the required documents, a digital
certificate can be issued. For more details please visit the website –
https://haryanaeprocurement.gov.in.

2.3 The bidders may obtain Class-II or III digital signature certificate from any Certifying
Authority or Sub-certifying Authority authorized by the Controller of Certifying
Authorities or may obtain information and application format and documents required for
the issue of digital certificate from:
M/s Nextenders (India) Pvt. Ltd.
O/o. DS&D Haryana,
SCO – 09, IInd Floor,
Sector – 16,
Panchkula – 134108
E - mail: Chandigarh@nextenders.com
Help Desk: 0172 – 2582008-09, 2618292 and 1800-180-2097 (Toll Free Number)

Contractor Witness Executive Engineer


-8-

2.4 Bid for a particular tender must be submitted online using the digital certificate
(Encryption & Signing), which is used to encrypt and sign the data during the stage of bid
preparation. In case, during the process of a particular tender, the user loses his digital
certificate (due to virus attack, hardware problem, operating system or any other problem)
he will not be able to submit the bid online. Hence, the users are advised to keep a backup
of the certificate and also keep the copies at safe place under proper security (for its use in
case of emergencies).

2.5 In case of online tendering, if the digital certificate issued to the authorized user of a firm is
used for signing and submitting a bid, it will be considered equivalent to a no-objection
certificate/power of attorney /lawful authorization to that User. The firm has to authorize a
specific individual through an authorization certificate signed by all partners to use the
digital certificate as per Indian Information Technology Act 2000. Unless the certificates are
revoked, it will be assumed to represent adequate authority of the user to bid on behalf of
the firm in the department tenders as per Information Technology Act-2000. The digital
signature of this authorized user will be binding on the firm.

2.6 In case of any change in the authorization, it shall be the responsibility of management /
partners of the firm to inform the certifying authority about the change and to obtain the
digital signatures of the new person / user on behalf of the firm/company. The procedure for
application of a digital certificate however will remain the same for the new user.

2.7 The same procedure holds true for the authorized users in a private/Public limited company.
In this case, the authorization certificate will have to be signed by the directors of the
company.

3 Opening of an Electronic Payment Account/offline payment:


The tender in documents fees is to be paid online.
4 Pre-requisites for online bidding:

In order to bid online on the portal https://haryanaeprocurement.gov.in , the user machine


must be updated with the latest Java & DC setup. The link for downloading latest java applet
& DC setup are available on the Home page of the e-tendering Portal.

5 Online Viewing of Detailed Notice Inviting Tenders:

The bidders can view the detailed N.I.T and the time schedule (Key Dates) for all the tenders
floated through the single portal e-Procurement system on the Home Page at
https://haryanaeprocurement.gov.in

6 Download of Tender Documents:

The tender documents can be downloaded free of cost from the e-Procurement portal
https://haryanaeprocurement.gov.in

Contractor Witness Executive Engineer


-9-

7 Key Dates:

The bidders are strictly advised to follow dates and times as indicated in the online Notice
Inviting Tenders. The date and time shall be binding on all bidders. All online activities are
time tracked and the system enforces time locks that ensure that no activity or transaction can
take place outside the start and end dates and the time of the stage as defined in the online
Notice Inviting Tenders.

8 Bid Preparation (Technical & Financial) Online Payment of Tender Document Fee, E-
Service fee, EMD fees.

8.1 The online payment for Tender document fee, eService Fee & EMD can be done using the
secure electronic payment gateway. The Payment for Tender Document Fee and eService
Fee can be made by eligible bidders/ contractors online directly through Debit Cards &
Internet Banking Accounts and the Payment for EMD can be made online directly through
RTGS/ NEFT.
The secure electronic payments gateway is an online interface between contractors and Debit
card / online payment authorization networks.
The electronic payments gateway service shall be integrated with the system very soon
till then it will be submitted manually.
Hence, the bidders have to provide information and credentials related to manual payment
submission at single portal e - Procurement system, under Technical Envelope of the
respective tenders.
8.2 The bidders shall upload their technical offer containing documents, qualifying criteria,
technical specification, schedule of deliveries, and all other terms and conditions except the
rates (price bid).
The bidders shall quote the prices in price bid format.
NOTE:-
(A) Bidders participating in online tenders shall check the validity of his/her Digital
Signature Certificate before participating in the online Tenders at the portal
https://haryanaeprocurement.gov.in.

For help manual please refer to the ‘Home Page’ of the eProcurement website at
https://haryanaeprocurement.gov.in, and click on the available link ‘How to...?’ to
download the file.

Contractor Witness Executive Engineer


- 10 -

HOUSING BOARD HARYANA, CONSTRUCTION DIVISION, FARIDABAD


GENERAL RULES AND DIRECTIONS FOR THE GUIDANCE OF CONTRACTORS

1. Tenders are hereby invited online on behalf of Housing Board Haryana for the below
mentioned work from the contractors currently enlisted in the appropriate category
with any State Government, Central Government, MES and Public Sector
Undertakings. The contractors of the appropriate class while applying for tender,
should submit the papers/ certificate(s) from appropriate authority of having
successfully completed three similar works, each of value not less than 40% of
estimated cost or two similar works each of value not less than 50% of the estimated
cost or one similar work of value not less than 80% of the estimated cost of the
relevant packages in the last five years.

For this purpose “ cost of work” shall means the value of the completed works
including cost of material supplied by the client organization, but excluding the
material supplied free of cost. This should be certified by an Officer not below the
rank of Executive Engineer or equivalent. The cost of works executed by the
tenderer shall be updated @ 10% per annum compoundable.

Note:
All unskilled works costing upto any value and all skilled works upto Rs.30.00 lacs
each will be reserved for Cooperative Labour and construction Societies upto the
rates approved for the concerned circle of the PWD in the immediate past for similar
works after inviting tenders.

Note: Following factors shall be used to update the cost of work @ 10% per annum:

Years Before Multiplying Factor


One 1.10
Two 1.21
Three 1.33
Four 1.46
Five 1.61

WORK FOR THE CONSTRUCTION OF 128 TYPE-A & 64 TYPE-B DWELLING


UNITS (STILT AT G F+8 STOREY) INCLUDING INTERNAL PUBLIC HEALTH
SERVICES, INTERNAL ELECTRICAL INSTALLATIONS AND COMMON AREA
IN SECTOR-56-56A (GH) FARIDABAD (For Serving/ Ex- Defence And Para-Military
Personnel Of Haryana) (Pocket 1.56 Acres)

2. The contractor should have minimum average annual financial turn over during last
three years ending 31st March of previous financial year at 30% percent of the
estimated cost, duly audited by the Charted Accountant (10% compounded value per
year to be added).

3. The contractor should not have incurred any loss in more than two years during the
last five years ending 31st March of previous financial year and shall enclose

Contractor Witness Executive Engineer


- 11 -

necessary certificate from the concerned authority. An affidavit has to be furnished


in this regard by the agency.

4. Bidding Capacity = AxNx3- B, where:


A Maximum value of works executed in any one year during the last five
years (taking into account the works completed and in progress and
updated to the price level as prescribed in the tender documents).

N Number of years prescribed for completion of the work for which the
tender invited (Period up to six months be taken as half-year and more
than six months as full year).

B Value at current price level, of existing commitments and ongoing


works to be completed during the period of completion of the works for
which these tender are invited.

5. CRITERIA FOR ASSESSING THE CAPACITY OF TENDERER FOR


AWARD OF WORKS

The Eligible tenderer shall be awarded those number of works for which the capacity
of the tenderer has been ascertained based on the evaluation of its/his bidding
capacity. In case, the tenderer is lowest in more works than the eligibility as per
their/his bidding capacity, then such works would not be awarded to them and the
next lowest tenderer shall be considered.

Note: - The following documents will be provided by the contractor in the


first envelope in the technical bid along with earnest money and proof of
enlistment.
1. Documents and information required as per condition
no.1 to 5 of General Rules and Directions of the Guidance
of the Contractors.
2. All Performa duly filled as prescribed in condition no. 37
& 43 of General Rules and Directions for the Guidance of
Contractors.

6. Documents of Technical bid not to be submitted online. The same are to be


submitted in Envelope ‘TE’.

Online Bidders are also required to submit any other document related to Technical
Bid which cannot be submitted online, the same will be submitted in physical form
in Technical Envelope-‘TE’.

Price Bids are to be submitted mandatory online and shall not be accepted in any
physical form.
Scanned copies of the EMD and tender documents fee are to be submitted online.
Also, in case of technical Bids, the list of documents being submitted physically is to
be uploaded online.
In first instance, the Earnest Money shall be opened online. If the Earnest Money is
found proper, the Envelope ‘TE’ containing Technical Bid documents, shall be
opened in the presence of such contractors who choose to be present. The financial
offer shall be opened only if the tenderers meet the qualification criteria and
availability of bid capacity as per qualification criteria of the Technical Bid
document. The date of opening of Financial Bid may be fixed and announced at the
time of opening of Technical Bid or later on.

Contractor Witness Executive Engineer


- 12 -

The contractual agencies will submit the necessary documents as under:-


Technical Bid Envelope ‘TE’.
Physical Technical Envelope- All the information and documents/certificates as
required to be submitted as per tender. Also, the list of such documents that cannot
be submitted online, if any.
This envelope will be opened only if the contractual agency fulfils the required
conditions.
The contractual agencies can submit their tender documents as per the date
mentioned in the schedule of important date of bids.

7. The proof of Earnest money @ 2% of the estimated cost as mentioned in the tender
notice subject to maximum of Rs 500000/- Lakhs must accompany each tender and
proof of tender document fee is to be in the sealed technical envelop prescribing the
name of the work and addressed to the Executive Engineer, Housing Board Haryana,
Faridabad.
Scanned copy of proof of earnest money and tender document fees and e-service fee
is also required to be uploaded online by the tendering agency.
The Co-operative labour & construction societies will make the payment of earnest
money Rs.15000/- or 1% whichever is less for works upto 30.00 lacs and for the
works beyond 30.00 lacs upto 50.00 lacs, the earnest money will be 50% of the
earnest money applicable to the contractors.
No other form of payment for earnest money will be accepted.

8. The contractual agency in whose favour allotment of work will be approved shall
have to deposit the remaining amount to make earnest money 2%, and in case of Co-
operative Labour and Construction Societies are required to deposit remaining
amount to make earnest money 1% of the estimated cost (upto 50.00 lacs estimated
cost of work) as mentioned in the tender notice of work within 14 days from the date
of the intimation from Executive Engineer before issuance of allotment letter of
work. In case contractual agency fails to deposit the remaining amount by the
stipulated date intimated by Executive Engineer, then earnest money deposited by
the agency shall be forfeited. In case of unavoidable circumstances for non deposit of
balance amount of earnest money at the part of the agency, Chief Engineer may
consider the request of the agency regarding deposit of earnest money of the
contractual agency.

9 Performance Security
9A Performance Security to be deposited by successful tenderer to Engineer-in-Charge
within 21 days from the date of receipt of allotment letter issued by the Engineer-in-
Charge in any of the forms as given below, for an amount equivalent to 2% of the
contract price. The performance security will be valid up to the end of the defect
liability period plus 45 days, in case the time of completion is enlarged, the validity
of the performance security shall be correspondingly extended. It carries no interest
and is refunded to the contractor without interest after the date as specified in the
contract:
i) A Bank guarantee in the form given in the requisite Performa.
ii) Certified Bank Draft.

9B. Performance Security for Co-operative L & C Societies shall be half of the
performance security applicable to the contractors for works up to Rs. 50.00 lacs.

9C. Failure of the successful tenderer to comply with the requirement of condition No 9
& 9A, mentioned above shall constitute sufficient ground for cancelation of the

Contractor Witness Executive Engineer


- 13 -

allotment of work, forfeiture of earnest money and debarring the agency to give
tender in Housing Board Haryana for 3 years.

10. Tender documents are also available on Housing Board Haryana Web site
www.hbh.nic.in and https://haryanaeprocurement.gov.in .Interested tenders can
download the documents through internet and can submit the tenders duly completed
online and tender document fee of Rs. 20000/- per tender online in favour of
Housing Board Haryana Payable at Faridabad (non refundable) should be enclosed in
the technical envelope containing earnest money. If the tender fail to submit the
tender documents fee and earnest money in technical envelope, then his tender will
not be considered
11. If the prescribed date is declared holiday due to any reason, the next working date
shall be the effective date.
12. Only online submission of tender will be accepted.
13. If the prescribed date is declared holiday due to any reason, the next working date
shall be the effective date
14. The tender is advised to visit the site of work at his own cost and examine it and its
surroundings by him to collect all information that the tender considers necessary for
proper assessment of the prospective assignment.
15. The intending tender shall fill his offer online in percentage rate above or below on
the rates of DNIT at its appropriate place.
16. Further information can be obtained and a schedule of quantities, details, plans and
Specifications can be seen in the Office of Executive Engineer between the hours
9.00 AM to 5.00 P.M. on every working day, except Saturday, Sunday and Public
Holidays.
17. The Validity of the tender is 120 days from the date of opening of tender. If a tender
limits the validity to a lesser period in his tender, his tender is liable to be rejected.

18. Each tender shall give proof to the entire satisfaction of Executive Engineer that he
has in possession of PWD B&R Specifications Book 1990 as applicable to Haryana
and amendment till date.
19. Executive Engineer reserves to himself the right of issuing the material to the
contractor as per list enclosed for use on work at the places and rates noted against
each plus 3% storage charges. The contractor shall be held responsible for obtaining
from Board all such material required for Work from Board’s store as per terms of
contract, regardless of fluctuations in the market rates or in the stock issue rates of
the Division. No carriage or incidental charges will be borne by the Board for
moving the materials beyond the place where the contractor has agreed to take
delivery thereof, even if there is a specific provision for the payment of carriage and
incidental charges in the preface of Haryana P.W.D. Schedule of Rates, 1988.

20. Acceptance of tender will rest with the competent authority that does not bind itself
to accept the lowest tender and reserves to itself the authority to reject any or all the
tenders without assigning any reason.
21. The tender shall comply with the detailed instructions incorporated in the tender
document.
22. The tender whose tender is accepted is required to execute a contract agreement on
the prescribed form of the contract and on Non-Judicial stamp paper of Rs.100/- and

Contractor Witness Executive Engineer


- 14 -

to furnish security for the fulfillment of the contract. This security will consist of
deduction of 10% from the running payments to be made on account of work done.
The 2% earnest money (mentioned at paragraph 7 above) will be treated as part of
the security. The Earnest Money may be forfeited, if the successful tenderer fails to
sign the agreement within 21 days from the issue of allotment letter.
23. If any information furnished by the Contractual Agency is found incorrect at a later
date, he shall be debarred from tendering/taking up works in future for forever in
Housing Board Haryana. The Board reserves the right to verify the particulars
furnished by the Contractual Agency independently.
24. If the tenderer is an individual, he shall sign the tender documents above his name
with seal and current address.
25. If the tenderer is a proprietary firm, the tender documents shall be signed by the
proprietor above his full typewritten name with seal and the full name of his firm
with its current address.
26. If the tenderer is a firm in partnership, the tender documents shall be signed by all
the partners of the firm above their full typewritten name and current addresses or
alternatively by a person holding power of attorney for the firm. In the later case a
certified copy of the power of attorney should accompany the tender documents. In
both cases a certified copy of the partnership deed and current address of all partners
of the firm with its seal should be accompany the tender document.
27 If the tenderer is a Limited Company or a Corporation, the tender documents shall be
signed by a person duly authorized by the Company/Corporation. The officer who
will give the power of attorney to the person for signing the tender document shall be
competent to give such power of attorney in the Memorandum of Articles of
Association. The tender document must accompany the copy of the Power Attorney
given to that person. The company/Corporation should also furnish a copy of the
Memorandum of Articles of Association duly attested by a Public Notary.

28. Performance certificates from respective Organizations certifying suitability,


technical knowhow will be submitted duly signed by an officer not below the rank of
Executive Engineer or Chief Project Manager or equivalent.
29. If the tenderer modifies or withdraws his tender without written consent of the
Executive Engineer within a period of 120 days from the date of tender, he will be
blacklisted and his earnest money will be forfeited.
30. The authority opening the tender will first of all open the first envelope subscribed as
“TE” (Physically). He will get each conditions priced from the concerned tenderers,
if the same has not been priced by the tenderer. If the tenderer fails to price the
condition and deviate from the above procedure, his tender would be treated as
invalid and his price Bid would not be opened submitted by tenderer online or if
erroneously opened, shall not be considered at all. Further the tenderer responsible
for the material deviations shall be liable to be delisted forthwith without assigning
any reason. However, it is made clear that in case the technical envelope is not
received physically, it will presumed that tenderer is not interested to participate and
his online price bid will not be opened and rejected if tenderer uploaded price bid
online on the website.
31. The tenderers should submit his documents in technical envelope. Technical Bid,
conditions, proof of enlistment & EMD, tender document fee, e-service fee should be
put in TE envelope subscribed Technical TE and enlistment of the contractual
agency in appropriate category and performance duly attested will also be enclosed
in Technical Envelope duly sealed, online .“Price Bid” will be opened who will

Contractor Witness Executive Engineer


- 15 -

fulfill conditions and eligibility criteria. Any departure from the above would make
the tender invalid and online Price Bid will not be opened and if erroneously opened
will not be considered at all.
32. The tenderers are required to submit all documents and earnest money & cost of
tender documents in technical envelope as per list available in the DNIT who wish to
participate in the tender, physically on prescribed date failing which online price bids
will not be opened, if the tenderers have offered their rates on online bids.
33. The online price bids of the tenderers will not be opened who do not fulfill the
criteria as prescribed in the DNIT and online price bid shall be rejected.

34. In case any tenderer does not comply with the procedure given above and fails to
give financial implication and pricing of his conditions (for the withdrawal of
conditions at variance with stipulation of Tender documents) it will be presumed that
he is not interested in the work and his price bid submitted on online will not be
opened.

35. No tenderer is allowed to give any fresh conditions/rates that are disadvantageous to
the Board after opening online Price Bid. Such a condition, if given, makes the
tender invalid

36. If a tenderer withdraws or modify any of condition that is already priced at the first
instance to Board then effect of condition as originally offered by the agency will be
accounted for, working out the lowest tenderer

37 The Tenderer shall give the following information along with the tender in the
prescribed Performa:

i) List of works already completed by the tenderer during the (Performa ‘A’)
last five years.

ii) Declaration regarding works in hand and existing (Performa ‘B’)


commitment to be completed during the period of
completion of the work for which tenders are invited.

iii) The financial turn over for the last three years. (Performa ‘C’)

iv) List of Plant and Machinery in good working condition is (Performa ‘D’)
available with the tenderer.
v) Affidavit that bidder has not abandoned any work of Govt. (Performa ‘E’)
of India / State Govt. / Govt. undertaking during the last five
years.
[

vi) Undertaking that bidder would invest minimum cash upto (Performa ‘F’)
25 % of value of the work during implementation of work.
vii) Structure of Organization (Performa-‘G’)

viii) Detail of technical & administrative personal to be (Performa-‘H’)


employed for the work

Contractor Witness Executive Engineer


- 16 -

Note: Performas A to H are enclosed with tender form

38 The contractual agencies enlisted with organizations other than Housing Board Haryana,
has to furnish the details of immovable and moveable property owned by them and their
residential address supported with documentary proof along with deposit of balance
earnest money to make 2% of estimated cost as mentioned in the tender notice before
issue of allotment letter.

39. The contractor shall associate an eligible Electrical contractor for the execution of
electrical works. The contractor executing the electrical works under this contract must
be enlisted with C.P.W.D., M.E.S., Railways or State P.W.D. or any State. The name of
the eligible Electrical contractor along with his consent shall be submitted by the main
civil contractor to the concerned Executive Engineer before the award of the tender
along with certified copy of Class-A license issued by the competent authority.

40. The tenderer should be understood as tenderer / consortium firm wherever mentioned in
the tender documents for all intents & purposes

41 Pre bid meeting:


In case of works with DNIT amount above Rs 10.00 crore, a pre bid meeting shall be
held at 3.00 PM dated 29.06.2018. The purpose of meeting will be to clarify
issues and to answer questions for clarification of any doubt. Any modification of bid
documents which may become necessary as a result of pre bid meeting shall be made.
42 The date of start of work shall be reckoned after 10 days from the date of issue of
allotment of work by the Engineer-in-charge.

43 ORGANIZATION INFORMATION

Tenderer is required to submit the following information in respect of his Organization


(in forms 'G' & 'H).
(a) Name & Postal Address, i/c Telephone & Telex Number etc.
(b) Copies of original documents defining the legal status, place of
Registration and principal places of business.
(c) Names & Title of Directors and Officers to be concerned with the work with
designation of individuals authorized to act for the organization.
(d) Information on any litigation in which the applicant was involved during the last five
years, including any current litigation.
(e) Authorization for employer to seek detailed references.
(f) Number of Technical & Administrative Employees in parent company, subsidiary
company and how these would be involved in this work (in form 'H')
44. Tenderer will have to install an automatic weigh batching plant conforming to I.S
Code and of required capacity to be used for the production of design mix concrete
where specified with all required accessories as under.

Sr. No Item of Equipment Requirement


1 Computerized Concrete 1 no. 15 cum/hour as per requirement
Batching Plant

Contractor Witness Executive Engineer


- 17 -

2 Concrete Weigh Batcher 1 no. (3 bag capacity minimum)


Computerized

3 Concrete Pump 1 no. 15 cum/hour minimum

4 Concrete Transit Mixer As required

5 Concreter Vibrator (Skin) 2 nos

6 Needle Vibrator 5 no. with minimum 1 no as petrol running


7 Plate Compactor 1 No

8 Tipper Dumper 2 Nos

9 Compressor Optional as required

10 Generator with CPRIO approved 1 No


canopy

11 Bar Bending machine 1 No

12 JCB 1 No

13 Hydraulic lift/ordinary lift 1 No

14 Tower Crane 1 no for works more than Rs 20 Crores

15 Reverse Osmosis Plant 1 no. for works where water as per IS 456 is
not available.

OR
The contractor can use “Ready Mixed Concrete” (RMC) to be laid with concrete pump as
per specification of HSR item of design mix concrete from the approved RMC plants i.e Ultratech,
Lafarge, ACC & Birla or any other RMC plant as approved by the Chief Engineer, Housing Board
Haryana, Panchkula.

The bidder can download the bidding documents from the e-procurement website at
https://haryanaeprocurement.gov.in.Tender document fee eservice fee and earnest money has
to be paid as described below.

Estimated cost Rs. 210527072/-


Earnest Money Rs. 4210540/-
Time Limit 27 months
Cost of tender documents Rs 20000/-
(Non refundable)
Fee of e-service( non refundable) Rs 1000/-

Certified that this NIT contains 1 to 150 pages


Sd/-
Sd/- Executive Engineer,
Divisional Accountant, Housing Board Haryana,
Housing Board Haryana, Faridabad.
Faridabad.

Contractor Witness Executive Engineer


- 18 -

PROFORMA ‘A’
LIST OF WORK ALREADY COMPLETED BY THE TENDERER

Sr.No Name of Place Date of Date of Time take in Remarks


work Start Completion month to
complete
work

(1) 2(a) 2(b) 2(c) (3) (4) (5)

Date Signature of the tenderer

Contractor Witness Executive Engineer


- 19 -

PROFORMA (‘B’)
DECLARATION REGARDING WORK IN HAND WITH THE TENDERER

Sr. Name Place Estimate Date of Stipulated Amount Brief Remarks


No. of work cost issue of period of work detail
work of done on of
order completion delay if
any

(1) 2(a) 2(b) (3) (4) (5) (6) (7) (8)

Note: 1. Amount of work done in column 6 should be given up to the month previous to
which tenders are invited.

Date Signature of the tenderer

Contractor Witness Executive Engineer


- 20 -

PROFORMA (‘C’)
FINANCIAL INFORMATION
Financial Analysis- Details to be furnished duly supported by figures in balance sheet/profit
& loss account for the last five years duly audited and certified by the Chartered
Accountant, as submitted by the Tender to the Income Tax Department (Copies of be
attached):
i) Years:
Sr. Description Years
No 2012-2013 2013-2014 2014-2015 2015-2016 2016-2017
1. Gross annual
Turnover on
construction
works.

2. Profit/loss

ii) Financial arrangements for carrying out the proposed work.

iii) The following certificates be also enclosed:

a) Tax deducted at source certificates from the clients for the last three years.

b) Income Tax Clearance Certificate.

c) Solvency Certificate from bankers of Tenderer of 15% of estimated cost of work.

Signature of
Chartered Accountant
With seal
Signature of Tenderer
With seal

Contractor Witness Executive Engineer


- 21 -

PROFORMA (‘D’)
LIST OF PLANT AND MACHINERY IN GOOD WORKING ORDER AVAILABLE
WITH THE TENDERER

Sr. Plant & Location Age of Make Capacity Approx Remarks


No Machinery Machinery Value

(1) (2) (3) (4) (5) (6) (7) (8)

Signature of the tenderer


Dated:

Contractor Witness Executive Engineer


- 22 -

PROFORMA (‘E’)
AFFIDAVIT

1. I, the undersigned, do hereby certify that all the statements made in the required

attachments are true and correct.

2. The undersigned also hereby certifies that neither our firm

M/s______________________________________ have abandoned any

work Govt. of India or any State or Govt. undertakings nor any contract awarded to

us for such works have been rescinded on account of our default, during last five

years prior to the date of this bid.

3. The undersigned hereby authorize(s) and request(s) any bank, person, firm or

corporation to furnish pertinent information deemed necessary and requested by the

Department to verify this statement or regarding my (our) competence and general

reputation.

4. The undersigned and agrees that further qualifying information may be requested

and agrees to furnish any such information at the request of the Department/Project

implementing agency.

__________________________
(Signed by an Authorized Officer of the Firm)

DATE ______________
(Title of Officer)

_______________
(Name of Firm)

Contractor Witness Executive Engineer


- 23 -

PROFORMA (‘F’)
UNDERTAKING
I, the undersigned do hereby undertake that our firm
M/s_______________________________________ would invest a minimum cash up to 25
% of the value of the work during implementation of the Contract.

__________________________

(Signed by an Authorized Officer of the Firm)


DATE ______________
(Title of Officer)

_____________
(Name of Firm)

Contractor Witness Executive Engineer


- 24 -

Performa- G
STRUCTURE OF ORGANIZATION

1. Name & address of the tenderer.


2. Telephone No I telex No I Fax No
3. Legal status of the tenderer (attach photo copy of original document defining the legal
status)
a. ) An Individual.
b. ) A proprietary firm
c. ) A firm in partnership
d. ) A limited company or Corporation
4. Particulars of registration with various Government Department
(attach documentary proof)

S. No. Organization I Place of Registration Registration


1
2
3
4
5 Name and title of Directors & Officers with
Designation to be concerned with this work

Designation of individual authorized to act for the


6 Organization

Was the Tenderer ever required to suspend construction for a period


of more than six month continuously after you commenced the
7 construction? If so, give the name of project and reasons of
suspension of work

Had the Tenderer or any constituent partner in case of partnership


firm, ever abandoned the awarded work before its completion? If so,
8
give the name of project and reasons for abandonment.

Had the Tenderer or any constituent partner in case of partnership


9 firm, ever been debarred I black listed for tendering in any
organization at any time? If so, give details.

Had the Tenderer or any constituent partner in case of partnership


10
firm, ever been convicted by a court of law? If so, give details.

In which field of Civil Engineering construction the


11
Tenderer has specialization and interest?
Any other information considered necessary but not included above
12

Signature of Tenderer,
With seal

Contractor Witness Executive Engineer


- 25 -

Performa – H

DETAILS OF TECHNICALS AND AMINISTRATIVE PERSONNEL TO BE


EMPLOYED FOR THE WORK

S. Designation Total Number Name Qualification Profession How these Remarks


No Number available experience would be
for this and details involved
work of work in this
carried out work
1

Signature of Tenderer with seal

Contractor Witness Executive Engineer


- 26 -

HOUSING BOARD HARYANA CONSTRUCTION DIVISION FARIDABAD

(FORM: F-1)

PERCENTAGE RATE TENDER AND CONTRACT FOR WORKS

1. All works proposed for execution by contract will be notified in form of invitation to
tender pasted on a board hung up in the office of Executive Engineer duly signed by
the Executive Engineer.
This form will state the work to be carried out, as well as the date for submitting and
opening tenders and the time allowed for carrying out the work also the amount of
earnest money to be deposited with tender, and the amount of the security deposit to
be deposited by the successful tender and percentage, if any to be deducted from
bills. Copies of the specifications, designs and drawings, Haryana P.W.D. Schedule
of Rates 1988 and any other documents required in connection with the work, signed
for the purpose of identification by the Executive Engineer shall also be open for
inspection by the contractors at the office of the Executive Engineer during office
hours.
2. In the event of the tender being submitted by a firm, the documents submitted in
“TE” must be signed separately by each member thereof, or, in the event of the
absence of any partner, it must be signed on his behalf by a person holding a power
of attorney from that partner to do so.
3. Any person who submits a tender shall fill up (BOQ e-tendering) at how much percentage
above or below the rates specified, he is willing to undertake the work. Only percentage
above or below on DNIT cost on the date of tender shall be named. Tender which propose
any alteration in the work specified in the said form of invitation to tender, or in time
allowed for carrying out the work, or which contain any other condition of any sort, will be
liable to rejection. No single tender shall include more than one work, but contractor who
wish to tender for two or more works shall submit a separate tender for each work. Tender
shall have to name and number of the work they refer written outside of the technical
envelope.
4. The Executive Engineer or his duly authorized Assistant Engineer will open technical
envelope tenders in the presence of any intending contractor or their authorized agents who
may be present at the time and will enter the amount of several tenders in a comparative
statement in a suitable form. In the event of a tender being accepted, a receipt for the earnest
money forwarded therewith shall thereupon be given to the contractor who shall thereupon
for the purposes of identification sign copies of the specification and other documents. In
the event of a tender being rejected, the earnest money forwarded with such unaccepted
tender shall thereupon be returned to the contractor.

5. The Board may refuse or suspend payments on account of a work when executed by firm or
by contractor described in their tender as a firm, unless receipts are signed by all the
partners, or one of the partners or some other person produces written authority enabling
him to give actual receipts on behalf of the firm.

Contractor Witness Executive Engineer


- 27 -

6 The receipt of an Accountant or Clerk for any money paid by the contractor will not be
considered as any acknowledgement of payment to the Executive Engineer and the
contractor shall be responsible for seeing that he procures receipt signed by the Executive
Engineer.

7 The Executive Engineer shall have the right of rejecting all or any of the tender without
assigning any reason.

Sd/-
Sd/- Executive Engineer,
Divisional Accountant, Housing Board Haryana,
Housing Board Haryana, Faridabad.
Faridabad.

Contractor Witness Executive Engineer


- 28 -

TENDER FOR WORKS


I/We hereby tender for the Chairman of Housing Board Haryana
hereinafter referred to as Board for the execution of the work specified in
the underwritten memorandum within the specified time at the
rates(mentioned in the BOQ online) percent below / above the rates
entered in the Haryana P.W.D. Schedule of rates 1988 / derived rates of
HSR 1988 plus sanctioned ceiling premium as applicable on the date of
receipt of tender / non- schedule (N.S.) items exhibited in the DNIT in
Part-II (Rule-1) and in accordance in all respects with the specification,
drawings and instructions in writing referred to in Rule 1 hereof and in
Clause 2 of the annexed conditions and with such materials as are
provided for and by all other respect in accordance with such conditions
so far as applicable
MEMORANDUM
a) General description :
WORK FOR THE CONSTRUCTION OF 128 TYPE-A & 64 TYPE-B
DWELLING UNITS (STILT AT G F+8 STOREY) INCLUDING
INTERNAL PUBLIC HEALTH SERVICES, INTERNAL ELECTRICAL
INSTALLATIONS ,COMMON AREA, ROAD WORK, WATER SUPPLY,
SEWERAGE SYSTEM, LANDSCAPING & HORTICULTURE,RAIN
WATER HARVESTING AND BOUNDARY WALL IN SECTOR-56-56A
(GH) FARIDABAD (For Serving/ Ex- Defence And Para-Military Personnel
Of Haryana) (Pocket 1.56 Acre.)

b) Estimated Cost : Rs. 210527072/-


c) Earnest Money : Rs.4210540/-
d) Security Deposit (including earnest money)
e) Percentage, if any, to be deducted from bills : 10% amount from the running
payments to be made on account of work done (with the earnest money
deposited by the contractor) subject to a maximum 5% of agreement amount
f) Time allowed for the work date of written order to commence 27 months.
Shall this tender be accepted I/We hereby agreed to abide by and fulfill all the
terms and provisions of the said conditions of contract annexed hereto so far as
applicable or in default thereof to forfeit and pay to the Board or its successors in
office the sums of money mentioned in the said conditions.
The sum of Rs……………………….. Deposited online as earnest money the
full value of which is to be absolutely forfeited to the Board or its successors in Signature of
office, without prejudice to any rights and remedies of the said Board or its contractor before
successors in office, should I/We fail to commence the work specified in the submission tender
above memorandum otherwise the said sum of Rs………………….. shall be
retained by Board on account of the security deposit specified in Clause 1 of the
said conditions of the contract. Signature of
Dated the ……………………. Day of ……………………….. 2018 witness to
contractor’s
Witness Contractor signature
Address
Occupation
The above tender is hereby accepted by me on behalf of the Board date the Signature of the
………………. Day of ………………… 2018 officer by whom
accepted

Sd/-
Executive Engineer,
Housing Board Haryana,
Faridabad

Contractor Witness Executive Engineer


- 29 -

CONDITIONS OF CONTRACT

Clause-1: The person/persons whose tender may be accepted


(hereinafter called the persons Contractor) shall permit Board Security Deposit
at the time of making any payment to him for work done under
the contract to deduct security @ 10% from the running
payments to be made on account of work done (with the
earnest money deposited by him) subject to the maximum 5%
of the agreement amount. Such deductions to be held by
Board by way of security deposit. All compensation or other
sums of money payable by the Contractor to Board under the
terms of his contract may be deducted from the security
deposit or from any sums which may be due or may become
due to the Contractor by the Board on any account whatsoever
and in the event of his security deposit being reduced by
reason of any such deduction, the Contractor shall within
ten days thereafter make good in cash or Board securities
endorsed as aforesaid any sum or sums which may have been
deducted from his security deposit or raised by sale of his
securities deposit or any part thereof.

Clause-2 : The time allowed for carrying out work as entered Compensation
in the tender shall be strictly observed by the contractor and for delay
shall be reckoned from the date on which the order to
commence work is given to the contractor. The work shall
throughout stipulated period of the contract be proceeded with
all due diligence (time being deemed to be the essence of the
contract on part of the contractor) and the contractor shall pay
as compensation an amount equal to1% which the Executive
Engineer may levy on the amount of the estimated cost of the
whole work as shown by the tender for every day and the work
remains un-commenced or unfinished, after the proper dates.
And, further to ensure good progress during the execution of
the work the contractor shall be bound, in all cases in which
the time allowed for any work exceeds one month to complete
one-fourth of the whole of the work before one-fourth of the
whole time allowed under the contract has elapsed, one-half of
the work before one-half of such time has been elapsed and 3/4
of the whole work before three-four of the whole time has
elapsed and so on. In the event of the contractor failing to
comply with this condition he shall be liable to pay as
compensation an amount equal to 1% of the initial contract
price per day which the Executive Engineer may levy on the
said estimated cost as mentioned in the tender notice of the
whole work for every day that the due quantity of the work
remain incomplete provided

always that the entire amount of compensation to be paid


under the provision of this clause shall not exceeds 10 percent

Contractor Witness Executive Engineer


- 30 -

on the estimated cost of work as shown in the tender. The


Chief Engineer may on representation from the contractor
recommend reduction of the compensation with reason to be
recorded in writing to the Chief Administrator whose decision
shall be final.
Clause-3: In any case in which under any clause or clauses in Action when
this contract, the contractor shall have rendered himself liable whole
of security deposit is
to pay compensation amounting to the whole of his security forfeited.
deposit(whether paid in one sum or deducted by installments)
the Executive Engineer on behalf of the Board shall have
power to adopt any of the following courses, as he may deem
best suited to the interest of Board:
(a) To rescind the contract (of which rescission notice in
writing to the contractor under the hand of the Executive
Engineer shall be conclusive evidence), and in which case
the security deposit of the contractor shall stand forfeited,
and be absolutely at the disposal of the Board.
(b) To employ labour paid by the Housing Board Haryana and
to supply material to carry out the work, or any part of the
work debiting the contractor with the cost of the labour and
the price of material (of the amount of which cost and price
a certificate of the Executive Engineer shall be final and
conclusive, against the contractor) and crediting him with
the value of the work done, in all respect in the same
manner and at the same rates as if it had been carried out
by the contractor under the terms of his contract, the
certificate of the Executive Engineer as to the value of the
work done shall be final and conclusive against the
contractor.
(c) To measure up the work of the contractor, and to take such
part thereof as shall be unexecuted out his hands and to
give to another contractor to complete, in which case any
expenses which may be incurred in excess of the sum
which would have been paid to the original contractor of
the whole work had been executed by him (of the amount
of which excess the certificate in writing of the Executive
Engineer shall be final and conclusive), shall be borne and
paid by the original contractor and may be deducted from
any money due to him by Board under the contract or
otherwise or from his security deposit or the proceeds of
sale thereof or sufficient part thereof.
In the event of any of the above courses being adopted by
the Executive Engineer, the contractor shall have no claim to
compensation for any loss sustained by reasons of his having
purchased or procured any material or entered in any
engagement or made any advances on account of or with a
view to the execution of the work for the performance of the
contract. And, in case the contract shall be rescinded under the
provision aforesaid, the contractor shall not be entitled to
recover or be paid any sum for any work thereof actually

Contractor Witness Executive Engineer


- 31 -

performed under this contract, unless and until the Executive


Engineer will certify in writing the performance of such work
and the value payable in respect thereof and he shall only be
entitled to be paid the value so certified.
Clause- 4 : In any case in which any power conferred upon the Contractor remains
Executive Engineer by clause-3 hereof shall have become liable to pay
compensation if action
exercisable and the same shall not be exercised, the non not taken under clause
exercise thereof shall not constitute a waiver of any of the 3.
conditions hereof and such powers shall not withstanding be
exercisable in the event of any future case of default by the Power to take
contractor for which by any cause or clauses hereof his is possession of or
require removal of or
declared liable to pay compensation amounting to the whole of sell contractor’s
his security deposit and the liability of the contractor for past plant.
and further compensation shall remain unaffected in the event
of the Executive Engineer putting in force either or the
powers(a) or (c) vested in him the preceding clause he may, if
he so desire, take possession of all or any tools, materials and
stores in or upon the works, or the site thereof or belonging to
the contractor or procured by him and intended to be used for
the execution of the work any part thereof,
paying or allowing for the same contract rates or in case of
these not being applicable at current market rates to be
certified by the Executive Engineer may by notice in writing to
the contractor or his clerk of the works, foreman or other
authorized agent required him to remove such tools, plant and
in the event of the contractor failing to comply with any such
requisition the Executive Engineer may remove them at the
contractor’s expense or sell them by auction or private sale on
account of the contractor and at his risk in all respects and the
certificate of the Executive Engineer as to the expense for any
such removal and the amount of proceeds and expense of any
such sale shall be final and conclusive against the contractor.
Clause-5: if the contractor shall desire an extension of the time Extension of time.
for completion of the work on the ground of his having
unavoidably hindrance in its execution or on any other ground,
he shall apply in writing to the Executive Engineer within 30
days of the due date of the hindrance on account of which he
desires such extension as aforesaid and the Chief Engineer
shall if in his opinion ( which shall be final ) responsible
ground be shown such as non supply of material that are to be
arranged by the Board as per contract or non making of
required drawings available to the contractor for execution of
works therefore authorized such extension of time, if any as
may, in his opinion be necessary or proper. Extension in time
limit would not be considered for non arrangement of material
that is required to be arranged by the contractor
Clause–6: The contractor shall deliver in the office of the Contractor to
Executive Engineer on or before the 10th day of every month submit a return
every month on any
during the continuance of the work covered by this contract a
works
return showing details of any work claimed for as extra and

Contractor Witness Executive Engineer


- 32 -

such return shall also contain the value of such work as claimed as extra
claimed by the contractor, which value shall be based upon the
rates and prices mentioned in the contract in the schedule of
rates in force. The contractor shall include in such monthly
return particulars of all claims of whatever kind and however
arising which at the date thereof he has or may claim to have
against the Executive Engineer under or in respect of or in any
manner arising out execution of the work and the contractor
shall be deemed to have waived all claims not included in such
return and will have no right to enforce any such claims not so
included, whatsoever by the circumstances.
Clause-7: Without prejudice to the rights of Board under any Final certificate
clause hereinafter contained on completion of the work, the
contractor shall be furnished with a certificate by the
Executive Engineer of such completion but no such certificate
shall be given nor shall the work be considered to be complete
until the contractor shall have removed from the premises on
which the work shall be executed all scaffolding, surplus
materials and rubbish and cleaned off the dirt from all wood
work, walls, floors or other parts of any building in upon or
about which the work is to be executed or of which he may
have had possession for the purpose of the execution thereof
and the measurements in the said certificate shall be binding
and conclusive against the contractor if the contractor shall fail
to comply with the requirements of this clause as to removal of
scaffolding, surplus materials and rubbish and cleaning of dirt
on or before the date fixed for the completion of the work, the
Executive Engineer may at the expenses of the contractor
remove such scaffolding, surplus materials and rubbish and
dispose off the same as thinks fit and clean of such dirt as
aforesaid and the contractor shall forthwith pay the amount of
all expenses so incurred and shall have no claim in respect of
any such scaffolding or surplus materials as aforesaid except
for any sum actually realized by the sale thereof.
Clause-8: No payments shall be made for works estimated to Payment on
cost less than rupees one thousand till after the whole of the intermediate
works shall have been completed and a certificate of certificate to be
regarded as advance
completion given. But in the case of works estimated to cost
more than rupees one thousand the contractor shall on
submitting bill thereof be entitled to receive a monthly
payment proportionate to the part thereof than approved and
passed by the Executive Engineer whose certificate of such
approval and passing of the sum so payable shall be final and
conclusive against the contractor. But all such intermediate
payments shall be regarded as payment by way of advance
against the final payments only and not as payments for work
actually done and completed and shall not preclude the
requiring of bad, unsounded and imperfect or unskillful work
to be removed and taken away and reconstructed or re-erected

Contractor Witness Executive Engineer


- 33 -

or be considered as an admission or the due performance of the


contract, or any part thereof in any respect or the occurring of
any claim nor shall it conclude determine or effect in any way
the power of Executive Engineer under the terms, conditions
or any of them as to the final settlement and adjustment of the
accounts or otherwise or in any other way vary of affect the
contract. The final bill shall be submitted by the contractor
within one month of the date fixed for completion of the work,
otherwise the Executive Engineer certificate of the
measurement and of the total amount payable for the work
accordingly shall be final and binding on all parties.

Clause-9: A bill shall be submitted by the contractor each Bills to be


month on or before the date fixed by the Executive Engineer submitted
for all work executed in the previous month and the Executive monthly
Engineer shall take or cause to be taken the requisite
measurement for the purpose of having the same verified and
the claim and for as admissible adjusted if possible before the
expiry of ten days from the presentation of the bill. If the
contractor does not submit the bill within the time fixed as
aforesaid the Executive Engineer may depute a subordinate to
measure up the said work in the presence of the contractor,
whose countersignature to the measurement list will be
sufficient warrant and the Executive Engineer may prepare a
bill from such list which shall be binding on the contractor in
all respects.
Clause-10: The contractor shall submit all bills on printed Bills to be on
forms to be had on application at the office of the Executive printed form
Engineer and the charge in the bill shall always be entered at
the rate specified in the tender or in the case of any extra work,
ordered in pursuance of these conditions and not mentioned or
provided for in the tender at the rates hereafter provided for
such work.
Clause-11: If the specification of estimate of the work
provides for the use of any special description of materials to
be supplied from the Executive Engineer’s store or if it
required that the contractor shall use certain stores to be
provided by the Executive Engineer(such materials and stores
and the prices to be charged therefore as hereinafter mentioned
being so far as practicable for the convenience of the
contractor but not so in any way to control the meaning or
effect of this control specified in the schedule or memorandum
hereto annexed) the contractor shall be supplied with such
materials and stores required from time to time to be used by
him for the purpose of the contract only and the value of the
full quantity of materials and stores so supplied the rates
specified in the said schedule or memorandum may be set of
so deducted from any sums then due or thereafter so become
due to the contractor under the contract or otherwise against

Contractor Witness Executive Engineer


- 34 -

for from the security deposit. All material supplied to the


contractor shall remain the property of the contractor but shall
not on any account be removed from the site of the work
without the written permission of Executive Engineer and shall
at time be opened to inspection by him. Any such materials
unused and in perfectly good condition at the time of the
completion of the contract shall be returned to the Executive
Engineer’s store, if by a notice in writing under his hand he
shall so require but the contractor shall not be entitled to return
any such material unless with such consent and shall have no
claims for compensation on account of any such materials so
supplied to him as aforesaid being unused by him, or for any
wastage in or damage to any such materials.
Clause-12: The contractor shall execute the whole and every Works to be
part of the work in the most substantial and workman like executed in
manner and both as regards materials and otherwise in every accordance with
specifications,
respect in strict accordance with the specification. The contract
drawings, orders etc.
shall also conform exactly, fully and faithfully to the designs,
drawings and instructions in writing relating to the work
signed by the Executive Engineer and lodged in the office and
to which the contractor shall be entitled to have access at such
office or on the site of the work for the purpose of inspection
during office hours and the contractor shall if he so require be
entitled at his own expense to make of cause to be made copies
of the specification and of all such designs, drawings and
instructions as aforesaid.

Clause-13: The Executive Engineer shall have full powers at Removal of


all time to object to the employment of any workman foreman employed work
or other employees on the work by the contractor and if the men and foremen.
contractor shall receive notice in writing from the Executive
Engineer requesting the removal of and such man or men from
the work the contractor to comply with the request forth with.
No such workman foreman or other employee after his
removal from the works by request of the Executive Engineer
shall be re-employed or reinstated on the works by the
contractor at any time except with the previous approval in
writing of the Executive Engineer. The contractor shall not be
entitled to demand the reason from the Executive Engineer for
requiring the removal of any such workman, foreman or other
employee.
Clause-14: The Executive Engineer shall have power to
make any alterations in or omission from additions to or Alternation in
substitutions for the original specifications, drawings, designs, specification &
designs
and instructions that may appeal to him to be necessary or
advisable during the progress of the work and the contractor
shall be bound to carry out the work in accordance with any
instructions which may be given to him in writing signed by

Contractor Witness Executive Engineer


- 35 -

the Executive Engineer and such alterations, additions or Do not invalidate


substitutions shall not invalidate the contract and any altered contracts
additional or substituted work which the contractor may be
directed to do in the manner above specified as part of the
work shall be carried out by the contractor on same conditions
in all respects on which he agreed to do the main work and at Extension of time of
the same rates as specified in the tender for main work. The time in consequence
time for the completion of the work shall be extended in of alterations
proportion that the altered additional or substituted work bears
to the original contract. And if the certificate of Executive
Engineer shall conclusive as to such proportion. And if the
altered additional or substituted work includes any class of
work for which no rate is specified in the contract then such
class of work shall be carried out at the rates entered in the
Haryana PWD Schedule of rates-1988 of the district, subject to
the same percentage above or below as included in the contract
Rates for works not
and if such class of work is not entered in the Haryana PWD
in estimate or
Schedule of rates 1988 of the district then the contractor shall schedule of rate of
within seven days of the date of receipt of his order to carry the district.
out the work inform the Executive Engineer of the rate which
in his intention to charge for such class of work and if the
Executive Engineer does not agree to his rate he shall by
notice in writing be at liberty to cancel his order to carry out
such class of work and arrange to carry it out in such manner
as he may consider advisable, provided always that if the
contract shall commence work or incur any expenditure in
regard there to before the rate shall have been determined
lastly hereinbefore mentioned then and in such case he shall be
entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the
determination of the rate aforesaid according to such rate or
rates as shall be fixed by Executive Engineer and the decision
of the Chief Engineer shall be final.

Clause-15: If any time after the commencement of the work, No compensation for
alternation or
the Board shall for any reason whatsoever not require the restriction of work
whole work thereof as specified in the tender to be carried out to be carried out.
the Executive Engineer shall give notice in writing of the fact
to the contract who shall have no claim to any payment or
compensation whatsoever on account of any profit or
advantage which he might have derived from execution of the
work in full that which he did not derive in consequence of the
full amount of work not having been carried out neither shall
he has any claim for compensation by reason of any alteration
having been made in the original specification drawings,
designs and instruction which shall involve any curtailment of
the work originally contemplated.
Clause-16: If it shall appear to the Executive Engineer or his Action &
compensation payable
subordinate-in-charge of the work that any work has been in case of bad work.

Contractor Witness Executive Engineer


- 36 -

executed with unsound imperfect or unskillful workmanship or


with materials of any inferior description or that any materials
or articles provided by him for the
execution of the work are unsound, or of a quality inferior to
that Executive Engineer specifying the work materials or
articles complained of not with-standing that the same may
have been inadvertently passed, certified and paid for,
forthwith rectify or remove and reconstruct the work so
specified whole or in part as the case may required, or as the
case may be, removed the material or article so specified and
provide other, proper and suitable materials or articles at his
own proper charge and cost, in the event of his failing to do so
within a period to be specified by the Executive Engineer in
his demand aforesaid then the contractor shall be liable to pay
compensation at the rate of one percent on the amount of the
estimate for every day not exceeding ten days while his failure
to do so shall continue and in the case of any such failure the
Executive Engineer may rectify or remove and re-execute the
work or remove and replace other materials or articles
complained of as the case may be, at the risk and expense in all
respect of the contractor.

Clause–17 : All work under or in course or executed in Works to be open


pursuance of the contract shall at all times be open to the to inspection
inspection and the supervision of the Executive Engineer and
his subordinate and the contractor shall at all times during the
Contractor or
usual working hours and at all other times at which reasonable responsible Agent
notice of intention of the Executive Engineer or his to be present
subordinate to visit the works shall have been given to the
contractor either himself be present to receive orders and
instruction or have a responsible agent duly accredited in
writing present for the purpose. Orders given to the
contractor’s agent shall be considered to have the same forces
as if they had been given to contract himself.
Clause-18 : The contractor shall give not less than five day’s Notice to be given
notice in writing to the Executive Engineer or his subordinate- before work is
in-charge of the work before covering up or otherwise placing commenced
beyond the reach of measurement any work in order that same
may be measured and correct dimensions thereof be taken
before the same is so covered up or placed beyond the reach of
measurement and shall not cover up or place beyond the reach
of measurement and work without the consent in writing of the
Executive Engineer or his subordinate-in-charge of the work
and if any work shall be covered up or placed beyond the reach
of measurement such notice having been given or consent
obtained the same shall be uncovered at the contractor’s
expense, or in default thereof no payment or allowance shall
be made for such work or the materials with which the same is
executed.

Contractor Witness Executive Engineer


- 37 -

Clause-19:If the contractor or his work people or servants Contractor liable for
damage done and for
shall break deface, injure or destroy any part of a building, if imperfections to
they may be working on any building, road fence enclosure or months after
grass land cultivated ground contiguous to the premises on certificate
which the work or any part of it is being executed or if any
damage shall happen, to the work while in progress, from any
cause whatever or any imperfections become apparent in it
within one year after a final certificate of its completion have
been given by the Executive Engineer as aforesaid, the
contractor shall make the same good at his own expense, or in
default, the Executive Engineer may cause the same to be
made good by other workman and deduct expense (of which
the certificate of the Executive Engineer shall be final) from
any sums that may be then, or at any time thereafter may
become due to contractor, or from his security deposit. The
warranty liability period of the contractor shall be one year from the
date of completion of work.

Clause-20 : The contractor shall supply at his own cost all


materials except such special materials if as may in accordance Contractor to
with the contract be supplied from the Executive Engineer supply plant,
ladder, scaffolding
stores, plants tools, appliance, implements, ladders cordage etc.
tackle scaffolding and temporary work requisites of proper for
the proper execution of the work, whether original, altered or
substituted and whether included in the specification or other And be liable for
documents forming part of the contract or referred to in these damage, arising
conditions or not, or which may be necessary for the purpose from non-provision
of satisfying or complying with the requirements of the of light, fencing etc.
Executive Engineer as to any matter to which under these
conditions he is entitled to be satisfied or which he is entitled
to require with carriage thereof to and from the work. The
contractor shall also supply without charge the requisite
number of the persons with the means and materials necessary
for the purpose of setting out works and counting weighing
and assisting in the measurement or examination at any time
and from time to time of the work of materials failing his so
doing the same may be provided by Executive Engineer at the
expense of the contractor shall also provided all necessary
fencing and lights required to protect the public from accidents
and shall be bound to bear expenses of difference of every suit
action or other proceedings at law that may be brought by any
person for injury sustained owing to neglect of the above
precautions and to pay damages and cost which may be
awarded in any such suit action or proceedings to any such
persons or which may with consent of the contractor be paid to
compromise any claim by any such person.
Clause–21: No female labourer shall be employed within the Female labour
limits of a cantonment.

Contractor Witness Executive Engineer


- 38 -

Clause–22: No labourer below the age 18 years shall be


employed on the work.

Clause–23: The contractor will have to pay not less than the
minimum wages fixed by the appropriate Govt. as per
provision of the act to the labour.
Clause–24: No work shall be done on Sunday without the Work on Sundays
sanction in writing of the Executive Engineer.

Clause-25: In every case in which by virtue of the provisions Contractor liable for
payment of
of section 12 sub-section (1) of workmen’s compensation Act, compensation
1923, Board is obliged to pay compensation to a workman to injured workman
employed by the contractor in execution of work Board will or in case of death to
recover from the contractor the amount of compensation so his relation.
paid and without prejudice to right to Board under section 12,
sub-section (2) of the said Act. Board shall be at liberty to
recover such amount or any part thereof by deduction it from
the security deposit or from any sum due by Board to the
contractors whether under their contract or otherwise. Board
shall not be bound to contest any claim made against it under
Section 12, sub-section (i) of the said act except on the written
request of the contract and upon his giving to Board full
security for all costs for which Board might become liable in
consequence of contesting claim.

Clause-26: The contract shall not be assigned or sublet Work not be sublet.
without the written approval of the Executive Engineer and if
the contractor shall assign or sublet his contract or attempt so Contract may be
rescinded &
to do or become insolvent or commence any insolvency
security deposit
proceedings or make any composition with his creditors or forfeited for
attempt so to do or if any bribe, gratuity, gift, loan, perquisite, subletting bribing
reward or advantage pecuniary or otherwise shall either or if contractor
directly or indirectly be given promised or offered by the become insolvent.
contractor or any of his servants or agents to any public officer
or person in the employ of the Board in any way relating to his
office or employment if any such officer or person shall
become in any way directly or indirectly interested in the
contract, the Executive Engineer may thereupon by notice in
writing rescind the contract and the security deposit of the
contractor shall thereupon stand forfeited and be absolutely at
the disposal of the Board and same consequence shall ensure
as the contract had been rescinded under clause-3 hereof and in
addition the contractor shall not be entitled to recover or be
paid for any work, therefore actually performed under the
contract.

Clause-27: All sums payable by way of compensation under Sum payable by way of
compensation to be
any of these conditions shall be considered as reasonable considered as

Contractor Witness Executive Engineer


- 39 -

compensation to be applied to the use of Board without reasonable


reference to the actual loss or damages sustained and whether
or not any damages shall have been sustained.

Clause-28: The contractor shall be debarred from claiming Compensation without


reference to actual loss.
any amount of compensation/damages on account of reduced
profitability.

Clause-29: Any excess payment made to the contractor Deductions of amount


due to Government on
inadvertently or otherwise under this contract or any account any account
whatever and any other sum found to be due to Board by the whatsoever to be
contractor in respect of his contract or any other contract or permissible from sums
work order or on any account whatever, may be deducted from payable to a contractor.
any sum whatsoever payable by Board to the contractor either
in respect of this contract or any order or contract or any other
account by any other department of the
Government/Board/Corporations.

Clause-30: In case of any firm/contractor make changes in Change in


the constitution of the firm/partnership then the same shall be constitution of firm
forthwith notified by the firm/contractor to the Executive
Engineer for his information.

Clause-31: All work to be executed under the contract shall Works to be under
be executed under the directions of and subject to the approval direction of
in all respect of the Executive Engineer or the Board for the Executive Engineer
time being who shall be entitled to direct at what point or
points and in what manner they are to be commenced and from
time to time carried on.

Clause-32: No claim for payment of an extraordinary nature, Claim for payments


of extraordinary
such as claims for a bonus for an extra labour employed in nature to be referred
completing the work before the expiry of the contractual to Board for decision.
period at the request of the Executive Engineer or claim for
compensation where work has been temporarily brought to
standstill though no fault of the contractor shall be allowed
unless and to the extent that the same shall have been
expressly sanctioned by the Board.
Clause-33: If any dispute or difference of any kind Arbitration clause
whatsoever shall arise between the Housing Board Haryana or
its authorized agent and the contract in connection with or
arising out of the contract or the execution of the work that is
(i) whether before its commencement or during the progress of
the work or after its completion, (ii) and whether before or
after the termination abandonment or breach of the contract it
shall in the first instance be referred to for being settled by the
Executive Engineer of the work at the time and he shall within
a period of sixty days after being requested in writing by the

Contractor Witness Executive Engineer


- 40 -

contractor to do so convey his decision to the contractor and


subject to arbitration as hereinafter provided such decision in
respect of every matter so referred shall be final and binding
upon the contractor. In case the work is already in progress the
contractor will proceed with the execution the work on receipt
of the decision by the Executive Engineer as aforesaid with all
due diligence whether he or the Housing Board Haryana/its
authorized agent requires arbitration as hereinafter provided or
not. If the Executive Engineer of the work has conveyed his
decision to the contractor and no claim to arbitration has been
filed with him by the contractor within a period of sixty days
from the receipt of letter communicating the decision, the said
decision shall be final and binding upon the contractor and will
not be a subject matter or arbitration at all. If the Executive
Engineer of the work fails to convey his decision within a
period of sixty days after being requested as aforesaid the
contractor may within further sixty days of the expiry of first
sixty days from the date on which request has been made to
the Executive Engineer request the Chief Administrator HBH
that the matter in dispute be referred to arbitration as
hereinafter provided.
(2) All disputes or differences in respect of which the
decision is not final and conclusive shall at the request
in writing of either party, made in a communication
sent through Registered A.D. post be referred to the
sole Arbitrator to be nominated by the Chief
Administrator from amongst officers who will be
either.
i) A serving Superintending Engineer or Chief Engineer of
the Housing Board, or Haryana PWD B&R Branch
Or
ii) A retired Superintending Engineer, Chief Engineer or an
Engineer-in-Chief of the Housing Board Haryana PWD
B&R or any the person to be selected out of panel of
Arbitrator approved by the Chief Administrator.

iii) It will be no objection to any such as appointment that


the Arbitrator so appointed is a Housing Board
Employee / Government servant or that he had to deal
with the matters to which the contract relates and that
in the course of his duties as a Housing Board
Employee/Government servant he had expressed his
views on all or any of the matters in dispute. The
Arbitrator to whom the matter is originally referred
being transferred or vacating his office his successor in
office as such shall be entitled to proceed with the
reference from the stage at which it was left by his
predecessor.

In case the Arbitrator nominated by the Chief

Contractor Witness Executive Engineer


- 41 -

Administrator Housing Board Haryana is unable or


unwilling to act as such for any reason whatsoever, the
Chief Administrator shall be competent to appoint and
nominate any other Superintending Engineer or Chief
Engineer as the case may be as Arbitrator in his place
and the Arbitrator so appointed shall be entitled to
proceed with the reference.

(3) It is also a term of this arbitration agreement that no


person other than a person appointed by the Chief
Administrator Housing Board Haryana Panchkula shall
act as Arbitrator and if for any reason that is not
possible, the matter shall not be referred to arbitration
at all. In all cases the Arbitrator shall give reasons for
his award in respect of each claim and counter claim
separately.

(4) The Arbitrator shall award separately giving his award


against each
claim and dispute raised by either party including any
counter- claims individually and that any lump-sum
award shall not be legally enforceable.

(5) The following matter shall not lie within the purview of
arbitration.

(a) Any dispute relating to the levy of compensation as


liquidated damages which has already been referred to
the Superintending Engineer/Chief Engineer and is
being heard or has been finally decided by the
Superintending Engineer/Chief Engineer of the work.

(b) Any dispute in respect of substituted, altered,


additional work/omitted work/defective work referred
by the contractor for the decision of the Chief
Engineer, HBH or if it is being heard or has already
been decided/heard by the said Chief Engineer. Any
dispute regarding the scope of the work or its execution
or suspension or abandonment that has been referred by
the contractor for the decision of the Housing
Board Haryana has been so decided finally by the
Housing Board Haryana.

(6) The independent claims of the party other than the one
getting the Arbitrator appointed, and the counter-claims
of any party will be entertained by the Arbitrator not
withstanding that the Arbitrator had been appointed at
the instance of the other party.
(7) It is also a term of this arbitration agreement that where
the party invoking arbitration is the contractor, no

Contractor Witness Executive Engineer


- 42 -

reference for Arbitrator shall be maintainable unless the


contractor furnishes to the satisfaction of the Executive
Engineer of the work, a security deposit of a sum
determined according to details given below and the
sum so deposited shall, on the termination of the
arbitration proceedings, be adjusted against the cost, if
any, awarded by the Arbitrator against the claimant
party and the balance remaining after such adjustment,
in the absence of any such cost being awarded the whole
of the sum will be refunded to him within one month
from the date of the award :

Sr. Amount Claims Rate of Security


No. Deposit
i) For Claims below Rs. 2% of amount
10,000/- Claimed

ii) For claims of Rs.10,000/-& 5% of amount


above but below Rs. claimed
1,00,000/-
iii) For claims of Rs. 1,00,000/- 7.5% of amount
and above claimed

The stamp-fee due on the award shall be payable by the


party as decided by the Arbitrator and in the event of
such party’s default the stamp-fee shall be recoverable
from any other sum due to such party under this or any
other contract.

(8) The venue of arbitration shall be such place or places as


may be fixed by the arbitrator in his sole discretion.
The work under the contract shall continue during the
arbitration proceedings.
(9) Neither party shall be entitled to bring a claim for
arbitration if the appointment of such Arbitrator has
not been applied within 6 months ;
OR
(a) from the date of completion of the work as certified
by Executive Engineer. OR
(b) from the date of abandonment of the work.
OR
(c) of its non commencement within 6 months from the
date of abandonment, Or written orders to
commence the work as applicable.
Or
(d) from the completion of the work through any
alternative agency or means after withdrawal of the
work from the contractor in whole or in part and /or

Contractor Witness Executive Engineer


- 43 -

its decision. Or
(e) of receiving the intimation from the Executive
Engineer of the work that final payment due to or
recovery from the contractor had been determined
which he may acknowledge and / or receive.
Which of (a) to (e) above is the latest?
If the matter is not referred to arbitration within the
period prescribed above, all the rights and claims of
any part under the contract shall be deemed to have
been forfeited and absolutely barred by time even for
civil litigation notwithstanding.

10) It is also a term of this arbitration agreement that no


question relating to this contract shall be brought
before any civil court first involving and completing
the arbitration proceedings as above, if the scope of the
arbitration specified herein covers issues that can be
brought before the arbitrator, i.e., any matter that can
be referred to arbitration shall not be brought before a
Civil Court. The pendency of arbitration proceedings
shall not disentitle the Government to terminate the
contract and make alternative arrangement for the
completion of the work.

11) The Arbitrator shall be deemed to have entered on the


reference on the day he issue notices to the parties
fixing the first date of hearing. The Arbitrator may
from time to time with the consent of the parties
enlarge the initial time for making and publishing the
award.

12) It is also a term of this arbitration agreement that


subject to the stipulation herein mentioned the
arbitration proceedings should be conducted in
accordance with the provisions of the Arbitration Act,
1996 or any other law in force for the time being.

(13) In case of dispute, if any, of the party intends to go for in


arbitration the expenses concerning to the arbitration
proceedings such as fee of the Arbitrator, if necessary
stamp paper for award and all the expenses concerning
to the traveling allowances of witnesses, stationery or
any other charges concerning to the arbitration case
shall be borne by the party going in for the arbitration.
The arbitration fee and other charges payable to
arbitrator shall be as given below:

For the works upto any amount, the fee of sole


Arbitrator is payable Rs.10,000/- per hearing subject to

Contractor Witness Executive Engineer


- 44 -

Rs.60,000/- maximum for whole proceedings.


Note: In case Arbitrator is appointed through Hon’ble
High Court or any other court than the fee will be paid
to the Arbitrator as per directions/norms of the court.

13) If the matter is not referred to Arbitrator within the


specified period, all the rights/claims under the contract
shall be deemed to have been forfeited and absolutely
time barred. The Arbitrator shall give a speaking
award otherwise the award shall be null & void and
will not be binding on the parties.
Clause-34: No alteration in the contract rate shall be Fluctuation in
admissible in consequence of fluctuation in railway freight Railway freight
when such railway freight is on account of material which is
required by a contractor in the manufacture of an article to be
supplied under this contract, e.g., fluctuation of railway freight
on coal required for burning bricks will not be taken into
consideration, or for an article which forms parts of a finished
work for purposes of this clause. Similarly no alteration in
rates will be allowed when a manufactured article is
transferred by rail from place A to B to form part of a finished
work.

Clause-35 : When the estimate on which a tender is made


includes lump-sum in respect of part of the work, the Lump sum
contractor shall be entitled to payment in respect of the items Estimate
of work involved or the part of the work in question at the
same rate as are payable under this contract for such items, or
if the part of the work in question is not in the opinion of the
Executive Engineer capable of measurement, the Executive
Engineer may at his discretion pay the lump-sum amount
entered in the estimate and the certificate in writing of the
Executive Engineer shall be final and conclusive against the
contractor with regard to any sum or sums payable to him
under the provisions of this clause.

Clause-36: In the case of any class of work for which there is Action where no
no such specification as is mentioned in (Rule-1), such work specification
shall be carried out in accordance with the Haryana PWD
Specification-1990 as and in the event of there being no
distinct specification then in such case the work shall be
carried out in all respect in accordance with the instructions
and requirements of the Executive Engineer.
Clause-37 : The expression “works” or “work” where used in Definition on
these conditions shall unless there be something either in the work
subject or context repugnant to such construction be
constructed and taken to mean the works by or by virtue of the
contract contracted to be executed whether temporary or

Contractor Witness Executive Engineer


- 45 -

permanent and whether original altered substitute or


additional.

Clause-38: The contractor shall be responsible for Housing


Sanitation and medical treatment of labour employed on the
work and shall abide by all the rules and regulations on the
subject.

Clause-39: The percentage referred to at page 6 of the tender


will be calculated on the gross amount value of finished work
including cost of materials whether purchased from the Board
or direct of (1) the item of work to which the rates in the tender
apply and also (2) the apply items of work for which the rates
exist in the schedule of rates.

Clause-40: The terms and conditions of the agreement have


been explained to me/us and I/we clearly understand them.

Clause-41: Unless otherwise provided for in the contract the


term “Executive Engineer” referred to in this tender and
contract for the means “Executive Engineer, Housing Board
Haryana Faridabad.

Contractor Witness Executive Engineer


- 46 -

LIST OF APPROVED MAKE OF VARIOUS ITEMS

S.No Items Make

1. ISI marked PVC pipe & special for Rain Prince, Finolex, Supreme & Atul
water
2. ISI marked UPVC Sanitary Pipe, SWR Prince, Finolex, Supreme, Atul, APL
grade & special Appolo, AKG
3. G.I. Pipe (ISI marked) Tata, Jindal (Hissar) Parkash Surya
4. G.I. Pipe fittings / special Unik, U,SVW, NVR, K.S
5. C.P. bath fittings Essco, ,Nova, Cera,Excel, K.S, Jalangi,
Jainko, coronet
6. ISI marked Chinaware, Wash basin & W.C. Perryware, Hindware, Cera, Glint
7. Seat Cover, ISI marked or of the same brand Comander, Cera, Duralite
of which W.C seat will be provided.
8. PVC Cistern 7.5 liter capacity (two lever Perryware, Hindware, Cera
cistern )
9. ISI marked Stainless Steel Sink with CP Nirali, Neelkanth, Jayna, Lotus,
waste Diamond, Bluestar, K.S
10. Aluminum Door / Window Fittings, ISI Nulite, Crown, Classic
marked
11. Aluminum section for door and window Jindal, Hindalco
frames and shutter
12. Hard wood for chowkhats Sal
Hard wood for shutter Red merrendy
st
13 Paint 1 Quality Nerolac, Berger, Asian, Dulex
Professional
14 Acrylic paint Asian, Berger, Nerolac, Dulex
Professional
15 Washable Oil Bound Distemper Berger , Asian, Nerolac
16 Pressed Steel Chowkhat All BIS approved
17 ISI marked Flush Door Shutter Minimax, Haryana Ply Wood, Swastic
Ply Board Ltd, Jaipur.
18 LLDPE Storage Tank ISI marked Atul, Sintex, Diplast,SPL
19 Ceramics glazed floor & wall tiles Kajaria, Somany, orient.
20 Vitrified tile (premium quality ) Kajaria, Somany, orient.
21 Iron hinges Maruti, Ashish, Garg
22 Glass Saint gobain, modiguard.
23 Cast Spun Iron Pipe & Fittings BIC (Bangel Iron Corporation)
Cement & Steel

Cement (OPC) confirming to relevant All agencies which approved by the


specification/IS code Director, Supplies & Disposals,
Haryana Chandigarh.
Steel (FE-500,TMT steel bars) SAIL,RINL,TATA,JINDALPANTHAR
ELECTRO STEEL LTD.

Contractor Witness Executive Engineer


- 47 -

ELECTRICAL ITEMS

1. ISI marked Rigid PVC pipe & Accessories Diplast, Precision, Polycab, Polypak.
(Medium quality) AKG Ravindra Hissar
2. ISI marked Cable with copper conductor Polycab, Havells, Delton, Bonton
with fire retarded insulation
3. ISI marked Piano type switches Anchor, SSK, Havells
4. ISI marked Batten holder, Ceiling Rose, Anchor, SSK, Havells
Bell
5. ISI marked ACB, MCBs & MCCB, Havells, North West, Indoasian,
enclosures & ELCBs, VCB, Relay etc Adhunik (Except MCCB)
6. PVC junction box ISI marked
7. Bakelite Sheets ISI marked V-Hylam, Super Hylam,
8. G I pipe B class for earthing Tata, Jindal (Hissar), Parkash Surya
9. T.V and telephone cable Delton, Phinolex, Havells
10. T-5,2800/14-W Flourscent Crompton Greaves, Philips/ Havells/
Bajaj
11. CFL Havells, Philips, Crompton Wipro
12. Street Light LED fitting Havells,Bajaj,Philips,Wipro, Crompton
13. Choke,Halogen,Lamp Havells,Bajaj,Philips,Wipro, Crompton

NOTE
 In respect of materials for which approved makes are not specified above, the same shall be
decided by the Chief Engineer, HBH and shall be as per sample got approved from Chief
Engineer before procurement. The Contractor shall submit samples of all such materials 3
month before the date of start of such work for approval from the Chief Engineer, HBH.

 The Contractor shall produce samples before procurement of the material for approval for all
materials required for works. Samples can be submitted for any of the above makes and they
shall confirm to specifications. Samples as approved by the Chief Engineer, HBH shall only be
used on the works and the decision of the Chief Engineer, HBH regarding make of material
shall be final. Only ISI marked will be allowed to use on works.

 UPVC specials will be used either of ISI marked or of the same brand of which UPVC pipe
will be provided.

 In case material bearing BIS/ISI certification mark are not available, the quality of material
shall be judged by standard laid down in the relevant BIS/ISI specification for which
make/brand shall be got approved from Chief Engineer, Housing Board Haryana.

Contractor Witness Executive Engineer


- 48 -

TECHNICAL CONDITIONS, IMPORTANT SPECIFICATIONS AND MODE OF


MEASUREMENTS FOR ELECTRICAL WORKS AND CONDUIT SYSTEM OF WIRING
(FOR BOTH PVC AND STEEL CONDUIT)
*******
1. Before energizing the system, following tests should be given by the contractor, so as to find
out that installation conforms to relevant rules/regulations.
Regulations:
(a)Earth Resistance Tests
(b) Earth Continuity Tests
(c) Insulation Tests
(d) Polarity Tests

2. The PVC Copper wire unless otherwise specified conforming to present enforced ISI
specifications shall only be used at site of work from the list of approved material appended
with this DNIT.

3. Looping in system of wiring shall be adopted for all sub-circuit wiring.

4. In the item of bell point, the contractor will install bell push , the cost of which will be
adjusted against the ceiling rose cost included in the item and nothing extra will be payable
on the this account and no compensation will be allowed to contractor.

5. All PVC conduit pipes should be embedded within slab or in walls after making chases and
at no point should be provided in the floor.

6. Sizes of M.S. boxes made from 18 gauge MS sheet as per relevant IS standard shall only be
used

7. MCB’s & enclosure etc will be installed of one make only and the thickness of CRCA
sheets should be 1.20 mm (18 gauge) for SPN box and 1.60 mm (16 gauge) for TPN boxes
as permitted by DGS&D.

8 G.I. pipes for earthing for protection of earth wire shall be medium
(B Class) quality.

9. The rigid PVC conduit pipes (Medium) to be used on the work should bear the
manufacturer’s Trade Mark and shall be ISI marked & should be out of the make indicated
in the list of material appended with DNIT. All specials should bear the trade mark of the
same manufacturer.

10. The contractor will have to employ licensed supervisor for the execution of Electrical
installation works. The contractor executing the electrical work under this contract will
possess ‘A’ class license from Chief Electrical Inspector to Govt. of Haryana. However, the
contractor can sublet the internal electrical work to a person/agency possessing ‘A’ class
license from the Chief Electrical Inspector to Govt. of Haryana. The contractor is required
to submit the test report in respect of each house/dwelling unit for its submission to electric
supply company.

11 All chases and holes made for wiring or for other purposes shall be refilled properly and
neatly for bringing to original finish to the satisfaction of Executive Engineer. If the building
construction work is in progress, the electrical work shall proceed along with for the purpose
of cutting chases and holes.

Contractor Witness Executive Engineer


- 49 -

12. The consideration of various sizes of cable and conduit pipes shall be allowed as tabulated
below:
Sr. Size of cable Size of conduit pipe/ No of wires allowed
No. 20 mm 25mm 32 mm
1 1.50 mm sqmm 5 10 14
2 4 mm sqmm 3 6 12
3 6 mm sqmm 2 5 8
4 10 mm sqmm - 4 7

13. The arrangements for the electric supply required for construction purpose shall be made by
the contractor at his own cost.
14. Material out of the list attached with D.N.I.T. shall only be used at site after getting the same
approved from Chief Engineer.
15. Contractor shall be responsible for damage/pilferage of electrical fittings till the houses are
handed over.
16. All the round junction box and fan box covers shall be of 3mm thick bakelite sheet and
nothing extra shall be paid on this account. The colour of these Bakelite sheet cover shall be
as approved by the Engineer -in-Charge.
17. The work will be executed strictly as per PWD specifications unless and otherwise specified.
18. Definition and measurement of points and wiring of DNIT no 1 strictly followed as per
Haryana PWD Specifications.
19. The size of bakalite sheet should be 20mm more than size of MS boxes ie for MS box of size
75 mm x 75 mm size of Bakelite sheet shall be 95 mm x 95 mm and so on
20. Multi Strand Copper Conductor cable shall be allowed.
21. 3mm thick Bakelite sheet of IS marked of approved will be used for item No 31.38 ie wiring in
existing conduit pipe installed of 5 mm thick Bakelite sheet without any deduction.
22. Separate conduit for power plug with independent circuit shall be made.
23. Contractor must employ following staff while carrying out the Electrical works:
Sr. Agreement Key personnel required by the Recovery rate in
No. amount contractor case of non-
employment
1 Up to One Electrical Engineer with Diploma Rs.30000/- P.M
Rs.1.00 in electrical Engineering with 5 years
crore experience in buildings
2 Rs. 1.00 One Electrical Engineer with Degree in Rs.50000/- P.M
crore to Electrical Engineering with 2 years
Rs.5.00 experience or One electrical Engineer
crore with Diploma in electrical Engineering
with 5 years experience in buildings
3 Above Rs. One Electrical Engineer with Degree in Rs.75000/- P.M
5.00 crore Electrical Engineering with 5 years
experience

In case the contractor fails to employ the key personnel required to be employed as above at
site, the department will employ the personnel and the recoveries will be made as above from the
bills of the contractor along with 14% departmental charges. The personnel so employed shall be
considered as employees of the contractor and all responsibilities of them shall lie with him only.

TECHNICAL CONDITIONS AND IMPORTANT SPECIFICATIONS

Contractor Witness Executive Engineer


- 50 -

1 Principles of design of concrete mix.

i) The design of concrete mix shall be based on latest PWD specifications/HSR-


1988.

ii) The concrete mix shall be designed for the specified target mean compressive
strength in order to ensure that the work-tests results do not fall below the
acceptance criteria specified for the concrete mix.

iii) Grades of concrete mix stipulated design criteria.

iv) The reinforced cement concrete work shall be executed using concrete mix of
grade as specified in the nomenclature of the item of work. The various grades
of concrete shall be designed for the strength criteria and other parameters.

v) In the designation of a grade of concrete mix, the letter ‘M’ stands for mix and
the number represents the characteristic compressive strength (fck) of 15
centimeter cube at 28 days expressed in Newton per square millimeter, i.e.,
N/mm2.

vi) A grade of concrete mix shall be designed and tested for a specified target mean
compressive strength.

vii) The contractor shall exercise very good quality control over site conditions for
production of controlled concrete by employing automatic weigh batching of all
materials grading of aggregate, determination of moisture contents and control of
water-cement ratio frequent supervision and regular workability, strength tests
and maintaining adequate field laboratory facilities to maintain the specified
quality of concrete consistently.

2 Materials
Cement aggregate and water shall in general conform to provision of PWD
specifications 1990 and IS 456 -2003 read with up to date correction slips

3 Mix Design of concrete


i) The contractor shall engage one of the following approved laboratories/test
houses for designing the concrete mix in accordance with relevant I S codes and
to conduct laboratory tests to ensure the target strength and workability criteria
for a given grade of concrete
(a) I.I.T., Delhi.
(b) National Council for Cement and Building Materials, Ballabhgarh.
(c) CRRI, Delhi
(d) NIT Kurukeshetra,
(e) PEC Chandigarh.
If all the above laboratories express in writing their inability to carry out the
designing and testing of concrete mixes by a specified date, the contractor may
be allowed to engage any other Govt approved laboratory with prior approval of
the Engineer-in-Charge.

ii) The source and quality of all ingredients of a concrete mix shall be got approved
from the Engineer-in-Charge before designing the mixes and their testing and the
same shall be maintained during the execution of the work as well.

iii) Any change in source or characteristics of any ingredient used in the

Contractor Witness Executive Engineer


- 51 -

concrete mix during the work execution shall require revised mix design
and laboratory testing as per direction of the Engineer-in-Charge and no
further concrete work shall be proceeded without approval of the revised
design mix.

iv) All cost and charges of designing the concrete mix and its testing by
approved laboratories including the redesigning of the concrete mix,
whenever required and directed by the Engineer-in-Charge shall be borne
by the contractor and nothing extra shall be payable over the quoted rates.

4 Production of controlled concrete

Mixing of Concrete

i) Automatic weigh batching plant conforming to relevant IS code and of


required capacity shall be used for production of controlled concrete.

ii) Automatic weigh batcher shall be charged by devices which, when


activated by a single starter switch, will automatically start weighing
operation of each material and stop automatically and interlocked when
the designated weight of each material has been reached

iii) The batching system shall have rated capacity (in terms of concrete in a
single batch) to match the maximum rated size of the mixer that could be
adopted for use with the plant.

iv) The mixers shall be free fall tilting type conforming to latest IS code.

v) All measuring equipment shall be maintained in a clean and serviceable


condition and their accuracy shall be checked at least once a month.

vi) Only single sized good quality stone aggregate shall be brought to site of
work from the approved source. The grading of the stone aggregate shall
be controlled by blending the aggregate of different sizes in the required
proportions at site of work.
vii) The aggregate of different sizes shall be stockpiled separately preferably a
day before use.
viii) The grading of coarse and fine aggregates shall be checked as frequently
as possible and as directed by the Engineer-in-Charge to ensure that the
specified grading and quality of aggregate is maintained.

ix) It is important to maintain the water cement ratio constant at its specified
or approved value.
x) All other operations involved in concrete work like laying, placing,
compaction and curing etc. shall be done as per PWD specifications 1990
and I.S. 456-2003 with up to date correction slips.

5 Sampling and strength of work test of concrete

Sampling

Contractor Witness Executive Engineer


- 52 -

i) Samples from fresh concrete shall be taken and the test cubes shall be
made cured and tested in accordance with relevant IS code.

ii) Each test sample shall comprise of six test cubes (specimen), three of
which shall be tested at 7 days and remaining of tests at 28 days

iii) A random sampling procedure shall be adopted to ensure that the sampling
is spread over the entire period of concreting and cover all mixing units.

iv) At least one test sample shall be taken on the day of completing

v) Each grade of concrete shall require different testing

Test strength of a sample

vi) The test strength of the sample shall be taken as the average of the strength
of its three specimens. The individual variation between the three
specimens should not be more than +15 percent of the average test results
of the sample.

vii) If individual variation in strength of three specimens is more than +15


percent of average, the test results of the sample shall be invalid.

viii) 50% of the total tests shall be done at the field laboratory established at the
site of work and the remaining 50% of total test shall be got done from the
laboratory as approved by Engineer-in-charge.

6 Standard of acceptance of concrete work

i) Out of the six specimen cubes of a test sample three cubes shall be tested
at 7 days and the remaining three cubes at 28 days.

ii) The test results at 7 days are only intended to indicate the likely strength at
28 days and to decide the continuation of further concrete work.

In case, the 7 days test results do not satisfy the specified strength criteria,
all further work structurally inter linked with the concrete work
represented by the sample, shall be stopped and the test results of the
remaining three cubes at 28 days shall be awaited before proceeding
further with the work or the work shall be carried out as per the written
directions of the Engineer-in-Charge.
The contractor shall have to setup a fully equipped field laboratory to
conduct field tests for conducting tests in addition to the tests which shall
be conducted from outside laboratory; for which nothing extra shall be
payable.

Test results at 28 days

Contractor Witness Executive Engineer


- 53 -

iii) The average compressive strength of the sample at 28 days shall alone
form the basis of acceptance of concrete work and the payment under the
contract subject to the specified criteria for acceptance.

iv) The concrete work of each grade and a lot shall be assessed separately.

v) The concrete shall be assessed daily for strict compliance of the specified
acceptance criteria.

vi) The concrete shall be deemed to comply with the strength requirements

vii) The concrete work shall liable to be rejected if it is porous or honey


combed; its planning has been interrupted without providing a proper
construction joint, the reinforcements have been displaced or it does not
satisfy the specified dimensional tolerance as per relevant IS code.[

7 Measurements

i) The measurements of work and the allowable tolerances shall be governed


by provisions of PWD specifications 1990 read with up to date correction
slips.

ii) The theoretical consumption of cement in design mix concrete shall be


worked out on the basis of proportions approved.
8 Rate
i) The rate shall include cost of all materials used and labour involved in all
operations described above including the cost of designing and testing of
concrete mix in the approved laboratory, but excluding the cost of
centering and shuttering and reinforcement.
ii) The average compressive strength of each test sample shall govern the rate
payable for the concrete represented by the sample.

iii) The concrete which does not meet the strength requirement as specified,
but has strength greater than that specified nothing extra shall be paid for
that.

iv) The payment for different grades of concrete shall be made strictly as
indicated in the structural drawings for the work. No extra payment for
richer mix projecting into any other member during concreting of
junctions of columns beams and slabs etc. shall be made except otherwise
admissible as per structural drawings.

Contractor Witness Executive Engineer


- 54 -

ADDITIONAL CONDITIONS

1) The work will be executed strictly in accordance with the Haryana PWD
Specification 1990 (as applicable to Haryana) corrected up to date at the time of
tenders, unless specified to contrary.
2) The contractor shall not be entitled to any payments on account of work done till he
signs the agreement and the same is accepted by the competent authority.

3) (a) Royalty, Sales Tax, service tax, Excise Duty, Octroi or any other tax or levy shall
be paid by the contractor direct to the respective department in accordance with their
rules and regulations enforce from time to time, without any liability to the Housing
Board Haryana.
(b) The contractor will quote his rates without GST. GST will be paid by Housing
Board Haryana on actual basis as applicable w.e.f 1.7.2017 And as amended from
time to time by the Government.

4) Technical Staff at the site of work


The contractor shall be required to keep at the site of work following technical staff
when work costing up to Rs. 1.00 Crore and above as under:-

Sr. Agreement Key personnel required by the contractor Recovery rate in case
No. amount of non- employment
1 Up toOne Civil Engineer with Diploma in Civil Rs. 30000/- P.M
Rs.1.00 Engineering with 5 years experience in
crore buildings
2 Rs. 1.00 One Civil Engineer with Degree in Civil Rs. 50000/- P.M
crore to Engineering with 2 years experience or
Rs.5.00 One Civil Engineer with Diploma in Civil
crore Engineering with 5 years experience in
building construction
3 Above Rs. One Civil Engineer with Degree in Civil Rs. 75000/- P.M for
5.00 crore Engineering with 5 years experience in Civil Engineer and
building constriction and one quality Rs. 25000/- per
control Engineer with 2 year experience month for Quality
in quality control. Control Engineer.

In case the contractor fails to employ the key personnel required to be employed as
above at site, the department will employ the personnel and the recoveries will be made as
above from the bills of the contractor along with 14% departmental charges. The personnel
so employed shall be considered as employees of the contractor and all responsibilities of
them shall lie with him only.

Contractor Witness Executive Engineer


- 55 -

5) Actual quantities of completed and accepted work shall only be paid.

6) In case of emergency, the contractor shall be required to pay his labour every day
and if this is not done, the Board will make the requisite payment and recover the
same from the contractor’s dues.

7) No claim shall be entertained on account of increase in price of material and wages


of labour due to any cause what so ever.

8) The Executive Engineer reserves the right to take away any item of work or any part
thereof at any time during the currency of work and re-allot to any other agency with
due notice to the contractor without liability of any kind or payment of any
compensation.
9) 10% security subject to a maximum of five percent of agreement amount will be
deducted from the running bill after adjusting 2% earnest money.

10) 50% security shall be released after 60 days, but before 75 days of the payment of
the final bill. Balance 50% security shall be released after 300 days, but before 330
days of the payment of the final bill.

11) DELETED

12) DELETED

14) In case samples have been drawn by the State Vigilance Bureau or by any other authority
but the report and test result of samples have not been received, the payment of running
bills; final bill & security will be released after the contractor furnished on undertaking in
shape of indemnity bond on the following lines :-
15)
“I/We__________son of Shri ________Resident of ____________ do hereby
undertake to bear the recoveries if any, levied by the Board on account of any
adverse results for the samples taken by the State Vigilance Bureau or by any other
authority from the work of _______________ . I further undertake that I will
reconstruct the structure if declared unsafe due to result of the samples. I also
undertake that in case of any item of work contains defect of nature which do not
endanger the structural stability of the work, it may be accepted and the payment
thereof shall be made to us at the reduced rates decided by the Chief Engineer which
will be final and binding on us as per additional condition No.17 of the contract
agreement. I have no objection if all the recoveries are made from any other contract
executed with the Board as well as with other Organization.”
14) The contractor will be responsible for any and all losses of material damages done to
unfinished works as result of floods and any other act of God. The Housing Board
Haryana will not be responsible for any compensation as a result of such

Contractor Witness Executive Engineer


- 56 -

damages or loss to the contractor and the contractor shall be liable to set right such
damages at his own cost to the satisfaction of the Executive Engineer.

15) Nothing extra will be paid to the contractor for any lead or lift unless otherwise
specified for any material required directly or indirectly under the contract.
16) Nothing extra will be paid to the contractor for diverting water in the channels or
streams if it becomes necessary for the execution and completion of the work.
17) Amount of the work can be increased or decreased due to any item omitted and
substituted in accordance with the requirement of the Board and no claim on this
account shall be entertained.

18) The contractor shall be responsible for providing to the entire satisfaction of the
Executive Engineer at his own expenses for the following amenities for all the
labour employed by him:-

i) Suitable temporary hutting accommodation.


ii) Trench latrines, bathing enclosures, platforms separately for men and women and
their regular cleanliness.
iii) Clean drinking water.
In event of his failure, to be provided by the Board and cost thereof shall be
recovered from the contractor. Any dispute regarding above points shall be settled
by the Executive Engineer and his decision shall be final.
19) No claim of any kind whatsoever shall be entertained for any or all the losses or
damages to the contractor, due to the completion of the work getting delayed or
failure on the part of the Executive Engineer to supply drawings, materials, tools and
plant required to be supplied by him under the terms and conditions of the contract.
20) For safe custody of materials and watch and ward thereof and proper double lock
arrangement, the contractor shall be bound to follow the instruction of the Executive
Engineer.
21) In case the work of any item of work contains defects of a nature which do not
endanger the structural stability of the work, it may be accepted and the payment
thereof shall be made to the contractor at reduced rates. The decision of the Chief
Engineer in this regard shall be final and binding.
22) The contractor executing the Public Health works should either posses a license or
engage a licensed plumber for supervision and execution of these works. The
license will be issued by the authority competent to issue such license.
23) The Executive Engineer shall have the right to get any item of work shown in the
contract schedule of rates executed under this contract to any limit when required for
the purpose of completion of the work on the same rates and terms as provided under
this contract.
24) All clause and notes given in the Haryana PWD Schedule of rates 1988 with up to
date correction slips will be applicable to the date of tender for all items in the
DNIT/Haryana PWD schedule of Rates 1988 wherever necessary except Para 9 (b)
of preface of Haryana PWD schedule of Rates-1988.
25) The size of reinforced cement concrete and other structural member shall be
measured and paid for as per size provided in the structural design.
26) Error or omission, if any in the nomenclature rate or unit of the items or work shall
be corrected as per Haryana PWD schedule of Rates-1988.

Contractor Witness Executive Engineer


- 57 -

27) The Executive Engineer reserves the discretion to order the use of Tor or TMT or
Mild steel as per structural requirement.
28) The Executive Engineer reserves the discretion to get any type of material used as
per new techniques innovation from the contractor for any work done under this
contract. However, the rates for such material/work shall be paid as per provision of
clause 14 of the contract agreement.
29) Paint conforms to relevant IS specification and of make indicated in the contract will
be arranged by the contractor irrespective of note appended in HSR 1988.
30) The contractor shall comply with the provision of the Apprentices Act, 1961 and the
rules and orders issued there under from time to time. If he fails to do so his failure
will be breach of contract and the Chief Engineer will have the power to cancel the
contract. The contractor shall also be liable for any pecuniary liability arising on
account of any violation by him of the provision of the Act.

31) If for execution of the work, the contractor engages imported labour, he shall
immediately inform the Local Health Authorities entrusted with the work of
eradication of Malaria for their labourers inclusion in the surveillance operation and
for getting their blood examined, from the aforesaid authorities in order to prevent
Malaria positively.

Imported labour: Means labour belonging to a State other than the State of Haryana.

32) The contractor shall have to make arrangement for nourishment of children where 10
or more women worker shall be engaged by him on work the children shall be under
the supervision of one women worker who shall provide them with milk and toys to
play in a tent provided at site.

33) Income tax will be deducted from the bills of the contractor according to section
194-C of the Income Tax 1961 and instruction issued by the concerned Department
from time to time.

34) No pits will be dug by the contractor near the site of building work or within road land
for taking out earth for use on the work. In case of default the pits so dug will be
filled in by the Board at the cost of the contractor plus fourteen percent department
charges.

35) All material left at site one month after the completion of work shall become the
property of the Housing Board Haryana and contractor shall have no claim wherever
for such material left by him at site after one month of completion of work.

36) The contractor shall supply at his own cost and expenses all labour materials etc. for
layout and checking of any portion of the work during construction, whereas over
required by the Executive Engineer or his representative and nothing extra shall be
paid for such services.

37) The contractor shall not remove from the site of work, without the written permission
of the Executive Engineer, any material which has been issued to him for use on the
work.

Contractor Witness Executive Engineer


- 58 -

38) The contractor will not have any claim in case of delay by the Board of removal of
trees of shifting, raising removing of telegraph, telephone or electric lines (over head
or underground) and other structure if any Which comes in the way of the work.
Material excavated dismantled or cut at the site during execution of work.

a) Unless otherwise provided in the contract documents, material such as rubble, gravels,
sand Murrum, Kankar, earth soil etc. obtained from excavation and material obtained
by dismantling and existing structure shall remain the property of the Govt. /Board. If
deemed fit, the Executive Engineer may with the approval of competent authority
permit the use of such materials on the work in substitution of materials which the
contractor would have otherwise provided, subject to the condition that a suitable
deduction shall be made in the rate of the items in which such materials are used.

b) Any trees, branches, bushes crops etc. which may be required to be cut during the
execution of the work shall be handed over to the Housing Board Haryana or disposed
of as directed by it.

39) Coarse crusher sand or natural sand of proper quality having FM as per specifications
& approved by the Executive Engineer will be used in all masonry work. In case of
plaster work, coarse and Jamuna sand of proper quality having FM as per
specifications & approved by the Executive Engineer will be used.

40) All material brought by the contractor to the site of work shall be opened to suitable
test by the Executive Engineer and in accordance with the approved make. The
contractor shall afford all such facilities as the Executive Engineer may require for
collecting and forwarding all such samples and shall hold the material represented by
the sample until tests have been made the material found as per standard. The
contractor will supply the material required for the test samples without any charges.
No material, until it is approved by the Executive Engineer, will be used on the work.

41) The contractor shall provide weighing and measuring equipments for the works to
the entire satisfaction of the Executive Engineer at site for measuring of the various
articles, materials brought by him to the site of work for use on the work.

42) Running payments made for any work will not confer any rights on the contract for
its final acceptance. A work measured for running payments can be totally rejected
at the time of final bill or accepted at such reduced rates which the Executive
Engineer thinks reasonable. In case of any dispute arising on this behalf, the
decision of the Chief Engineer will be final.

43) Mechanical Mixer would be used for mixing of mortar in terms of provision of PWD
specification and nothing extra will be payable on this account.

44) Earnest money of all the tendered will be released only after 120 days or the
acceptance of the tender whichever is earlier.
45) In this contract schedule of rates only essential portion of items has been written, but
it will deem to cover the entire items as fully described in Haryana PWD schedule of
rates-1988.

Contractor Witness Executive Engineer


- 59 -

46) No claim will be entertained from the contractor, In case of any omission in
description, rate or unit occurred in any of the items taken in this schedule while
comparing the schedule or on account of typing comparison or over writing and in
case of error. The same shall be rectifiable at any stage as per Haryana PWD
schedule of rate-1988 along with the amendments made from time to time.

47) If due to any circumstances the site of work is shifted to another nearby site in the
same town, the agency will have to execute the work on the rates, Items & condition
of allotment letter. No claim on account of change of site shall be entertained.

48) The rates included in the contract schedule of rates cover the cost of filling the water
retaining structures; testing for water tightness to the full satisfaction of the
Executive Engineer and implying, if desired.

49) Building drawing approved with the unit are tentative may be revised by the Executive
Engineer with the permission of competent authority. The agency will have to
execute the work in accordance with the revised drawings may not claim any this
due to this revision.
50) The Contractor shall have to arrange water of good quality at its own which is
suitable for construction work as per IS necessary code. Nothing extra shall be paid
on this account water shall have to be got tested every two months by the tenderer
from HUDA or any other Government approved laboratory.
51) Any cement slurry added over base surface or for the continuation of concreting for
better bond is considered to have been included in the

items (unless otherwise explicitly stated) and nothing extra shall be payable for
extra cement consumed on this account.
52) The preparation of new approach road entrance or repair of the existing approach
road and its maintenance during the execution of the work including its restoration
shall all be carried out by the tenderer and nothing extra shall be payable on this
account.
53) Site shall mean the land (s) or other places into or through which the work is to be
executed under the contract OR any adjacent land, path, OR street, through which
the work is to be executed under the contract or any adjacent land path or street
which may be allotted or used for the purpose of carrying out the contract.
\54) The contract shall plan transportation of construction materials components and
equipments over public roads in accordance with traffic regulations as applicable at
the time and without causing any obstruction to other traffic or causing accident. No
claim whatsoever will be entertained on this account.
55) The contractor shall get the layout for installation of plant machinery labour huts,
stores, site office, workshop, batching plant etc. approved from Executive Engineer
in advance. Nothing extra shall be payable on this account.
56) Executive Engineer or his authorized representative may appoint any number of
assistant to assist them. Their names duties and scope of authority shall be notified
to the contractor and they shall have the authority to issue instructions/give
decisions to the extent of duties assigned and powers delegated to them.

Contractor Witness Executive Engineer


- 60 -

57). The contractor shall take all safety precautions pertaining to construction of works
such as excavation, trenching blasting demolition provisions of scaffolds ladder
working platforms, gangways, mixing asphalted materials, electric are and gas
welding, use of hoisting and construction machinery shall be governed by relevant
provisions Under the Building & other Construction Workers (Regulation of
Employment and Conditions of Services) Act-1996 and as directed by the
Executive Engineer and nothing extra shall be payable on this account.
58). The contractor shall make his own arrangements for water supply and electric power
necessary required for the work and shall make necessary payments directly to the
W/S & Electricity Department concerned and nothing extra shall be payable on this
account any recommendatory letters shall be issued by the department if requested
by the contractor, but shall be in no way be responsible in got getting delay in
getting required connections and no claim will be entertained in this regard.
59) The contractor shall provide at his own cost suitable leveling, weighing and
measuring instruments at site for checking the levels, weight and dimensions etc. as
may be necessary for execution of the work without any extra cost. The contractor
shall also have to carry out preliminary work of setting permanent bench marks,
reference points etc. at his own cost.
60) A number of other agencies will also simultaneously execute the works like
electrification, horticulture or external services and other building works etc. for the
same project along with this work in particular. The contractor shall work in close
co-ordination and shall provide necessary facilities for the same. No claim
whatsoever in the matter shall be entertained.
61) Some restrictions may be imposed by the security staff etc. on the working and/or
movement of labourers, materials etc. the contractor shall be bound to follow all
such restrictions/instructions and nothing extra shall be payable on this account.
62) The Contractor shall take all precautions to avoid accidents by exhibiting necessary
caution boards day and night, speed limit boards, red flags, red lights and providing
barriers. He shall be responsible for a damages and accidents caused to existing new
work due to negligence on his part. No hindrance shall be caused to traffic/running
of institution during the execution of the work.
63) The Contractor shall be responsible for the watch and ward of the building, safety of
all fittings and fixtures including sanitary and water supply fittings and fixtures
against pilferage and breakage during the period of installation and thereafter till the
building is physically handed over to the Housing Board Haryana.
64) In order to indemnify the Board for any claim on account of damage to
adjacent/existing properties/structure, the contractor shall at his own cost, ensure
before commencement of the actual work and as per direction of Executive Engineer
against such claim that may arise out of or due to work done by him.
65) The Contractor shall give due notices to municipal, police and / or other authorities
that may be required under the Law/Rules under force in the area and obtain all
requisite licenses for temporary obstructions/enclosure and pay all charges which
may be livable on account of his execution of works, under the agreement nothing
extra shall be payable on this account.
66) Clearance of sites at the commencement and completion of work shall be done by
the Contractors at his own cost. It includes clearance of site, jungle, bushes,

Contractor Witness Executive Engineer


- 61 -

undulations trees drains, culverts, temporary structures including any underground


features etc. before start of work and dismantling of underground or of other
structures, features constructed by the Contractor for execution of works, after
completion of work including disposal of malba.
67) The Contractor shall submit programme for successful completion of contract within
20 days from the date of award of work, in case he fails to do so Executive Engineer
will prepare such programme which shall be binding on him.
68) If the Contractor might be required to work in two or more shifts (including night
work) and no claim whatsoever shall be entertained on this account notwithstanding
the fact that the contractor will have to pay the labourers and other staff engaged
directly or indirectly on the work according to the provisions of the labour
regulations and the agreement entered upon and/ or extra amounts for any other
reasons. Prior approval for such programme be obtained from Executive Engineer.
69) Before commencement of the work, the contractor shall co-relate all the relevant
architectural and structural drawings issued for the work and satisfy himself that the
information available there from is complete and unambiguous. The figures and
written dimensions on the drawings shall supersede the measurement by scale.
70) The discrepancy, if any, shall be brought to notice of Executive Engineer for
decision before execution of the work. The contractor, alone shall be responsible for
any loss or damage occurring by the commencement of work on the basis of any
erroneous and incomplete information.
71) The contractor shall ensure quality construction in a planned and time bound
manner. Any sub-standard material/work beyond set out tolerance limits shall be
summarily rejected.
Materials and testing of materials for quality:
72) The materials shall be subject to inspection and approval of the Executive Engineer

73) Sub-standard Material/Work:


In case any materials/work is found sub-standard the same shall be rejected by the
Executive Engineer and the same shall be removed from the time of work within 48
hours, failing which the same shall be got removed by the Executive Engineer at the
risk and cost of the contractor without giving any further notice and time.
74) Sample of Materials:
The contractor shall submit to the Executive Engineer samples of all materials for
approval before bringing bulk supplies and before commencing the work. These
approved samples shall be preserved and retained in the custody of the Executive
Engineer as standards of materials and workmanship till the completion of the work.
The cost of testing of such samples shall be borne by the contractor and nothing shall
be payable on this account. The material shall be got tested from the Govt. Lab /
IIT/NIT/ PEC/ Shree Ram Institute Delhi.

The Executive Engineer shall reserve the right for number of samples drawn from the
works for its testing as he may consider proper as per provision of I S Codes. In
case, the contractor does not comply with any such provisions, the Board shall get it
done and the charges shall be recovered from the contractor’s dues.

Insurance against accident for injury to workers

Contractor Witness Executive Engineer


- 62 -

75) The Board shall not be liable for, or in respect of any damages of compensation
payable at law in respect or in consequence of any accident or injury to any
workman or other person in the employment of the contractor or any sub-contractor,
the contractor shall indemnify and keep indemnified the Board against all such
damages and compensation, and against all claim, proceedings, costs, charges and
expenses whatsoever in respect thereof or in relation thereto.

76) Use of Fly Ash

The contractor is required to use fly ash clay bricks conforming to IS: 3812 if the
same are available, in view of the Fly Ash Notification issued by the Haryana
Government from time to time.

77) In case of any item of HSR which has not been exhibited in DNIT due to any
reason, the same shall be paid with the premium quoted for the relevant chapter of
HSR 1988. Further, if more than one premium has been quoted for that chapter, then
premium of nearest item of that chapter or overall premium at which the tender has
been approved whichever is less will be paid. It is further clarified that if no rate for
the relevant chapter has been quoted, then payment with overall premium at which
tender has been approved will be paid.

78) One percent or as applicable from time to time labour cess on the construction cost
shall be deducted from the contractor’s bill as per the building and other
Construction Workers Welfare Cess Act 1996 with latest amendments.
79) No extra payment will be made to the contractor for use of batch mixture, transit
mixture, belt conveyer and overhead crane in case it is used at site.

80) That the specific loose material will be given to the allottee at the time of
possession and he has to get it fixed at his own. No labour rate for fixing the loose
material will be paid to the agency.

81) Laboratory will be set up by the contractual agency at site of the work at his own
cost for the work having agreement cost more than one Crore, as details given
below. If the contractual agency will fail to establish field laboratory within one
month from the date of start of work, the same will be established by the Engineer-
in-charge of work and recovery shall be made from the contractor’s bill @ of
double the cost of the items as given in the list of the laboratory equipments:

List of the Laboratory equipments

Contractor Witness Executive Engineer


- 63 -

Sr.No Name of the item Quantity


1 Tool kit (Vernier 15cm, micrometer, try scale, spirit 3 sets
level, plumb Bob, tape 3m and screw driver.
2 Compression testing Machine 200 T, manual 1 set
3 Cube moulds 150 x 150mm 4 sets
4 Cube moulds 75 x 75mm 4 sets
5 Slump test apparatus 1 set
6 Sieve set 200mm dia Brass (150 micron to 4.75mm) 1 set
7 Sieve set 300mm dia Brass (2.36 to 10mm) with 1 set
sieve shaker
8 Enameled Tray 450x300mm 6 Pcs
9 Oven 1 set
10 Timber moisture meter 1 set
11 Electronics weighing machine 5 kg capacity 1 set
12 Measuring Jar 4 Pcs
13 Vernier Caliper 1 set
14 Vernier megger 1 set
15 Electric Operated Machine Saker for F.M. 2 sets

82) The contractor shall comply with the provision of “Building and other construction
workers (Regulation of Employment and Conditions of Service) Act-1996 and rules
and other orders issued there under and as amended from time to time” at his level and
Housing Board Haryana will not be responsible in case any litigation is arisen.
83) Watch and ward of completed houses for four months from the date of completion
will be responsibility of contractual agency without any extra payment.
84) Any kind of Leakage causing dampness in the building will be rectified by the
contractual agency up to one year from the date of completion of the work. In case of
failure of contractual agency, action under clause-19 of the contract shall be taken for
rectification of the defect.
85)
86) Third Party Inspection will be got carried out by Housing Board Haryana for future
projects through reputed Institutes i.e. PEC, Chandigarh, NIT, Kurukshetra, Chottu
Ram College of Engineering, Murthal, YMCA, Faridabad etc. The charges will be
borne by Housing Board Haryana and cost of the same will be charged on work.

86: Price Adjustment.

86.1 The rate of cement/steel issued under the authority of Engineer-in-Chief Haryana PW
(B&R) deptt Chandigarh on the date of receipt of tender shall be considered as base
rate. If during execution of the works, the rate of cement/steel increases or decreases,
the difference in cost shall be paid/ recouped from the contractor in the bill, as per
formula given below subject to the following conditions:

86.1.1 The cement/steel will be arranged by the Contractor.

Contractor Witness Executive Engineer


- 64 -

86.1.2 The contractor shall submit original bill/ voucher while claiming the payment for the
work done. The bill/ voucher should pertain to the period of original contractual time
limit and should correspond with the progress of work. No extra payment due to
increase in rate of cement/steel will be paid if the original bill/ vouchers are not
submitted by the agency. No increase in prices of the cement/steel shall be
reimbursed to the contractor beyond the original time period allowed for construction
as per contract agreement irrespective of extension of time limit granted to the agency
for any reason, whatsoever.

86.1.3 After approval of tender, the Contractor shall submit the work programme for
execution of wok and get it approved from the Chief Engineer Housing Board
Haryana in the time limit prescribed in the tender document. The increase in rates of
cement/steel shall only be paid if the work is carried out within the prescribed period
as per the approved work programme.

86.2 To the extent that full compensation for any rise or fall in costs to the contractor is
not covered by the provisions of this or other clauses in the contract, the unit rates and
prices included in the contract shall be deemed to include amounts to cover the
contingency of such other rise or fall in costs

(a) For contract(s) amounting to more than Rs.1.00 crore,

A) if after submission of the tender, the price of cement and /or steel reinforcement
bars incorporated in the works increase(s) beyond the price(s) prevailing at the time of
last stipulated date for receipt of tenders (including extensions, if any) for the work,
then the amount of the contract shall accordingly be varied and provided further that
any such increase shall not be payable if such increase has become operative after the
stipulated date of completion of work in question.
B) If after the submission of the tender, the prices of cement and / or steel
reinforcement bars incorporated in the works is decreased, Govt. shall in respect of
these materials incorporated in the works be entitled to deduct from the dues of the
contractor such amount as shall be equivalent to the difference between the prices of
cement and/ for steel reinforcement as prevailed at the time of last stipulated date for
receipt of tenders including extensions if any for the work and the prices of these
materials on the coming into force of such base price of cement and / or steel
reinforcement bars issued under Chief Engineer Housing Board Haryana. The base price
of cement & steel is as below
Pc (Cement) Rs.5000/- Per MT including taxes
Ps(Steel Reinforcement Bars) Rs.47,000/-Per MT including taxes
It is further clarified that the decrease in the prices of cement & steel shall be
deducted from the dues of the contractor if such decrease has become operative after
the stipulated date of completion of work in question and increase shall not be payable
if such increase has become operative after the stipulated date of completion of work
in question. The increase/decrease in price shall be determined by the All India
Wholesale Price Indices for Cement (OPC/PPC Cement) and Steel (MS Long
Products) as published by the Economic Advisor to Government of India,
Ministry of Commerce and Industry ) and base price for cement and /or steel
reinforcement bars as issued under authority of Engineer-in-Chief Haryana PW (B&R)

Contractor Witness Executive Engineer


- 65 -

Department, Chandigarh as valid on the last stipulated date of receipt of tender


including extension if any and for the period under consideration.
If the purchase rate of cement and steel is less than the base rate no variation in cost will
be payable to the agency.

The amount of the contract shall accordingly be carried for cement and /or steel
reinforcement bars and will be worked out as per the formula given below

a) Adjustment for component of ‘Cement’

Vc=Pc xQc x C1-C10


C10
Where,

Vc = Variation in cement cost i.e. increase or decrease in the amount in


rupees to be paid or recovered.

Pc = Base price of cement as issued under authority of Engineer-In-chief,


Hr.PW(B&R) Department., Chandigarh valid at the time of the last stipulated
date of receipt of tender including extensions, if any.

Qc = Quantity of cement used in the works since previous bill.

C10 = All India Wholesale Price index for Cement (OPC/PPC Cement)as published by
the Economic Advisor to Government of India, Ministry of Industry and
Commerce as valid on the last stipulated date of receipt of tenders including
extensions, if any.

C1 = All India Wholesale Price index for cement for period under. Consideration as
published by Economic Advisor to Government of India, Ministry and
Commerce s valid on the date of purchase of material.
b) Adjustment for Component of ‘Steel’

Vs = Ps x Qs x S1-S10
S10
Where,
Vs = Variation in cost of steel reinforcement bars i.e. increase or decrease in the amount
in rupees to paid or recovered.

Base price of steel reinforcement bars, as issued under authority of Engineer-In-chief,


Hr.PW(B&R) Deptt., Chandigarh at the time of the last stipulated date of receipt of
tender including extension , if any.
= Quantity of steel paid either by way of secured advance or used in the works since
pervious bill (whichever is earlier)

Contractor Witness Executive Engineer


- 66 -

= All India wholesale Price Index for Steel (MS Long Products) for the period under
consideration as published by Economic Advisor to Government of India,
Ministry of Industry and Commerce as valid on the last stipulated date of tenders
including extensions, if any.

= All India wholesale Price Index for steel (MS Long Products) in for the period under
consideration as published by Economic Advisor to Government of India, Ministry
of Industry and Commerce as valid on the date of purchase of material.

87 The procurement of steel & cement will be done stage wise only for requirement of four
months without advance payment of cement.
88 The progress of the work shall be planned in such a way that:-
(a) At any given time activities shall be in progress in 1/3 of the number of stairs/flats in
the project. Activity in further stairs/flats shall be taken up in the ration of stairs/flats
finished in the first lot of 1/3 stairs/flats.
For example in a project there are say 100 flats having 16 stairs of six flats each and two
stairs of two flats each as such total 18 stairs. So I first lot, activity will be started in 6
stairs/32 or 36 flats. Out these six stairs when one stair is fully finished, only then activity
shall be started in the seventh stairs and so on.
(b)The expenditure as any work shall be so controlled that the gap between expenditure as
%age of agreement amount does not exceed by more than 30% over the actual physical
delivery of stairs/flats completed. For example say in a project 100 flats are to be
constructed at an average cost of 3 lakh each. The agreement amount is Rs. 3.00 Crore.
Now the expenditure or first one crore shall be so utilized that by that time some of flats
are nearing completion. In next bill of say Rs. 1.20 Crore, there must a delivery of one
stair of six flats fully finished and so on. Further payment release shall have a rider of
proportionate delivery of finished flats and this gap shall not exceed 30% in financial
terms.
Note: Above condition is applicable only in row houses and not in multi-storeyed flats.

Sd/-
Executive Engineer
Housing Board Haryana
Faridabad

Contractor Witness Executive Engineer


- 67 -

HOUSING BOARD HARYANA CONTRACTOR LABOUR REGULATIONS AND


FAIRWAGE CLAUSES.
(1) Short title: These regulations may be called Haryana (1) Public works Department
Contractor Labour Regulations.
(2) Definitions: In the regulations unless otherwise expressed or indicated the following
words and expressions shall have the meaning hereby assigned to them respectively
that is to say.
(a) “Labour” means workers employed by Housing Board Haryana contractor directly
or indirectly though a sub-contractor other person or by an agent on his behalf.
(b) “Fair wages” means wages whether for time or piece work for the work and where such
wages have not been so notified, the wages prescribed by the Haryana Public Works
Department for the district in which the work is done wages to be paid as applicable from
time to time.
(c) “Contractor shall include every person whether a sub-contractor or headman or agent
employing labour on the work taken on contract.
(d) “Wages” shall have the same meaning as defined in the payment of wages Act, 1936
and include time and piece rate wages.
(3) Display of notice regarding wages, etc. The contractor shall before the commences
his work on contract display and correctly maintain and continue to display and
correctly maintain in clean and legible condition in conspicuous place on the work
notice in English and in the local Indian language spoken by the majority of the
workers giving, the fair wages notified or prescribed by the Haryana by the Haryana
Public Works Department and hours of work for which such wages are earned.
(4) Payment of wages
(i) Wages due to every worker shall be paid to him direct.
(ii) All wages shall be paid in current coin or currency or in both.
(5) Fixation of wages periods
(i) The contractor shall fix wages periods in respect of which the
wages shall be payable.
(ii) No wages period shall exceed one month.
(iii) Wages of every workman employed on the contract shall be paid before
expiry of ten days after the last day of the wage period in this respect of
which the wages are payable.
(iv) When the employment of any worker is terminated by or on behalf of the
contractor, the wages earned by him shall be paid before the expiry of the
day succeeding the one on which his employment is terminated.
(v) All the payments of wages shall be made on working day.
(6) (i) Wages books and wages slip etc. The contractor shall maintain a wage book
of each worker in such form as may be convenient, but the same shall include
the particulars.
(a) Rate of daily or monthly wages.
(b) Nature of work on which employed.
(c) Total number of days worked during each wage period.
(d) Total amount payable for the work during each wage period.
(e) All deduction made from the wages with an indication in each of the ground
for which the deduction is made.
(ii) Wage actually paid for each wages period.
(iii) The contractor shall also maintain a wages slip for each worker employed.
(iv) The authority competent to accept the contract may grant an exemption from
the maintenance of wages book and wages slip to a contractor who is his

Contractor Witness Executive Engineer


- 68 -

opinion may not directly or indirectly employ more than 100 persons on the
work.
(7) (i) Fines and deductions which may be made from wages: The wages of a
worker shall be paid to him without any deduction of any kind except the
following.
(a) Fines
(b) Deduction for absence from duty, i.e. from the place where by the terms of
his employment he is required to work. The amount of deductions shall be in
proportion to the period for which he was absent.
(c) Deduction for damage to or lost of goods expressly entrusted to the
employed person for custody or for loss of money for which he is required to
account where such damages or loss is directly attributable to his neglect or
default.
(d) Any other deduction which the Board may from time to time allow.
(ii) A fine shall be imposed on a worker and no deduction for damages or loss
shall be made from his wages until the worker has been given an opportunity
of showing cause against such fines or deduction.
(iii) The total amount of fines which may be imposed in any one wages period on
a worker shall not exceed an amount equal 50% of the wage payable to him
in respect of that wages period.
(iv) No fine imposed on a worker shall be recovered from him by installment or
after the expiry of 60 days from the date on which it was imposed.
8. Register of fines etc.
(i) The contractors shall maintain a register of fines and of all deductions for
damages or loss. Such register shall mention the reason for which fine was
imposed or deduction for damage or loss which was made.
(ii) The contractor shall maintain a list in English and the local Indian language,
clearly defining act and omissions for which penalty or fine can be
composed. He shall display such list and maintained it in a clear and legible
condition in conspicuous place.
9 Preservation of Book: The wage book, the slip and the register of the
deductions required to be maintained under the regulations shall be preserved
for 12 months after the date of entry made in them.
10. Power of Labour Welfare Officers to make investigations or enquiry:
The Labour Welfare Officer or any other person authorized by the Haryana
State Housing Board on their behalf shall have power to make enquiries with
a view to ascertaining and enforcing due and power observance of the wage
clause and the provisions of these regulations he shall investigate into any
complaint regarding the default made by the contractor or sub-contractor in
regard to such provision.
11. Report of Labour Welfare Officer : The Labour Officer or any other persons
authorized as aforesaid shall submit a report of the result of his investigations
or enquiry to the Executive Engineer concerned, indicating the extent if any
to which the default has been committed and the amount of the fine
recoverable in respect of the acts of omission of the labourer with a note that
necessary deduction from the contractor’s bill be made and the wages and
other dues paid to the labourers concerned.
12. Appeal against decision of the Labour Welfare Officer any persons aggrieved
by the decision and recommendation of the Labour Welfare
Officer or other persons so authorized may appeal, against such decision to

Contractor Witness Executive Engineer


- 69 -

the Labour Commissioner but subject to such appeal, the decision of the
officer shall be final and binding upon the contractor.

13. No partly shall be allowed to be represented by lawyer during any


investigation enquiry appeal or any other proceedings under these
regulations.

14. Inspection of Register: The contractors shall allow inspection of the Wage
Book and Wage Slips to any of his workers or to his agent at a convenient
time and places after due notices is received or the Labour Welfare Officer or
any other person authorized by the Haryana Housing Board on his behalf.

15. Submission of return: The contractor shall submit periodical return as may be
specified from time to time.

16. Amendments: The Haryana Housing Board may from time to time add or
amend these regulations and or any question as to the application
interpretation or affect of these regulations, the decision of the Labour
Commissioner to Haryana shall be final.
(i)Government or any other person authorized by the Haryana Housing Board
in that behalf be final.

17. The Government of India with a view to regulate employment of contract


labour in certain establishment has enacted the CONTRACT LABOUR
(REGULATION & ABOLITION) ACT, 1970. This Act applies to:-

i) to every establishment in which twenty or more workmen are employed or


were employed on any day of the preceding twelve months as contract labour;
ii) To every contractor who employs or who employed on any day of the preceding
twelve months twenty or more workmen.

Contractor Witness Executive Engineer


- 70 -

LABOUR WAGE CLAUSES

Fair Wage Clause: Fair Wage Clause should invariably in all notices and conditions of
contract forms used in this Department.

(a) The contractor shall pay not less than fair wage to labourers engaged by him on the
work.
Explanation:

Fair wage means wage whether, for time of piece work notified at the time of
inviting tenders for the work and where such wages have not been so notified, the
wages prescribed by the Public Works Department Building and Roads Haryana (1)
for the district in which the work is done.

(b) The contractor shall, notwithstanding the provision of any agreement to the contrary
cause to be paid fair wage to labourers indirectly engaged on the work, including any
labour engaged by the Sub-contractors in connection with the said work, as if the
labourers had been directly employed by him.

(c) In respect to all labour directly or indirectly employed on the work for the
performance of the contractor’s part of this agreement, the contractor shall comply
with or cause to be complied with the Haryana(1) Public works Department
Contractor’s labour Regulations (page …….. to ……….) made by the Govt. from
time to time in regard to payments of wages, wage period, deduction from wages,
recovery of wages not paid unauthorized made, maintenance of wage register, wages
cards, publication of wages and other terms of employment, inspection and
submission of periodical returns and all other matters of a like nature.

(d) The Executive Engineer or the Sub-Divisional Engineer concerned shall have the
right to deduct from the money due to the contractor any sum required or estimated
to be required for making good the loss suffered by a worker or worker by reason of
non fulfillment of the conditions of the contract for benefit of the workers, non-
payments of wages which are not justified by the terms of contract or for non-
observance of the regulations referred to in clause (c) above.

(e) Vis-à-vis Housing Board Haryana the contractor shall primarily be liable for all
payments to be made under Haryana for the observance of the regulations aforesaid
without prejudice to his right to claim indemnity from his sub-contractors.

(f) The regulations aforesaid shall be deemed to be a part of this contract and any breach
thereof shall be deemed to be breach of this contract.

Contractor Witness Executive Engineer


- 71 -

GUARANTEE TO BE EXECUTED BY CONTRACTORS ON NON JUDICIAL STAMP


PAPER FOR REMOVAL OF DEFECTS AFTER COMPLETION IN RESPECT OF WATER
PROOFING

This Agreement made this………Day of…………, Two Thousand Fourteen and


...............between……………Son of……….(hereinafter called the Guarantor of the One Part) and
the Board (hereinafter called the HBH of the other Part)
Whereas this Agreement is supplementary to the Contract (Hereinafter called the 'Contract') dated...
... ... ... ... ... made between the guarantor of the One Part and HBH on the Other Part, whereby the
Contractor, inter-alia, undertook to render the buildings and structures in the said contract recited,
completely Water and Leak Proof.
AND whereas the guarantor agreed to give a guarantee to the effect that the said work will remain
water and LEAK PROOF and the life of such water proofing treatment shall be ten years to be
reckoned from the date after the expiry of maintenance period prescribed in the contract.
Provided that guarantor will not be responsible for leakage cause of earthquake or structural defects
or misuse or alteration.
During this period of guarantee the guarantor shall make good all defects and in case of any defect
being found render the building water proof to the satisfaction of the Engineer-in-Charge at his cost
and shall commence the work for such rectification within seven days from the date of issue of the
notice from Engineer-in-Charge mass to the cost, payable by the guarantor shall be final binding.
That if guarantor fails to make good all the defects commits breach there under guarantor will
indemnify the principal and his successors against all loss, damage, expense otherwise which may be
incurred by him by reason of any default on the part of the guarantor in performance and observance
of this supplementary agreement. As the amount of less and /or damage and /or cost incurred by
HBH the decision of the Engineer-in-Charge will be final and binding on the parties.
In witness where of these presents have been executed by the obligator..........
and by …… for and on behalf of the Board on the day, month and year first above written.

Signed, Sealed and delivered by obligator in present of:


1. ...........................

2. ...........................
Contractor
Signed for all behalf of the Board by:

1. …………................

2……………………….

Sd/-
Executive Engineer,
Housing Board Haryana,
Faridabad.

Contractor Witness Executive Engineer


72

PART-A
Detailed Measurements of External Development in Sector-56, 56A(1.56 Acre) Faridabad.

1. CIVIL WORK
2. INTERNAL PUBLICE HEALTH WORK
3. INTERNAL E.I. WORK

Contractor Witness Executive Engineer


73

PART-A
SCHEDULE OF SPECIFICATION OF ITEMS, QUANTITIES, RATES TO BE ATTACHED WITH NOTICE INVITING E-TENDER FOR
THE CONSTRUCTIOON OF 128 NOS. TYPE-A & 64 NOS. TYPE-B FLATS (STILT AT GF + 8 STOREY) INCLUDING INTERNAL
PUBLIC HEALTH SERVICES, INTERNAL ELECTRICAL INSTALLATIONS AND COMMON AREA SERVICES IN SEC-56-56A(GH)
FARIDABAD (FOR SERVING/ EX-DEFENCE AND PARA-MILITARY PERSONNEL OF HARYANA) (POCKET 1.56 ACRES LAND)

ESTIMATED COST

EARNEST MONEY

TIME LIMIT 27 MONTHS


DATE OF CLOSE OF RECEIPT OF TECHNICAL BID
DATE OF OPENING OF TECHNICAL BID

PART A - CIVIL WORK

S.No. Total DESCRIPTION OF ITEMS RATE UNIT HSR/ NS Total Cost


Qty. (in Rs.)

For 128 For 64


Type-A Type-B
flats flats

1 2938.96 1275.17 4214.13 Earth work in excavation by mechanical and carriage of 92.125 Cum 5.2 + 4.1 388227.00
excavated soil upto 1 km lead including loading and
unloading

Contractor Witness Executive Engineer


74

2 3024.40 1312.23 4336.63 Earth work excavation in foundation, trenches, etec. In all 3079.65 100 6.2 (b) 133553.00
kinds of soils, not exceeding 2 metres depth including Cum
dressing of bottom and sides of trenches, stacking the
excavated soil, clefar from the edge of excavation and
subsequent filling around masonry, in 15cm layers with
compaction, including disposal of all surplus soil, as
directed within a lead of 30 metres.

3 1097.88 548.94 1646.82 Extra for every 7.5 meters additional lead beyond 15 472.5 100 6.2 C (i) 7781.00
meters, but up to 60 meters by manual or animal driven Cum
cart.

4 1097.88 548.94 1646.82 Extra for every 7.5 meters additional lead beyond 60 2226.00 100 6.2 (ii) 36658.00
meters, but upto 300 meters by animal or by animal-driven Cum
cart.

5 1097.88 548.94 1646.82 Extra for every 7.5 meters additional lead beyond 300 1638.00 100 6.2 C(ii) 26975.00
meters, but upto 495 meters by animal or by animal-driven Cum
cart.

6 2938.96 1275.17 4214.13 Earth filling under floors with surplus soil excavated 1613.98 100 6.13 (a) 68015.00
from foundation and taken only from outside the Cum
building plinth, in 15 cm layers including ramming
watering and consolidating lead up-to 30 meters.

Contractor Witness Executive Engineer


75

7 4270.84 1864.57 6135.41 Earth filling under floors with earth brought from outside 200.00 Cum N.S. 1227082.00
the building campus only with irrespective of lead in 15
cm layers including ramming watering and consolidating
and including loading & unloading, carriage royality/
compensation etc. as per PWD specification including
handing of earth complete in all respects to the satisfaction
of the Engineer-in-Charge.

8 4549.80 1974.08 6523.88 Clearing jungle including uprooting of rank vegetation, 313.96 100 6.26 20482.00
grass brush wood, trees and saplings of girth upto 30 cm Sqm
measured at a height of 1 meter above ground level and
removal of rubbish upto a distance of 50M outside the
periphery of the area cleared

9 Centering and shuttering for flat surfaces such as 9.1


suspended floors, roofs, landing, chhajjas, shelves etc
inclination not exceeding 25 degree with horizontal.

1160.08 552.83 1712.91 1st Storey 203.25 Sqm 9.1 348149.00


nd
1187.68 566.64 1754.32 2 Storey 223.25 Sqm 9.1+ Note 391652.00
1187.68 566.64 1754.32 3rd Storey 243.25 Sqm 9.1+ Note 426738.00
1187.68 566.64 1754.32 4th Storey 263.25 Sqm 9.1+ Note 461825.00
1187.68 566.64 1754.32 5th Storey 283.25 Sqm 9.1+ Note 496911.00
1187.68 566.64 1754.32 6th Storey 303.25 Sqm 9.1+ Note 531998.00
1187.68 566.64 1754.32 7th Storey 323.25 Sqm 9.1+ Note 567084.00
1187.68 566.64 1754.32 8th storey 343.25 Sqm 9.1+ Note 602170.00
1239.28 592.44 1831.72 9th storey 363.25 Sqm 9.1+ Note 665372.00
340.60 170.30 510.90 10th storey 383.25 Sqm 9.1+ Note 195802.00

Contractor Witness Executive Engineer


76

218.36 109.18 327.54 11th storey 403.25 Sqm 9.1+ Note 132081.00
10 Centring and shuttering for sides and soffits of beams 9.7
haunching, girders, bressumers and lintels.

863.24 347.16 1210.40 1st Storey 289.00 Sqm 9.7 349806.00


996.84 409.92 1406.76 2nd Storey 309.00 Sqm 9.7+ Note 434689.00
996.84 409.92 1406.76 3rd Storey 329.00 Sqm 9.7+ Note 462824.00
996.84 409.92 1406.76 4th Storey 349.00 Sqm 9.7+ Note 490959.00
996.84 409.92 1406.76 5th Storey 369.00 Sqm 9.7+ Note 519094.00
996.84 409.92 1406.76 6th Storey 389.00 Sqm 9.7+ Note 547230.00
996.84 409.92 1406.76 7th Storey 409.00 Sqm 9.7+ Note 575365.00
996.84 409.92 1406.76 8th Storey 429.00 Sqm 9.7+ Note 603500.00
996.84 409.92 1406.76 9th Storey 449.00 Sqm 9.7+ Note 631635.00
156.08 78.04 234.12 10th storey 469.00 Sqm 9.7+ Note 109802.00
57.28 28.64 85.92 11th storey 489.00 Sqm 9.7+ Note 42015.00
11 Centring and shuttering for Stairecases with sloping soffits 9.8
including risers and stringers.
123.32 61.66 184.98 1st Storey 254.50 Sqm 9.8 47077.00
123.32 61.66 184.98 2nd Storey 274.50 Sqm 9.8+ Note 50777.00
123.32 61.66 184.98 3rd Storey 294.50 Sqm 9.8+ Note 54477.00
123.32 61.66 184.98 4th Storey 314.50 Sqm 9.8+ Note 58176.00
123.32 61.66 184.98 5th Storey 334.50 Sqm 9.8+ Note 61876.00
123.32 61.66 184.98 6th Storey 354.50 Sqm 9.8+ Note 65575.00
123.32 61.66 184.98 7th Storey 374.50 Sqm 9.8+ Note 69275.00
123.32 61.66 184.98 8th Storey 394.50 Sqm 9.8+ Note 72975.00
123.32 61.66 184.98 9th Storey 414.50 Sqm 9.8+ Note 76674.00
123.32 61.66 184.98 10th storey 434.50 Sqm 9.8+ Note 80374.00

Contractor Witness Executive Engineer


77

12 Centring and shuttering for columns (Square or rectangular 9.9


or polygonal in plan).

769.28 384.64 1153.92 1st Storey 247.25 Sqm. 9.9 285307.00


769.28 384.64 1153.92 2nd Storey 267.25 Sqm. 9.9+ Note 308385.00
769.28 384.64 1153.92 3rd Storey 287.25 Sqm. 9.9+ Note 331464.00
769.28 384.64 1153.92 4th Storey 307.25 Sqm. 9.9+ Note 354542.00
769.28 384.64 1153.92 5th Storey 327.25 Sqm. 9.9+ Note 377620.00
769.28 384.64 1153.92 6th Storey 347.25 Sqm. 9.9+ Note 400699.00
769.28 384.64 1153.92 7th Storey 367.25 Sqm. 9.9+ Note 423777.00
769.28 384.64 1153.92 8th Storey 387.25 Sqm. 9.9+ Note 446856.00
769.28 384.64 1153.92 9th Storey 407.25 Sqm. 9.9+ Note 469934.00
636.92 318.46 955.38 10th storey 427.25 Sqm. 9.9+ Note 408186.00
219.60 109.80 329.40 11th storey 447.25 Sqm. 9.9+ Note 147324.00

13 Centering and shuttering for faces of walls partitions, 9.5


retaining walls, well steining and the like (vertical or
battering) including attached pilasters, buttresses etc

166.40 83.20 249.60 1st Storey 274.25 Sqm. 9.5 68453.00


166.40 83.20 249.60 2nd Storey 294.25 Sqm. 9.5+ Note 73445.00
166.40 83.20 249.60 3rd Storey 314.25 Sqm. 9.5+ Note 78437.00
166.40 83.20 249.60 4th Storey 334.25 Sqm 9.5+ Note 83429.00
166.40 83.20 249.60 5th Storey 354.25 Sqm. 9.5+ Note 88421.00
166.40 83.20 249.60 6th Storey 374.25 Sqm. 9.5+ Note 93413.00
166.40 83.20 249.60 7th Storey 394.25 Sqm. 9.5+ Note 98405.00
166.40 83.20 249.60 8th Storey 414.25 Sqm. 9.5+ Note 103397.00
166.40 83.20 249.60 9th Storey 434.25 Sqm. 9.5+ Note 108389.00
900.92 450.46 1351.38 10th storey 454.25 Sqm. 9.5+ Note 613864.00

Contractor Witness Executive Engineer


78

458.40 229.20 687.60 11th storey 474.25 Sqm. 9.5+ Note 326094.00
14 1211.20 525.52 1736.72 Shuttering for faces of concrete foundations and 153.25 Sqm 9.13 266152.00
foundation beams (vertical or battering).

15 163.84 72.86 236.70 Cement Concrete 1:4:8 with stone aggargats 40 mm 2217.05 Cum 10.39 524776.00
nominal size in foundation and plinth.

16 1107.44 478.3 1585.74 Design mix cement concrete of grade M-25 with minimum 4290 Cum 10.66 6802825.00
cement contents 410 Kg./cum in foundation and plinth.

17 Design mix cement concrete of grade M-25 with minimum 10.73


cement contents 410 Kg. /cum in first storey upto 4 meters
above plinth level.
303.52 139.52 443.04 1st Storey 4324.375 Cum 10.73 1915871.00
320.04 147.78 467.82 2nd Storey 4338.400 Cum 10.73+ Note 2029590.00
320.04 147.78 467.82 3rd Storey 4352.425 Cum 10.73+ Note 2036151.00
320.04 147.78 467.82 4th Storey 4366.450 Cum 10.73+ Note 2042713.00
320.04 147.78 467.82 5th Storey 4380.475 Cum 10.73+ Note 2049274.00
320.04 147.78 467.82 6th Storey 4394.500 Cum 10.73+ Note 2055835.00
320.04 147.78 467.82 7th Storey 4408.525 Cum 10.73+ Note 2062396.00
320.04 147.78 467.82 8th Storey 4422.550 Cum 10.73+ Note 2068957.00
326.48 151.00 477.48 9th Storey 4436.575 Cum 10.73+ Note 2118376.00
151.16 75.58 226.74 10th storey 4450.600 Cum 10.73+ Note 1009129.00
90.84 45.42 136.26 11th storey 4464.625 Cum 10.73+ Note 608350.00

Contractor Witness Executive Engineer


79

18 Cement concrete 1:1.5:3 with stone aggregate 20 mm 10.81+10.95(a) +


nominal size for reinforced concrete work in shelves Note (b)
excluding steel reinforcement but including cent ring and
shuttering laid in position complete in all respects.

2.00 1.00 3.00 2nd Storey 5730.45 Cum 17191.00


2.00 1.00 3.00 3rd Storey 5770.60 Cum 17312.00
2.00 1.00 3.00 4th Storey 5810.75 Cum 17432.00
2.00 1.00 3.00 5th Storey 5850.90 Cum 17553.00
2.00 1.00 3.00 6th Storey 5891.05 Cum 17673.00
2.00 1.00 3.00 7th Storey 5931.20 Cum 17794.00
2.00 1.00 3.00 8th storey 5971.35 Cum 17914.00
2.00 1.00 3.00 9th Storey 6011.50 Cum 18035.00

19 Cement concrete 1:1.5:3 with stone aggregate 20mm 10.86+ 10.95(a)


nominal size for reinforcement concrete work for walls
exceeding 20 cm thickness (straight and curved ) beams,
girders, stairs, columns ( square or rectangular ) battens
and lintels etc. excluding steel reinforcement ,but
including centering and shuttering , laid in position,
complete in all respect.

10.28 4.96 15.24 2nd Storey 6578.275 Cum 100253.00


10.28 4.96 15.24 3rd Storey 6618.425 Cum 100865.00
10.28 4.96 15.24 4th Storey 6658.575 Cum 101477.00
10.28 4.96 15.24 5th Storey 6698.725 Cum 102089.00
10.28 4.96 15.24 6th Storey 6738.875 Cum 102700.00
10.28 4.96 15.24 7th Storey 6779.025 Cum 103312.00

Contractor Witness Executive Engineer


80

10.28 4.96 15.24 8th Floor 6819.175 Cum 103924.00


10.28 4.96 15.24 9th storey 6859.325 Cum 104536.00
20 Masonary work using flyash-lime based bricks class 11.102
designation-10 (IS:12894-2002) laid in cement sand
mortar 1:6 in super structure.
161.48 239.86 1st Storey 2163.00 Cum 11.102 518817.00
78.38
298.08 137.44 435.52 2nd Storey 2171.25 Cum 11.102 + Note 945623.00
298.08 137.44 435.52 3rd Storey 2179.50 Cum 11.102 + Note 949216.00
298.08 137.44 435.52 4th Storey 2187.75 Cum 11.102 + Note 952809.00
298.08 137.44 435.52 5th Storey 2196.00 Cum 11.102 + Note 956402.00
298.08 137.44 435.52 6th Storey 2204.25 Cum 11.102 + Note 959995.00
298.08 137.44 435.52 7th Storey 2212.50 Cum 11.102 + Note 963588.00
298.08 137.44 435.52 8th Storey 2220.75 Cum 11.102 + Note 967181.00
298.08 137.44 435.52 9th storey 2229.00 Cum 11.102 + Note 970774.00
101.40 50.70 152.10 10th storey 2237.25 Cum 11.102 + Note 340286.00
th
64.04 32.02 96.06 11 storey 2245.50 Cum 11.102 + Note 215703.00
9.68 4.84 14.52 12th storey 2253.75 Cum 11.102 + Note 32724.00

OR
First class brickwork laid in cement sand mortar 1:6 in first 11.7
storey upto 4 meters above plinth level.
161.48 78.38 239.86 1st storey 2901.15 Cum 11.7 695870.00
nd
298.08 137.44 435.52 2 Storey 2958.9 Cum 11.7 + Note 1288660.00
rd
298.08 137.44 435.52 3 Storey 3016.65 Cum 11.7 + Note 1313811.00
298.08 137.44 435.52 4th Storey 3074.4 Cum 11.7 + Note 1338963.00
298.08 137.44 435.52 5th Storey 3132.15 Cum 11.7 + Note 1364114.00
298.08 137.44 435.52 6th Storey 3189.9 Cum 11.7 + Note 1389265.00
298.08 137.44 435.52 7th Floor 3247.65 Cum 11.7 + Note 1414417.00

Contractor Witness Executive Engineer


81

298.08 137.44 435.52 8th storey 3305.4 Cum 11.7 + Note 1439568.00
th
298.08 137.44 435.52 9 storey 3363.15 Cum 11.7 + Note 1464719.00
101.4 50.7 152.10 10th storey 3420.9 Cum 11.7 + Note 520319.00
th
64.04 32.02 96.06 11 storey 3478.65 Cum 11.7 + Note 334159.00
9.68 4.84 14.52 12th storey 3536.4 Cum 11.7 + Note 51349.00
21 11.0cm thick brick wall using flyash lime based bricks 11.101
class designation-10 (IS:12894-2002) laid in cement sand
mortar 1:4 in superstructure.

138.24 51.84 190.08 1st storey 299 Sqm 11.101 56834.00


nd
716.76 264.54 981.30 2 Storey 299.95 Sqm 11.101 + Note 294341.00
716.76 264.54 981.30 3rd Storey 300.9 Sqm 11.101 + Note 295273.00
716.76 264.54 981.30 4th Storey 301.85 Sqm 11.101 + Note 296205.00
716.76 264.54 981.30 5th Storey 302.8 Sqm 11.101 + Note 297138.00
716.76 264.54 981.30 6th Storey 303.75 Sqm 11.101 + Note 298070.00
716.76 264.54 981.30 7th Floor 304.7 Sqm 11.101 + Note 299002.00
716.76 264.54 981.30 8th storey 305.65 Sqm 11.101 + Note 299934.00
716.76 264.54 981.30 9th storey 306.6 Sqm 11.101 + Note 300867.00

OR
Half Brick Masonry
11.43 cm thick brick wall laid in cement sand mortar 1:4 in 11.48 (a )
superstructure.
138.24 51.84 190.08 1st storey 385.70 Sqm 11.48 (a ) 73314.00
nd
716.76 264.54 981.30 2 Storey 392.35 Sqm 11.48 (a ) + Note 385013.00
716.76 264.54 981.30 3rd Storey 399.00 Sqm 11.48 (a ) + Note 391539.00
716.76 264.54 981.30 4th Storey 405.65 Sqm 11.48 (a ) + Note 398064.00
716.76 264.54 981.30 5th Storey 412.30 Sqm 11.48 (a ) + Note 404590.00

Contractor Witness Executive Engineer


82

716.76 264.54 981.30 6th Storey 418.95 Sqm 11.48 (a ) + Note 411116.00
716.76 264.54 981.30 7th Floor 425.60 Sqm 11.48 (a ) + Note 417641.00
716.76 264.54 981.30 8th storey 432.25 Sqm 11.48 (a ) + Note 424167.00
716.76 264.54 981.30 9th storey 438.90 Sqm 11.48 (a ) + Note 430693.00
22 3840.00 1920.00 5760.00 Dressing, Chamfering of bricks to required shape in 516.25 100 11.81 29737.00
masonry work. Nos.

23 1105.72 500.62 1606.34 Terracing consisting of tiles 22.86 cm x 11.43 cm x 3.81 426.65 Sqm 13.13 + Note-iii 685345.00
cm, laid over 87.50 mm mud filling, on a layer of 25 mm
mud plaster and on other layer of mud mortar for laying
the tiles, including two coasts of bitumen laid hot at 1.65
Kg per Sqm on top of R.C.C. slab including grouting with
cement sand mortar 1:3 and top surface to be left clean
etc.(9th Storey)

24 48.00 16.00 64.00 Top khurra 0.6 m x 0.6 m for rain water pipe in 25 mm 41.82 Each 13.50 2676.00
thick cement concrete 1:2:4 over 50 mm thick cement
concrete 1:8:16.
25 775.76 366.16 1141.92 Cement concrete 1:2:4 gola 10 cms x 10 cms quadrant 18.19 Meter 13.64 20772.00
along junction of roof with parapet wall finished smooth
where specially specified.

Contractor Witness Executive Engineer


83

26 Providing and fixing PVC Rain water pipe 6 kg pressure of 13.89(a)


ISI Mark in cement mortar during masonry work.

896.00 480.00 1376.00 a) 100mm dia PVC Pipe 6kg pressure. 218.40 Meter 300518.00

27 Providing and fixing PVC Bend of ISI Mark. 13.90(a)

64.00 24.00 88.00 a) 100mm dia PVC Bend. 116.88 Each 10285.00

28 256.00 128.00 384.00 Providing and fixing PVC Door-Tee 110 x 110x63 mm 125.00 Each N.S. 48000.00
(ISI marked) of approved make compete in all respect as
per full satisfaction of the Engineer-in charge. (Rate for all
storey)

29 256.00 128.00 384.00 Providing and fixing PVC REDUCER 63mm x 90mm (ISI 45.00 Each N.S. 17280.00
marked) of approved make complete in all respect as per
full satisfaction of the Engineer in charge (Rate for all
storey)

30 1218.56 376.32 1594.88 Providing and fixing false ceiling with 12mm thick 660.00 Sqm 13.91 1052621.00
Gympsum Board fixed on M.S. Steel runners frame i/c
cost of screw angles, cleats, rawel plugs, with taping,
filling with Sympsum compound and supplying priming
coat etc. complete in all respect

31 1547.08 671.24 2218.32 Base course of floors consisting of 100 mm thick cement 184.75 Sqm 14.1 409835.00
concrete 1:8:16 and 100 sand or stone filling

Contractor Witness Executive Engineer


84

32 Screed of 50mm thick cement concrete 1:8:16 to be laid 14.4


below the topping.
895.44 443.76 1339.20 2nd Storey 78.25 Sqm 14.4 + Note 104792.00

895.44 443.76 1339.20 3rd Storey 79.75 Sqm 14.4 + Note 106801.00

895.44 443.76 1339.20 4th Storey 81.25 Sqm 14.4 + Note 108810.00

895.44 443.76 1339.20 5th Storey 82.75 Sqm 14.4 + Note 110819.00

895.44 443.76 1339.20 6th Storey 84.25 Sqm 14.4 + Note 112828.00

895.44 443.76 1339.20 7th Storey 85.75 Sqm 14.4 + Note 114836.00

895.44 443.76 1339.20 8th Storey 87.25 Sqm 14.4 + Note 116845.00

895.44 443.76 1339.20 9th storey 88.75 Sqm 14.4 + Note 118854.00

36.00 18.00 54.00 10th storey 90.25 Sqm 14.4 + Note 4874.00

62.80 31.40 94.20 11th storey 91.75 Sqm 14.4 + Note 8643.00

33 279.04 122.24 401.28 Providing and fixing Marble stone flooring 15 to 18 mm 1133 Sqm N.S. 454650.00
and above thick slab including matching grains of marble
laid in any pattern including skirting & dado as specified
and jointed with white cement slurry mixed with pigment
to match the shade of marble including rubbing and
polishing complete in all respects. Note:- Baroda Green
Marble to be fixed on L-iron fixed in wall.

Contractor Witness Executive Engineer


85

34 Kotah stone flooring, minimum 25mm thick in any pattern 14.62 (i)
as specified over 20 mm thick base of cement coarse sand
mortar 1:3 laid and jointed with neat cement slurry mixed
with pigment to match the shade of stone including
rubbing and polishing.

93.12 46.56 139.68 1st storey 706.825 Sqm 14.62 (i) 98729.00
201.60 100.80 302.40 2nd Storey 707.875 Sqm 14.62 + Note (i) 214061.00
201.60 100.80 302.40 3rd Storey 708.925 Sqm 14.62 + Note (i) 214379.00
201.60 100.80 302.40 4th Storey 709.975 Sqm 14.62 + Note (i) 214696.00
201.60 100.80 302.40 5th Storey 711.025 Sqm 14.62 + Note (i) 215014.00
201.60 100.80 302.40 6th Storey 712.075 Sqm 14.62 + Note (i) 215331.00
201.60 100.80 302.40 7th Storey 713.125 Sqm 14.62 + Note (i) 215649.00
201.60 100.80 302.40 8th Storey 714.175 Sqm 14.62 + Note (i) 215967.00
201.60 100.80 302.40 9th storey 715.225 Sqm 14.62 + Note (i) 216284.00
61.20 30.60 91.80 10th storey 716.275 Sqm 14.62 + Note (i) 65754.00
46.48 23.24 69.72 11th storey 717.325 Sqm 14.62 + Note (i) 50012.00
35 Kotah stone 20 mm thick in skirting risers of steps, dados 14.66 (i)
and wall facing (lining) and pillars laid on 12 mm thick
cement coarse sand plaster 1:3 laid and jointed with neat
cement slurry, mixed with pigment to match the shade of
stone including rubbing and polishing including labour for
fixing cramps, dowels and pins etc

45.76 22.88 68.64 1st storey 829.50 Sqm 14.66 (i) 56937.00
55.44 27.72 83.16 2nd Storey 830.55 Sqm 14.66 + Note (i) 69069.00
55.44 27.72 83.16 3rd Storey 831.60 Sqm 14.66 + Note (i) 69156.00

Contractor Witness Executive Engineer


86

55.44 27.72 83.16 4th Storey 832.65 Sqm 14.66 + Note (i) 69243.00
55.44 27.72 83.16 5th Storey 833.70 Sqm 14.66 + Note (i) 69330.00
55.44 27.72 83.16 6th Storey 834.75 Sqm 14.66 + Note (i) 69418.00

55.44 27.72 83.16 7th Storey 835.80 Sqm 14.66 + Note (i) 69505.00

55.44 27.72 83.16 8th Storey 836.85 Sqm 14.66 + Note (i) 69592.00

55.44 27.72 83.16 9th storey 837.90 Sqm 14.66 + Note (i) 69680.00

19.64 9.82 29.46 10th storey 838.95 Sqm 14.66 + Note (i) 24715.00

8.60 4.30 12.90 11th storey 840.00 Sqm 14.66 + Note (i) 10836.00

36 502.00 251.00 753.00 Extra for kotah stone flooring in treads of steps not 4.025 Sqm 14.64 3031.00
exceeding 30 cm in width.
37 2124.00 1062.00 3186.00 Extra for nosing in treads of steps of kotah stone slabs 21.35 Meter 14.65 68021.00

38 1596.72 692.80 2289.52 Conglomerate floor 50 mm thick cement concrete topping 188.00 Sqm 14.10 430430.00
1:2:4 ( 11th storey)
39 4961.88 2431.26 7393.14 Providing and fixing vitrified tiles of size 600x600 mm of 785.655 Sqm 14.89 5808457.00
approved make in flooring laid in any pattern as specified
over base of 20 mm thick cement coarse sand mortar 1:3
and jointed with white cement slurry mixed with pigment
to match the shade to-tiles.
Note: - Tile shall be of premium quality (1st quality) of
reputed manufacturer like: NITCO, KAJARIA, SOMANI,
ORIENT, JOHNSONS & RAK.

Contractor Witness Executive Engineer


87

40 583.68 244.88 828.56 Providing and fixing of vitrified tiles of size 600x600 mm 790.33 Sqm 14.90 654836.00
of approved make in skirting/ dado laid in any pattern as
specified over base of 12 mm thick cement coarse sand
mortar 1:3 and jointed with white cement slurry mixed
with pigment to match the shade to tiles.
Note: - Tile shall be of premium quality (1st quality) of
reputed manufacturer like: NITCO, KAJARIA, SOMANI,
ORIENT, and JOHNSONS & RAK.

41 1470.00 574.02 2044.02 Providing and fixing ceramic tiles (anti skid) tiles of size 530.40 Sqm 14.91 1084148.00
400 mm x 400 mm size of above size of approved make in
flooring, laid in any pattern as specified over base of 20
mm thick cement coarse sand mortar 1:3 and jointed with
white Cement slurry mixed with pigment to match the
shade of tiles. Note: - Tile shall be of premium quality (1st
quality) of reputed manufacturer like: NITCO, KAJARIA,
SOMANI, ORIENT, JOHNSONS & RAK.

Contractor Witness Executive Engineer


88

42 5164.96 1753.72 6918.68 Providing and fixing 1st quality ceramic glazed wall tiles 648.15 Sqm 14.92 (b) 4484342.00
confirming to I.S. 15622 (thickness to be specified by the
manufacturer) of approved make in all colours, shades
except burgundy, bottle green, black of any size as
approved by Engineer-In-Charge in skirting, risers of steps
and dados over 12 mm thick bed of cement mortar 1:3
coarse and jointed with grey cement slurry, including
pointing in white cement mixed with pigment of matching
shades complete. Size of ceramic glazed tile 300 x 450mm

43 229.62 114.81 344.43 Providing and fixing geranite stone in all shades 15mm to 2010.00 Sqm N.S. 692304.00
18mm thick in skirting/ dado, risers of stps, pillars and
feacing laid in any pattern as specified over base of 12mm
thick cement coarse sand mortar 1:3 and jointed with white
cement slurry mixed pigment to match the shade of granite
including nosing/ rounding & labour for fixing cramps
pins and dowels etc. complete in all respects as per full
satisfaction of Engineer-inCharge. (Rate for all storey)
(upto 4 ft. height)

Contractor Witness Executive Engineer


89

44 12mm thick cement plaster 1:4 on internal walls. 15.5

339.40 169.70 509.10 1st Storey 76.20 Sqm 15.5 38793.00


1668.20 721.54 2389.74 2nd Storey 77.28 Sqm 15.5 + Note 184679.00
1668.20 721.54 2389.74 3rd Storey 78.36 Sqm 15.5 + Note 187260.00
1668.20 721.54 2389.74 4th Storey 79.44 Sqm 15.5 + Note 189841.00
1668.20 721.54 2389.74 5th Storey 80.52 Sqm 15.5 + Note 192422.00
1668.20 721.54 2389.74 6th Storey 81.60 Sqm 15.5 + Note 195003.00
1668.20 721.54 2389.74 7th Storey 82.68 Sqm 15.5 + Note 197584.00
1668.20 721.54 2389.74 8th Storey 83.76 Sqm 15.5 + Note 200165.00
1668.20 721.54 2389.74 9th Storey 84.84 Sqm 15.5 + Note 202746.00
th
305.08 152.54 457.62 10 Storey 85.92 Sqm 15.5 + Note 39319.00
45 12 mm thick cement plaster 1:4 on top of parapet. (12th 15.5 (derived)
storey)
15.56 7.78 23.34 11th storey 82.92 Sqm 15.5 (derived + Note) 1935.00
22.36 11.18 33.54 12th storey 84 Sqm 15.5 (derived + Note) 2817.00
46 20mm thick cement plaster 1:4 on walls.(outside) (Two 15.15
coats)
1425.40 677.12 2102.52 1st storey 120.90 Sqm 15.15 254195.00
1255.32 479.74 1735.06 2nd Storey 123.00 Sqm 15.15 + Note (i) 213412.00
1255.32 479.74 1735.06 3rd Storey 125.10 Sqm 15.15 + Note (i) 217056.00
1255.32 479.74 1735.06 4th Storey 127.20 Sqm 15.15 + Note (i) 220700.00
1255.32 479.74 1735.06 5th Storey 129.30 Sqm 15.15 + Note (i) 224343.00
1255.32 479.74 1735.06 6th Storey 131.40 Sqm 15.15 + Note (i) 227987.00
1255.32 479.74 1735.06 7th Storey 133.50 Sqm 15.15 + Note (i) 231631.00
1255.32 479.74 1735.06 8th Storey 135.60 Sqm 15.15 + Note (i) 235274.00
1255.32 479.74 1735.06 9th Storey 137.70 Sqm 15.15 + Note (i) 238918.00
260.92 130.46 391.38 10th Storey 139.80 Sqm 15.15 + Note (i) 54715.00

Contractor Witness Executive Engineer


90

565.04 282.52 847.56 11th Storey 141.90 Sqm 15.15 + Note (i) 120269.00
th
47.04 23.52 70.56 12 Storey 144.00 Sqm 15.15 + Note (i) 10161.00
47 15mm thick cement plaster 1:4 on rough side of single or 15.10
half on brick walls. (internal)
545.12 272.56 817.68 1st storey 93.90 Sqm 15.10 76780.00
1583.16 812.88 2396.04 2nd Storey 94.98 Sqm 15.10 + Note(i) 227576.00
1583.16 812.88 2396.04 3rd Storey 96.06 Sqm 15.10 + Note(i) 230164.00
1583.16 812.88 2396.04 4th Storey 97.14 Sqm 15.10 + Note(i) 232751.00
1583.16 812.88 2396.04 5th Storey 98.22 Sqm 15.10 + Note(i) 235339.00
1583.16 812.88 2396.04 6th Storey 99.30 Sqm 15.10 + Note(i) 237927.00
1583.16 812.88 2396.04 7th Storey 100.38 Sqm 15.10 + Note(i) 240514.00
1583.16 812.88 2396.04 8th Storey 101.46 Sqm 15.10 + Note(i) 243102.00
1583.16 812.88 2396.04 9th Storey 102.54 Sqm 15.10 + Note(i) 245690.00
th
218.76 109.38 328.14 10 Storey 103.62 Sqm 15.10 + Note(i) 34002.00
290.52 145.26 435.78 11th Storey 104.70 Sqm 15.10 + Note(i) 45626.00
48 20mm thick cement plaster 1:4 on rough side of single or 15.15
half on brick walls. (outside) (Two coats)
539.80 269.90 809.70 1st storey 120.90 Sqm 15.15 97893.00
347.04 151.68 498.72 2nd Storey 121.98 Sqm 15.15 + Note (i) 60834.00
347.04 151.68 498.72 3rd Storey 123.06 Sqm 15.15 + Note (i) 61372.00
347.04 151.68 498.72 4th Storey 124.14 Sqm 15.15 + Note (i) 61911.00
347.04 151.68 498.72 5th Storey 125.22 Sqm 15.15 + Note (i) 62450.00
347.04 151.68 498.72 6th Storey 126.30 Sqm 15.15 + Note (i) 62988.00
347.04 151.68 498.72 7th Storey 127.38 Sqm 15.15 + Note (i) 63527.00
347.04 151.68 498.72 8th Storey 128.46 Sqm 15.15 + Note (i) 64066.00
347.04 151.68 498.72 9th Storey 129.54 Sqm 15.15 + Note (i) 64604.00
322.12 161.06 483.18 10th Storey 130.62 Sqm 15.15 + Note (i) 63113.00

Contractor Witness Executive Engineer


91

187.40 93.70 281.10 11th Storey 131.70 Sqm 15.15 + Note (i) 37021.00
th
40.40 20.20 60.60 12 Storey 132.78 Sqm 15.15 + Note (i) 8046.00
49 10 mm thick cement plaster 1:4 on top of sunshade. 15.46 derived

47.20 23.60 70.80 2nd Storey 65.88 Sqm 15.46 derived + Note (i) 4664.00
47.20 23.60 70.80 3rd Storey 66.96 Sqm 15.46 derived + Note (i) 4741.00
47.20 23.60 70.80 4th Storey 68.04 Sqm 15.46 derived + Note (i) 4817.00
47.20 23.60 70.80 5th Storey 69.12 Sqm 15.46 derived + Note (i) 4894.00
47.20 23.60 70.80 6th Storey 70.20 Sqm 15.46 derived + Note (i) 4970.00
47.20 23.60 70.80 7th Storey 71.28 Sqm 15.46 derived + Note (i) 5047.00
47.20 23.60 70.80 8th Storey 72.36 Sqm 15.46 derived + Note (i) 5123.00
47.20 23.60 70.80 9th Storey 73.44 Sqm 15.46 derived + Note (i) 5200.00
45.04 22.52 67.56 10th Storey 74.52 Sqm 15.46 derived + Note (i) 5035.00
50 10 mm thick cement plaster 1:4 underside of ceiling. 15.52

1202.20 543.02 1745.22 1st storey 75.90 Sqm 15.52 132462.00


1081.68 506.00 1587.68 2nd Storey 76.98 Sqm 15.52 + Note 122220.00
1081.68 506.00 1587.68 3rd Storey 78.06 Sqm 15.52 + Note 123934.00
1081.68 506.00 1587.68 4th Storey 79.14 Sqm 15.52 + Note 125649.00
1081.68 506.00 1587.68 5th Storey 80.22 Sqm 15.52 + Note 127364.00
1081.68 506.00 1587.68 6th Storey 81.30 Sqm 15.52 + Note 129078.00
1081.68 506.00 1587.68 7th Storey 82.38 Sqm 15.52 + Note 130793.00
1081.68 506.00 1587.68 8th Storey 83.46 Sqm 15.52 + Note 132508.00
1081.68 506.00 1587.68 9th Storey 84.54 Sqm 15.52 + Note 134222.00
261.68 130.84 392.52 10th Storey 85.62 Sqm 15.52 + Note 33608.00
107.88 53.94 161.82 11th Storey 86.70 Sqm 15.52 + Note 14030.00

Contractor Witness Executive Engineer


92

51 10 mm thick cement plaster 1:4 on walls or thin vertical 15.52 derived


section
295.04 147.52 442.56 2nd Storey 70.38 Sqm 15.52 derived + Note 31147.00
295.04 147.52 442.56 3rd Storey 71.46 Sqm 15.52 derived + Note 31625.00
295.04 147.52 442.56 4th Storey 72.54 Sqm 15.52 derived + Note 32103.00
295.04 147.52 442.56 5th Storey 73.62 Sqm 15.52 derived + Note 32581.00
295.04 147.52 442.56 6th Storey 74.70 Sqm 15.52 derived + Note 33059.00
295.04 147.52 442.56 7th Storey 75.78 Sqm 15.52 derived + Note 33537.00
295.04 147.52 442.56 8th Storey 76.86 Sqm 15.52 derived + Note 34015.00
295.04 147.52 442.56 9th Storey 77.94 Sqm 15.52 derived + Note 34493.00
900.92 425.54 1326.46 10th Storey 79.02 Sqm 15.52 derived + Note 104817.00
189.12 94.56 283.68 11th Storey 81.18 Sqm 15.52 derived + Note 23029.00
52 4844.52 2365.40 7209.92 Preparation of ply wood surface for painting including 15.18 Sqm 16.1 109447.00
sand papering the surface and applying filling with
approved quality filler consisting of white lead, linseed oil,
varnish and chalk mitti including finishing the surface to
the required finish complete.

53 6099.64 2946.08 9045.72 Applying pink primer or aluminium priming coat on wood 12.375 Sqm 16.2 111941.00
work including preparation of surface, knotting and
stopping etc. (1st quality paint).

54 6422.60 2946.08 9368.68 Painting two coats excluding priming coat with synthetic 31.02 Sqm 16.3 290616.00
enamel paint in all shades on new woodwork or metallic or
plastered or concrete surfaces to give an even shade. (1st
quality paint).

Contractor Witness Executive Engineer


93

55 3018.64 1441.56 4460.20 Applying primer coat with metal primer on new steel or 10.395 Sqm 16.9 46364.00
iron work including preparation of surface.(1st. Quality)

56 5251.72 2448.24 7699.96 Painting two coats excluding priming coat with ready- 23.10 Sqm 16.17 177869.00
mixed paint for metallic surfaces in all shades on new steel
or iron work.(1st. Quality)

57 Applying priming coat with cement primer in all shades on


newly plastered or concrete exterior surfaces

21319.68 9030.06 30349.74 A) Primer only 13.695 Sqm 16.25 415640.00

58 Providing two coats of exterior acrylic emulsion

21319.68 9030.06 30349.74 B) 1st quality 48.75 Sqm 16.79(b) 1479550.00

59 36732.76 17370.00 54102.76 Preparation of plastered surface for distempering including 13.035 Sqm 16.51 705229.00
sand papering the surface applying filling with approved
quality filler consisting of plaster of Paris and chalk mitti
including finishing the surface to required finish complete.

60 36732.76 17370.00 54102.76 Distempering with washable oil bound distemper (of 30.03 Sqm 16.58 1624706.00
approved manufacture) two coats over one priming coat on
new work.

61 128.00 64.00 192.00 Providing number plate and writing of house number as 50.00 Each NS 9600.00
per numbering plan.

Contractor Witness Executive Engineer


94

62 Cost of aluminium fittings complete for doors and 17.72


windows, such as tower bolts, handles, etc, and screws for
these fittings (excluding sliding bolt)

2406.08 1086.00 3492.08 a) for single leaf shutter 71.20 Sqm. 17.72 (a) 248636.00

444.32 222.16 666.48 b) for double leaf shutter 109.80 Sqm. 17.72 (b) 73180.00

63 1276.00 574.00 1850.00 Providing and fixing sliding bolt with nuts and screws etc, 161.20 Each 17.83 (b) ii 298220.00
complete. Aluminium : - size 250mm x 16mm

64 2153.12 985.58 3138.70 Factory manufactured solid flush door shutters with block 1155.7975 Sqm 17.93 (a)(iii) - 3627702.00
board core as per I.S. No.1659-1969 bonded with water Note under 17.18
proof type phenol formaldehyde synthetic resin, hot-
pressed, conforming to I.S. 2202 part-I and part-II, fixed in
position, including iron hinges, screws, chocks/cleats and
stops, etc. (excluding the cost of any fittings, other than
specified above, but including labour for fixing the same in
position):- (a) Commercial veneering with vertical grains
or cross bands and face veneer on both sides commercial
facing with laminated core and lipped edges 35mm thick

Note : 1. Style of the frame shall be without any joint.


2. Block board core (filling) shall be hard wood e.g.
Mango, Jmun, Neem. 3. Lipping of edge shall be
factory fitted.

Contractor Witness Executive Engineer


95

65 697.28 322.60 1019.88 Factory manufactured paneled door or glazed window, 1696.60 Sqm 17.90 (-) 1730328.00
shutters, of commercial hard wood, such as hollock, Note-I of 17.18
champ, Chirkrassy and chaplash, etc. (non-coniferous
timber other than teak, conforming to I.S. specification
No.1003, kiln seasoned), with 100 mm wide vertical
styles, 150 mm wide lock rail, 200 mm wide bottom rail
and 100 mm wide other rails, with panels of 15 mm thick,
tongued and grooved of commercial hard wood and
including cost of iron hinges, screws, chocks/cleats, stops,
nails etc. complete, fixed in position (excluding the cost of
any fittings, other than specified above, but including
labour for fixing the same in position). 35mm thick

66 12159.12 6079.56 18238.68 Providing and fixing Staircase railing / parapet railing of 50.00 Kg N.S. 911934.00
40 mm M.S square pipe or 40mm round pipe having
thickness 2.5 to 3.00 mm including MS bar and flats and
L-iron fixed in wall to fix marble stone slab in kitchen
including cutting, jointing and welding and priming coat,
complete as per Architectural design and fixed in position
as per full satisfaction of Engineer-in-Charge.(Rate for all
storey)

Contractor Witness Executive Engineer


96

67 7676.00 3570.00 11246.00 {FE-500 EQR TMT steel bars for R.C.C. works, where not 5502.30 Qtl 18.22 61878866.00
included in the complete rate of R.C.C. including bending,
binding and placing in position complete.

68 369.52 171.80 541.32 Supplying and fixing glass panes including specials sash 692.40 Sqm 18.30 (b) 374810.00
putty of approved make. Glass panes 4mm thick exceeding
40 Sq.dm area

69 Pressed steel sheet frames (chowkats), consisting of 2 mm 18.34(b)


thick steel sheet of the specified section, including iron
lugs (hold fasts), iron hinges, conforming to P.W.D.
specifications, including bolts for fixing stops, lock notch,
provision for receiving tower bolts, and finished with one
coat of ready-mixed paint red lead non-setting primer, of
approved quality, fixed in position including the cost of
cement concrete 1:3:6 for lugs complete.

5095.76 2226.00 7321.76 Single rebate 2574331.00


351.60 Meter
172.80 86.40 259.20 Centre mullion 136702.00
527.40 Meter
4495.36 2036.48 6531.84 Double rebate 418.50 Meter 2733575.00

1373.68 638.84 2012.52 Centre mullion 1263299.00


627.72 Meter
70 2.40 1.20 3.60 Cement concrete 1:2:4 with stone aggregate 20mm 3420.18 Cum 10.59 12313.00
nominal size in first storey upto 4 metres above plinth
level

Contractor Witness Executive Engineer


97

71 76.52 33.20 109.72 First class brickwork laid in cement sand mortar 1:6 in 2754.15 Cum 11.2 302185.00
foundation and plinth.
72 4067.20 2033.60 6100.80 20mm thick raised or sunk cement mortar band/ drip 2.70 P.Mtr. 15.79 16472.00
coarse in cement mortar 1:4 Per cm
wide
73 800.00 400.00 1200.00 20mm thick raised or sunk cement mortar band/ drip 2.70 P.Mtr. 15.79 3240.00
coarse in cement mortar 1:4 Per cm
wide
Total 182719947.00

1. Cost with 1st class brick work = Rs 171509165/-


2. Cost with Flyash brick work = Rs 166768632/-

Contractor Witness Executive Engineer


98

PART B - PUBLIC HEALTH WORK

S.No. Total DESCRIPTION OF ITEMS RATE (in Rs.) UNIT HSR/ NS Total Cost
Qty.

For 128 Type-A flats For 64 Type-B flats

Contractor Witness Executive Engineer


99

1. 983.92 426.90 1410.82 EARTH WORK IN EXCAVATION IN 4380.40 100 6.7 61800.00
FOUNDATIONS, TRENCHES, OF UNDER Cum
GROUND STRUCTURES. SULLAGE
DRAINS,ETC., AND OTHER SIMILAR WORKS
IN ORDINARY SOIL INCLLUDING DRESSING
of bottom and sides, to correct levels and
templates, cutting of trees and bushes,
dewatering of rain water, diversion of traffic,
fixing and maintenance of caution boards, and
night signals, crossing over trenches for access
to houses, watching, stacking of excavated soil,
clear from the edge of excavation, and
subsequent filling, where required around
masonry, in 15 cm layers, with compaction
AND DISPOSAL OF SURPLUS SOIL AS
DIRECTED WITHIN A LEAD OF 30
METRES FOR DEPTH UPTO 2 METRES
BELOW NATURAL GROND LEVEL (For
Public Health works only).

Contractor Witness Executive Engineer


100

2 128.36 55.70 184.06 Cement concrete 1:4:8 with stone aggregate 20 2310.00 Cum 10.38 425179.00
mm nominal size in foundation and plinth. (For
UPVC pipe)
3 Cement concerete 1:4:8 with stone aggregate 10.56 +
20mm nominal size in first storey upto 4 mtr. Note
above plinth level.
11.44 4.16 15.60 For UPVC pipe (2nd Storey) 2358.400 Cum 36791.00
11.44 4.16 15.60 For UPVC pipe (3rd Storey) 2372.425 Cum 37010.00
11.44 4.16 15.60 For UPVC pipe (4th Storey) 2386.450 Cum 37229.00
11.44 4.16 15.60 For UPVC pipe (5th Storey) 2400.475 Cum 37447.00
11.44 4.16 15.60 For UPVC pipe (6th Storey) 2414.500 Cum 37666.00
11.44 4.16 15.60 For UPVC pipe (7th Storey) 2428.525 Cum 37885.00
11.44 4.16 15.60 For UPVC pipe (8th Storey) 2442.550 Cum 38104.00
11.44 4.16 15.60 For UPVC pipe (9th Storey) 2456.575 Cum 38323.00
4 Cutting holes up to 23 cm through stone 28.24(A, B)
masonry or brick work in cement walls for
pipes and making Goods including re-pointing,
re-plastering and finishing according to existing
finish where required.
256.00 128.00 384.00 a) 11.43 cm thickness of walls. 56.00 Each 21504.00
512.00 216.00 728.00 b) 22.86 cm thickness of walls. 81.40 Each 59259.00

Contractor Witness Executive Engineer


101

5 CUTTING HOLES by way of core cutting N.S.


method UPTO 23 CM SQUARE FOR PIPES
IN FLOOR AND ROOFS OF CEMENT
CONCRETE REINFORCED CONCRETE OR
REINFORCED BRICK WORK AND MAKING
GOOD Including/ re-pointing/ re-plastering/
replacing bitumen and colour or white washing
where required.
128.00 64.00 192.00 115 mm thickness of floor or roof 200.00 Each 38400.00

Contractor Witness Executive Engineer


102

6 CONSTRUCTING BRICK MASONRY 29.84 (c )


INSPECTION CHAMBER SIZES AS GIVEN
BELOW UPTO 0.60 METRE AVERAGE
DEPTH in cement mortar 1:5 LIME
CONCRETE with 40 percent lime mortar 2:3 in
foundation cement concrete 1:2:4 BENCHING
12mm THICK CEMENT PLASTER 1:2 with a
floating coat of 1mm thick of neat cement
R.C.C.1:2:4 SLAB 100mm THICK
/C.C.TOPPING 50 mm THICK WITH 455 MM
x 455MM/455MMx 610 MM INSIDE LIGHT
DUTY C.I.INSPECTION CHAMBER COVER
AND FRAME weight as per I.S.I. specification
painted WITH 3 COATS OF black bitumastic
superior paint complete as per standard-
design.
(c) Size 600 mm X 900 mm inside (with 455
mm x 455 mm cover and frame light duty
single seal weighing 20 kg with R.C.C. slab).

Contractor Witness Executive Engineer


103

40.00 20.00 60.00 Note: - Normally inspection chambers of 450 3795.00 Each 227700.00
mm x 450mm and 450mm x 600 mm should
be constructed. In very exceptional cases
where connections cannot be accommodated
in 450 mm X 600 mm size inspection chamber
of 600 mm x 900 mm be adopted.
7 EXTRA FOR EVERY 0.30 METER DEPTH OF 29.85( c)
INSPECTION CHAMBER.
24.00 12.00 36.00 ( c) 600 mm x 900 mm 764.50 Per 91740.00
0.30
Mtr
depth
8 Providing salt glazed stone ware pipes grade 29.95
‘A’ in standard length of 600mm each pipe
marked with IS:651 and their lowering, cutting,
jointing and testing as described in HSR item
No. 29.38, 29.39, 29.40 including the cost of
jointing materials as well as carriage, loading,
unloading stacking, handling, re-handling etc.
complete in all respects to the satisfaction of
Engineer-in-Charge.
314.00 141.30 455.30 a) 200mm internal dia 265.65 P.Pmtr 120950.00

57.60 28.80 86.40 b) 150mm internal dia 208.95 P.Pmtr 18053.00

Contractor Witness Executive Engineer


104

9 Providing and fixing in position PVC clamps not N.S.


less than 5mm of approved design for fixing CI/
PVC soil waste vent or anti pipes to walls complete
in all rerspect incuding utting and making good the
wall and floor etc. and painting.
1008.00 432.00 1440.00 A) For 100mm dia pipe 56.00 Each 80640.00

128.00 108.00 236.00 A) For 90mm dia pipe 50.00 Each 11800.00
10 Cutting chase in brick walls in cement or in
floor for embedding GI or H C I. pipe lines and
making good the same to its original condition.
3264.00 1056.00 4320.00 (c) Size 75 mm x 50 mm. 17.60 Metre 76032.00

Contractor Witness Executive Engineer


105

11 Providing and fixing in position gully traps fixed 30.114 ( c)


in cement concrete 1:4:8 complete with H C I.
grating 150 mm x 150 mm cast iron cover
weighting approximately 7.26 kg. and frame
clear opening 300 X 300 mm and outside size
330 mm x 300 mm and chamber including cost
of brick work in Cement Mortar 1:5 cement
concrete 1:8:16 in foundations, and cement
concrete1:2:4 in coping around C. I. cover and
frame etc, with three coats of black bitumastic
superior paint of approved manufacture on all
C.I. work as per standard design, minimum
depth of water should be 150 mm with a
minimum seal 50 mm.
48.00 16.00 64.00 c) 150 mm internal diameter S.W. gully trap 800.80 Each 51251.00

Contractor Witness Executive Engineer


106

12 Providing, fixing and jointing in position UPVC N.S.


(SWR) pipe Type-B for soil waste vent or
antisyphonage pipe of approved make
including suitable jointing to ensure leak proof
service as per instructions for laying & jointing
laid by the manufacturer, including cutting and
wastage etc and cutting holes in walls, roofs
and floors etc and making good to its original
conditions but excluding cost of cement
concrete 1:2:4 around pipe lines complete in
all respects as per full satisfaction of the
Engineer–in–Charge. (Rate for all storey)
160.00 64.00 224.00 150mm i/d pipeline for sewerage & sanitary 345.00 P.Pmtr 77280.00
2592.00 836.00 3428.00 100mm i/d pipeline for sewerage & sanitary 220.00 P.Pmtr 754160.00

1920.00 1056.00 2976.00 90mm i/d pipeline for sewerage & sanitary 190.00 P.Pmtr 565440.00

Contractor Witness Executive Engineer


107

13 Providing & fixing U.P.V.C. (SWR) 110mm x N.S.


90mm size Nahni trap within 110mm dia PVC
pipe upto level and jali approved make
including suitable jointing to ensure leak proof
service and cement concrete 1:2:4 with stone
aggregate 20mm nominal size under& around
the trap where required upto floor level
complete in all respect including cutting and
making good the wall and floor etc. as per
satisfaction of Engineer-in-Charge. (Rate for all
storey)
640.00 256.00 896.00 With 90 mm i/d outlet. 170.00 Each 152320.00
14 Providing and fixing UPVC(SWR) Type-B of N.S.
size 110 mm x75x40 mm Multi Floor Trap
along with 110 mm dia PVC pipe up to floor
level and PVC grating of approved make with
suitable jointing to ensure leak proof service as
per instruction for laying & jointing
recommended by the manufacturer and
including cement concrete 1:2:4 under and
around the multi floor trap where required up
to floor level complete in all respects including
cutting and making good the walls and floors
etc. complete in all respect as per full
satisfaction of the Engineer – in – Charge.
(Rate for all storey)

Contractor Witness Executive Engineer


108

256.00 128.00 384.00 With 63 mm i/d outlet.(110 x 75 x 40)mm 150.00 Each 57600.00

15 Providing, fixing and jointing in position UPVC N.S.


(SWR) specials for soil waste of approved
make including suitable jointing to ensure leak
proof service as per instruction for laying &
jointing recommended by the manufacturer
and including cutting and wastage etc., cutting
holes in walls, roof or floors etc and making
good to its original condition complete in all
respect as per full satisfaction of the Engineer
– in – Charge. (Rate for all storey)

a) For 150 mm outer dia pipes line.


16.00 8.00 24.00 Socket / collar ( 6 per block - ground floor only) 90.00 Each 2160.00

b) For 110 mm outer dia pipes line.


80.00 24.00 104.00 Plain Bend 105.00 Each 10920.00
256.00 192.00 448.00 Colar 60.00 Each 26880.00
80.00 24.00 104.00 Cowl 20.00 Each 2080.00
256.00 64.00 320.00 Tee junction with door of 110 mm x 110 mm x 130.00 Each 41600.00
110 mm

384.00 128.00 512.00 Tee junction with door of 110 mm x 110 mm x 130.00 Each 66560.00
90 mm

c) For 90 mm outer dia pipe line.

Contractor Witness Executive Engineer


109

32.00 24.00 56.00 Plain Bend 75.00 Each 4200.00


384.00 256.00 640.00 Collar 55.00 Each 35200.00
32.00 24.00 56.00 Cowl 20.00 Each 1120.00
256.00 128.00 384.00 Tee junction with door of 95 mm x 95 mm x 95 125.00 Each 48000.00
mm

256.00 128.00 384.00 Collar 63mm 55.00 Each 21120.00


16 128.00 64.00 192.00 Providing and Fixing in position best quality 2500.00 Each N.S. 480000.00
stainless steel kitchen sink with complete
fittings of approved make as below confirming
to IS specifications and :

(i) ISI marked stainless steel kitchen sink


without drainage board of approved make and
size given below:

(ii) 40mm stainless steel waste of approved


make.

(iii) PVC flexible waste pipe of approved make


as required by the engineer-in-charge

Overall size:24" x 18" x 8"


(Bowl size 20" x 16"x 8")

Contractor Witness Executive Engineer


110

17 Providing, laying, jointing, fixing and testing ISI N.S.


marked medium quality Class-B of approved make
GI pipe lne and specials tees, bends, sockeets,
elows, reducers, nipples, short piece etc. complete
including cutting threading inside the building an
testing etc. complete in all respect as per full
satisfaction of Engineer-in-Charge.
4352.00 1408.00 5760.00 15mm internal diameter 165.00 Metre 950400.00
2048.00 768.00 2816.00 20mm internal diameter 190.00 Metre 535040.00
1564.00 558.00 2122.00 50mm internal diameter 280.00 Metre 594160.00
720.00 360.00 1080.00 100mm internal diameter 600.00 Metre 648000.00
Or
Providing and fixing Chlorinated polyvinyl chloride NS
(CPVC) pipe having thermal stability for hot & cold water
supply, including all CPVC plain and brass threaded
fittings, including fixing the pipe with clamps at 1.00M
spacing. This includes jointing of pipes and fittings with
one step CPVC solvent cement and including testing of
joints complete as per direction of Engineer-in-Charge
4352.00 1408.00 5760.00 20mm internal diameter 142.00 Metre 817920.00
2048.00 768.00 2816.00 25mm internal diameter 194.00 Metre 546304.00
18 Painting on GI pipes and fittings with two coats N.S.
of anti corrosive bitumastic paint of approved
quality complete in all respect as per full
satisfaction of Engineer-in-Charge.
4352.00 1408.00 5760.00 15 mm internal diameter 2.00 Metre 11520.00
2048.00 768.00 2816.00 20 mm internal diameter 2.50 Metre 7040.00
1564.00 782.00 2346.00 50 mm internal diameter 4.50 Metre 10557.00
720.00 360.00 1080.00 100 mm internal diameter 9.00 Metre 9720.00
19 Providing and fixing, jointing union coupling ISI N.S.
marked of approved make in GI pipe line complete
in all respect as per full satisfaction of Engineer -in-
charge.
512.00 256.00 768.00 15 mm internal diameter 60.00 Each 46080.00
768.00 384.00 1152.00 20 mm internal diameter 100.00 Each 115200.00

Contractor Witness Executive Engineer


111

56.00 16.00 72.00 50 mm internal diameter 260.00 Each 18720.00


20 Providing and fixing in position gun metal gate N.S.
valve with C.I. wheel of approved quality
screwed end (of approved make and ISI
marked) complete in all respect as per full
satisfaction of Engineer-in-Charge.
52.00 16.00 68.00 50 mm internal diameter 700.00 Each 47600.00
16.00 8.00 24.00 100 mm internal diameter 900.00 Each 21600.00
21 Providing and fixing jointing (ISI marked) gun N.S.
metal ball valve (heaavy pattern) of apaproved
make on GI pipe line laid in the ground or
inside building including cost of ball valve and
materialscomplete in all respect as per full
satisfaction of Engineer-in-Charge.
4.00 2.00 6.00 50 mm internal diameter 300.00 Each 1800.00

Contractor Witness Executive Engineer


112

22 Providing and fixing in position best quality N.S.


Indian make European type water closet suite
of approved make consisting of :
i) Wash down closet set Virreous Chinaware
with 'P' or 'S' strap with or without vent, as
required suitable joints for closet inlet including
cost of cement concrete 1:2:4 under and
around 'P' & 'S' strap and W.C. pan as
required.
ii) 7.5 Litres capacity PVC low level dual
button/ lever flushing cistern including all other
required necessary fittings and fixtures
complete as per full satisfaction of the
Engineer-in-Charge.
iii) One piece seat and lid in hollow black or
white plastic fitted with rubber buffers (to the
approval of Engineer-in-Charge)
iv) 32mm dia PVC flush pipe complete with
fittings as required:
256.00 64.00 320.00 (b) White 2105.00 Each 673600.00

Total 8986664.00

1 Cost with G.I. pipe Rs. 7622440.00


15mm & 20mm
2 Cost with CPVC Rs. 7501224.00
pipe 20mm &
25mm

Contractor Witness Executive Engineer


113

PART -C ELECTRICAL WORK (INTERNAL)

S.No Qty. Total DESCRIPTION OF ITEMS RATE (in Rs.) UNIT HSR/ NS Total Cost
.
For 128 For 64
Type-A Type-B
flats flats
1 256.00 128.00 384.00 Supply and erection of blanking sheet 3.60 Each 31.16 1382.00
in existing distribution board
2 Miniature circuit breaker and
isolator

Supply and erection of miniature circuit


breaker / isolator 240/415 V in the
existing distribution board including
making necessary connection.
(a) Miniature Circuit Breakers of 9
K. A. breaking capacity.
1536.00 768.00 2304.00 ii) 6 Amp to 32 Amp (Single pole) 123.50 Each 31.17(ii) 284544.00
128.00 64.00 192.00 iii) 40 Amp to 63 Amp.(Triple Pole with 648.70 Each 31.17(iii) 124550.00
Neutral)
128.00 64.00 192.00 (iii) (B) 40 Amp (Four Pole) 423.80 Each 31.17(b)(i) 81370.00
3 Supply & Erection of FITTINGS AND
ACCESSORIES.
128.00 64.00 192.00 Electrical Buzzer of 220/230 volts A.C. 54.00 Each 31.18(viii) 10368.00
bakelite with double coil.

4352.00 2176.00 6528.00 Bakelite Angle/ Straight Button holder 18.60 Each 3118(xi) 121421.00
large size.

Contractor Witness Executive Engineer


114

384.00 192.00 576.00 Supply and erection of hexagonal 78.90 Each 31.18(xxvi 45446.00
M.S. box 1.60 mm thick having each )
side 8 cm., 7.5 cm., deep top covered
with M.S. lid by means of screws
including 10 mm dia. 30 cm. long M.S.
rod made into suitable suspension
hook and erected in RCC slab for
errection of fan the bottom covered
with 3mm thick Bakelite sheet with
suitable holes painting etc. complete
with all labour and material required to
complete the job.
Note : Fan box Zinc coated no extra
payment will be made on this account.

4 EARTHING
128.00 64.00 192.00 i) Earthing with G.I. earth pipe 4.5 1701.00 Each 31.22(i) 326592.00
Mtr. Long and 40 mm dia. With
masonry enclosures on the top etc. as
required.

128.00 64.00 192.00 ii) Extra for using salt and 562.50 Each 31.22(ii) 108000.00
charcoal/coke for pipe earth electrode
as required.

Contractor Witness Executive Engineer


115

512.00 256.00 768.00 iii) Earthing with G.I. earth plate 600 2038.50 Each 31.22(iii) 1565568.00
mm X 600 mm X 6 mm thick including
accessories and providing masonry
enclosures with cover plate having
locking arrangement and watering pipe
etc. (But without charcoal or coke and
salt) complete as required.
512.00 256.00 768.00 iv) Extra for charcoal or coke and salt 837.00 Each 31.22(v) 642816.00
for GI plate or copper plate earth
electrode.
1280.00 640.00 1920.00 v) Providing and laying earth 110.25 Metre 31.22(xii) 211680.00
connections from earth electrode with
4 mm dia. G.I. wire in 15 mm dia. G.I.
pipe from earth electrode as required.
3200.00 1600.00 4800.00 vi) Providing. and fixing 25 mm X 5 mm 91.35 Metre 31.22(xv) 438480.00
G.I. strip on surface or in recess for
connections etc. as required with all
labour and material.
1280.00 640.00 1920.00 vii) Providing and fixing 4 mm dia. G.I. 15.30 Metre 31.22(xvi) 29376.00
wire on surface or in recess for loop
earthing as required.
5 512.00 256.00 768.00 Excavation earth pit 180 cm round at 762.00 Each 31.23(ii) 585216.00
top and 90 cm at bottom 4.5 metres
deep and refilling the same in plains
including supply of necessary charcoal/
coke and salt mixture.

Contractor Witness Executive Engineer


116

6 128.00 64.00 192.00 Supply and erection of 75 mm x 75 mm 41.40 Each 31.35(vii) 7949.00
x 60 mm deep M.S. box for telephone
and intercommunication system
including 2 pin 5 amp socket including
cost of bakelite sheet.
7 Supply and errection of PVC 31.40
unsheathed copper conductor cable
single core 1100 volts grade in pipe of
suitable size excluding cost and
errection of pipe.
Note: Equivalent size of multi
stranded cable ISI wire will be used,
on this account, no extra payment
will be made.

15360.00 7680.00 23040.00 i) Size 1.50 Sq. mm ( 3/0.81 mm) 11.22 Metre 258509.00
1280.00 640.00 1920.00 iii) Size 4.00 Sq. mm (7/0.85 mm) 26.95 Metre 51744.00
1280.00 640.00 1920.00 iv) Size 6.00 Sq. mm ( 7/1.05 mm) 39.16 Metre 75187.00
15360.00 7680.00 23040.00 iv) Size 10.00 Sq. mm ( 7/1.35 mm) 55.00 Metre 1267200.00
1280.00 640.00 1920.00 iv) Size 16.00 Sq. mm ( 7/1.70 mm) 92.07 Metre 176774.00
8 Supply and erection of double door 31.41 (vi)
sheet steel enclosure distribution board
suitable for MCBs and ELCBs etc.
recessed in wall including bonding to
earth with all labour and material
required to complete the job in all
respect upto to the entire satisfaction
of the Engineer-in-charge of the work.

Contractor Witness Executive Engineer


117

128.00 64.00 192.00 8-way,T.P. & N. (Horizontal) (8+24) 2310.00 Each 443520.00
9 Supplying and Erection double pole/ 31.42(xiv)
four pole residual current circuit
breaker (RCCB/ELCB) suitable for
operation on 240/ 415V, 50 Hz, AC
supply installed in existing sheet steel
enclosures including making necessary
connections and bonding to earth with
all labour and material required to
complete the job in all respect upto the
entire satisfaction of the engineer-in-
charge of the work.
128.00 64.00 192.00 40A/415V 4 pole ELCB with 100 mA 1760.00 Each 337920.00
sensitivity
10 Supply and erection of PVC conduit 31.44(b)
pipe ISI marked (medium) recessed in
wall/ ceiling etc including cost of PVC
bends, inspection box and all other
material required to complete the job in
all respect upto the entire satisfaction
of Engineer-in-charge of the work.
10880.00 5440.00 16320.00 i) 25 mm dia. 40.70 Metre 664224.00

Contractor Witness Executive Engineer


118

11 Supply and erection of PVC conduit 31.58


pipe ISI marked (Medium ) recessed in
wall / ceiling etc. including the cost of
PVC bends, inspection boxes, iron
hooks & cement concrete etc.
complete up to the entire satisfaction of
Engineer –in- charge of work.

2304.00 1152.00 3456.00 i) PVC pipe 32 mm dia. 45.00 Metre (i) 155520.00

8320.00 4160.00 12480.00 ii)PVC pipe 45 mm dia. 56.00 Metre (ii) 698880.00

12 Providing and fixing modular type 31.56


accessories of approved make in
existing box including fixing and
making necessary connection,
compolete in all respect.
708.00 384.00 1092.00 Blinking plate 25.00 Each 27300.00

13 Providing and fixing GI concealed sheet 31.57


metal boxes with inner outer face plate
including cocealing the box in wall and
fixing in position with inner plate and face
plate with all labour and material required
for job complete in all respect.

512.00 256.00 768.00 1& 2 Modules 101.00 Each 77568.00

Contractor Witness Executive Engineer


119

14 Wiring in 1.5 Sq.mm (22/0.30mm) PVC N.S.


insulated unsheathed multistranded
copper conductor cable ISI marked
1100 volts grade as per IS-694 in rigid
PVC conduit pipe ISI Medium IS-9537
including bends, MS Round inspection
boxes with with all accessories,
including ISI Modular Switch/socket,
bell push step type fan regulator, MS
Round junction box & covered with
1.5mm thick Baklite sheet, electronic
step type (socket size) fan regulator,
cutting and refilling the chases
complete in all respect to complete the
job.
Note: Inner and outer modular face
plate will be provided in place of
1.50mm thick bakelite sheet no extra
payment will be made.

Measurement: As classified for the


Fan, Light, Bell, Double Control light,
5A socket & 15Amp. Socket etc. i.e
short, medium, long as per Chapter 31
Condition No.vii

A) Fan Point

128.00 64.00 192.00 i) Short point 605.00 Each 116160.00


128.00 64.00 192.00 ii) Medium point 753.00 Each 144576.00
128.00 64.00 192.00 iii) Long point 915.00 Each 175680.00

Contractor Witness Executive Engineer


120

B) LIGHT POINT
640.00 320.00 960.00 i) Short point 341.00 Each 327360.00
1536.00 768.00 2304.00 ii) Medium point 471.00 Each 1085184.00
2176.00 1088.00 3264.00 iii) Long point 623.00 Each 2033472.00

C) LIGHT POINT TWIN CONTROL

256.00 128.00 384.00 i) Short point 375.00 Each 144000.00


256.00 128.00 384.00 ii) Medium point 505.00 Each 193920.00
256.00 128.00 384.00 iii) Long point 657.00 Each 252288.00

D) CALL BELL POINT


128.00 64.00 192.00 Long point 665.00 Each 127680.00
E) 5 PIN 5 AMP PLUG POINT
COPPER WIRE including earthing
3rd pin with 1.5 sq mm. (22/0.30mm)
PVC insulated unsheathed copper
wire.
1280.00 640.00 1920.00 i) Short point 377.00 Each 723840.00
1280.00 640.00 1920.00 ii) Medium point 525.00 Each 1008000.00
512.00 256.00 768.00 iii) Long point 674.00 Each 517632.00
F) 6 PIN 15 AMP PLUG POINT (in
4Sq.mmCopper conductor Cable
including earthing 3rd pin with 1.5
sq mm. (22/ 0.30mm) PVC insulated
unsheathed copper wire.

256.00 128.00 384.00 i) Short point 505.00 Each 193920.00

Contractor Witness Executive Engineer


121

256.00 128.00 384.00 ii) Medium point 664.00 Each 254976.00


384.00 192.00 576.00 iii) Long point 837.00 Each 482112.00
15 128.00 64.00 192.00 Supply and Erection of generator 9050.00 Each N.S. 1737600.00
backup relay 1 KW to 1.5 KW with
Energy Meter standard quality as
required complete in all respect as per
satisfaction of Engineer-in-charge.
Make : L & T, Legrend Schneider.
Total 18337504.00

Contractor Witness Executive Engineer


122

ELECTRICAL WORKS
Common Area Services Type-A and Type-B Flats

S.No Qty. Total DESCRIPTION OF ITEMS RATE (in Rs.) UNIT HSR/ NS Total Cost
.
For 128 For 64
Type-A Type-B
flats flats
1 Supply and erection of moulded case
circuit breaker on wall or on existing
pedestal including bonding to earth and
necessary connections.
32.00 16.00 48.00 i) 100 Amp. To 220 Amp. 415 V 10 6793.60 Each 31.12( 326093.00
K.A. 3 phase. c)(ii)
16.00 8.00 24.00 i) 300 Amp. To 400 Amp. 415 V 35 16803.20 Each 31.12(iv) 403277.00
K.A. 3 phase.
2 Supply and erection of M.S. angle iron
frame duly welded for housing M.S.
sheet & main switches etc. on it, fixed
on wall by means of suitable size of rag
bolts with cement concrete, duly
painted with three coats of approved
paint including one coat of red oxide.
16.00 8.00 24.00 i) Size 40 mm x 40mm x 6 mm 162.75 Mtr 31.13(ii) 3906.00
3 16.00 8.00 24.00 Supply and erection of 3mm thick mild 1179.50 Sqm 13.14 28308.00
steel sheet duly welded on existing
M.S. angle iron frame for fixing the
main switches etc. as required, duly
painted with three coats of approved
paint including one coat of red oxide.

Contractor Witness Executive Engineer


123

4 72.00 36.00 108.00 Supply and erection of blanking sheet 3.60 Each 31.16 389.00
in existing distribution board.
5 Supply and erection of miniature circuit
breaker / isolator 240/ 415 V in the
existing distribution board including
making necessary connection:-
(a) Miniature Circuit Breakers of 9 K.
A. breaking capacity.
152.00 76.00 228.00 i) 6 Amp to 32 Amp ( Single pole) 123.50 Each 31.17(ii) 28158.00

40.00 20.00 60.00 (iii) 40 Amp to 63 Amp. (Siingle Pole 312.00 Each 31.17(iii)( 18720.00
with Neutral) a)

8.00 4.00 12.00 (iii) 40 Amp to 63 Amps. (Triple Pole 648.70 Each 31.17(iii)( 7784.00
with Neutrarl) a)

6 Supply & Erection of FITTINGS AND


ACCESSORIES.

640.00 320.00 960.00 Bakelite Angle/Straight Button holder 18.60 Each 31.18(xi) 17856.00
large size.

Contractor Witness Executive Engineer


124

7 64.00 32.00 96.00 Supply and erection of hexagonal M.S. 78.90 Each 31.18(xxvi 7574.00
box 1.60 mm thick having each size 8 )
cm., 7.5 cm., deep top covered with
M.S. lid by means of screws including
10 mm dia. 30 cm. long M.S. rod made
into suitable suspension hook and
erected in RCC slab for errection of fan
the bottom covered with 3mm thick
Bakelite sheet with suitable holes
painting etc. complete with all labour
and materiarls required to complete the
job.
Note: Fan box zink coated No extra
payment will be made on this account.
8 Supply and erection of pipe for wiring
purpose including bends inspection
boxes etc. where necessary and
painting as required.
16.00 8.00 24.00 Galvanized iron pipe 40mm dia 273.15 Mtr 31.21(xii) 6556.00
flushed.
16.00 8.00 24.00 Galvanized iron pipe 50mm dia 347.85 Mtr 31.21(xiii) 8348.00
flushed.
9 EARTHING

Contractor Witness Executive Engineer


125

16.00 8.00 24.00 i) Earthing with G.I. earth pipe 4.5 Mtr. 1701.00 Each 31.22(i) 40824.00
Long and 40 mm dia. With masonry
enclosures on the top etc. as required.
16.00 8.00 24.00 ii) Extra for using salt and 562.50 Each 31.22(ii) 13500.00
charcoal/coke for pipe earth electrode
as required
24.00 12.00 36.00 iii)Earthing with GI earth plate 600mm 2038.50 Each 31.22(iii) 73386.00
x 600mm x 6mm thick including
accessories and providing masonry
enclosures with cover plate having
locking arrangement and watering pipe
etc (but without charcoal or coke and
salt) complete as required.
24.00 12.00 36.00 iv) Extra for charcoal or cock and salt 837.00 Each 31.22(v) 30132.00
for GI plate or copper plate earth
electrode.
480.00 240.00 720.00 (v) Providing and laying earth 110.25 Mtr 31.22(xii) 79380.00
connections from earth electrode with 4
mm dia GI wire in 15mm dia GI pipe
from earth electrode as required.

Contractor Witness Executive Engineer


126

440.00 220.00 660.00 (vi) Providing and fixing 25mm X 91.35 Mtr 31.22(xv) 60291.00
5mm GI strip on surface or in recess for
connections etc. as required with all
labour and material.
200.00 100.00 300.00 (vii) Providing and fixing 4mm dia GI 15.30 Mtr 31.22(xvi) 4590.00
wire on surface or in recess for loop
earthing as required.

600.00 300.00 900.00 xix) Supply and erection of 200 x 3mm 63.45 Mtr 31.22(xix) 57105.00
thick G.I. tape fixede ith suitable G.I.
stapples of same size.

10 24.00 12.00 36.00 Excavation earth pit 180cm round at 762.00 Each 31.23(ii) 27432.00
top and 90 cm at bottom 4.5 meter deep
and refilling the same in plains i/c
supply of necessary charcoal/ cock and
salt mixture.

11 24.00 12.00 36.00 Providing standard watering tank 855.00 Each 31.24(v) 30780.00
including down pipe and C.I. cover
with locking arrrangement.

8.00 4.00 12.00 Supply and erection of 25mm dia meter 486.00 Each 31.24(viii) 5832.00
1.5 meter long lighting GI tube rod
tapered into a point at the top with
16cmx16cmx3mm thick GI base plate
and necessary nuts and bolts with
washers.

Contractor Witness Executive Engineer


127

16.00 8.00 24.00 Providing and fixing testing joint made 30.15 Each 31.24(ix) 724.00
of 20mm x 3mm thick GI strips 125mm
long with 4 Nos. GI bolts and nuts with
washer complete.
Wires and Cables
12 28.00 14.00 42.00 Supply and erection of caution notice 4.60 Job 31.35(iii) 193.00
plate in three languages.
13 Supply and erection PVC unsheathed 31.40
copper conudctor cable single core
1100 volts grade in pipe of suitable size
excluding the cost and erection of pipe.
Note : Equivalent size of multi-
standard cable ISI wire will be used,
on this account, no extra payment
will be made.
800.00 400.00 1200.00 i) Size 1.50 Sq.mm (3/ 0.81)mm 11.22 Mtr (i) 13464.00
200.00 100.00 300.00 iii) Size 4.00 Sq.mm (7/ 0.85)mm 26.95 Mtr (iii) 8085.00
200.00 100.00 300.00 iv) Size 6.00 Sq.mm (7/ 1.05)mm 39.16 Mtr (iv) 11748.00
200.00 100.00 300.00 v) Size 10.00 Sq.mm (7/ 1.35)mm 55.00 Mtr (v) 16500.00
160.00 80.00 240.00 vi) Size 16.00 Sq.mm (7/ 1.70)mm 92.07 Mtr (vi) 22097.00
14 Supply and errection of double door 31.41
sheet steel enclosure distribution board
suitable for MCBs and ELCBs etc.
recessed in wall including bonding to
earth with all labour and material
required to complete the job in all
respect upto to the entire satisfaction of
the Engineer-in-charge of the work.
32.00 16.00 48.00 8-way, SP. & N. (Horizontal) 957.00 Each (ii) 45936.00
8.00 4.00 12.00 12-Way SP & N (Horizontal) 1221.00 Each (iii) 14652.00

Contractor Witness Executive Engineer


128

8.00 4.00 12.00 8 Way TP & N (Horizontal) (8+24) 2310.00 Each (vi) 27720.00
15 Supplying and Erection of double pole/four 31.42(xiv)
pole residual current circuit breaker
(RCCB/ELCB) suitable for operation on
240/415V, 50 Hz, AC supply installed in
existing sheet steel enclosures including
making necessary connections and bonding
to earth with all labour and material
required to complete the job in all respect
upto the entire satisfaction of the engineer-
in-charge of the work.
8.00 4.00 12.00 40A/415V 4 pole 100 mA sensitivity 1760.00 Each 21120.00

16 Supply and erection of PVC conduit 31.44(b)


pipe ISI marked (medium) recessed in
wall/ceiling etc including cost of PVC
bends, inspection box and all other
material required to complete the job in
all respect upto the entire satisfaction of
Engineer-in-charge of the work.
920.00 460.00 1380.00 b) 25 mm dia. 40.70 Mtr 56166.00

Contractor Witness Executive Engineer


129

17 20.00 10.00 30.00 Supply and erection of weathr proof 890.00 Each 31.50 26700.00
MS box size 20cm x 30cm of 16G and
covered with MS sheet hinged cover
having locking arrangement housed in
1:2:4 CC muff of size 40cm dia 55cm
high including cost of PVC pipe of
suitable size for incoming and outgoing
cable, 4 copper bars of size 20mm x
3mm, 125mm duly tined, insulated and
supported with porcalain insulator, 2
No. 16A 416 V Kit-Kat fixed in the MS
box including painting etc. complete
the job in all respet upto the entire
satisfaction of Engineer-in-Charge of
work. Note: The MS box will be fixed
in awall on gate pillar without CC muff
on size 40cm dia 55cm high. No
payment will be deducted on this
account.
18 Supply and erection of PVC conduit 31.58
pipe ISI marked (medium) recessed in
wall/ ceiling etc including cost of PVC
bends, inspection boxes iron hooks and
cement concrete etc. complete in all
respect upto the entire satisfaction of
Engineer-in-charge of the work.

1280.00 640.00 1920.00 i) PVC pipe 32 mm dia. 45.00 Mtr (i) 86400.00
1280.00 640.00 1920.00 ii) PVC pipe 40 mm dia. 56.00 Mtr (ii) 107520.00

Contractor Witness Executive Engineer


130

19 Providing and fixing modular type 31.56


accessories of approved make in
existing box including fixing and
making necessary connections,
complete in all respect.

120.00 60.00 180.00 Blinking plate 25.00 Each 4500.00


20 Providing and fixing GI concealed 31.57
sheet metal boxes with inner and outer
face plate including concealing the box
in wall and fixing in position with inner
plate and face plate with all labour and
material required for the job complete
in all respects.

40.00 20.00 60.00 1 & 2 Modules 101.00 Each 6060.00

Contractor Witness Executive Engineer


131

21 Supply installation testing and


commissioning of Wall / free standing
floor mounting dust & vermin proof
compartmentalized cubical panel made
out of 2mm thick CRCA sheet,
required hardware 3mm thick Bakelite
sheet provided all along the bus bar and
cable alley separating switches
compartment and supporting suitable
channel duly painted by 2 coat of Zinc /
Red oxide primer followed by 2 coats
140.00 70.00 210.00 of powder coating in grey or required 2160.00 P.Sqm 31.63 453600.00
shade after rinsing. The panel having
PU/ Neoprene rubber gasket of not less
than 3 mm thickness separate
detachable gland of not less than 3 mm
thickness separate detachable gland
plate MS base channel hinged door
with inter locking arrangement for
equipment / switch wear.

Contractor Witness Executive Engineer


132

Transparent acrylic sheet shall be


provided in front of bus bar
compartment to prevent direct access to
bus bar Bakelite sheet 3 mm thick for
separately cable alley to BBC from
switch chamber Extended solid copper
bars up to cable alleys shall be
provided for outgoing connection
which shall be paid as extra items. Side
wall and cable alley compartments
shall be having bolted type doors with
detachable extension type structure.
The panel will be complete with control
wiring (copper) and fuse protection
(only outer area on all sides shall be
measured).

22 200.00 100.00 300.00 Supplying and fixing of copper bus bar 525.00 P.kg 31.64 157500.00
duly tinned by means of SMC/DMC
type insulator high tensile nuts and
bolts spring washers fixing to same in
existing panel including bending,
cutting in required shape and size and
insulation with colour coding heat
shrinkable PVC insulation complete in
all respect.

Contractor Witness Executive Engineer


133

23 Supply & fixing of rotary handle for 31.66


on/off operation of existing MCCB in
the LT panel including fixing the same
in position with all labour and material
required to complete the job in all
respect.

32.00 16.00 48.00 i) Rotary handle up to 125 A. MCCB 675.00 Each (i) 32400.00

16.00 8.00 24.00 ii)Rotary handle above 125 A. MCCB 790.00 Each (ii) 18960.00

24 Supply & erection of mark double 31.67


walled corrugated (DWC) HDPE pipe
laid 1 mtr below ground level including
digging and refilling of earth including
cost of suitable size socket/coupler for
HDPE pipe including the cost of labour
and material required to complete the
job in the respect upto the entire
satisfaction of Engineer-in-Charge of
the work.

1360.00 680.00 2040.00 i) HDPE pipe 90/75mm outer dia / 135.00 Mtr (ii) 275400.00
inner dia

1360.00 680.00 2040.00 ii)HDPE pipe 145/123mm outer dia / 235.00 Mtr (iii) 479400.00
inner dia

Contractor Witness Executive Engineer


134

25 Wiring in 1.5 Sq.mm (22/0.30mm) PVC N.S.


insulated unsheathed multistranded
copper conductor cable ISI marked
1100 volts grade as per IS-694 in rigid
PVC conduit pipe ISI Medium IS-9537
including bends, MS Round inspection
boxes with with all accessories,
including ISI Modular Switch/socket,
bell push step type fan regulator, MS
Round junction box & covered with
1.5mm thick Baklite sheet, electronic
step type (socket size) fan regulator,
cutting and refilling the chases
complete in all respect to complete the
job.
Note: Inner and outer modular face
plate will be provided in place of
1.50mm thick bakelite sheet no extra
payment will be made.

Measurement: As classified for the


Fan, Light, Bell, Double Control light,
5A socket & 15Amp. Socket etc. i.e
short, medium, long as per Chapter 31
Condition No.vii
A) Fan Point

24.00 12.00 36.00 ii) Medium point 753.00 Each 27108.00

32.00 16.00 48.00 iii) Long point 915.00 Each 43920.00

B) LIGHT POINT

128.00 64.00 192.00 i) Short point 341.00 Each 65472.00

Contractor Witness Executive Engineer


135

96.00 48.00 144.00 ii) Medium point 471.00 Each 67824.00

160.00 80.00 240.00 iii) Long point 623.00 Each 149520.00

C) LIGHT POINT TWIN CONTROL

160.00 80.00 240.00 i) Short point 375.00 Each 90000.00

240.00 120.00 360.00 ii) Medium point 505.00 Each 181800.00

112.00 56.00 168.00 iii) Long point 657.00 Each 110376.00

D) CALL BELL POINT


4.00 2.00 6.00 Long point 665.00 Each 3990.00
E) 5 PIN 5 AMP PLUG POINT
COPPER WIRE including
earthing 3rd pin with 1.5 sq mm.
(22/0.30mm) PVC insulated
unsheathed copper wire.
4.00 2.00 6.00 i) Short point 377.00 Each 2262.00
4.00 2.00 6.00 ii) Medium point 525.00 Each 3150.00
8.00 4.00 12.00 iii) Long point 674.00 Each 8088.00
F) 6 PIN 15 AMP PLUG POINT (in
4Sq.mmCopper conductor Cable
including earthing 3rd pin with 1.5
sq mm. (22/ 0.30mm) PVC insulated
unsheathed copper wire.
20.00 10.00 30.00 iii) Long point 837.00 Each 25110.00
Total 3945686.00

Contractor Witness Executive Engineer


136

PART-B
Detailed Measurement of External Development in Sectro-56, 56A (1.56 Acres), Faridabad.

1. ROAD WORK
2. WATER SUPPLY
3. SEWERAGE SYSTEM
4. LANDSCAPING AND HORTICULTURE
5. RAIN WATER HARVESTING
6. BOUNDARY WALL

Contractor Witness Executive Engineer


137

Detailed Measurements of External Development in Sector-56 (1.56 Acres), Faridabad

ROAD WORK
Sl.No Qty Description Rate Unit HSR Total Cost
1 5124.00 Earth filling and laying brought from outside the campus with irrespective of 170.00 cum N.S. 871080.00
lead including loading, unloading and carriage, royality and acompaction etc.
and laid in 25cm layers in roads and campus including reaming, watering and
consolidation complete laid as per PWD specification including handling earth
upto 30 mtr complete in all respect to the entire satisfaction of the Engineer-in-
Charege.
2 2061.60 Preparation of sub grade, including trenching, rough dressing of spoil, final 434.52 100 24.1 8958.00
dressing of earth to given levels and camber, watering, roiling with road roller Sqm
and compacting the bed
3 412.32 Providing and laying 200mm thick granular sub base consisting of filer layer 530.00 cum NS 218530.00
conforming to Table-400.1 grading-III of MORT&H 5th edition, mixing in
mechanical mkx plant at OMC, carriage of mix material to the site of work,
spreading in unform lahyer with motar grader on prepared surface and
compacting with vibratory power roller to achieve desired density complete as
per clause No.401 of MORT&H specification. Note-I. Only crushed matal
material should be used. No local earth sand shall be used. The material finear
than 425 nucron shall have zero plasticity Inded (P1). 2. Material and operation
manufacturing shall be aproved by Engineer.

4 3339.85 Providing and laying 80mm thick interlocking paver blocks of all shapes and 495.00 Sqm 10.159 1653226.00
colours in design mix M-35 or head of 30mm thick fine sand complete in all
respect.
Total 2751794.00

Contractor Witness Executive Engineer


138

WATER SUPPLY
Sl.No Qty Description Rate Unit HSR Total Cost
1 175000 Construction of RCC underground water storage tank as per design (structural 4.78 Litre NS 836500.00
design to be got evolved by the contractual agency duly vetted by Govt.
Institute i.e NIT/IIT/PEE) including cost of cement concrete, steel
reinforcement side apron, gate, glazed ceramic tiles on wall and floor,
aluminum ladders, PVC foot rest DI man holes covers double seal sump, DI
cowls and contingent item & thereto complete in all respect as per the full
satisfaction of the Engineer-in-charge. Size of tank 9.00x6.00x3.55 mtr with
free board of 0.30 mtr.( size of tank UGSR:- 9mx6mx3.25m= 175.50 cum) x 1000
ltr = 175500 ltrs.
2 2.00 Providing and installing submersible pumping set for UGSR ISI marked 100500 nos NS 201000.00
submersible motor sets should be directly coupled with submersible motor as
per BIS specification No IS: 8034:1989 as amended upto date for pumps and
IS:9283:1995 (As amended upto date) for motors. The pump motors sets
should be capable of pumping leer, fresh cold water having characteristics as
specification in clauses 4 of IS: 8034:1989 and clause 4.1 of Is 9283:1995. Each
pump motor set shall be supplied with 50 meter joint free, double length PVC
insulated and PVC sheeted, flexible 3 crore flat type submersible cable dully
ISI marked with copper conductor confirming to BIS specification No. IS:694 :
1900 (as amended upto date) The size of the copper conductor should be
adequate for continuous use under water and in air. The material of
construction should be as per clauses 6.2 (table-1) of IS 8034:1989 (As
amended upto date). The nominal speed should correspond to 2 pole motors
(2800 to 3000) rev/min (*Synchronous). Approximate Horse power of motor
=10 HP. Capable of delivering 450 LPM water against 501 M head driven by
electric motor along with cable of make (KSB/ Kriloskar /Crompton) & cubical
panel board fitted with push button starter of reputed make such as Kriloskar,
Crompton, suitable capacity completed with voltmeter, Ampere meter,
Capacitor Bank, Buss bass of suitable size, double casting including material
installation charges & 100 mm die GI delivery pipe B class in to flanges 10 mtr
long including all other arrangements required for commissioning to the enter
satisfaction of -In-charge with delivery pipe.

Contractor Witness Executive Engineer


139

3 1.00 Providing and fixing in position delivery pipes consisting of 4 nos base plates, 35300 nos NS 35300.00
2 nos 150mm dia CI bend, 1 nos non returnable valve 150mm dia, 100mm dia
DI pipe 3 mtr long, 150 mm dia sluice valve complete in all respect i/c jointing
& fixing in position complete to the entire satisfaction of the Engineer-in
Charge.
4 392.00 Providing stringing out 100MM DIA D.I pipes ISI marked laying the same in 880.00 mtr NS 344960.00
trenches to correct alignment & gradient including cutting jointing & testing
complete in all respects including excavation of trenches for pipe line.
Including cost of rubber tighten rings. (DI pipe K-7 class IS: 8329-2000 in
standard length 4.0 to 6.0 mtrs.)
5 6.00 Providing and fixing cast iron double flanged sluice valves PN -1.6 marked 4067.80 each 28.10 24407.00
with IS: 14846 including nuts and bolts marked with IS: 1363, rubber sheet
marked with IS: 638. Carriage, loading, unloading, stacking, handling, re-
handling etc. complete in all respect to the satisfaction of the Engineer-in-
charge.(Makes : ARKO,VENUS,LEADER,BIR PANJA UPADHAY.
100mm i/d
6 6.00 Providing, fixing and jointing standard underground fire hydrants fixed with 5800.00 each NS 34800.00
socket or flange conforming to IS: 909-1992 as amended upto date consisting
of C/1 body brass spindle GM outlet screwed type and provided with eternal
round thread, covered with CI cap attached to the body with chain fitted over
the water main fire hydrant tee including cost of nuts, bolts & rubber packing
etc. complete in all respect.
100 mm i/d
7 1.00 Providing and fixing CAST IRON KINETIC AIR VALVES of size 100 mm 3407.80 each 28.13A 3408.00
MARKED WITH IS : 14845, including carriage, loading, unloading, stacking,
handling, re-handling etc. drilling, tapping screws in valves connections
complete in all respects to the satisfaction of Engineer-in-charge.

8 3.00 Providing and fixing CAST IRON KINETIC AIR VALVES of size 80 mm MARKED 3106.40 each 28.13A 9319.00
WITH IS : 14845, including carriage, loading, unloading, stacking, handling, re-
handling etc. drilling, tapping screws in valves connections complete in all
respects to the satisfaction of Engineer-in-charge.
9 6.00 Construction of brick masonary 9" thick S.V. Chamber inside size 1.0x1.0x1.0 6670.00 each NS 40020.00
mtr in 1:5 cement sand motor & 12mm thick cement plaster 1:3 with floating
coat complete with standard C.I. box fixed in R.C.C. top slab including
excavation, foundation concrete and steel complete in all respect.

Contractor Witness Executive Engineer


140

10 6.00 Construction of brick masonary 9" thick fire hydrant Chamber inside size 6670.00 each NS 40020.00
1.0x1.0x1.0 mtr in 1:5 cement sand motor & 12mm thick cement plaster 1:3
with floating coat complete with standard C.I. box fixed in R.C.C. top slab
including excavation, foundation concrete and steel complete in all respect.

11 22.00 Providing and fixing RUBBER SHEET 3mm THICK MARKED WITH IS:638 for 14.30 each 28.51 315.00
jointing flanged pipes, specials etc. including making of holes etc.complete in
all respect to the satisfaction of Engineer in charge.
For pipe size 100mm dia

12 4.00 Supplying GI PIPES CLASS B MARKED WITH IS:1239 IN 3.05M LENGTH,their 2360.60 each 28.52 9442.00
threading and weilding with flanges(Heavy Duty) on both sides,jointing with
nuts and bolts marked with IS:1363, rubber gaskets, mqarked with IS:638
JOINTING WITH PUMPING MACHINERY AND LOWERING INTO TUBEWELLS
and testing including carriage,loading,unloading etc. complete in all respect
to the satisfaction of engineer in charge.
For pipe size 100mm dia

13 22.00 Providing and fixing Cast Iron Detachable Joints class-15 marked with IS:8794 242.00 each 28.56 5324.00
for use with A.C/P.V.C/C.I Pipes complete with 2 nos. rubber rings marked with
IS:5382& IS:1363 including carriage,loading,unloading etc complete in all
respects to the satisfaction of engineer in charge.(Excavation will be paid
seperately)
100mm i/d C/D joint

14 150.00 Supplying MS bolt of required sizes with nuts and washers complete 84.00 Kg. 18.15 a 12600.00

15 350.00 Providing and fixing DI Specials for pipe size 100 mm i/d socketed/flanged 75.00 each NS 26250.00
confirming to IS specifications such as Tees, bends, reducers, sokets, plugs,
tail piece etc.

Total 1623665.00

Contractor Witness Executive Engineer


141

SEWERAGE SYSTEM
Sl.No Qty Description Rate Unit HSR Total Cost
1 Earth work in excavation in foundation, trenches of underground structure,
sullage drains etc. and other similar works in ordinary soil including dressing
bottom and sides, to correct levels and templates, cutting of trees and bushes,
dewatering of rain water, diversion of traffic, fixing and maintained of caution
boards, and night signals, crossing over trenches for access to houses,
watching, stacking of excavated soil, clear from the edge of excavation, and
subsequent filling, where required around masonry, in 15cm layers, with
compaction and disposal of surplus soil as directed within a lead of 30mtr for
depth upto 2mtr below natural ground level.(for P.H. work only)
424.57 For depth of excavation 0-2 meters below ground level 4380.40 % cum 6.7 18598.00
2 20.84 Cement concrete 1:8:16 with stone aggregate 20mm nominal size laid in the 1849.38 Cum 10.29 + 38541.00
foundation and plinth for main holes Note
2 43.42 Cement concrete 1:4:8 with stone aggregate 20mm nominal size laid in the 2310.00 Cum 10.38 100300.00
foundation and plinth for main holes

3 15.68 Cement concrete 1:1.5:3 with stone aggregate 20mm nominal size for 5966.40 Cum 10.82 + 93553.00
reinforced concrete working slabs with inclination not exceeding 25 degree 10.95 A
with horizontal, excluding steel reinforcement ,but including centering and
shuttering ,laid in position, complete in all respects
4 50.91 First class brick work laid in cement sand mortar 1:5 in foundation and plinth 2853.20 Cum 11.3 145256.00
5 220.31 12mm thick cement plaster 1:2 99.60 Sqm 15.3 21943.00
6 220.31 cement rendering on plaster 1mm thick 25.50 Sqm 15.75 5618.00
7 24.00 Fe 500 EQR TMT Steel bars for RCC, works, where not including in the 5502.30 Qtls 18.22 132055.00
complete rate of RCC including bending, binding and placing in position
complete
9 Providing salt glazed stone ware pipes grade "A" in standard length of 600mm
each pipe marked with IS:651 and their lowering, cutting, pointing and testing
as described in HSR item no.29.38,29.39,29.40 including the cost of jointing
materials as well as carriage, loading, unloading, stacking, handling, re-
handling etc., complete in all respect to the satisfaction of Engineer-in-charge
334.00 (b) 200mm i/d SW pipes 265.65 Mtr 29.95 88727.00
sewer

Contractor Witness Executive Engineer


142

10 Providing and fixing SFRC manhole covers and frames marked with IS:12592 29.94
including setting the same to correct lines and levels in 1:2 cement sand
mortar over manhole including carriage loading, unloading, stacking,
handling, re-handling etc., complete in all respects to the Engineer-in-charge
61.00 Extra Heavy Duty Set (EHD-35)560mm Clear Opening 1260.00 No. 76860.00
11 40.00 Providing and fixing plastic coated steps (steel bar embedded) for manholes 198.00 No. 29.28 7920.00
including setting the same with 1:2 cement sand mortar.

Total 729371.00

Contractor Witness Executive Engineer


143

LANDSCAPING AND HORTICULTURE


Sl.No Qty Description Rate Unit HSR Total Cost
1 480.00 Trenching in all kinds of soil upto a depth of 60 cm including removal and stacking of 16.50 cum 33.4 7920.00
serviceable materials and then disposing of by spreading and neatly leveling with in a lead of
50 meters and making up the trenched area to proper levels by filling with earth or earth mixed
with sludge or/and farmyard manure before and after flooding trench with water(excluding cost
of imported earth and sludge or farmyard manure)
2 1080.00 Rough dressing the trench ground including breaking clods 30.60 100 sqm 33.5 330.00
3 1080.00 Uprooting weeds from the trenched area after 10 to 15 days of its flooding with water including 102.00 100 sqm 33.6 1102.00
disposal of uprooted vegetation
4 900.00 Fine dressing the ground 77.40 100 sqm 33.7 697.00
5 480.00 Supplying at site of work well-decayed farm-yard manure, from any available source, approved 308.00 cum 33.1 147840.00
by the Engineer-incharge including screening and stacking
6 480.00 Spreading of sludge, farm-yard manure or/and good earth in required thickness (Cost of 11.10 cum 33.8 5328.00
sludge, farm-yard manure or/and good earth to be paid for separately)

7 480.00 Mixing earth and sludge or farm yard manure in proportion specified or as directed. 7.80 cum 33.9 3744.00
8 850.00 Grass with "Doob" grass including watering and maintenance of the lawn for 30 days or more
till the grass forms a thick lawn free from weeds and fit for moving including supplying good
earth if needed-
(i) In rows 7.5 cm apart in either direction. 241.20 100 sqm 33.10 2050.00
9 900.00 Uprooting rank vegetation and weeds by digging the area to a depth of 60 cm removing all 1297.80 100 sqm 33.11 11680.00
weeds and other growth with roots by forking repeatedly, breaking clods, rough dressing,
flooding with water, uprooting fresh growths after 10 to 15 days and then fine dressing for
planting new grass, including disposal of all rubbish with all leads and lifts.

10 480.00 Filling mixture of earth and sludge or farm yard manure in the desired proportion in trenches, 3.90 cum 33.12 1872.00
flooding with water and leveling (cost of supplying earth and sludge or farmyard manure and
mixing does not include in this rate)
11 900.00 Making lawns including ploughing and ragging with dragging with ‘swagha’ breaking of clods, 379.50 100 sqm 33.15 3416.00
removal of rubbish, dressing and supplying doob grass roots, and planting at 15 cm apart,
including supplying and spreading of farm-yard manure at the rate of 0.18 cum per 100 Sqm
12 900.00 Maintenance of lawns or turfing of slopes (rough grassing), for a period of one year including 714.60 100 33.16 6431.00
watering etc.
sq.m
13 900.00 Turfings lawns with fine grassing including ploughing, dressing including breaking 935.10 100 sqm 33.17 8416.00
of clods, removal of rubbish, dressing and supplying doob grass roots at 10 cm
apart, including supplying and spreading of farm-yard manure at the rate of 0.60 cum
per 100 sqm

14 900.00 Maintenance of lawns with fine grassing for the first year including watering etc. 1268.10 100 sqm 33.18 11413.00

Contractor Witness Executive Engineer


144

15 150.00 Planting permanent hedges including digging of trenches, 60 cm wide and 13670.10 100 sqm 33.19 20505.00
45 cm deep, refilling the excavated earth, mixed with farm-yard manure,
supplied at the rate of 4.65 cu pr 100 meters and supplying and planting
hedge plants at 30 cm apart
16 300.00 Maintaining the hedges for the first two years including 6186.00 100 sqm 33.20 18558.00
watering, etc. complete
17 100.00 Digging holes in all kinds of soil, and refilling the same, with the excavated 100.80 Each 33.21 10080.00
earth, mixed with well decayed farmyard manure (cost of well decayed farm
yard manure to be paid separately)
(i) hole 1.2 metres dia and 1.2 metres deep
18 900.00 Renovating lawns, including, weeding, cheeling the grass, forking the 715.20 100 sqm 33.22 6437.00
ground, top dressing with forked soil, watering and maintaining the laws, for
30 days or more, till the grass forms a thick lawn, free from weeds, and fit
for moving and disposal of rubbish as directed, including supplying good
earth, if needed, but excluding the cost of well decayed farm-yard manure.

Total 267819.00

Contractor Witness Executive Engineer


145

RAIN WATER HARVESTING


Sl.No Qty Description Rate Unit HSR Total Cost
1 237.06 Earth work in excavation in foundations, trenches, of under ground structures, sullage drains, etc. and other 4380.40 100 6.7 10384.00
similar works in ordinary soil including dressing of bottom and sides, to correct levels and templates, cutting Cum
of trees and bushes, dewatering of rain water, diversion of traffic, fixing and maintenance of caution boards,
and night signals, crossing over trenches for access to houses, Watching, stacking of excavated soil, clear from
the edge of excavation, and subsequent filling, where required around masonry, in 15cm layers, with
compaction and disposal of surplus soil as directed within a lead of 30mtr for depth upto 2mtrs below natural
ground level(for P.H. work only ).
2 106.25 Excavation of trenches in streets, lanes or in open areas for storm sewer, sewers running by gravity and 9935.80 100 6.10(b) 10557.00
manhole to full depths as shown in drawings including shoring timbering of poling boards, frame system Cum
type, dressing to correct sections and dimensions, according to templates and levels, dewatering, provision for
diversion of traffic, cutting trees and bushes, etc. night signals, profiles, pegs, sight rails, boining rods, crossing
over trenches for access to the houses, watching fencing etc. fixing and maintenance of caution board refilling
of tranches, watering of refill, in 15 cm layers remaining and restoration of unmetalled or unpaved surface to
original condition and removal of surplus soil, from site of work, upto a lead of 1km in ordinary soil.
b) For depths of excavation exceeding 3 meters, but not exceeding 4.5 meters.
3 34.283 Cement concrete 1:6:12 with brick ballast 40mm nominal size in foundation and plinth 1915.375 Cum 10.32 65665.00
4 7.2 Cement concrete 1:4:8 with brick ballast 20mm nominal size in foundation and plinth 2310.00 Cum 10.38 16632.00
5 2.29 Cement concrete 1:1.5:3 with stone aggregate 20mm nominal size for reinforced concrete work in 5966.40 Cum 10.82 + 13663.00
slabs with inclination not exceeding 25 degree with horizontal, excluding steel reinforcement, but 10.95 A
including centering and shuttering ,laid in position, complete in all respects.
6 105.0732 First class brick laid in cement sand mortar 1:6 in first storey upto 4 meters upto above plinth 2901.15 Cum 11.7 304833.00
level
7 216 Providing & fixing pre stressed perforated cover for drain, 60mm thick complete in all respects as 1000.00 sqm N.S. 216000.00
per direction of the Engineer-in-charge.
8 Fe-500 EQR TMT steel bars for RCC, works, where not included in the complete rate of RCC 5502.3 qtl 18.22 15021.00
2.73 including bending, binding and placing in position complete.
9 75 Boring/Drilling bore well of required dia for casing/strainer pipe,by suitable method prescribed 610 Rmtr NS 45750.00
in IS:2800 part (I) including collecting samples from different strata and submitting strata
chart/bore log,hire & running plants and machineries required for the job,all complete as per
direction of the Engineer-in-charge,upto 200 meter depth below(500 mm dia bore)

10 Supplying,assembling,lowering and fixing in vertical position in bore well,unplasticized PVC


medium well casing(CM) pipe of required dia,conforming to IS:12818,including required hire
and labour charges & acessories etc, all complete,for all depths, as per direction of Engineer-in-
charge

48 a)200mm nominal size dia 754 Mtr NS 36192.00

Contractor Witness Executive Engineer


146

27 c)200mm dia slotted pipe 853 Mtr NS 23031.00


11 1 Providing and fixing Bail plug/bottom plug of required dia to the bottom of pipe assembly of 211 Each NS 211.00
tubewell as per IS:2800 part -I 200mm dia
12 9.6 Coarse sand screened, cleaned and washed and graded 1.5mm to 2mm (from Ghaggar or 1383.36 Cum 28.50(b) 13280.00
approved equivalent quarry)
7.2 (c) Bajri screened, washed and graded from 6mm to 20mm 699.6 Cum 28.50(c) 5037.00
13 Providing salt glazed stone ware pipes grade "A" in standard length of 600mm each pipe marked 29.95 0.00
with IS:651 and their lowering, cutting, pointing and testing as described in HSR item
no.29.38,29.39,29.40 including the cost of jointing materials as well as carriage loading, unloading
stacking handling re-handling etc complete in all respects to the satisfaction of Engineer-in-
charge.

40.00 450 mm Internal dia. 1988.70 Mtr 79548.00


14 15 Development of tube well in accordance with IS:2800 & IS:1189,to establish maximum rate of 512 hours NS 7680.00
usable water yield without sand content with required capacity air compressor, running the
compressor for required time till well is fully developed, measuring yield of well by "V" notch
method or any other approved method, measuring static level &draw down etc, by step draw
down method, collecting water samples & getting tested in approved laboratory , i/c disinfecting
of tubewell, all complete ,including hire and labour charges of air compressor tools and
accessories etc.,as per requirement and direction of Engineer in charge
15 1 Providing and fixing M.S Clamp of required dia to the top of cashing/housing pipe of tubewell as 1041 nos NS 1041.00
per IS:2800 mm, supported on grinders not less than 75X150 mm,2 mtr .Long embedded in
suitable foundation including necessary bolts & nuts of required size complete3(200 mm clamp)
16 30 Providing and fixing M.S. sheet cover and frame including locking arrangement for the duct of 52 kg NS 1560.00
injection well including primer and paint complete ai all respects as per direction of Engineer-in-
charge.
Total 866085.00

Contractor Witness Executive Engineer


147

BOUNDARY WALL
Sl.No Qty Description Rate Unit HSR Total Cost
1 180.32 Earth work in excavation in foundation, trenches etc. in all kinds of soils, not 5817.525 100 Cum 6.6 10490.00
exceeding 2 meters depth including dressing of bottom and sides of trenches,
stacking the excavated soil, clear from the edge of excavation and
subsequent filling around masonry, in 15 cm layers with compaction,
including disposal of all surplus soil, as directed within a lead of 30 meters.
2 31.02 Cement concrete 1:4:8 with stone aggregate 40mm nominal size in 2217.05 Cum 10.39 68773.00
foundation and plinth.
3 54.39 Cement concrete 1:1.5:3 with stone aggregate 20mm nominal size for 6538.13 Cum 10.86 + 355609.00
reinforced concrete work for walls exceeding 20cm thickness (straight and 10.95 (a)
curved) beams, girders, stairs, columns, (square or rectangular) battens and
lintels etc. excluding steel reinforcement but including centering and
shuttering, laid in position, complete in all respects
4 94.01 Cement concrete 1:1.5:3 with stone aggregate 20mm nominal size for 4257.00 Cum 10.90+ 400201.00
reinforced concrete work in footing, strips, foundations, beams, rafts, 10.95(a)
pedestals and approach slabs of bridges etc., excluding steel reinforcement
but including centering and shuttering laid in position, complete in all
respects .(for work upto 1.5 meters below ground level
5 59.72 First class brick work laid in cement sand mortar 1:6 in foundation and 2754.15 Cum 11.2 164478.00
plinth
6 First class brick work laid in cement sand mortar 1:6 in first storey upto 4 11.7+
meters above plinth level Note
124.89 1st storey 2901.15 Cum 362325.00
2.48 2nd storey 2958.9 Cum 7338.00
7 13.35 Terracing consisting of tiles 22.86 cm X 11.43cm X 3.81cm laid over 87.50 mm mud 370.65 Sqm 13.13+ 4948.00
filling on a layer of 25mm mud plaster and on other layer of mud mortar for laying NOTE
the tiles, including two coasts of bitumen laid hot as 1.65 Kg per sqm on top of
R.C.C. slab including grouting with cement sand mortar 1:3 and top surface to be
left clean etc.
8 13.35 Base course of floors consisting of 100mm thick cement concrete 1:8:16 and 100 184.75 Sqm. 14.1 2466.00
sand or stone filling

Contractor Witness Executive Engineer


148

9 13.35 Providing and fixing of vitrified tiles of size 600X600 mm of approved make 785.66 Sqm. 14.89 10489.00
in flooring laid in any pattern as specified over base of 20mm thick base of
cement coarse sand mortar 1:3 and jointed with white cement slurry mixed
with pigment to match the shade to tiles
10 637.74 12mm thick cement plaster 1:4 on wall 76.2 Sqm. 15.5 + 48596.00
13.79 77.28 Sqm. Note 1066.00
11 637.74 15 mm thick cement plaster 1:4 on the rough side of single or half brick wall. 93.9 Sqm. 15.10 59884.00
13.79 94.98 Sqm. Note 1310.00
12 25.12 10mm thick cement plaster 1:4 on underside of ceiling 75.90 Sqm. 15.52 1907.00
13 18.60 Pressed steel sheet frames (chowkhats) consisting of 2 mm thick steel sheet of the 351.6 Meter 18.34 6540.00
specified section, including iron lugs (hold fasts) iron hinges, conforming to P.W.D.
specifications, including bolts for fixing stops, lock notch, provision for receiving
tower bolts, and finished with one coat of ready mixed paint red lead non-setting
primer, of approved quality, fixed in position including the cost of cement concrete
1;3:6 for filling in the frame, and cement concrete 1:3;6 lungs complete:-
b) Door & window frame of size 76mmX38mm with 35mm wide single
rebate.
14 16.06 Preparation of ply wood surface for painting including sand papering the 15.18 Sqm. 16.1 244.00
surface and applying filling with approved quality filler consisting of white
lead , linseed oil , varnish and chalk mitto including finishing the surface to
required finish complete.
15 16.06 Applying pink primer or aluminum priming coat on wood work, including 12.375 Sqm. 16.2 199.00
preparation of surface, knotting and stopping etc.(1st quality)
16 16.06 Painting two coats excluding priming coat with synthetic enamel paint in all 31.02 Sqm. 16.3 498.00
shades on new woodwork or plastered or concrete to give an even shade
17 191.31 Applying primer coat with metal primer on new steel work or iron work 10.395 Sqm. 16.9 1989.00
including preparation of surface
18 191.31 Painting two coats excluding priming coat with ready-mixed paint for 23.10 Sqm. 16.17 4419.00
metallic surfaces in all shades on new steel or iron work
19 Cost of Aluminum fittings complete for doors and windows, such as tower 17.72
bolts, handles, etc. and screws for these fittings (excluding sliding bolt)
3.78 a)for single leaf shutter 71.20 Sqm. 269.00
2.16 a)for Double leaf shutter 109.80 Sqm. 237.00

Contractor Witness Executive Engineer


149

20 Providing and fixing sliding bolt with nuts and bolts and screws etc
2.00 (b) Iron(ii)size 250mmx16mm 65.40 nos 17.83 131.00
21 Factory manufactured paneled door or glazed window shutters of commercial hard 17.90 (-
wood, such as holock, champ, chikrassy and chaplash, etc.,(non coniferous timber note-I of
other than teak, conforming to I.S. specification no.1003, kiln seasoned ),with 100mm 17.18
wide vertical styles,150mm wide lock rail,200mm wide bottom rail and 100 mm wide
other rails, with panels of 15mm thick ,tongued and grooved of commercial hard
wood and including cost of iron hinges, screws chocks / cleats, stops, nails etc,
complete fixed in position ( Excluding cost of any fittings, other specified above
but including labour for fixing the same in position. )
2.16 30mm thick 1592.60 Sqm. 3440.00
22 3.78 Factory manufactured solid flush door shutter ,with block board core as per 1155.80 Sqm. 17.93 (- 4369.00
I.S.No.1659-1969 bonded with water proof type phenol formaldehyde synthetic resin, )note-I of
hot pressed, conforming to IS 2202 part-1 and II, fixed in position, including iron 17.18
hinges, screws, chocks/cleats,and stops etc, (excluding the cost of any fitting other
than specified above, but including labour for fixing the same in position ):-(a)
commercial veneering with vertical grains or cross bands and face veneer on both
sides commercial facing with laminated core and lipped edges:- a(iii) 35mm thick
(For all storeys)
23 51.87 Wrought iron and mild steel(using angles, flats, square bars, tees and channels) 6242.1 Qtls 18.12 323778.00
ladders, grills, grating frames, window guards, iron doors open able or fixed stair
case or parapet or any other type of railing ,gates and tree guards etc., including cost
of screws and welding rods or bolts and nuts complete fixed in position
24 171.00 Fe-500 EQR TMT steel bars for R.C.C works, where not included in the complete 5502.30 Qtls 18.22 940893.00
rate of R.C.C including bending, binding and placing in position complete
25 6.00 Providing and fixing had drawn steel wire fabric 75mm X25mm rectangular mesh 624.60 Sqm. 18.33 3748.00
with 3.25mm dia wire fixed on steel windows of standard rolled sections with 3mm
thick flat iron cover moulding of 12.5 mm width fixed with machine screws welded
complete in all respect
26 1328.19 Applying primer coat with cement primer in all shades on newly plastered work. 13.695 Sqm. 16.25 18190.00
27 1328.19 Providing two coats of exterior acrylic emulsion paint (1st quality) 48.75 Sqm. 16.79 64749.00
Total 2873573.00

1. Total Cost with provision of Ist Class Brick work & GI pipe 15mm & 20mm i/d = Rs. 210527072/-
2. Total Cost with provision of Fly Ash Brick work & PVC pipe 20mm & 25mm i/d = Rs. 205665353/-

Contractor Witness Executive Engineer


150

BOQ
ESTIMATED COST OF DNIT = Rs 210527072/-

Contractor Witness Executive Engineer