Professional Documents
Culture Documents
Article 3.12
Inspection and Repair of Shell and Tube Heat Exchangers
130
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
ASME PCC-2–2015 Part 3 — Article 3.12
(2) For heat exchangers deemed critical to the oper- due to the potential for the plates to corrode at the
ation and/or process safey of the facility, the following regions where the tubes penetrate the supports and lead
should also be considered: to tube vibration induced issues. If zero, consideration
(a) total replacement of the tube bundle when should be given to assigning a nominal value of 3 mm
tubes inspected indicate a wall loss of 40% or more of (1⁄8 in.).
the initial, nominal thickness (2) Consideration should be given to use of alloy
(b) tube bundle replacement or individual tube support plates/baffles instead of thicker carbon steel;
replacement when tubes inspected indicate a wall loss however, harder material may result in more damage
of 20% to 40% of the initial, nominal thickness to the tubes rather than the support plates/baffles. Also,
the effects of differential thermal expansion should be
3.3 Tubes and Tube Bundles considered. Consultation with a materials/corrosions
(a) Tubes and tube bundles should be assessed using specialist may also be necessary.
the data obtained by inspection performed in accor- (3) The spacing between the support plates should
dance with Mandatory Appendix I for the types of be evaluated and adjusted if analysis indicates potential
repairs to perform; plugging by welded, mechanical, or vibration of tubes resulting in damaged tubes and/or
friction fit plugs, partial replacement of the tube bundle, support plates. Evaluation per TEMA RCB Section 5 and
or full replacement of the tube bundle. Section 6 should be considered. Consultation with a heat
(b) When considering the use of mechanical or friction transfer specialist may also be necessary.
fit plugs, the user should consider the impact on the (4) Tube stakes are rods, strips, or other devices
efficiency and other operational characteristics of the inserted between tubes for bracing and/or support.
heat exchanger due to the reduction of heat transfer They may be used to add tube support to an existing
area, especially for heat exchangers that are deemed as bundle for the purpose of eliminating tube vibration.
critical to the operation and/or process safety of the Installation requires access from the shell side, and the
facility. Consultation with a heat transfer specialist may main advantage is that disassembly of the tube bundle
be necessary. is not required. Special consideration may be necessary
(c) Sleeves may be installed in tubes to line a region for the use of stakes in U-tube bends because some
of tube damage or to restore tubes that have thinned. stake designs require that the tubes be round and evenly
They are not typically used for protection of tube ends; spaced.
see para. 3.3(d) and para. 4.4. Tube stakes were developed for use when a change
(d) Ferrules may be installed in tubes for entrance in tube material or an increased flow rate requires addi-
erosion protection of for thermal protection of tube ends. tional tube supports, and increasing the number of sup-
They are not typically used for general tube damage; port plates is not possible or desirable. They can be used
see paras. 3.3(c) and 4.3. anytime additional tube support is required such as to
(e) For paras. 3.3(c) and (d), one should consider the provide additional support for deteriorated or damaged
following: support plates, to provide additional support between
(1) uniformity of contact between the sleeve or fer- segmented baffles, or to provide additional support at
rule and tube, see paras. 4.3(b) and 4.4 inlet nozzles. If tube stakes are fabricated from flat bar
(2) possibility of crevice corrosion between the and inserted in every other tube row, it may be necessary
sleeve or ferrule and tube to vary the bar thickness such that each tube is contacted
(3) possibility of bulging the tube, which can make or even displaced from its original position.
retubing difficult Evaluation of the shell-side pressure drop, and
(4) additional pressure drop changes in shell-side flow are necessary. The compatibil-
(5) reduction of tube fluid flow due to the sleeve ity of tube and stake materials should be evaluated.
or ferrule Also, the effects of differential thermal expansion should
(6) additional heat transfer resistance be considered.
(7) differential radial and axial thermal expansion (g) If impingement protection is required to prevent
between sleeve or ferrule and tube flow-induced erosion, refer to applicable standards such
(f ) The tube bundle supports should be assessed as API Standard 660, TEMA, and HEI for design
using the data obtained by inspection performed in requirements.
accordance with Mandatory Appendix I. If data indi-
cates that failure of tubes is due to damaged support
3.4 Tubesheet
plates, consideration should be given to replacing with (a) Material used to replace a tubesheet shall be of
alternative designs. Specific items to consider include the same or greater allowable stress as used for the
the following: original component.
(1) The corrosion allowance provided for the sup- (b) If an engineering analysis indicates tube replace-
port plate should be twice the value for the shell side ment of a larger diameter is required, additional analysis
131
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
Part 3 — Article 3.12 ASME PCC-2–2015
on the tubesheet shall be performed to determine if the (b) plugging a tube, see para. 4.2
ligament efficiency is acceptable. The analysis shall meet (c) removing the tube and performing weld buildup
the original code of construction, or if this is not known, of the tube hole and then remachining the tube hole to
the analysis shall meet the requirements of ASME BPVC the original tube hole diameter. Design of the mechanical
Section VIII, Division 1. joint should be made to the original code of construction,
(c) Tubesheets should be assessed using the data an applicable post-construction code, or to ASME BPVC
obtained by inspection performed by a method listed Section VIII, Division 1, Appendix A. Caution must be
in Mandatory Appendix II for determination of repair exercised to avoid damage to adjacent tubes.
or replacement of the tubesheet. Common conditions (d) seal welding or strength welding of the joint.
for consideration include Design of the welded joint, if previously welded, should
(1) cracking (not through the total thickness) of be made to the original code of construction, an applica-
tubesheet on shell side; more typical in vertical units. ble post-construction code, or to ASME BPVC
Installation of a tubesheet vent and drain should be Section VIII, Division 1, Appendix A. Consideration
considered to promote liquid full operation. The vent should be given to the cleanliness of the joint considering
should be a 19 mm (3⁄4 in.) nozzle welded to the edge potential residue from the fluids.
of the tubesheet, with a 16 mm (5⁄8 in.) hole in the tube- (e) consideration shall also be given to the effect of
sheet that is parallel to the tubes to the midsection of style of heat exchanger on loading of the
the tubesheet, then normal to the tubes to the edge of tube-to-tubesheet joint. For example, a fixed tube
the tubesheet. A gate or ball valve should be installed exchanger may have higher loadings due to differential
on the nozzle along with a blind flange or plug. thermal expansion than a U-tube exchanger.
(2) separation of weld overlay cladding resulting
from wire drawing of high-pressure tubeside fluid leak- 3.6 Bimetallic Shell-to-Tubesheet Welds
ing through tube-to-tubesheet joints. When the shell and tubesheet are made of different
(3) cracking in the ligament of the tubesheet. A materials, the thermal stress between the shell and tube-
failure analysis should be performed to determine the sheet should be considered. A common solution to
damage mechanism. The decision to repair versus cracking of this weld is to change the shell material to
replace the tubesheet should be based on the damage match the tubesheet. An entire shell may be replaced,
mechanism along with the extent of the ligament or bands or shell material may be installed adjacent
cracking. to the tubesheet. Reevaluation of the heat exchanger
(4) corrosion of the tubesheet can occur on the back- mechanical design due to the change in thermal expan-
side (shell side) of the tubesheet. When the corrosion sion or strength of the shell may be required.
allowance on the backside has been consumed, the tube-
sheet should either be replaced or an engineering evalua- 3.7 Shell, Channel, or Other Pressure-Retaining
tion performed to determine its fitness for service. Components
(5) corrosion of the tubesheet can occur on the front (a) Materials used to replace or repair pressure-
face (tube side) of the tubesheet. When the corrosion retaining portions of a shell or channel shall be of the
allowance on the face has been consumed, the tubesheet same allowable stress as the original component, unless
should either be replaced or an engineering evaluation additional analysis is performed to justify changing the
performed to determine its fitness for service. Alterna- material.
tively, the face of the tubesheet may be repaired by weld (b) Replacement of these or other pressure-retaining
buildup that is conditioned by grinding or other components shall comply with the applicable code of
mechanical means such that it is returned to the original construction. For additional guidance on replacement,
thickness of the tubesheet. Factors to consider when see Article 3.1.
pursuing this option include (c) Nonpressure-retaining portions of components
(a) minimum distance between the front face of shall meet the original construction or applicable post-
the tubesheet and the groove for tube-to-tubesheet joints construction code.
(b) the need for welding, strength or seal, of the (d) Additional guidance on pass-partition plates may
tube-to-tubesheet joint and the need for setback from be found in API Standard 660.
the front face
132
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
ASME PCC-2–2015 Part 3 — Article 3.12
service can result in higher flows to the other heat Fig. 1 Typical Friction Fit Tapered Tube Plug
exchanger(s) that may cause damage from erosion, tube
bundle vibrations, or other mechanical damage.
(b) Prior to repairs and to increase accuracy of inspec-
tion, the tubes should be evaluated for the need to be
cleaned. Cleaning may be performed by high pressure
water blasting, chemical solutions, or abrasive
blasting/scrubbing. Selection of a cleaning methodology
shall give consideration to the nature of fouling, tube
material type, and tube enhancements.
(1) High pressure water blasting is normally per-
formed at 70 MPa (10,000 psi). In some cases, ultra-high
pressure water blasting may be necessary at pressures
up to 275 MPa (40,000 psi). Other factors essential to
removal of deposits include water flow rate and the
spray tip configuration.
(2) When cleaning with chemical solutions, a mate-
rials engineer should be consulted to ensure no detri-
mental effects occur to the tubes and/or shell of the heat
exchanger. For example, a caustic solution should not (a) All tubes that are plugged should be pierced to
be used in 300 series stainless steel tubes. provide for venting and draining. When doing so, verti-
(3) When performing abrasive blasting/scrubbing, cal tubes should be pierced at each end, and horizontal
care shall be exercised to ensure no adverse damage to tubes should be pierced on top and bottom of the tube.
the tubes occurs. Deterioration of heat transfer capability Piercing of each tube prevents possible plug blowout
shall be considered when cleaning tubes with internal and permits the validation of the integrity of the tube
components designed to enhance heat transfer by plug, see para. 4.2(b)(4). Large temperature differential
increasing turbulence through the tubes. between tubeside and shell side may require the tube
(c) Inspection of the tubes periodically during the to be cut in two.
cleaning process should be made to ensure consistent (b) Friction fit tapered plugs (Fig. 1) shall only be
results. Use of a boroscope may improve inspection used in services that meet all of the following conditions,
results. unless an engineering evaluation is performed indicat-
(d) When a tube bundle must be removed from its ing the acceptability of these plugs in other services:
shell for purposes of inspection or repair, caution should (1) shell-side operating pressure 1.5 MPa (200 psi)
be exercised to avoid damage to the tubes or other or less
components. (2) shell-side operating temperature 205°C (400°F)
(e) When it is known that a tube or multiple tubes or less
are leaking, consideration shall be given to pulling a (3) tube-to-tubesheet joints are expanded and not
tube for failure analysis to aid in determination of the welded
damage mechanism.
NOTE: Inspection of the expanded tube for tube thinning should
(f) All welded repairs shall be made using qualified be made to ensure that installation of the plug does not further
welding procedures. Welders and welding operators damage the tube leading to seal failure between the plug and
shall be qualified in accordance with the requirements the tubes.
of the applicable code of construction or the applicable
post-construction code. Welding procedure qualifica- (4) tapered plugs that are installed where tubes are
tions shall include impact tests if required by the applica- not pierced can present a serious safety hazard. If the
ble code of construction for the component being tube cannot be pierced, the tube should be pulled or
repaired. other measures should be taken to ensure personnel
(g) Welding materials and processes shall be as cur- protection, such as welding the plug to the tubesheet
rently permitted by the applicable code of construction and draining all liquids from the tube being plugged.
or post-construction code for the component. Welding (c) Mechanical plugs (Fig. 2) should be considered
of carbon and low alloy steels should be performed with in situations where friction fit tapered plugs are not
low hydrogen electrodes and processes. appropriate for the pressure and/or temperature of ser-
vice or other mechanical/environmental conditions.
4.2 Tubeside Repair by Plugging These types of plugs have been used in services of up
Repair of tubes may be accomplished by plugging to 50 MPa (7,000 psi) and 595°C (1,100°F). Mechanical
the tube at the tubesheet with a welded or mechanical plugs are typically installed by a pneumatic or hydraulic
attachment. system. See Fig. 3. Other styles of plugs may be
133
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
Part 3 — Article 3.12 ASME PCC-2–2015
134
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
ASME PCC-2–2015 Part 3 — Article 3.12
Number of Months
considered for higher pressures. Consideration shall also (c) A map should be developed to record the number
be given to the following: and location of tubes that have been sleeved. Addition-
(1) tubes with internal surface severely corroded or ally, the number of tubes, cumulative number of tubes
cracked versus the service time should be charted. If a sharp
(2) when the tube and the plug have dissimilar increase in tube failures occurs, replacement of the tube
metallurgy bundle should be considered. See Fig. 4 for example
(3) installation in severely corrosive service chart.
(4) condition of the mechanical joint of the tube-
to-tubesheet in rolled tube situations 4.4 Tubeside Repair by Ferrule Installation
(d) A plug map should be developed to record the Ferrules may be held in place by a flanged end with
number and location of tubes that have been plugged. a tight fit to the tube inside diameter, by expanding the
Additionally, the number of tubes, cumulative number ends of the ferrule into the tube at the tubesheet, or by
of tubes versus the duration, should be charted. When welding. Uniform contact with the tube may be achieved
the sharp turn in tube failure numbers occurs, replace- by roller or hydraulic expansion of the ferrule. One
ment of the tube bundle should be considered. See Fig. 4 should consider the possibility of bulging the tube,
for example chart. which can make retubing difficult. A mock-up may be
(e) Tracking of pressure loss due to tube pluggage advisable to ensure weld or expansion quality.
should be considered as some exchanger types cannot
function properly beyond certain tubeside pressure 4.5 Tubeside Repair by Pulling Tubes
losses. Provisions for internal bypass should be consid-
(a) Pulling the tube from the exchanger and plugging
ered if repair is not performed in order to prevent failure
the tubesheet as described in para. 4.2 should be consid-
of pass partitions. Proper design of this bypass can be
ered as a repair option when plugging is not a viable
determined from industry references in section 7 of this
alternative, or when the tube will be retained for labora-
Article.
tory metallurgical analysis or other specific examination.
4.3 Tubeside Repair by Sleeving Tubes (b) When pulling a tube and not replacing, potential
damage to the baffle could occur and consideration to
(a) Sleeving versus tube replacement may be advanta-
replacing the tube should be made. Consultation with
geous when repairing previously plugged tubes because
a heat transfer specialist may also be necessary.
of perforations in discreet identifiable locations, or to
bridge failures in discreet locations of tubes that are
4.6 Tubeside Repair by Replacement
otherwise intact.
(b) The methods of sleeve installation include the fol- Repair may be performed by tube replacement, which
lowing: forcing a ball though the sleeve, welding the may be accomplished in one of the following methods:
ends of the sleeve, roller expansion of the sleeve, explo- (a) replacing individual tubes, which may include
sive bonding of the sleeve and hydraulic expansion of repair/refurbishing of the tubesheet in the area of the
the sleeve. One should consider the possibility of bulg- subject tube.
ing the tube, which can make retubing difficult. A mock- (b) replacement of the entire tube bundle. See
up may be advisable to ensure weld or expansion quality. para. 3.2(c).
135
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
Part 3 — Article 3.12 ASME PCC-2–2015
4.7 Tubesheet Repair 4.8.2 Weld Buildup Repair of Tube Holes and
Machining
4.7.1 Weld Repair of Cracks (a) When a tube is replaced and the tube hole has
(a) Repair of general cracks that are not completely been damaged, repair may be effected by weld buildup
through the thickness of the tubesheet and are not in and machining of the hole.
the ligaments may be made in accordance with the (b) All welded tube hole repairs shall be made using
guidelines of Article 3.4. qualified welding procedures. Welders and welding
(b) Repair of general cracks that are through the thick- operators shall be qualified in accordance with the
ness of the tubesheet and not in the ligaments may be requirements of the applicable code of construction or
repaired by preparing a U- or V-shaped groove to the the applicable post-construction code. Welding proce-
full depth and length of the crack and then filling the dure qualifications shall include impact tests if required
groove with weld metal in accordance with paras. 4.7.1 by the applicable code of construction for the tubesheet.
and 4.7.2. (c) Welding materials and processes shall be as cur-
(c) Repair of cracks in the ligament area of the tube- rently permitted by the applicable code of construction
sheet may be made in accordance with (a) or (b) above. or post-construction code for the tubesheet. Welding of
Consideration may also be given to performing an engi- carbon and low alloy steels should be performed with
neering analysis to determine if the equipment may con- low hydrogen electrodes and processes.
tinue to operate with the damaged tubesheet. This (d) Machining of the hole shall be to original manufac-
analysis may be performed in accordance with turer’s specifications for diameter and grooving.
API 579/ASME FFS-1 or other post-construction
4.8.3 Seal Welding or Strength Welding
standard.
(a) Tube-to-tubesheet welds shall be in accordance
(d) When making tubesheet repairs, consideration
with the applicable code of construction or
should be given to the impact of this repair on the tubes
post-construction code.
in the general area of the repair. The following actions
(b) If seal welds are to be made, consideration shall
may be necessary:
be given to the mechanical tube-to-tubesheet joint to
(1) removal of tubes in the general area of the repair.
ensure its strength. If seal welds are determined to be
See para. 4.5(b).
inadequate, the weld shall be full strength to ensure the
(2) repair of the tube-to-tubesheet joints. integrity of the joint.
4.7.2 Face Repair by Overlay and Machining (c) All welds shall be made using qualified welding
procedures. Welders and welding operators shall be
(a) General and localized thinning of tubesheets may
qualified in accordance with the requirements of the
be repaired by overlay welding and remachining of
applicable code of construction or the applicable post-
the face.
construction code. Welding procedure qualifications
(b) See Article 2.2 for additional items of
shall include impact tests as required by the applicable
consideration. code of construction for the tubesheet.
(d) Welding materials and processes shall be as cur-
4.8 Tube-to-Tubesheet Joint Repair rently permitted by the applicable code of construction
4.8.1 Re-Expanding or post-construction code for the tubesheet. Welding of
carbon and low alloy steels should be performed with
(a) Cleaning and inspection shall be performed to
low hydrogen electrodes and processes.
determine the condition of the tube-to-tubesheet joint
prior to performing this type of repair. See para. 4.1. 4.9 Repair of Pressure Containment Components
(b) Tube-to-tubesheet joints with leaks of a small flow
Repairs to the heat exchanger shell may be performed
rate, otherwise known as weeping tubes, where no
to the original code of construction or applicable post-
apparent damage has occurred to the seating surfaces, construction code. See also Article 2.1 and Article 2.2.
may be reexpanded to obtain an acceptable mechanical
fit of tube to tubesheet. Rerolling is one acceptable
method of re-expanding. 5 EXAMINATION
(c) Prior to re-expanding, the existing inside diameter Examination of heat exchangers typically covers three
of the tube in the tubesheet shall be determined as well areas; external, internal, and tube bundle. It is not neces-
as the loss of material due to corrosion/erosion. sary for each inspection to have the same frequency.
Calculations for allowable maximum inside diameter
shall be based on measured field conditions, tube prop- 5.1 Examination of Tubes and Tube Bundle
erties, and tubesheet ligament condition. It is important for the proper examination technique
(d) See ASME BPVC Section VIII, Division 1, to be selected for the application at hand. The following
Appendix HH for additional considerations. nondestructive examination (NDE) techniques should
136
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
ASME PCC-2–2015 Part 3 — Article 3.12
be considered for the given application. See also Table I-1 (c) visual examination (VT) in accordance with
in Mandatory Appendix I for effectiveness of examina- ASME BPVC Section V, Article 9
tion methods. Other examination methods may be cho-
sen by the owner/operator, as follows: 5.3 Examination of Tubesheet Repair
(a) Eddy Current Examination (ET) is generally (a) VT in-process weld examination shall be
selected for inspection of nonferromagnetic tubes, or performed.
those that are slightly magnetic. Note that the sensitivity (b) Surface examination by PT shall be performed at
of this method decreases for the U-bend portion of the completion of the weld repair.
U-tube bundles. (c) Volumetric examination by UT should be consid-
(b) Remote Field Eddy Current (RFET) is generally ered when there is a possibility of additional flaws being
used for inspection of ferromagnetic tubes. Its sensitivity introduced to the tubesheet during the repair.
and accuracy may be less than desired or required and
will require a higher number of tubes to be inspected. 5.4 Examination of Pressure Containment
It is a quicker method than ultrasonic methods. Components Repairs
(c) Partial Saturation Eddy Current (PSET) can locate (a) All welded repairs should receive VT and PT or
and size cracks in ferromagnetic tubes. It might not be MT examination, especially for heat exchangers deemed
sensitive to O.D. defects. critical to the operation and/or process safety of the
(d) Magnetic Flux Leakage (MFL) may also be facility.
selected for inspection of ferromagnetic tubes. However, (b) Where possible, welded repairs shall receive volu-
sensitivity of this method can be poor for carbon steel metric examination by RT or UT.
tubes, and might only be best at determining the overall
condition of the tube, not determining individual defect 6 TESTING
location.
(e) Ultrasonic examination systems designed to mea- Following completion of the inspection, a pressure test
sure tube wall thickness may be used for small heat or tightness test in accordance with Article 5.1 should be
exchangers, where damage may be localized, or for vali- considered, particularly if the integrity of the
dation of other NDE results. These ultrasonic examina- tube-to-tubesheet joint is in question.
tion systems are particularly suited for carbon steel tubes
due to the lack of sensitivity of other NDE methods. 7 REFERENCES
One type of system is the Internal Rotary Ultrasonic
Inspection (IRIS) system. IRIS is an accurate NDE API RP 579/ASME FFS-1, Fitness-For-Service, 2nd
method for detecting and sizing I.D. and O.D. metal Edition, 2007
loss in tubes. Another type of system is Shear Wave IRIS API Standard 660, Shell and Tube Heat Exchangers for
(SWIRIS) and this can be effective for detecting I.D. and General Refinery Services, 2003 Edition
O.D. cracks. Both IRIS and SWIRIS require clean tubes. Publisher: American Petroleum Institute (API),
(f) Other NDE methods may be more appropriate for 1220 L Street, NW, Washington, DC 20005
the inspection. Consideration should be given to the use (www.api.org)
of radiography (RT) or video probe inspection. These ASME Boiler and Pressure Vessel Code, 2007 Edition,
methods may be better suited for inspection of the Section V — Nondestructive Examination
U-bend portion of U-tube bundles. ASME Boiler and Pressure Vessel Code, 2007 Edition,
(g) Consideration should be given to the monitoring Section VIII, Division 1 — Rules for Construction of
and trending of tube condition as part of a predictive Pressure Vessels
maintenance and/or replacement program. ASME PCC-3, Inspection Planning Using Risk Based
(h) The minimum number of tubes to be inspected Methods
may be determined by the methods provided in Publisher: The American Society of Mechanical
Mandatory Appendix I. Engineers (ASME). Two Park Avenue, New York, NY
10016-5990; Order Department: 22 Law Drive, P.O.
5.2 Examination of Tube-to-Tubesheet Repair Box 2900, Fairfield, NJ 07007-2900 (www.asme.org)
Repairs shall be examined by one or more of the fol- ASTM E2283-03, Standard Practice for Extreme Value
lowing methods: Analysis of Nonmetallic Inclusions in Steel and Other
(a) pressure or leak testing on the shell side; see Microstructural Features
section 6 Publisher: American Society for Testing and Materials
(b) liquid penetrant examination (PT) in accordance (ASTM International), 100 Barr Harbor Drive, P.O.
with the applicable code of construction or Box C700, West Conshohocken, PA 19428-2959
post-construction code (www.astm.org)
137
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
Part 3 — Article 3.12 ASME PCC-2–2015
Wolf, Gerald M. and Adams, Robert B., An Improved Standards of the Tubular Exchanger Manufacturers
Plugging System for HX Tubing, EPRI BPO Association, Eighth Edition
Conference paper, June 1996 Publisher: Tubular Exchanger Manufacturers
Association, Inc. (TEMA), 25 North Broadway,
Publisher: Electric Power Research Institute
Tarrytown, NY 10591 (www.tema.org)
(EPRI), 3420 Hillview Avenue, Palo Alto, CA 94304
(www.epri.com) Andreone, Carl F. and Yokell, S., Tubular Heat Exchanger
Inspection, Maintenance and Repair, McGraw-Hill,
Standards for Power Plant Heat Exchangers, 4th New York, NY, 1997.
Edition, 2004 Wang, W. David, Ph.D., “Extreme Value Analysis of Heat
Standards for Closed Feedwater Heater, 7th Edition, Exchanger Tube Inspection Data,” Proceedings of
2004 PVP2006-ICPVT-11, 2006 ASME Pressure Vessels and
Publisher: Heat Exchange Institute, Inc. (HEI), 1300 Piping Division Conference, July 2006.
Summer Avenue, Cleveland, OH 44115 Bypass-calculation-R3.xls, http://www.mgt-inc.com/
(www.heatexchange.org) docs/Bypass-calculation-R3.xls.
138
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
ASME PCC-2–2015 Part 3 — Article 3.12, Mandatory Appendix I
139
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
Part 3 — Article 3.12, Mandatory Appendix I ASME PCC-2–2015
Highly effective Wall loss IRIS 80% to 100% 80% to 100% Not applicable
[excluding MIC]
140
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
ASME PCC-2–2015 Part 3 — Article 3.12, Mandatory Appendix I
GENERAL NOTES:
(a) MIC — microbiologicaly induced corrosion
(b) IRIS — internal rotary inspection system
(c) EVA — extreme value analysis
(d) RFET — remote field eddy current
(e) MFL — magnetic flux leakage
(f) ET — eddy current testing
(g) SWIRIS — shear wave internal rotary inspection system
(h) PSET — partial saturation eddy current
141
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.
C
Part 3 — Article 3.12, Mandatory Appendix II ASME PCC-2–2015
142
Copyright c 2015 by the American Society of Mechanical Engineers.
No reproduction may be made of this material without written consent of ASME.