Republic of the Philippines

Provincial Local Government Unit of Ifugao


OFFICE OF THE PROVINCIAL ENGINEER
APPROVED BUDGET FOR THE CONTRACT
Package No.:
Name of Project : 1. Pob. South Provincial Road Concreting (Alindayo Section)
2. Kitikit Road Concreting, Pob. North. Lagawe Contract No.
Location : Lagawe, Ifugao

1. Pob. South Provincial Road Concreting (Alindayo Section)


ESTIMATED INDIRECT COST
Item No.
DESCRIPTION Wt.%Tage QTY. Unit DIRECT COST (EDC) in Percent of (EDC) TOTAL COST
% Value
I Removal of Structures 2.28% 6.00 cu.m 12,242.00 26.5 3,244.13 15,486.13
II Subgrade Preparation 2.00% 416.50 sq.m 10,759.00 26.5 2,851.14 13,610.14
III Aggregate Base-Course 5.26% 35.80 cu.m 28,246.11 26.5 7,485.22 35,731.33
IV Form Works 2.68% 238.00 li.m 14,391.94 26.5 3,813.86 18,205.80
V PCCP 55.55% 357.00 sq.m 298,422.08 26.5 79,081.85 377,503.93
VI Side Embankment 3.18% 23.80 cu.m 17,099.50 26.5 4,531.37 21,630.87
SPL I Lay-out and Stacking 0.74% 1.00 lot 5,000.00 5,000.00
BILLBOARD (Tarpaulin) w/
SPL II 1.00 lot 1,000.00
frame 0.15% 1,000.00
71.84% 387,160.63 101,007.57
2. Kitikit Road Concreting, Pob. North. Lagawe
ESTIMATED INDIRECT COST
Item No.
DESCRIPTION Wt.%Tage QTY. Unit DIRECT COST (EDC) in Percent of (EDC) TOTAL COST
% Value
I Removal of Structures 0.36% 0.75 cu.m 1,957.00 26.5 518.61 2,475.61
II Subgrade Preparation 0.72% 158.60 sq.m 3,842.50 26.5 1,018.26 4,860.76
III Aggregate Base-Course 1.74% 7.93 cu.m 9,371.61 26.5 2,483.48 11,855.09
IV Form Works 0.81% 61.00 lot 4,344.54 26.5 1,151.30 5,495.84
V PCCP 24.38% 155.25 sq.m 130,956.62 34,703.50 165,660.12
BILLBOARD (Tarpaulin) w/
SPL frame 0.15% 1.00 lot 1,000.00 1,000.00
28.16% 151,472.27 39,875.15
TOTAL= 100.00% 538,632.90 140,882.72

Prepared By: Reviewed By: Approval Recommended: Approv

FILEMON A. BULAWAN MENELEO D. OTGALON JULIAN B. DULAWAN JR. PE


Area Engineer Engineer III Provincial Engineer
the Philippines
vernment Unit of Ifugao
ROVINCIAL ENGINEER
FOR THE CONTRACT

Date:
Duration(CD)

TOTAL ADJUSTED
UNIT COST COST

2,581.02 15,486.12
32.68 13,611.22
998.08 35,731.26
76.49 18,204.62
1,057.43 377,502.51
908.86 21,630.87
5,000.00 5,000.00

1,000.00 1,000.00
488,166.60

TOTAL ADJUSTED
UNIT COST COST

3,300.81 2,475.61
30.65 4,861.09
1,494.97 11,855.11
90.10 5,496.10
1,067.05 165,659.51
1,000.00 1,000.00
191,347.42
679,514.02

Approved:

PEDRO G. MAYAM-O
Provincial Governor
Package No.:
NAME OF PROJECT : 1. Pob. South Provincial Road Concreting (Alindayo Section)
2. Kitikit Road Concreting, Pob. North. Lagawe
LOCATION : Lagawe, Ifugao
BAR CHART
1. Pob. South Provincial Road Concreting (Alindayo Section) WEEKS
Item ACTIVITIES ITEM COST W.T % DAYS 1 2 3 4 5 6 7
Hauling of Materials 6.0
I Removal of Structures 15,486.12 6.0
II Subgrade Preparation 13,611.22 7.0
III Aggregate Base-Course 35,731.26 5.0
IV Form Works 18,204.62 2.5
V PCCP 377,502.51 9.0
VI Side Embankment 21,630.87 3.5
SPL I Lay-out and Stacking 5,000.00 1.0
SPL II BILLBOARD (Tarpaulin) w/ frame 1,000.00 1.0

2. Kitikit Road Concreting, Pob. North. Lagawe


Item ACTIVITIES ITEM COST W.T % DAYS 1 2 3 4 5 6 7
I Removal of Structures 2,475.61 1.0
II Subgrade Preparation 4,861.09 2.5
III Aggregate Base-Course 11,855.11 1.5
IV Form Works 5,496.10 1.0
V PCCP 165,659.51 4.0
SPL BILLBOARD (Tarpaulin) w/ frame 1,000.00 1.0

7 7 7 7 7 7 7

Prepared By: Checked By: Reviewed By: Approved b

MIKE D. ROLDAN FILEMON A. BULAWAN MENELEO D. OTGALON JU


Engineer I Area Engineer Engineer III
HART
WEEKS
8 9 10 11 12 TOTAL

8 9 10 11 12

7 7 7 3 73 CD

Approved by: LEGEND

half day
JULIAN B. DULAWAN JR. whole day
Provincial Engineer sunday
G E N E RAL AN D TE C H N I CAL S PE C I F I CATI O N S
Package No.:
Project name: 1. Pob. South Provincial Road Concreting (Alindayo Section)
2. Kitikit Road Concreting, Pob. North. Lagawe
Location: Lagawe, Ifugao

A. GENERAL REQUIREMENT:

I. BILLBOARD
- project billboard must conform with the specification provided by the implementing agency.
- it shall be erected at the project site before the start of any construction activities.
B. TECHNICAL REQUIREMENT:

I. Removal of Structures
- Remove all structures and obstruction that would interfere within the boundaries or limits of
work to be done.
II. Subgrade Preparation
- Remove all structures and obstruction that would interfere within the boundaries or limits of
work to be done.
III. Aggregate Base-Course
- Aggregate Base Course shall attain at least 95% compaction.
IV. Form Works
- Forms shall be properly supported to avoid movements during concrete pouring.
- Forms shall be checked as to vertical and horizontal alignment.
- Forms shall be used three times.
V. PCCP
- Cement to be used shall be Portland Cement only.
- Aggregates to be used shall conform to the standard specification for concrete aggregates.
- Concrete mixture shall be"Class A" 1:2:3 that is 1 part of cement 2 parts of sand and 3 parts
of gravel.
- Aggregates and water to be used shall be clean and free from foreign or any deleterious
matters.
VI. Side Embankment
- Side fill shall attain at least 95% compaction.

Prepared by: Checked by:

FILEMON A. BULAWAN MENELEO D. OTGALON


Area Engineer Engineer III

Approved by:

JULIAN B. DULAWAN JR.


Provincial Engineer
SCOPE OF WORK
Package No.:
Name of Contract : 1. Pob. South Provincial Road Concreting (Alindayo Section)
2. Kitikit Road Concreting, Pob. North. Lagawe
Location: Lagawe, Ifugao
Procuring Entity: Provincial Local Government of Ifugao
Date of Bid:

Description Unit
General Requirement
Billboard 1.0 lot
Supply of materials, labor,equipments/tools and supervision for the production of project
billboard in accordance to the specifications of the provincial Government Unit (PLGU) to be at the
project site on a location approved by the Engineer before the commencement of any civil works.

I. Removal of Structures 6.75 cu.m


Supply of materials, equipment/tools, labor and supervision for the removal of structures within
the limits of work to be done.

II. Subgrade Preparation 575.1 sq.m


Supply of materials, equipment/tools, labor and supervision for the Subgrade preparation.

III. Aggregate Base-Course 43.73 cu.m


1. Spreading (manual)
Supply of materials, tools, labor and supervision for the manual spreading of aggregate
base course.

2. Compaction
Provision of labor, tools/equipment and supervision for the compaction of aggregates
to meet atleast 95% compaction.

IV. Form Works 299.00 li.m


Supply of materials, tools, labor and supervision for the installation and
removal of forms.

V. PCCP 512.25 sq.m


Supply of materials, tools/equipment, labor and supervision for the pouring
of concrete.

VI. Side Embankment


Supply of materials, tools/equipment, labor and supervision for placing and
compaction of the side embankment.

Prepared by: Checked by:


FILEMON A, BULAWAN MENELEO D. OTGALON
Area Engineer Engineer III

Approved by:

JULIAN B. DULAWAN JR.


Provincial Engineer
B B B B B B B B B B B B B B B B
Package No.:
PROJECT: 1. Pob. South Provincial Road Concreting (Alindayo Section)
2. Kitikit Road Concreting, Pob. North. Lagawe
LOCATION: Lagawe, Ifugao

1. Pob. South Provincial Road Concreting (Alindayo Section)


Pay Item No. Description Unit Quantity Unit Price Total Price
I Removal of Structures cu.m 6.00
II Subgrade Preparation sq.m 416.50
III Aggregate Base-Course cu.m 35.80
IV Form Works li.m 238.00
V PCCP sq.m 357.00
VI Side Embankment cu.m 23.80
SPL I Lay-out and Stacking lot 1.00
BILLBOARD (Tarpaulin) w/
SPL II lot 1.00
frame

2. Kitikit Road Concreting, Pob. North. Lagawe


Pay Item No. Description Unit Quantity Unit Price Total Price
I Removal of Structures cu.m 0.75
II Subgrade Preparation sq.m 158.60
III Aggregate Base-Course cu.m 7.93
IV Form Works lot 61.00
V PCCP sq.m 155.25
BILLBOARD (Tarpaulin) w/
SPL lot 1.00
frame

TOTAL AMOUNT:
AMOUNT IN WORDS:

SIGNATURE:
CONTRACTOR:
ADDRESS:
Package No.:
Name of Project: 1. Pob. South Provincial Road Concreting (Alindayo Section)
2. Kitikit Road Concreting, Pob. North. Lagawe
Location: Lagawe, Ifugao
Appropriation: Php 300,000.00
Source of Fund: 2017 - 20% DF (SB)
DETAILED ESTIMATES
1. Pob. South Provincial Road Concreting (Alindayo Section)
Item No.
I Removal of structures Qty. = 6.00 cu.m
Labor Cost
Manpower No. Rate Days Amount
Foreman 1 6.0
Laborers 2 6.0
Portable Jackhammer 1 6.0
Electric Drill 1 6.0
total
DIRECT COST =
II Subgrade Preparation Qty. = 416.5 sq.m
Labor Cost
Manpower No. Rate Days Amount
Foreman 1 7.0
Laborers 4 7.0
total
DIRECT COST =
III Aggregate Base-Course Qty. = 35.80 cu.m
A. Material Cost
Description Unit Qty. U-Price Amount
Mixed Aggregate cu.m 41.50

B. Labor Cost
Manpower/Equipment No Rate Days Amount
Foreman 1 5.00
Laborer 2 5.00
Plate Compactor 1 1.00
total
DIRECT COST =
IV Form Works Qty. = 238 li.m
A. Material Cost
Description Unit Qty. U-Price Amount
27pcs- 8" x 2" x 10' lumber bd.ft 360.00
4-16 mmRSB Pins kg. 37.88
Assorted CWN kg. 1.00

B. Labor Cost
Manpower/Equipment No Rate Days Amount
Foreman 1 2.50
Skilled Laborers 1 2.50
Laborers 2 2.50
total
DIRECT COST =
V PCCP Qty. = 357 sq.m.
A. Material Cost
Description Unit Qty U-Price Amount
Cement bags 650.00
Sand (S1) cu.m 36.00
Gravel (G2) cu.m 57.50
Asphalt bags 1.00
24pcs- 16 mm RSB Dowels kgs. 227.28
20pcs-12 mm RSB Dowels kgs. 106.60
Measuring Box pcs. 2.00
Water Provision drums 88.00
total
B. Labor Cost
Description No. Rate Days Amount
Foreman 1 9
Skilled Laborers 2 9
Laborers 12 9
1 bagger-Concrete Mixer 1 9
total
DIRECT COST =
VI Side Embankment Qty. = 23.8 sq.m
A. Material Cost
Description Unit Qty. U-Price Amount
Mixed Aggregate cu.m 27.50

B. Labor Cost
Manpower/Equipment No Rate Days Amount
Foreman 1 3.50
Laborer 2 3.50
total
DIRECT COST =
SPL I Lay-out & Stacking Qty. = 1.0 lot

DIRECT COST =

SPL II BILLBOARD (Tarpaulin) w/ frame Qty. = 1.0 lot

DIRECT COST =

2. Kitikit Road Concreting, Pob. North. Lagawe


Item No.
I Removal of structures Qty. = 0.75 cu.m
Labor Cost
Manpower No. Rate Days Amount
Foreman 1 1.0
Laborers 2 1.0
Portable Jackhammer 1 1.0
total
DIRECT COST =
II Subgrade Preparation Qty. = 158.6 sq.m
Labor Cost
Manpower No. Rate Days Amount
Foreman 1 2.5
Laborers 4 2.5
total
DIRECT COST =
III Aggregate Base-Course Qty. = 7.93 cu.m
A. Material Cost
Description Unit Qty. U-Price Amount
Mixed Aggregate cu.m 9.50

B. Labor Cost
Manpower/Equipment No Rate Days Amount
Foreman 1 1.50
Laborer 2 1.50
Plate Compactor 1 1.50
total
DIRECT COST =
IV Form Works Qty. = 61 li.m
A. Material Cost
Description Unit Qty. U-Price
7pcs- 8" x 2" x 10' lumber bd.ft 93.33
2-16 mmRSB Pins kg. 18.94
Assorted CWN kg. 1.00

B. Labor Cost
Manpower/Equipment No Rate Days Amount
Foreman 1 1.00
Skilled Laborers 1 1.00
Laborers 1 1.00
total
DIRECT COST =
V PCCP Qty. = 357 sq.m.
A. Material Cost
Description Unit Qty U-Price Amount
Cement bags 283.00
Sand (S1) cu.m 16.00
Gravel (G2) cu.m 25.00
Asphalt bags 1.00
6pcs- 16 mm RSB Dowels kgs. 56.82
Measuring Box pcs. 2.00
Water Provision drums 39.00
total
B. Labor Cost
Description No. Rate Days Amount
Foreman 1 4
Skilled Laborers 2 4
Laborers 12 4
1 bagger-Concrete Mixer 1 4
total
DIRECT COST =
SPL BILLBOARD (Tarpaulin) w/ frame Qty. = 1.0 lot

DIRECT COST =

SUMMARY

1. Pob. South Provincial Road Concreting (Alindayo Section)


Item
Description Unit Qty Direct Cost Indirect Cost Unit Cost Adj. Cost % age
No.
I Removal of Structures cu.m 6.00
II Subgrade Preparation sq.m 416.50
III Aggregate Base-Course cu.m 35.80
IV Form Works li.m 238.00
V PCCP sq.m. 357.00
VI Side Embankment sq.m 23.80
SPL I Lay-out & Stacking lot 1.00
BILLBOARD (Tarpaulin)
SPL II lot 1.00
w/ frame
2. Kitikit Road Concreting, Pob. North. Lagawe
Item
Description Unit Qty Direct Cost Indirect Cost Unit Cost Adj. Cost % age
No.
I Removal of Structures cu.m 0.75
II Subgrade Preparation sq.m 158.60
III Aggregate Base-Course cu.m 7.93
IV Form Works li.m 61.00
V PCCP sq.m. 357.00
BILLBOARD (Tarpaulin)
SPL lot 1.00
w/ frame

TOTAL BID PRICE =


Prepared by:
Signature:
Name:
Construction Firm:
Republic of the Philippines
Provincial Local Government Unit of Ifugao
OFFICE OF THE PROVINCIAL ENGINEER
Lagawe, Ifugao

STATEMENT OF WORK ACCOMPLISHED

Name of Project : #REF!

Location : A. Lista, Ifugao

ITEM %TAGE PHYSICAL ACCOMPLISHMEN


DESCRIPTION UNIT QTY. U - Cost Amount
NO. WEIGHT PREVIOUS THIS PAYMENT
I Removal of Structures cu.m 6.00 23,712.50 142,275.00 13.61% - 6.00
II Subgrade Preparation sq.m 416.50 2,043.10 850,951.15 81.42% - 416.50
III Form Works cu.m 35.80 354.60 12,694.68 1.21% - 35.80
VI Err:509 cu.m 23.80 1,608.36 38,278.97 3.66% - 23.80
SPL II BILLBOARD (Tarpaulin) w/ frame lot 1.00 900.00 900.00 0.09% - 1.00
total = 1,045,099.80 100.00%

I HEREBY CERTIFY THAT THE WORK ITEMIZED ABOVE HAVE BEEN ACCOMPLISHED I HEREBY CERTIFY THAT THE BILL S
IN ACCORDANCE WITH THE PLANS, SPECIFICATION, AND REQUIREMENTS THEREOF. THEREOF, HAS NOT BEEN RECEIVED FOR W

PREPARED BY: CHECKED BY:

JOSE T. LIWAYAN JR. MENELEO D. OTGALON


Area Engineer Section Chief

CONFORME:

CNRJ CONSTRUCTION
Contractor
of the Philippines
overnment Unit of Ifugao
PROVINCIAL ENGINEER
awe, Ifugao

ORK ACCOMPLISHED

Project No:
Date:

PHYSICAL ACCOMPLISHMENT FINANCIAL ACCOMPLISHMENT %TAGE


TOTAL PREVIOUS THIS PAYMENT TOTAL Weight
6.00 - 142,275.00 142,275.00 13.61%
416.50 - 850,951.15 850,951.15 81.42%
35.80 - 12,694.68 12,694.68 1.21%
23.80 - 38,278.97 38,278.97 3.66%
1.00 - 900.00 900.00 0.09%
1,045,099.80 ### 99.99%

I HEREBY CERTIFY THAT THE BILL STATED ABOVE IS CORRECT AND JUST, THAT THE PAYMENT
THEREOF, HAS NOT BEEN RECEIVED FOR WORK ACCOMPLISHED AS INDICATED.

APPROVED BY:

MENELEO D. OTGALON JULIAN B. DULAWAN JR.


Section Chief Provincial Engineer
Republic of the Philippines
Provincial Local Government Unit of Ifugao
OFFICE OF THE PROVINCIAL ENGINEER
Lagawe, Ifugao
STATE M E NT O F W O R K AC C O M PLI S H E D

Name of Project : #REF!

Location : Aguinaldo, Ifugao

ITEM %TAGE PHYSICAL ACCOMPLISHMEN


DESCRIPTION UNIT QTY. U - Cost Amount
NO. WEIGHT PREVIOUS THIS PAYMENT
I Diversion of Water Flow cu.m 6.00 23,712.50 142,275.00 Err:509 - 6.00
Err:509 Err:509 Err:509 Err:509 3,638.14 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 3,141.09 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 90.78 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 107.64 Err:509 Err:509 - Err:509
II Subgrade Preparation sq.m 416.50 2,043.10 850,951.15 Err:509 - 416.50
III Form Works cu.m 35.80 354.60 12,694.68 Err:509 - 35.80
VI Err:509 cu.m 23.80 1,608.36 38,278.97 Err:509 - -0.20
SPL II BILLBOARD (Tarpaulin) w/ frame lot 1.00 900.00 900.00 Err:509 - 1.00
total = Err:509 Err:509

I HEREBY CERTIFY THAT THE WORK ITEMIZED ABOVE HAVE BEEN ACCOMPLISHED I HEREBY CERTIFY THAT THE BILL S
IN ACCORDANCE WITH THE PLANS, SPECIFICATION, AND REQUIREMENTS THEREOF. THEREOF, HAS NOT BEEN RECEIVED FOR W

PREPARED BY: CHECKED BY:

JOSE T. LIWAYAN JR. MENELEO D. OTGALON


Area Engineer Section Chief

CONFORME:

CNRJ CONSTRUCTION
Contractor
of the Philippines
overnment Unit of Ifugao
PROVINCIAL ENGINEER
awe, Ifugao
ORK ACCOMPLISHED

Project No:
Date: February 07, 2016

PHYSICAL ACCOMPLISHMENT FINANCIAL ACCOMPLISHMENT %TAGE


TOTAL PREVIOUS THIS PAYMENT TOTAL Weight
6.00 - 142,275.00 142,275.00 Err:509
Err:509 - Err:509 Err:509 Err:509
Err:509 - Err:509 Err:509 Err:509
Err:509 - Err:509 Err:509 Err:509
Err:509 - Err:509 Err:509 Err:509
416.50 - 850,951.15 850,951.15 Err:509
35.80 - 12,694.68 12,694.68 Err:509
-0.20 - (321.67) (321.67) Err:509
1.00 - 900.00 900.00 Err:509
Err:509 Err:509 Err:509

I HEREBY CERTIFY THAT THE BILL STATED ABOVE IS CORRECT AND JUST, THAT THE PAYMENT
THEREOF, HAS NOT BEEN RECEIVED FOR WORK ACCOMPLISHED AS INDICATED.

APPROVED BY:

MENELEO D. OTGALON JULIAN B. DULAWAN JR.


Section Chief Provincial Engineer
REQUEST FOR INSPECTION

29-Mar-16
DATE

DENIS B. HABAWEL
Provincial Governor
Lagawe,Ifugao

ATTENTION: JULIAN B. DULAWAN JR.


Provincial Engineer

Sir:

Reference Contract: #REF!


Location : Aguinaldo, Ifugao
Contract Amount : PHP 1,045,099.80

Contractor : CNRJ CONSTRUCTION

Requesting the members of your inspectorate Team for infrastructure to inspect the physical
accomplishment on the above referenced contract. This request is to support our billing request for
One Hundred percent ( 100 %) accomplishment.

Schedule of inspection will be on April 7, 2016

Anticipating your favorable action regarding this request.

Very truly yours,

CNRJ CONSTRUCTION
Contractor

Approval Recommended: Approved:

JULIAN B. DULAWAN JR. DENIS B. HABAWEL


Provincial Engineer Provincial Governor

Cc:

1. Provincial Accounting Office 3. Provincial Engineering Office


Lagawe,Ifugao Lagawe,Ifugao
2. Commission on Audit
Lagawe,Ifugao 4. F i l e
m for infrastructure to inspect the physical
quest is to support our billing request for
Republic of the Philippines
Provincial Local Government Unit of Ifugao
OFFICE OF THE PROVINCIAL ENGINEER
Lagawe, Ifugao

CERTIFICATE OF INSPECTION AND ACCEPTANCE

TO WHOM IT MAY CONCERN:

I HEREBY CERTIFY that I personally inspected this 7th day of April, 2016 the work accomplished by
CNRJ CONSTRUCTION under his/her contract and found that 100% (percentum) of the work called for the said
contract has been fully accomplished in accordance with the Plans and Specifications.

Name of Contract: #REF!


Location of Contract: Aguinaldo, Ifugao
Item Contract Previous Payment This Payment Total Accomp. To Date
Description
No. % Price % Amount % Amount % Amount
I Removal of Structures 13.61% 142,275.00 - - 13.61% 142,275.00 13.61% 142,275.00
Err:5
Err:509 Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
09
Err:5
Err:509 Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
09
Err:5
Err:509 Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
09
Err:5
Err:509 Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
09
II Subgrade Preparation 81.42% 850,951.15 - - 81.42% 850,951.15 81.42% 850,951.15
III Form Works 1.21% 12,694.68 - - 1.21% 12,694.68 1.21% 12,694.68
VI Err:509 3.66% 38,278.97 - - 3.66% 38,278.97 3.66% 38,278.97
SPL
BILLBOARD (Tarpaulin) w/ frame 0.09% 900.00 - - 0.09% 900.00 0.09% 900.00
II
subtotal Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

The work accomplished has been accordingly inspected and accepted by us for and in behalf of the Provincial Engineer in our
capacity as project inspector and the contractor is hereby entitled to payment as called for in the contract.
Measurements taken on the exposed dimensions of the final works satisfactorily conform to the plans/as-built plan prepared by the
project-in-charge, however for the inner/covered portions that could not be visibly checked during the inspection, the assessment was
based on the dimensions provided by the Project Engineer in the plans/as built plans and other project documents provided by them.
This report does not relieve the contractor of his obligations stipulated in the contract.

Done at Lagawe, Ifugao this 11th day of April 2016.

JOSE T. LIWAYAN JR. / MICHAEL B. BINUHI JONATHAN D. PAHIGON


Planning Section Quality Control

(P E O Representatives)

MOISES G. GALLANGI MOISES C. BAYANGAN


PGO Representative End-User Representative

Reviewed by:
Recommending Approval:
MENELEO D. OTGALON
Engineer III JULIAN B. DULAWAN JR.
Provincial Engineer
Approved:

DENIS B. HABAWEL
Provincial Governor
Republic of the Philippines
Provincial Local Government Unit of Ifugao
OFFICE OF THE PROVINCIAL ENGINEER
Lagawe, Ifugao

CERTIFICATE OF COMPLETION AND TURN-OVER

Inspected and found to have been 100% accomplished in accordance with Plans, Specifications,
and Program of Work as of April 7, 2016 and therefore recommended this turn-over to
end-users for custody.

1 Project No.
2 Name of Project: #REF!
3 Location of Project: A. Lista, Ifugao
4 Source of Fund: 2015-20% DF
5 Contractor: Name CNRJ CONSTRUCTION
Address: Ubao, Aguinaldo, Ifugao
6 Date of Notice to Proceed: December 11, 2015
7 Start of Contract Time December 20, 2015
8 Contract Duration (CD) 50 CD
9 Original Completion Date: February 7, 2016
10 Approved Time Extension: (CD) -
11 Revised Completion Date -
12 Actual Completion Date March 29, 2016
13 Percentage of Time Elapsed -
14 Percentage of Work Accomplished: 100%
15 Amount of Work Accomplished: Err:509
16 Slippage:
17 Original Contract Price Err:509
18 Revised Contract Price -

Prepared by: Checked by:

JOSE T. LIWAYAN JR. MENELEO D. OTGALON


Area Engineer Engineer III

Approval Recommended: Approved:

JULIAN B. DULAWAN JR. DENIS B. HABAWEL


Provincial Engineer Provincial Governor

April 11, 2016


Date

ACKNOWLEDGEMENT
Revised and accepted for custody and safekeeping the above specified project as per approved and
accepted work by the Provincial Local Government Unit of Ifugao.

As the project end-user, we assume full responsibility for the operation and maintenance of the structure.

MOISES C. BAYANGAN
Name and Signature

Barangay Captain
Official Designation
C O M P U TAT I O N O F LI Q U I DAT E D DAMAG E S

Name of Project : 1. Pob. South Provincial Road Concreting (Alindayo Section)

Location : Aguinaldo, Ifugao


Contract Amount : Php1,045,099.80
Date of NTP: December 11, 2015
Start of Contract Time: December 20, 2015
Contract Duration (CD): 0.0
Target Date of Completion: February 7, 2016
Actual Completion Date: March 29, 2016

Number of days delayed - 51.0 cal. Days


Percentage of accomplishment as of February 7, 2016

Err:509 of contract Err:509


Err:509 remaining Err:509
1% of Err:509 Err:509
Daily Charges = 1/10 of 1% Err:509

Liquidated Damages for 51.0 cal. Days = Err:509

Prepared by: Checked by :

JOSE T. LIWAYAN JR. MENELEO D. OTGALON


Area Engineer Engineer III

Approved:

JULIAN B. DULAWAN JR.


Provincial Engineer