You are on page 1of 6

STTS WIDEBODY AIRCRAFT FACILITY

METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

Document No: P103-STTS-GEC-ASI-MS-ELE-001

REV. DATE DESCRIPTION GENFOCUS ASI/WSP


PREPARED APPROVED

000 27-05-18 Issued for Approval QA/QC PM

DOCUMENT No. REV DATE


Page 1 of 6
P103-STTS-GEC-ASI-MS-ELE-001 00 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

1.0 PURPOSE

1.1 The purpose of this Method Statement is to describe step by step the procedure for the
Installation of Transformers.

2.0 SCOPE

2.1 The scope of this Method Statement is to define the sequence for executing the
Installation Transformers.

3.0 TOOLS AND RESOURCES

3.1 Crane
3.2 ‘D’ Shackles
3.3 Sling wire ropes
3.4 Spirit level
3.5 Measuring Tape
3.6 Hand tools
3.7 Chain Block

4.0 RESPONSIBILITIES

4.1 PROJECT MANAGER

4.1.1 Is responsible for ensuring that all works are carried out as per the specifications,
drawing/shop drawings and method statement as per the manufacturer's instructions,
coordinated with other works and will plan for the required manpower and tools for
all activities.

4.2 SITE ENGINEERS/ SUPERVISOR

4.2.1 Ensure the foreman is aware of Installation Transformers.

4.2.2 Check periodically that the job is executed safely and following the standards.
4.2.3 Ensure that the installation complies with the approved shop drawings/specifications.

DOCUMENT No. REV DATE


Page 2 of 6
P103-STTS-GEC-ASI-MS-ELE-001 00 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

4.2.4 Maintain records of work done and submit the progress report to the authorities
concerned.

4.2.5 Follow the ITP procedures and co-ordinate with the QA/QC team for inspections.

4.3 QA/QC ENGINEERS

4.3.1 Carry out the material inspection to ensure that materials received on site are approved
materials.

4.3.2 Monitored the installation works according to the approved drawings and method
statement.

4.3.3 Coordinate with the ENGINEERS and EMPLOYERS REPRESENTATIVE to carry out
inspection/testing of the completed works.

4.4 HSE OFFICER

4.4.1 Ensure that all installation or construction works will be carried out in accordance with
the ENGINEERS safety manual and EMPLOYERS REPRESENTATIVE standard
regulations and practices.

4.4.2 Ensure that all necessary permits shall be obtained from EMPLOYER
REPRESENTATIVE and the concerned authorities wherever necessary.

4.4.3 Ensure that good housekeeping at work site is implemented.

4.4.4 Ensure that all necessary personal protective equipment will be provided as per the
requirement of the job.

4.4.5 Ensure that usage of cranes, lifting items and working platforms will be used in
accordance with the ENGINEERS and EMPLOYERS REPRESENTATIVE Safety
Manual.

DOCUMENT No. REV DATE


Page 3 of 6
P103-STTS-GEC-ASI-MS-ELE-001 00 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

5.0 PROCEDURE

5.1 GENERAL INFORMATION

5.1.1 DELIVERY TO SITE

5.1.1.1 The Transformer’s shall be deliver by low bed or open cargo truck whichever
recommended by the hauler and must arrange in group according to which transformer
room it is located .The transformer’s shall be latched properly and covered during the
transportation. Another physical inspection to be conducted once the transformer arrived
at the site for any damages during the transportation and must be reported and put in
record.

5.1.2 SAFETY

5.1.2.1 Prior to unloading and even during final site installation, the perimeter of the work area
is to be barricaded with warning tapes, and signages indicating “Heavy Lifting in
Progress”.

5.2 LIFTING PREPARATION

5.2.1 The transformers are factory provided with lifting eye for lifting purpose. Proper lifting
tools and materials shall be used for the total rigging operation. Prepare the sizes of the
shackles and sling cables according to the dry weight of the transformer units to be lifted.

5.3 CRANE SETTING LOCATION PREPARATION:

5.3.1 The area outside adjacent to the transformer rooms where the crane will be set in position
shall be graded flat, leveled, well compacted, free from obstructions and with enough
space to fully extend outriggers.

5.4 INSIDE THE TRANSFORMER ROOM PREPARATION:

5.4.1 Ensure that prior to the scheduled installation of the transformer, the embedded railing are
properly clean and the floor is ready dry with epoxy paint.

5.5 INSTALLATION PROCEDURE

5.5.1 CRANE SETTING

DOCUMENT No. REV DATE


Page 4 of 6
P103-STTS-GEC-ASI-MS-ELE-001 00 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

5.5.1.1 .Set-up the crane on rigging position that it can equally sway the boom into the temporary
platform.

5.5.1.2 Test the actual crane boom length, height, lifting angle and the distance from the center
of the temporary platform by actually operating the crane in fewer loads. Over view the
situation to ensure safe lifting operation.

5.5.2 BRINGING THE TRANSFORMER TO LIFTING AREA

5.2.2.1 Transport four numbers of transformers for designated room and position the delivery
truck as close as possible to the crane boom swing radius.

5.5.3 LIFTING THE TRANSFORMERS FOR INSTALLATION

5.5.3.1 Attach the slings or chain to the transformer lifting eyes using the ‘D’ shackles and the
center point is put to the lifting hook. Ensure that the boom and block are directly
centered to the transformer weight. Make a trial lift to check balance of the transformer
weight. If any adjustment required, the load should be properly put to rest before making
adjustment.

5.5.3.2 Attach guide ropes on two sides of the transformer to control the swing movement while
lifting.

5.5.3.3 Start lifting the unit according to the rigging supervisors signal, which are accordingly
followed by the crane operator.

5.5.3.4 Control the transformer unit movement while on lift, by guiding the unit with the two
ropes.

5.5.3.5 Slowly lower the load into the platform area and ensure that the four wheels of
transformer are orientated to the rail direction when placing it on to the temporary
platform.

5.5.3.6 Slowly release the weight of the transformer into the platform, evaluate the platform
stability before slowly removing the slings, and guide the slings away in order not to
damage the transformer enclosure.

5.5.3.7 Anchor a plate into a tiebeam and connect the chain block into it by the hook.

DOCUMENT No. REV DATE


Page 5 of 6
P103-STTS-GEC-ASI-MS-ELE-001 00 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER

5.5.3.8 Manually slide the transformer along the guide rails using Chain block and position the
transformer at permanent location and suitable packing is welded in the rail to obstruct
the further movement of the Transformer.

5.5.3.9 Transformer stopper shall be bolted at the both ends to prevent the transformer from
further movements.

5.5.3.10 Proceed with the same lifting procedure for all other units.

5.5.3.11 Upon completion of all transformer installation, proceed with the fixing of the
protection covers using thick vinyl to cover the unit from dust and place a ply board on
top securely tied to protect from any falling debris.

DOCUMENT No. REV DATE


Page 6 of 6
P103-STTS-GEC-ASI-MS-ELE-001 00 27-05-2018

You might also like