You are on page 1of 13

[G.R. No. 129916.

March 26, 2001] 355 Scra 157 Disagreeing with the position taken by
MAGELLAN CAPITAL MANAGEMENT petitioners, respondent Zosa invoked the Arbitration
CORPORATION and MAGELLAN CAPITAL Clause of the Employment Agreement.
HOLDINGS CORPORATION, petitioners,
vs. ROLANDO M. ZOSA and HON. JOSE P. 23. Arbitration. In the event that any dispute,
SOBERANO, JR., in his capacity as Presiding controversy or claim arises out of or under any
Judge of Branch 58 of the Regional Trial Court provisions of this Agreement, then the parties hereto
Of Cebu, 7th Judicial Region, respondents. agree to submit such dispute, controversy or claim
to arbitration as set forth in this Section and the
determination to be made in such arbitration shall be
FACTS:
final and binding.
March 18, 1994 – a management agreement
were entered between Magellan Capital Holdings Arbitration shall be effected by a panel of
Corporation [MCHC] and Magellan Capital three arbitrators. The Manager, Employee and
Management Corporation [MCMC] the latter being Corporation shall designate one (1) arbitrator
appointed as the manager for the operation of its who shall, in turn, nominate and elect who
business and affairs of the prior. among them shall be the chairman of the
committee.
MCHC, MCMC, and private respondent
Rolando M. Zosa entered into an "Employment Any such arbitration, including the rendering
Agreement" designating Zosa as President and of an arbitration award, shall take place in Metro
Chief Executive Officer of MCHC. Manila. The arbitrators shall interpret this
Under the "Employment Agreement", the Agreement in accordance with the substantive laws
term of respondent Zosa's employment shall be co- of the Republic of the Philippines.
terminous with the management agreement, or until
March 1996,[2] unless sooner terminated pursuant to The arbitrators shall have no power to add to,
the provisions of the Employment Agreement. subtract from or otherwise modify the terms of
Agreement or to grant injunctive relief of any nature.
May 10, 1995 - majority of MCHCs Board of
Directors decided not to re-elect respondent Zosa as Any judgment upon the award of the
President and Chief Executive Officer of MCHC on arbitrators may be entered in any court having
account of loss of trust and confidence[4] arising from jurisdiction thereof, with costs of the arbitration to be
alleged violation of the resolution issued by MCHC's borne equally by the parties, except that each party
board of directors and of the non-competition clause shall pay the fees and expenses of its own counsel
of the Employment Agreement.[5] in the arbitration.
Nevertheless, respondent Zosa was elected
to a new position as MCHC's Vice- November 10, 1995 - respondent Zosa
Chairman/Chairman for New Ventures designated his brother, Atty. Francis Zosa, as his
Development. representative while MCHC designated Atty. Inigo S.
Fojas[10] and MCMC nominated Atty. Enrique I.
September 26, 1995 - Zosa communicated Quiason[11] as their respective representatives in the
his resignation for good reason from the position of arbitration panel.
Vice-Chairman under paragraph 7 of
the Employment Agreement on the ground that said But instead of submitting the dispute to
position had less responsibility and scope than arbitration, respondent Zosa, on April 17, 1996, filed
President and Chief Executive Officer. He an action for damages against petitioners before the
demanded that he be given termination benefits. RTC OF CEBU[12] to enforce his benefits under
October 20, 1995 - MCHC communicated its the Employment Agreement.
non-acceptance of respondent Zosa's resignation July 3, 1996 - petitioners filed a motion to
for good reason, but instead terminated him for dismiss[13] arguing that (1) the trial court has no
cause. He was further advised that he shall have no jurisdiction over the instant case since respondent
further rights under the said Agreement or any Zosa's claims should be resolved through arbitration
claims against the Manager or the Corporation pursuant to Section 23 of the Employment
except the right to receive within thirty (30) days from Agreement with petitioners; and (2) the venue is
November 19, 1995. improperly laid since respondent Zosa, like the
petitioners, is a resident of Pasig City thus the case The law of the case doctrine has been
is cognizable by RTC of PASIG. defined as a term applied to an established rule that
when an appellate court passes on a question and
July 5, 1996 - respondent Zosa filed an remands the cause to the lower court for further
amended complaint proceedings, the question there settled becomes the
ISSUE/S: law of the case upon subsequent appeal.[27] CAs
decision has already attained finality as evidenced
WON SEC has jurisdiction over the case - by a Resolution of this Court ordering entry of
Negative judgment of said case.
WON Article 23 of the Employment
Agreement or the Arbitration Clause Valid - Petitioners, therefore, are barred from
Affirmative challenging anew, through another remedial
measure and in any other forum, the authority of the
HELD: regional trial court to resolve the validity of the
The controversy does not in any way involve arbitration clause.
the election/appointment of officers of petitioner
MCHC, as claimed by petitioners in their assignment There is no quarrel that both defendants are
of errors. entirely two different corporations with personalities
Respondent Zosas amended complaint distinct and separate from each other and that a
focuses heavily on the illegality of the Employment corporation has a personality distinct and separate
Agreements Arbitration Clause initially invoked by from those persons composing the corporation as
him in seeking his termination benefits under well as from that of any other legal entity to which it
Section 8 of the employment contract. may be related.
And under Republic Act No. 876, otherwise
known as the Arbitration Law, it is the regional trial But as the defendants [herein petitioner]
court which exercises jurisdiction over questions represent the same interest, it could never be
relating to arbitration. expected, in the arbitration proceedings, that they
would not protect and preserve their own interest,
That jurisdiction lies with the SEC, which is much less, would both or either favor the interest of
raised for the first time in this petition, suffice it to the plaintiff.
state that the Amended Complaint squarely put in The arbitration law, as all other laws, is
issue the question whether the Arbitration Clause is intended for the good and welfare of everybody. In
valid and effective between the parties. fact, what is being challenged by the plaintiff herein
is not the law itself but the provision of the
Although the controversy which spawned the Employment Agreement based on the said law,
action concerns the validity of the termination of the which is the arbitration clause but only as regards
service of a corporate officer, the issue on the the composition of the panel of
validity and effectivity of the arbitration clause is arbitrators. Arbitration Clause state:
determinable by the regular courts, and do not fall
within the exclusive and original jurisdiction of the (Go to first page for the Arbitration Clause)
SEC.
It appears that the two (2) defendants
The determination and validity of the [petitioners] (MCMC and MCHC) have one (1)
agreement is not a matter intrinsically connected arbitrator each to compose the panel of three (3)
with the regulation and internal affairs of arbitrators.
corporations it is rather an ordinary case to be As the defendant MCMC is the Manager of
decided in accordance with the general laws, and do defendant MCHC, its decision or vote in the
not require any particular expertise or training to arbitration proceeding would naturally and certainly
interpret and apply. be in favor of its employer and the defendant MCHC
would have to protect and preserve its own interest;
Decision of the CA affirming the trial courts hence, the two (2) votes of both defendants (MCMC
assumption of jurisdiction over the case has become and MCHC) would certainly be against the lone
the law of the case which now binds the petitioners. arbitrator for the plaintiff [herein defendant].
Hence, apparently, plaintiff [defendant] mutually acceptable solution to their conflicting
would never get or receive justice and fairness in the claims.
arbitration proceedings from the panel of arbitrators
as provided in the aforequoted arbitration clause. Any arrangement or scheme that would give
undue advantage to a party in the negotiating table
is anathema to the very purpose of arbitration and
In fairness and justice to the plaintiff should, therefore, be resisted.
[defendant], the two defendants (MCMC and
MCHC)[herein petitioners] which represent the WHEREFORE, premises considered, the
same interest should be considered as one and petition is hereby DISMISSED and the decision of
should be entitled to only one arbitrator to represent the trial court dated July 18, 1997 is AFFIRMED.
them in the arbitration proceedings. SO ORDERED.

Accordingly, the arbitration clause, insofar as


the composition of the panel of arbitrators is [G.R. No. 141833. March 26, 2003] 399 Scra 562
concerned should be declared void and of no effect, LM POWER
because the law says, Any clause giving one of the ENGINEERING CORPORATION, petitioner,
parties power to choose more arbitrators than the vs. CAPITOL INDUSTRIAL CONSTRUCTION
other is void and of no effect. GROUPS, INC., respondent.
DECISION
The dispute or controversy between the The Facts
defendants (MCMC and MCHC) [herein petitioners] On February 22, 1983, Petitioner LM Power
and the plaintiff [herein defendant] should be settled Engineering Corporation and Respondent Capitol
in the arbitration proceeding in accordance with the Industrial Construction Groups Inc. entered into a
Employment Agreement, but under the panel of Subcontract Agreement involving electrical work at
three (3) arbitrators, one (1) arbitrator to represent the Third Port of Zamboanga.[5]
the plaintiff, one (1) arbitrator to represent both
defendants (MCMC and MCHC) [herein petitioners]
and the third arbitrator to be chosen by the plaintiff On April 25, 1985, respondent took over
[defendant Zosa] and defendants [petitioners]. some of the work contracted to
petitioner.[6] Allegedly, the latter had failed to finish it
because of its inability to procure materials.[7]
This issue of estoppel, well- settled is the rule
that issues not raised below cannot be resolved on
review in higher courts.[31] Upon completing its task under the Contract,
petitioner billed respondent in the amount
of P6,711,813.90.[8] Contesting the accuracy of the
Secondly, employment agreements such as the amount of advances and billable accomplishments
one at bar are usually contracts of adhesion. Any listed by the former, the latter refused to pay.
ambiguity in its provisions is generally resolved
against the party who drafted the document.
Respondent also took refuge in the
A contract of employment, being a contract of termination clause of the Agreement.[9] That clause
adhesion, is ambiguous, any ambiguity therein allowed it to set off the cost of the work that petitioner
should be construed strictly against the party who had failed to undertake -- due to termination or take-
prepared it. over -- against the amount it owed the latter.
And, finally, respondent Zosa never submitted
himself to arbitration proceedings (as there was Because of the dispute, petitioner filed with
none yet) before bewailing the composition of the the Regional Trial Court (RTC) of Makati (Branch
panel of arbitrators. 141) a Complaint[10] for the collection of the amount
representing the alleged balance due it under the
He in fact, lost no time in assailing the arbitration Subcontract.
clause upon realizing the inequities that may mar the
arbitration proceedings if the existing line-up of
arbitrators remained unchecked. Instead of submitting an Answer, respondent
filed a Motion to Dismiss,[11] alleging that the
We need only to emphasize in closing that Complaint was premature, because there was no
arbitration proceedings are designed to level the prior recourse to arbitration.
playing field among the parties in pursuit of a
In its Order[12] dated September 15, 1987, accomplishments, and the set off of expenses
the RTC denied the Motion on the ground that the incurred by respondent in its take-over of petitioners
dispute did not involve the interpretation or the work.
implementation of the Agreement and was, We side with respondent. Essentially, the
therefore, not covered by the arbitral clause.[13] dispute arose from the parties ncongruent positions
on whether certain provisions of their Agreement
After trial on the merits, the RTC[14] ruled that could be applied to the facts.
the take-over of some work items by respondent was
not equivalent to a termination, but a mere The instant case involves technical
modification, of the Subcontract. discrepancies that are better left to an arbitral body
that has expertise in those areas.
The latter was ordered to give full payment
for the work completed by petitioner. In any event, the inclusion of an arbitration
The Issues clause in a contract does not ipso facto divest the
In its Memorandum, petitioner raises the courts of jurisdiction to pass upon the findings of
following issues for the Courts consideration: arbitral bodies, because the awards are still judicially
reviewable under certain conditions.[18]
A
Whether or not there exist[s] a In the case before us, the Subcontract has
controversy/dispute between petitioner and the following arbitral clause:
respondent regarding the interpretation and
implementation of the Sub-Contract Agreement 6. The Parties hereto agree that any dispute
dated February 22, 1983 that requires prior recourse or conflict as regards to interpretation and
to voluntary arbitration; implementation of this Agreement which cannot be
settled between [respondent] and [petitioner]
B amicably shall be settled by means of arbitration x x
x.[19]
In the affirmative, whether or not the
requirements provided in Article III [1] of CIAC Clearly, the resolution of the dispute between
Arbitration Rules regarding request for arbitration the parties herein requires a referral to the provisions
ha[ve] been complied with[.][17] of their Agreement.

The Courts Ruling Within the scope of the arbitration clause are
discrepancies as to the amount of advances and
The Petition is unmeritorious.
billable accomplishments, the application of the
provision on termination, and the consequent set-off
First Issue: of expenses.
Whether Dispute Is Arbitrable
Petitioner claims that there is no conflict A review of the factual allegations of the
regarding the interpretation or the implementation of parties reveals that they differ on the following
the Agreement. questions: (1) Did a take-over/termination occur? (2)
May the expenses incurred by respondent in the
Thus, without having to resort to prior take-over be set off against the amounts it owed
arbitration, it is entitled to collect the value of the petitioner? (3) How much were the advances and
services it rendered through an ordinary action for billable accomplishments?
the collection of a sum of money from respondent.
The resolution of the foregoing issues lies in
On the other hand, the latter contends that the interpretation of the provisions of the
there is a need for prior arbitration as provided in the Agreement. According to respondent, the take-over
Agreement. was caused by petitioners delay in completing the
work. Such delay was in violation of the provision in
This is because there are some disparities the Agreement as to time schedule:
between the parties positions regarding the extent of
the work done, the amount of advances and billable G. TIME SCHEDULE
[Petitioner] shall adhere strictly to the letters of credit, and taxes and duties as set forth in
schedule related to the WORK and complete the the Agreement.
WORK within the period set forth in Annex C
hereof. NO time extension shall be granted by These data can be gathered from a review of
[respondent] to [petitioner] unless a corresponding the Agreement, pertinent portions of which are
time extension is granted by [the Ministry of Public reproduced hereunder:
Works and Highways] to the CONSORTIUM.[20]
C. CONTRACT PRICE AND TERMS OF
PAYMENT
Because of the delay, respondent alleges xxxxxxxxx
that it took over some of the work contracted to
petitioner, pursuant to the following provision in the
Agreement: All progress payments to be made by
[respondent] to [petitioner] shall be subject to a
retention sum of ten percent (10%) of the value of
K. TERMINATION OF AGREEMENT the approved quantities.
[Respondent] has the right to terminate
and/or take over this Agreement for any of the
Any claims by [respondent] on [petitioner]
following causes:
may be deducted by [respondent] from the progress
xxxxxxxxx payments and/or retained amount.

6. If despite previous warnings by Any excess from the retained amount after
[respondent], [petitioner] does not execute the deducting [respondents] claims shall be released by
WORK in accordance with this Agreement, [respondent] to [petitioner] after the issuance of [the
or persistently or flagrantly neglects to carry out [its] Ministry of Public Works and Highways] of the
obligations under this Agreement.[21] Certificate of Completion and final acceptance of the
Supposedly, as a result of the take-over, WORK by [the Ministry of Public Works and
respondent incurred expenses in excess of the Highways].
contracted price. xxxxxxxxx

It sought to set off those expenses against D. IMPORTED MATERIALS AND


the amount claimed by petitioner for the work the EQUIPMENT
latter accomplished, pursuant to the following
[Respondent shall open the letters of credit for the
provision:
importation of equipment and materials listed in
If the total direct and indirect cost of Annex E hereof after the drawings, brochures, and
completing the remaining part of the WORK exceed other technical data of each items in the list have
the sum which would have been payable to been formally approved by [the Ministry of Public
[petitioner] had it completed the WORK, the amount Works and Highways].
of such excess [may be] claimed by [respondent]
from either of the following:
However, petitioner will still be fully
responsible for all imported materials and
1. Any amount due [petitioner] from equipment.
[respondent] at the time of the termination of this
Agreement.[22]
All expenses incurred by [respondent], both
in foreign and local currencies in connection with the
The issue as to the correct amount of opening of the letters of credit shall be deducted
petitioners advances and billable accomplishments from the Contract Prices.
involves an evaluation of the manner in which the
xxxxxxxxx
parties completed the work, the extent to which they
did it, and the expenses each of them incurred in
connection therewith. N. OTHER CONDITIONS
xxxxxxxxx
Arbitrators also need to look into the 2. All customs duties, import duties,
computation of foreign and local costs of materials, contractors taxes, income taxes, and other taxes
foreign and local advances, retention fees and that may be required by any government agencies in
connection with this Agreement shall be for the sole have been exhausted within 90 days from the time
account of [petitioner].[23] the dispute arose.

Being an inexpensive, speedy and amicable Tesco was promulgated by this Court, using
method of settling disputes,[24] arbitration -- along the foregoing provision as reference.
with mediation, conciliation and negotiation -- is On the other hand, Section 1 of Article III of
encouraged by the Supreme Court.Aside from the new Rules of Procedure Governing Construction
unclogging judicial dockets, arbitration also hastens Arbitration has dispensed with this requirement and
the resolution of disputes, especially of the recourse to the CIAC may now be availed of
commercial kind.[25] whenever a contract contains a clause for the
submission of a future controversy to arbitration, in
It is thus regarded as the wave of the future this wise:
in international civil and commercial
disputes.[26] Brushing aside a contractual agreement SECTION 1. Submission to CIAC
calling for arbitration between the parties would be a Jurisdiction An arbitration clause in a construction
step backward.[27] contract or a submission to arbitration of a
construction dispute shall be deemed an agreement
Consistent with the above-mentioned policy to submit an existing or future controversy to CIAC
of encouraging alternative dispute resolution jurisdiction, notwithstanding the reference to a
methods, courts should liberally construe arbitration different arbitration institution or arbitral body in such
clauses. contract or submission.

Provided such clause is susceptible of an When a contract contains a clause for the
interpretation that covers the asserted dispute, an submission of a future controversy to arbitration, it is
order to arbitrate should be granted.[28] Any doubt not necessary for the parties to enter into a
should be resolved in favor of arbitration.[29] submission agreement before the claimant may
invoke the jurisdiction of CIAC.
Second Issue:
Prior Request for Arbitration The foregoing amendments in the Rules
were formalized by CIAC Resolution Nos. 2-91 and
According to petitioner,
3-93.[31]
assuming arguendo that the dispute is arbitrable,
the failure to file a formal request for arbitration with
the Construction Industry Arbitration Commission The difference in the two provisions was
(CIAC) precluded the latter from acquiring clearly explained in China Chang Jiang Energy
jurisdiction over the question. Corporation (Philippines) v. Rosal Infrastructure
Builders et al.[32] (an extended unsigned Resolution)
and reiterated in National Irrigation Administration v.
To bolster its position, petitioner even cites
Court of Appeals,[33] from which we quote thus:
our ruling in Tesco Services Incorporated v.
Vera.[30] We are not persuaded.
Under the present Rules of Procedure, for a
particular construction contract to fall within the
Section 1 of Article II of the old Rules of
jurisdiction of CIAC, it is merely required that the
Procedure Governing Construction Arbitration
parties agree to submit the same to voluntary
indeed required the submission of a request for
arbitration.
arbitration, as follows:

Unlike in the original version of Section 1, as


SECTION. 1. Submission to Arbitration --
applied in the Tesco case, the law as it now stands
Any party to a construction contract wishing to have
does not provide that the parties should agree to
recourse to arbitration by the Construction Industry
submit disputes arising from their agreement
Arbitration Commission (CIAC) shall submit its
specifically to the CIAC for the latter to acquire
Request for Arbitration in sufficient copies to the
jurisdiction over the same.
Secretariat of the CIAC; PROVIDED, that in the case
of government construction contracts, all
administrative remedies available to the parties must Rather, it is plain and clear that as long as
the parties agree to submit to voluntary arbitration,
regardless of what forum they may choose, their by the parties before the CIAC and incorporated in
agreement will fall within the jurisdiction of the CIAC, the original TOR, are as follows :
such that, even if they specifically choose another
forum, the parties will not be precluded from electing 1. On 21 April 1994, the parties formally
to submit their dispute before the CIAC because this entered into a contract for the construction of the
right has been vested upon each party by law, i.e., "Chatham House" . . . for the contract price of price
E.O. No. 1008.[34] of P50,000,000.00

Clearly, there is no more need to file a 2. On 12 July 1994, a Supplemental Contract


request with the CIAC in order to vest it with was executed by and between the parties whereby
jurisdiction to decide a construction dispute. CHATHAM authorized MCI to procure in behalf of
the former materials, equipment, etc.
The arbitral clause in the Agreement is a
commitment on the part of the parties to submit to 3. Under Section I.04 of the Supplemental
arbitration the disputes covered therein. Contract, the total amount of procurement and
transportation cost[s] and expenses which may be
Because that clause is binding, they are reimbursed by MCI from CHATHAM shall not
expected to abide by it in good faith.[35] And because exceed the amount of P75, 000,000.00.
it covers the dispute between the parties in the
present case, either of them may compel the other 4. In the course of the construction, Change
to arbitrate.[36] Orders No. 1, 4, 8A, 11, 12 and 13 were
implemented,
Since petitioner has already filed a
Complaint with the RTC without prior recourse to 5. CHATHAM reimbursed MCI the amount of
arbitration, the proper procedure to enable the CIAC P60,000.00 corresponding to bonuses advanced to
to decide on the dispute is to request the stay or its workers by the latter for the 14th, 16th, and 17th
suspension of such action, as provided under RA floors.
876 [the Arbitration Law].[37]
6. CHATHAM's payments to MCI totaled
P104,875,792.37, representing payments for
WHEREFORE, the Petition is DENIED and the portions of MCI's progress billings and x x x
assailed Decision AFFIRMED. Costs against additional charges..
petitioner.
In the resolution of these issues, the CIAC
G.R. No. 141897 September 24, 2001, 365 Scra discovered significant data, which were not evident
697 METRO CONSTRUCTION, INC., petitioner, or explicit in the documents and records but
vs. CHATHAM PROPERTIES, INC., respondent. otherwise revealed or elicited during the hearings,
FACTS : which the CIAC deemed material and relevant to the
Respondent Chatham Properties, Inc. complete adjudication of the case
(CHATHAM) and petitioner Metro Construction, Inc.
(MCI) entered into a contract for the construction of The CIAC disposed of the specific money
a multi-storey building known as the Chatham claims by either granting or reducing them. On Issue
House. In April 1998, MCI sought to collect from No. 9, i.e., whether CHATHAM failed to complete
CHATHAM a sum of money for unpaid progress and/or deliver the project within the approved
billings and other charges and instituted a request completion period and, if so, whether CHATHAM is
for adjudication of its claims with the CIAC. liable for liquidated damages and how much.

The preliminary conference before the CIAC CIAC rendered Judgment in favor of the
started in June 1998 and was concluded a month Claimant [MCI] directing Respondent [CHATHAM] to
after with the signing of the Terms of Reference pay Claimant [MCI] the net sum of SIXTEEN
(TOR) of the Case. MILLION ONE HUNDRED TWENTY SIX
THOUSAND NINE HUNDRED TWENTY TWO &
In the meantime, the TOR was amended and 91/100 (16,126,922.91) PESOS. Impugning the
finalized on 19 August 1998. The facts, as admitted decision of the CIAC, CHATHAM instituted a petition
for review with the Court of Appeals
of the CIAC even if it is not named in the
In upholding the decision of the CIAC, the enumeration of quasi-judicial agencies.
Court of Appeals confirmed the jurisprudential
principle that absent any showing of arbitrariness, In sum, under Circular No. 1-91, appeals
the CIAC's findings as an administrative agency and from the arbitral awards of the CIAC may be brought
quasi-judicial body should not only be accorded to the Court of Appeals, and not to the Supreme
great respect but also given the stamp of finality. Court alone. The grounds for the appeal are likewise
broadened to include appeals on questions of facts
However the Court of Appeals found and appeals involving mixed questions of fact and
exception in the CIAC's disquisition of Issue No.9 on law
the matter of liquidated damages.
The jurisdiction of the Court of Appeals over
ISSUE : appeals from final orders or decisions of the CIAC is
WON under existing law and rules the Court further fortified by the amendments to B.P. Blg. 129,
of Appeals can also review findings of facts of the as introduced by RA. No. 7902.
Construction Industry Arbitration Commission
(CIAC) With the amendments, the Court of Appeals
is vested with appellate jurisdiction over all final
HELD : judgments, decisions, resolutions, orders or awards
of Regional Trial Courts and quasi-judicial agencies,
EO. No. 1008 vest upon the CIAC original
instrumentalities, boards or commissions, except
and exclusive jurisdiction over disputes arising from,
"those within the appellate jurisdiction of the
or connected with, contracts entered into by parties
Supreme Court in accordance with the Constitution,
involved in construction in the Philippines, whether
the Labor Code of the Philippines under Presidential
the dispute arises before or after the completion of
Decree No. 442, as amended, the provisions of this
the contract, or after the abandonment or breach
Act, and of subparagraph (1) of the third paragraph
thereof.
and subparagraph (4) of the fourth paragraph of
By express provision of Section 19 thereof, Section 17 of the Judiciary Act of 1948.".
the arbitral award of the CIAC is final and
unappealable, except on questions of law, which are
appealable to the Supreme Court. In view of all the foregoing, The Supreme
Court rejects MCI's submission that Circular No. 1-
91, B.P. Blg. 129, as amended by RA. 7902, Revised
The parties, however, disagree on whether Administrative Circular 1-95, and Rule 43 of the
the subsequent Supreme Court issuances on 1997 Rules of Civil Procedure failed to efficaciously
appellate procedure and R.A. No. 7902 removed modify the provision on appeals in E.O. No. 1008.
from the Supreme Court its appellate jurisdiction in
318 Scra 558 HOME BANKERS SAVINGS
Section 19 of E.O. No. 1008 and vested the same in
AND TRUST COMPANY V. CA (G.R. NO. 115412)
the Court of Appeals, and whether appeals from
CISC awards are no longer confined to questions of
law. Facts:
Victor Tancuan issued Petitioner Home
Through Circular No. 1-91, the Supreme Bankers Savings and Trust Company a check while
Court intended to establish a uniform procedure for Eugene Arriesgado issued Private Respondent Far
the review of the final orders or decisions of the East Bank and Trust Company three checks; both
Court of Tax Appeals and other quasi judicial. checks totaling the amount of P25,250,000.00.

The Circular designated the Court of Appeals Tancuan and Arriesgado exchanged each
as the reviewing body to resolve questions of fact or other’s checks and deposited them with their
of law or mixed questions of fact and law. respective banks for collection. When FEBTC
presented Tancuan’s HBSTC check for clearing, it
was dishonored for being DAIF.
It is clear that Circular No. 1-91 covers the
CIAC. In the first place, it is a quasi judicial agency.
In the second place, the language of Section 1 of Meanwhile, HBSTC sent Arriesgado’s 3
Circular No. 1-91 emphasizes the obvious inclusion FEBTC checks through the Philippine Clearing
House Corporation (PCHC) to FEBTC but was Petitioner’s exposition of the foregoing
returned for being DAIF. provision deserves scant consideration. Section 14
simply grants an arbitrator the power to issue
HBSTC receive the notice of dishonor but subpoena and subpoena duces tecum at any time
refused to accept the checks and returned them to before rendering the award.
FEBTC through the PCHC for the reason “Beyond
Reglementary Period,” implying that HBSTC already The exercise of such power is without
treated the 3 checks as cleared and allowed the prejudice to the right of a party to file a petition in
proceeds thereof to be withdrawn. court to safeguard any matter which is the subject of
the dispute in arbitration.
FEBTC demanded reimbursement for the
returned checks and inquired from HBSTC whether In the case at bar, private respondent filed an
it had permitted any withdrawal of funds against the action for a sum of money with prayer for a writ of
unfunded checks. preliminary attachment. Undoubtedly, such action
involved the same subject matter as that in
HBSTC, however refused to make any arbitration, i.e., the sum of P25,200,000.00 which
reimbursement and to provide FEBTC with the was allegedly deprived from private respondent in
needed information. what is known in banking as a “kiting scheme.”
Thus, FEBTC submitted the dispute for
arbitration before the PCHC Arbitration Committee, However, the civil action was not a simple
under its Supplementary Rules on Regional Clearing case of a money claim since private respondent has
to which FEBTC and HBSTC are bound as included a prayer for a writ of preliminary
participants in the regional clearing operations attachment, which is sanctioned by section 14 of the
administered by the PCHC. Arbitration Law.
While the arbitration proceeding was still
pending, FEBTC filed an action for sum of money Simply put, participants in the regional
and damages with preliminary attachment against clearing operations of the Philippine Clearing House
HBSTC. Corporation cannot bypass the arbitration process
HBSTC moved to dismiss on the ground that laid out by the body and seek relief directly from the
there is no cause of action and because it seeks to courts.
enforce an arbitral award which as yet does not In the case at bar, undeniably, private
exist. The trial court denied the motion to dismiss respondent has initiated arbitration proceedings as
and the motion for reconsideration. Petitioner then required by the PCHC rules and regulations, and
filed a petition for certiorari with respondent CA to pending arbitration has sought relief from the trial
which it had dismissed. court for measures to safeguard and/or conserve the
subject of the dispute under arbitration, as
Issue: sanctioned by section 14 of the Arbitration Law, and
otherwise not shown to be contrary to the PCHC
Whether or not private respondent which
rules and regulations.
commenced an arbitration proceeding under the
auspices of the PCHC may subsequently file a
separate case in court over the same subject matter At this point, we emphasize that arbitration,
despite the pendency of that arbitration, simply to as an alternative method of dispute resolution, is
obtain the provisional remedy of attachment against encouraged by this Court.
the adverse party in the arbitration proceeding.
Aside from unclogging judicial dockets, it
Ruling: also hastens solutions especially of commercial
We find no merit in the petition. Section 14 of disputes. The Court looks with favor upon such
Republic Act 876, otherwise known as the amicable arrangement and will only interfere with
Arbitration Law, allows any party to the arbitration great reluctance to anticipate or nullify the action of
proceeding to petition the court to take measures to the arbitrator.
safeguard and/or conserve any matter which is the
subject of the dispute in arbitration. Wherefore, premises considered, the petition
is hereby dismissed and the decision of the court a
quo is affirmed.
TOYOTA MOTOR PHILIPPINES CORPORATION Issue:
V. CA (G.R. NO. 102881) 216 Scra 236 Whether or not Judge Tensuan had
Facts: jurisdiction to take cognizance of the case for
This case involves a boundary dispute reformation of instrument.
between petitioner Toyota Motor Phil. Corporation
(Toyota) and private respondent Sun Valley Ruling:
Manufacturing and Development Corporation (Sun Attention must first be brought to the fact that the
Valley). contract of sale executed between APT and Toyota
Both Toyota and Sun Valley are the provides an arbitration clause which states that:
registered owners of two (2) adjoining parcels of land 5. In case of disagreement or conflict arising out
which they purchased from the Asset Privatization of this Contract, the parties hereby undertake
Trust (APT). The properties in question formerly to submit the matter for determination by a
belonged to Delta Motors Corporation (DMC) which committee of experts, acting as arbitrators,
were foreclosed by the Philippine National Bank the composition of which shall be as follows:
(PNB) and later transferred to the national a) One member to be appointed by the
government through the APT for disposition. VENDOR; b) One member to be appointed
by the VENDEE; c) One member, who shall
APT then proceeded to classify the DMC be a lawyer, to be appointed by both of the
properties, called the GC III-Delta Motors aforesaid parties;
Corporation, and divided into Delta I, Delta II, and The contention that the arbitration clause has
Delta III. Further subdivisions for the separate become dysfunctional because of the presence of
catalogues were made for each division e.g. Delta I third parties is untenable.
into Lots 1, 2 and 3. After this classification, APT
parcelled out and catalogued the properties for
Toyota filed an action for reformation of its
bidding and sale.
contract with APT, the purpose of which is to look
into the real intentions/agreement of the parties to
Part of the duly parcelled Delta I property (Lot the contract and to determine if there was really a
2) was sold to Toyota through public bidding. After mistake in the designation of the boundaries of the
its purchase, Toyota constructed a concrete hollow property as alleged by Toyota.
block (CHB) perimeter fence around its alleged
property. Another part of the parcelled Delta I (Lot 1)
Such questions can only be answered by the
was purchased by Sun Valley from APT.
parties to the contract themselves. This is a
controversy which clearly arose from the contract
Petitioner then filed a case against APT for entered into by APT and Toyota. Inasmuch as this
the reformation of the Deed of Sale executed concerns more importantly the parties APT and
between them alleging that the instrument failed to Toyota themselves, the arbitration committee is
reflect the true intention of the parties as the title therefore the proper and convenient forum to settle
failed to include 723 square meters strip of land. the matter as clearly provided in the deed of sale.

On the other hand, Sun Valley, filed a case Having been apprised of the presence of the
for recovery of possession of the disputed 723 arbitration clause in the motion to dismiss filed by
square meters relying upon the title description of its APT, Judge Tensuan should have at least
property and the surveys it has commissioned. suspended the proceedings and directed the parties
to settle their dispute by arbitration. Judge Tensuan
Through legal maneuverings, the parties should have not taken cognizance of the case.
have succeeded in muddling up the vital issues of
the case and getting the lower courts embroiled in In view of all the foregoing, the petition is
numerous appeals over technicalities. hereby dismissed for failure to show reversible error,
much less grave abuse of discretion, on the part of
Hence, the three appellate the respondent court.
decisions/resolutions before the Court for review
and conflicting orders issued by lower courts as a DEL MONTE CORP. USA vs. CA, 351 Scra 373
result of the separate cases filed by the parties.
GR No. 136154 | Feb 7, 2001 | Petition for Review
on Certiorari | Bellosillo  3 October 1996 - MMI, SFI and MMI’s
Petitioners: Del Monte Corp. USA, Paul Derby Managing Director LiongLiong C. Sy (LILY
Jr., Daniel Collins & Luis Hidalgo SY) filed a Complaint against DMC-USA,
Respondents: CA, Malabon RTC Branch Managing Director of Del Monte
74 Judge Bienvenido Reyes, Corporation’s Export Sales DepartmentPaul
MontebuenoMarketing, Inc., LiongLiong C. Sy E. Derby, Jr.,Regional Director of Del Monte
and SabrosaFodds, Inc. Corporation’s Export Sales
DepartmentDaniel Collins, Head of Credit
Facts: Services Department of Del Monte
Corporation Luis Hidalgo and Dewey Ltd.
 1 July 1994 - in a Distributorship Agreement, before Malabon RTC.
Del Monte Corporation-USA (DMC-USA)
appointed Montebueno Marketing, Inc.
(MMI) as the sole and exclusive distributor of  MMI et al. predicated their complaint on the
its Del Monte products in the Philippines for alleged violations by Del Monte et al. of
a period of five (5) years, renewable for two Articles 201, 212 and 233 of the Civil Code.
(2) consecutive five (5) year periods with the
consent of the parties. According to them, DMC-USA products
continued to be brought into the country by parallel
 Said agreement provided for an arbitration importers despite the appointment of MMI as the
clause, which states: sole and exclusive distributor of Del Monte products
thereby causing them great embarrassment and
This Agreement shall be governed by the laws of
substantial damage.
the State of California and/or, if applicable, the
United States of America. All disputes arising out of
or relating to this Agreement or the parties’ They alleged that the products brought into the
relationship, including the termination thereof, shall country by these importers were aged, damaged,
be resolved by arbitration in the City of San fake or counterfeit, so that in March 1995 they had
Francisco, State of California, under the Rules of the to cause, after prior consultation with Antonio
American Arbitration Association. Ongpin, Market Director for Special Markets of Del
Monte Philippines, Inc., the publication of a "warning
to the trade" paid advertisement in leading
The arbitration panel shall consist of three
newspapers. DMC-USA and Paul E. Derby, Jr.,
members, one of whom shall be selected by DMC-
apparently upset with the publication, instructed
USA, one of whom shall be selected by MMI, and
private respondent MMI to stop coordinating with
third of whom shall be selected by the other two
Antonio Ongpin and to communicate directly instead
members and shall have relevant experience in the
with DMC-USA through Paul E. Derby, Jr.
industry

 MMI et al. further averred that:


 October 1994 - appointment of MMI as the
sole and exclusive distributor of Del Monte 1. DMC-USA et al. knowingly and
products in the Philippines was published in surreptitiously continued to deal with the
several newspapers in the country. former in bad faith by involving
disinterested third parties and by
proposing solutions which were entirely
 Immediately after its appointment, MMI out of their control
appointed Sabrosa Foods, Inc. (SFI), with
the approval of DMC-USA, as MMI’s
marketing arm to concentrate on its 2. they had exhausted all possible avenues
marketing and selling function as well as to for an amicable resolution and settlement
manage its critical relationship with the trade. of their grievances

1Art.20. Every person who, contrary to law, wilfully or negligently


causes damage to another, shall indemnify the latter for the same. 3Art. 23. Even when an act or event causing damage to another's
property was not due to the fault or negligence of the defendant,
2Art.21. Any person who wilfully causes loss or injury to another the latter shall be liable for indemnity if through the act or event
in a manner that is contrary to morals, good customs or public he was benefited.
policy shall compensate the latter for the damage.
Suspend Proceedings of 17 October 1996
3. as a result of the fraud, bad faith, malice and Motion for Reconsideration of 14
and wanton attitude of DMC-USA et al., January 1997.
they should be held responsible for all the
actual expenses incurred by MMI et al. in  11 November 1997 - the Motion to Suspend
the delayed shipment of orders which Proceedings was denied by the trial court on
resulted in the extra handling thereof, the the ground that it "will not serve the ends of
actual expenses and cost of money for justice and to allow said suspension will only
the unused Letters of Credit (LCs) and delay the determination of the issues,
the substantial opportunity losses due to frustrate the quest of the parties for a
created out-of-stock situations and judicious determination of their respective
unauthorized shipments of Del Monte- claims, and/or deprive and delay their rights
USA products to the Philippine Duty Free to seek redress.
Area and Economic Zone
 On appeal, the CA affirmed the RTC
4. the bad faith, fraudulent acts and willful decision.
negligence of DMC-USA et al., motivated
by their determination to squeeze MMI et
al. out of the outstanding and on-going  Hence, this petition.
Distributorship Agreement in favor of
another party, had placed Lily Sy on Issue:
tenterhooks since then WON the dispute between the parties
warrants an order compelling them to submit to
5. the shrewd and subtle manner with which arbitration [NO]
DMC-USA et al. concocted imaginary
violations by MMI of the Distributorship Ratio:
Agreement in order to justify the untimely  There is no doubt that arbitration is valid and
termination thereof was a subterfuge constitutional in our jurisdiction. Even before
the enactment of RA 876, this Court has
 21 October 1996 – DMC-USA et al. filed countenanced the settlement of disputes
a Motion to Suspend Proceedings, invoking through arbitration.
the arbitration clause.
Unless the agreement is such as
 RTC: deferred consideration of DMC-USA et absolutely to close the doors of the courts
al.’s Motion to Suspend Proceedings as the against the parties, which agreement would
grounds alleged therein did not constitute the be void.
suspension of the proceedings considering
that the action was for damages with prayer The courts will look with favor upon
for the issuance of Writ of Preliminary such amicable arrangement and will only
Attachment and not on the Distributorship interfere with great reluctance to anticipate or
Agreement nullify the action of the arbitrator.

 DMC-USA et al. filed a MR to which MMI et Moreover, as RA 876 expressly


al. filed their comment/opposition. authorizes arbitration of domestic disputes,
 DMC-USA et al. filed a reply. They later on foreign arbitration as a system of settling
filed a Motion to Admit Supplemental commercial disputes was likewise
Pleading. recognized when the Philippines adhered to
the United Nations "Convention on the
 Said motion was admitted. Recognition and the Enforcement of Foreign
Arbitral Awards of 1958" under the 10 May
1965 Resolution No. 71 of the Philippine
 As a result of the admission of Senate.
the Supplemental Complaint, DMC-USA et
al. filed on 22 July 1997
a Manifestation adopting their Motion to
Giving reciprocal recognition and o In Toyota, the Court ruled that "[t]he
allowing enforcement of international contention that the arbitration clause
arbitration agreements between parties of has become dysfunctional because
different nationalities within a contracting of the presence of third parties is
state. untenable ratiocinating that
"[c]contracts are respected as the law
 A careful examination of the instant case between the contracting parties “and
shows that the arbitration clause in the that "[a]s such, the parties are
Distributorship Agreement between DMC- thereby expected to abide with good
USA and MMI is valid and the dispute faith in their contractual
between the parties is arbitrable. However, commitments."
this Court must deny the petition.
o However, in Salas, Jr., only parties to
 The Agreement between DMC-USA and the Agreement, their assigns or heirs
MMI is a contract. The provision to have the right to arbitrate or could be
submit to arbitration any dispute arising compelled to arbitrate. The Court
went further by declaring that in
therefrom and the relationship of the
recognizing the right of the
parties is part of that contract and is itself
a contract. As a rule, contracts are contracting parties to arbitrate or
to compel arbitration, the splitting
respected as the law between the
of the proceedings to arbitration
contracting parties and produce effect as
as to some of the parties on one
between them, their assigns and heirs.
hand and trial for the others on the
other hand, or the suspension of
 Clearly, only parties to the Agreement, i.e., trial pending arbitration between
DMC-USA and its Managing Director for some of the parties, should not be
Export Sales Paul E. Derby, Jr., and MMI and allowed as it would, in effect,
its Managing Director LILY SY are bound by result in multiplicity of suits,
the Agreement and its arbitration clause as duplicitous procedure and
they are the only signatories thereto. unnecessary delay.

o Daniel Collins and Luis Hidalgo, and  The object of arbitration is to allow the
SFI, not parties to the Agreement and expeditious determination of a dispute.
cannot even be considered assigns
or heirs of the parties, are not bound
by the Agreement and the arbitration Clearly, the issue before us could not be speedily
clause therein. and efficiently resolved in its entirety if we allow
simultaneous arbitration proceedings and trial, or
suspension of trial pending arbitration.
 Consequently, referral to
arbitration in the State of
Accordingly, the interest of justice would only be
California pursuant to the
served if the trial court hears and adjudicates the
arbitration clause and the
case in a single and complete proceeding.
suspension of the proceedings in
Civil Case No. 2637-MN pending
the return of the arbitral award Dispositive:Petition denied.
could be called for but only as to
DMC-USA and Paul E. Derby, Jr.,
and MMI and LILY SY, and not as
to the other parties in this case, in
accordance with the recent case
of Heirs of Augusto L. Salas, Jr. v.
Laperal Realty Corporation, which
superseded that of Toyota Motor
Philippines Corp. v. Court of Appeals.

You might also like