Professional Documents
Culture Documents
PROMODEL SOFTWARE
A Thesis
by
SHARANYA ELUKURTHI
MASTER OF SCIENCE
August 2016
Designing the Facility Layout of An Industrial Vice Production Using Promodel Software
(August 2016)
Facility layout always plays a prominent role for a manufacturing industry since layout is
the deciding factor for the major operations of the manufacturing unit. The thesis covers the
importance of the facility layout and designing of optimum layout of a facility for the production
of an industrial vice. The purpose of the study is to develop a layout with the best efficiency in
manufacturing of industrial vice. The machining operations performed during the manufacturing
process are identified and are arranged into a sequence of operations using the operations process
charts. After preparing the process chart, the cycle time is balanced. This time includes the time
taken for a part to be machined and also the delay time the amount of time the part has to wait to
be machined. As the cycle time is defined, the number of work stations are defined depending
upon the cycle time. Once everything is setup, the logic is made and the virtual layout is
generated. The simulation process is implemented for the designed model to understand the
efficiency of the layout and by making any further changes and improvements to the layout. This
iii
ACKNOWLEDGMENTS
I would like to take this opportunity to express my deepest thanks and gratitude to my
advisor. Dr. Farzin Heidari, for all his encouragement, advice, and guidance during this thesis. I
thank the members of my committee, Dr. Bruce Marsh and Dr. Ulan Dakeev for all their support
I would also like to thank my husband, parents and my family members for their support
iv
TABLE OF CONTENTS
Page
ABSTRACT ……………………………………………………………………………………..iii
ACKNOWLEDGMENTS……………………………………………………………………..... iv
TABLE OF CONTENTS…………………………………………………………………............v
LIST OF FIGURES…………………………………………………………………………........vi
CHAPTER I: INTRODUCTION…………………………………………………………….........1
Significance of Study……………………………………………………………………...7
Purpose of Study…………………………………………………………………………..7
Definition of Terms………………………………………………………………………..8
Summary…………………………………………………………………………………..8
Product Layout…………………………………………………………………………...17
Process Layout…………………………………………………………………………...30
CHAPTER V: CONCLUSION………………………………………………………………….56
REFERENCES…………………………………………………………………………………..59
VITA……………………………………………………………………………………………..61
v
LIST OF FIGURES
Page
Figure 3. Window with dialog box asking for details of new project……………………………19
Figure 16. Arrival station2 connected to saw station and saw station to Milling station………..27
vi
Figure 22. Window with dialog box asking for details of new project………………………….30
Figure 27. Processing window showing the material flow from arrival station1 to saw station..34
Figure 31. Processing window with wait logic and move logics…………..…………………...36
Figure 33. Dialog box with defined run time for simulation…………………………………….37
vii
Figure 45. Assembled Industrial Vice Back View………………………………………………54
viii
CHAPTER I
INTRODUCTION
For an association to have a compelling and effective assembling unit, it is essential that
exceptional consideration is given to the actuality format. Facility is the actual space where the
industrial activities takes place (Phillips, 1997). Facility layout is a course of action of various
parts of assembling in a proper way as to accomplish desired creation results. Facility layout
The purpose of the facility layout is to “ensure the smooth flow of production material,
equipment, manpower at the possible minimum cost” (Phillips, 1997). However, safe and
comfortable environment plays a key role in the design of the facility layout. There are various
other objectives of facility layout like minimizing the delays, efficient use of space available
taken into consideration for an efficient and effective layout (Phillips, 1997).
In the design of any layout, the first point to be considered is the safety. The layout aims
at a comfortable work environment for the employees by organizing the equipment and facilitate
movement of goods. This is achieved by allocating the optimum space required to arrange the
One of the many other main goals of the facility layout is to target the reduction in the
movement of the equipment, raw materials and the workers. This, in turn, increases the
efficiency and decreases the production time by increasing production output capacity
(Tompkins, 2003).
improving fast. In such circumstances, the design should be able to provide an appropriate space
for the advanced equipment that the organizations may buy in future.
1
The material handling, storage, and movement of material has a direct relationship with
the plant layout. The layouts that are being addressing typically involves the handling of the
discrete unit loads of material. A well’ planned and implemented plant layout is said to yield the
best results (Phillips, 1997). When designing a layout, it should always target the reduction of
human labor to move and transport materials which is possible through the ergonomics, injury
It is said that “the best materials handling system is no materials handling system at all,”
as it is fact that the materials handling adds no value to the part but it does add to the cost
(Phillips, 1997). A perfect analysis is to be performed about the type of materials handling that
will be used in the plant. In order to perform the analysis, there are various factors regarding
On the first note it should be clear with the operations that will be done and the type of
materials that will be moved. To reduce the movement of the material, consider combining one
operation with another if there is a possibility of doing so. Once it is clear about the operations
that are going to be performed, it should be made sure that there are no unnecessary operations
and no irrelevant moving of materials. The next step is to decide the start and end points of the
material to be moved. As the path is decided, alternative paths can be calculated to shorten the
distance and the number of trips to move the material. Next step, operations scheduling needs to
be decided where the frequency of the operations and by what time the material is to be moved is
determined. Once it is decided when to perform the operations, how to perform the operations is
to be determined. During this stage redesigning options are considered and the best one is
picked. In the next stage, analysis of the operations that need be performed on tasks is done.
2
For a smooth flow of analysis and simplification of work, four tasks are involved. They
are study, eliminate, combine, and simplify (Phillips, 1997). Work simplification is an important
Various flow patterns for a typical manufacturing plant are taken into consideration. A
flow pattern depends upon a specific amount of space that is assigned to each work station
considering the handling and equipment factors. It is quite normal to combine operations like
shipping and receiving operations in one area, though there are certain industries that are
prohibited (as per government regulations) in combining operations during material handling.
Pharmaceutical companies are one of the examples that are prohibited in combining such
operations.
Competition has always been the deciding factor for companies to stay in business, which
means only the fittest will survive the world market. In order to keep up to the competition, the
The facility layout is usually performed in five phases. They are the need analysis,
location analysis, block layout, detail layout, and installation (Phillips, 1997). As discussed
earlier, facility layout plays a key role in improving the efficiency and also reducing the cost.
The first phase of the layout is a determination of what actually is required to meet the
challenges or to solve the problems that occur. During this phase, the strategic goals and the
overall production needs are also developed. For example, the best suitable type from cellular
manufacturing and traditional manufacturing is determined during the phase of need analysis
(Phillips, 1997).
In the second phase, a complete analysis of the location where the facility is going to be
laid out is studied. Usually, the location analysis may involve a site, redesigning the current
location or rearranging various units within the present location. The analysis includes the area
3
of the site, sewer, water, and railcar access requirements and various kinds of wastes that will be
generated. It is always highly recommended the layout planner be involved in the analysis of the
The block layout phase determines the allocations of major individual areas and the basic
patterns of it. During this phase, “the general size, configuration of each area, proximity
relationships, affinities, and major material flows between these areas are specified.” Main aisles
and their patterns are also specified during this phase. Flexibility is of the major aspects to be
In the detail layout, machinery and equipment are determined for each location
specifically. This also includes the utilities and services. This detail layout could be done in the
form of drawings, drawing layers in Computer Aided Design (CAD) systems, or 3-D replicas
Once the above details are analyzed, the installation process takes place where the
installation instruction and timeline schedules are developed. During this phase, the approvals
and permits that are required for the actual installation process are acquired. This phase aims the
rearrangement or movement with the least amount of interruption to the ongoing operations
(Phillips, 1997).
To perform the analysis, the ProModel software will be used. The objective of the thesis
is to compare two facility layouts for manufacturing an industrial vice using the ProModel
software. The layouts considered are the product layout and the process layout using the
operational process chart. In a product layout, the units or the equipment is arranged in such a
way that the route in which the product flows and the sequence of the operations is given the
importance. Whereas in process layout, the operations that should be performed on the parts are
grouped together.
4
“ProModel is discrete event simulation technology that is used to plan, design, and
improve new or existing manufacturing, logistics, and other operational systems” (Promodel,
2016). It accurately represents the production layout, along with their variability and
independencies. ProModel also optimizes the production system around the required key
performance indicators.
represents the physical layout and create the dynamic animated model of the facility environment
in order to clearly see and understand the processes and strategies in action. Analyze means to
comprehend to identify potential issues and changes and develop situations which will
accomplish the goals of the facility. Optimization is to instantaneously test the effect of changes
of present and upcoming operations which are risk free with predictive situations and
assessments.
ProModel provides the opportunity for the decision makers to trial their concepts of
process and system design and develop them beforehand building a definite system. ProModel
also concentrates on various issues such as, “resource utilization, system capacity, process
improvement, throughput and bottleneck analysis, supply chain and logistics and customer
service levels” (Promodel, 2016). By modeling the significant parts of manufacturing and
logistics, it can be investigate with the operational approaches to attain optimal performance for
The capability of the ProModel in modeling the most complex systems has particularly
pleased the users. Because of its perceptive and straightforward approach to modeling,
instructors in business and engineering programs are attracted to this software as they can teach
modeling and analysis prototypes without teaching the computer programming. The ProModel
software is so flexible that engineers who wish to code the complicated logic using programing
5
languages like C, Pascal,or Basic that can be connected to the model and can be used inside the
model at runtime. ProModel allows the experts and analysts to use the tools they are at easy with
ProModel complies with the Graphical User Interface standards, which means that it is a
user’ friendly software and users have no trouble learning the software. This approach not only
reduces the efforts of learning for beginners but also increases the effectiveness for modifying
Through the ProModel’s “integrated help system and online tutorials,” a quick and useful
online documentation is accessible. This system has the maximum flexibility allowing to look up
everything needed from a command syntax to explanations of model building handbooks. The
tutorial provided by the ProModel contains quick lessons on building models and how to run the
models also access output reports for modeling numerous applications with the ProModel
software.
ProModel provide the model merging capabilities in order to reduce the model
development time. With this feature, individuals can work individually on diverse segments of
the model and at the end all the individual models can be merged into one desired model.
Additionally, frequently used cells may be stored as templates for future use. The users can also
Significance of Study
It is impossible to physically layout kinds of plant layouts and check which has the best
efficiency with respect to the company since it not only involves large budget but also involves
the most valuable time. Simulating the plant makes it simpler to develop various different
layouts of the plant. By comparing the layouts it is easy to choose the best suitable one for the
6
facility. It also helps in understanding and analyzing the problems in the layout and benefits in
Simulation makes it easy to present the idea to the management and get it approved. The
inputs can be taken from the management and can be discussed with the workers of departments
Purpose of Study
The purpose of the study is to develop a layout with the best efficiency for manufacturing
of industrial vice. The machining operations performed during the manufacturing process are
identified and are arranged into a sequence of operations using the operations process charts. The
operation process charts are the graphical representation of the operations including the sequence
After preparing the operation process chart, the cycle time is balanced. Cycle time is
defined as the total time taken from the beginning of the process to the end of the process. This
time includes the time taken for a part to be machined and also the delay time the amount of time
the part has to wait to be machined. As the cycle time is defined, define the number of work
stations depending upon the cycle time. Once everything is setup, the logic is made and the
virtual layout is generated. The simulation is implemented to understand the efficiency and learn
The above method is called product layout will be compared to a simulation model
designed using process layout method. The results of the two simulation models will be
Definition of Terms
Facility layout: “Facility layout is a course of action of various parts of assembling in a proper
7
ProModel: “ProModel is discrete event simulation technology that is used to plan, design and
improve new or existing manufacturing, logistics and other operational systems” (Promodel,
2016).
(Promodel, 2016).
Summary
The industrial vice constitutes of five components. They are lead screw, vise body,
movable jaw, upper guide plate, and lower guide plate. The parts are machined and assembled to
make the vice. These five parts have machining processes to be performed on them which
includes cutting, turning, drilling, milling, finishing and, various other miscellaneous operations.
The operations are defined with the machining time and it is also decided how often the
The information is then transferred to the ProModel for simulation. Making sure the
layout is efficient and meets the requirements for manufacturing the vice. The simulation is
performed for a month on both layouts. From the results obtained by running the simulation the
layout models are analyzed, compared, and the best layout is selected.
8
CHAPTER II
LITERATURE REVIEW
A plant or facility layout is one of the most critical parts of an efficient and cost effective
businesses. It is important for a business to make few decisions in such a way that they are not to
be modified. If they have to change these decisions, the company might not be able to afford the
changes. Modifications in the facility layout is one such a change. Once a facility layout is
designed and implemented, it is highly expensive to modify the layout (Pochamarn, Suwadee, &
Chonthica, 2007).
constructed in real life. In simulation, a model with desired requirements is designed and run like
the real system. A number of experiments are conducted on this model to ensure the efficiency of
the designed model. A model can be anything from various fields of businesses like
other streams. Once a model is build, it is tested for its efficiency, cost effectiveness and also
other alternative layouts. In this study two models are simulated and used to compare to facility
Arena, simio, flexsim are few simulation software like the ProModel. Business processes
dwell in every type of organization regardless of size or industry. In the event they are
unmistakably characterized and upgraded, they will without a doubt add to the organizational
general achievement and benefit. Simulating or modeling a particular business process gives the
capacity to separate and settle on choices on the most ‘proficient method to enhance the
procedure. Through business process modeling software, the results can be accomplished well
9
Business process modeling provides the ability to graphically represent process flow for
most complex business processes. They help in monitor, analyze and to better understand the
workflow. They predict design or system performance, response time, and bottlenecks. They
evaluate the impact of failure rates. Test alternatives determines which are best for the business.
understanding of decisions.
“Arena business process simulation software allows to create business process models
providing with the capability to measure performance, reduce cost and to optimize the business
operations” ( Arenasimulation, 2016). Its ease of use adaptability, flexibility, and scalability will
help in modeling any aspect of the industry. active dashboard reporting tools helps in enhancing
the presentations to make best decisions without requiring additional time, resources, or capital
investment before the decision impacts the bottom line (Arenasimulation, 2016)
They realized the need for the additional capacity for the developing operations of the industry.
For this they need to consider upgrading the machinery to keep up to the cost competitiveness of
the economy. However, the machinery and tools cannot be fixed in the existing plant and they
need to expand their plant for a smooth transition of upgradation and also no future issues. So
they have purchased land and decided to make the plant layout. The objectives of the plant were
designed. For the best efficiency of their plant, they decided to construct the plant first in
ProModel. They choose the optimum layout for their operations. When executed the model they
Simulation is also used for introducing new product lines by considering plant layout
models. These plant layout models help the clients to analyze the startup risk and also to ramp up
to reach plant capacity of the factory. To achieve success, the selected equipment and layout
10
must support the demand requirements. Simulating this kind of situations using software such as
ProModel helps us to reduce the risk and reach profitability quickly. The analysis includes more
than 50 parameters available to control the process time, assignment of labor, time handling and
various other parameters. The analysis predicts the throughput from the existing design and
suggest to improve the machine tools and facility layouts to meet the 100% throughput with
The simulation can help in identifying the most cost effective course of action such that
facility could produce the required demand. It also ensures that investment will be met by the
venture objectives. The impact of repairs and remanufacture of products from the field can be
predicted through simulation. This can be used to develop the basis for supply chain analysis for
the flow of returns from remanufacturing and rebuilding fields (Promodel, 2016).
“Facility planning is concerned with the design, layout, and accommodation of people,
machines and activities of a system or enterprise within a physical spatial environment” (Garcia,
2008).
factory output in conformance with production schedule can be achieved by arranging locating
and distributing the equipment and support services in a manufacturing facility”(Huang, 2003).
The three main types of layouts in the manufacturing system are product, process and
group which is further subdivided into flow line, cell, and center (Askin & Standridge, 1993).
Tompkins states that, “system characteristics such as production volume and product variety” are
11
According to Hessen, process layout is connected with “low volume production and high
product variety while product layout is associated with high volume production and low product
enquiries from the business sector such as enlarging the item runs, expanding quality and exact
conveyance time. The global rivalry requires a bigger assortment of sorts and variations in large
volume products (Nica, 2008). Zuhdi and Taza (2008) proposes that “manufacturing companies
should be knowledge intensive and exceptionally imaginative to develop new items. “To stay
focused, to remain competitive and adopting information technology” are the challenges faced
by medium and small industries. Decision making for either updating the particular procedure or
reconfiguring the entire frame work as a reaction to showcase interest is a basic movement which
can effect on the remaining part of the organization. Hence an appropriate analysis tool must be
used to support it” (Zuhdi & Taza, 2008). Rieth and Gerlach (1996) states that the simulation
method is favored due to the capacity in catching the elements of the complex framework. The
importance of simulation in the period of lean manufacturing is the approval of the outline or
upgrade of perplexing manufacturing system before execution (Rieth & Gerlach, 1996).
cell, and streamline designs appropriate for manufacturing companies that are having high mix
low volume (HMLV) environment (Tompkins, 1996). Irani and Huang (2000) suggested a novel
approach that can be utilized for planning a layout having product flow and high flexibility,
modular layout is an example. A group of layout modules is called a modular layout. A layout
module is basically a group of machines associated by a material flow network that shows a floor
pattern characteristic for a specific type of layout such as functional, cell and flow line.
Generally, the design module grows the cells in a format and offices in a utilitarian format by
12
permitting a module to have an item, process, or part family focus. Flexible layouts are those that
can effectively survive with the variations in product mix and product demand. There execution
is measured by material expenses over the possible demand scenarios (Irani & Huang, 2000).
The effectiveness of a plant layout can be expanded by updating the plant design,
utilizing the string outline, and organized design arrangement. These essential instructions when
taken after format plan and upgrades are done. It gives fundamental insights about the stream of
material through the shop floor and the interrelation of exercises. It clarifies about the material
stream and format plan utilizing string graph (Muther, 1994). One such research by Schenk
(1988) explains the planning strategies and methodologies for various type of facility. The type
of layout designs to be embraced and executed during layout design and has additionally given
the key components to layout design (Schenk, 1988). The kind of flow of material and the
practice activity relationship chart (ARC) and diagrams for layout redesign and layout planning.
“The utilization of activity relationship chart diagram in designing a layout has given a
Another research concentrates on the issues occur during the design of flexible plant
layouts for manufacturing facilities where product requested are liable to variability. “A flexible
layout is one that keeps up low material handling cost despite of changes in the demand level”
(Benjafaar & Hillier, 1963). A research led in an industry clarifies about the warehouse redesign
of a manufacturing plant layout, furthermore the issues confronted amid the update of the layout.
production facility differs from that of manufacturing layout” (Tobiah & Francis, 1992). “The
examination of the limit of the hardware is done, then by utilizing this investigation a group
13
technology is utilized to make distinctive kinds of parts in a layout and identification of material
The above layout can benefit from designing a simulation model. Alternatives can be
designed and a simulation can be run for a set time. The analysis showing the efficiency of each
model can be created. Comparing the results of each model the best layout can be selected.
14
CHAPTER III
METHODOLOGY
In this project two facility layouts for the production of industrial vice are compared. As
discussed earlier, the two layouts are the product and process layouts. A product layout is a
layout designed with respect to the design of the product. Whereas the process layout is the
The tool used for the designing the facility layout is the ProModel software. Using the
software, the two layouts were designed and the simulation process was run. The results are
compared for the best layout. To design a layout on ProModel, there are a sequence of steps that
are to be followed. Before going to the modeling of layout, the operation process chart is needed
to be prepared. From the operation process chart (Figure 1) number of work stations and the type
of manufacturing processes are defined. Depending upon the type of layout whether it is a
product layout or a process layout, the manufacturing operations are grouped together.
To create a model using ProModel software, following steps are followed. First define
the location, entities, arrivals and processing of the part. In locations, define the type of
machinery, number of work stations including the raw material arrival stations and the buffer
stations, the capacity of the stations and the machinery and number of workers. Once the
locations are defined, move on to define the entities of the layout. The raw materials or in
general the inputs are defined. The entities vary depending on the number of parts the finished
product has.
15
Figure 1. Operation Process Chart
In the arrivals section the inputs are given a starting point, in this case it would be an
arrival station, and also define their pattern of arrival. The pattern can be one at a time or in a
group. The frequency at which the input is arrived at its starting point should be defined in this
section. Once the arrivals are defined comes the important part of the modeling which is the
processing. The path in which the input is traveled is defined. The important part of the whole
16
modeling is the logic of the model. That is comprised of the wait and move times of the inputs.
For every workstation, the wait time and the moves should be defined. Wait time is defined as
the time it stays at the workstation for the machining process to be performed on it. Move time is
the time the material takes to move from one station to another. Thus once the logic is ready the
Product Layout
A product layout can be defined as the one in which the workstations are aligned in a line
so that the product is manufactured in a sequence of operations (Phillips, 1997). As a layout for
the production of an industrial vice is being designed, the operation process chart needs to be
constructed. The parts of the industrial vice are the lead screw, vice body, movable jaw, upper
guide plate, and the lower guide plate. The manufacturing operations that are to be carried out to
form the respective parts of the industrial vice are define in the form of an operational process
chart. Consider modeling the first 10 operations of the operations process chart which include the
eight machining operations to form the lead screw and first two operations of the vice body.
As we enter the ProModel software, go to the file option (Figure 2) which is located on
the upper left corner, click on New and a dialog box pops up (Figure 3) asking the details of the
new project. Give the project the name, which is a product layout. Then click on the build option
(Figure 4) and see the categories of the build option where the steps that are required to build a
17
Figure 2. Window showing File Option
The first step is to define the locations (Figure 5) of the model. The first location is the arrival
station for the raw material with a capacity of 100 units (Figure 6). Define the sawing station for
the saw operations and lathe station for the facing, center drill, and turning operations of the lead
screw. A buffer station with the capacity of 100 units is defined for the parts coming from
sawing and lathe stations for a smooth flow of the parts so that the next stations are neither idle
nor overloaded. Define another lathe station for the process of threading and knurling. From this
station the part move to another buffer station of 100-unit capacity and next another lathe station
is placed for the operations of chamfering and cutting groove (Figure 7).
18
Figure 3. Window with dialog box asking for details of new project.
19
Place another arrival station of capacity of 100 units for the second raw material for the
vice body. Define a saw station to cut the raw material to size and a milling station for roughly
20
Figure 7. Locations window with all the workstations
The next section is to define the entities of the layout (Figure 8). Click on the build option
and select entities. Define the raw materials required to build the product (Figure 9). In the next
step the arrival stations which is the starting point of the raw material are defined. One part at a
time comes to the arrival station in the project and at a frequency of 7 min for lead screw and at a
21
Figure 8. Entity window
22
Figure 10. Arrivals window
Click on the build option and select the processing (Figure 11).The logic of the model is
defined. If the logic is not correct or the syntax is not followed the simulation does not run.
Before the logic, connect the workstations in a line as the sequence of the processes which are
represented by arrow lines. Select the lead screw raw material (Figure12) and then connect the
arrival station1 to the second workstation which is saw station (Figure13). Saw station to third
station, the lathe station (Figure14) and lathe station to the fourth station, buffer station 1. Then
the buffer station 1 is connected to the lathe station 2 which is in turn connected to the buffer
station 2 and from buffer station 2 to the lathe station 3 from which the completed part of lead
23
Figure 11. Selecting the Processing option
24
Figure 13. Connection of arrival station1 to saw station.
25
Figure 15. Route to Exit of lead screw.
The arrival station 2 is where the raw material for the vice body enters. It is connected to
a saw station and then to a lathe station (Figure 16). Once the connections are defined, write the
logic for the operation column and the move logic. At the arrival station 1 the move logic is
move for 1 min which means it moves to the next station after a minute. At the saw station the
operation logic would be wait 1 min, because it takes one minute for the saw operation to finish.
Here the saw operation is done to cut the raw material to the required size. Likewise, the logic is
written for all the operations at the workstations (Figure 17). Once the logic is defined, click on
the simulation option (Figure 18) which is right next to the build option from the top pane. From
the options under the simulation, select options and a dialog box appears with number of
specifications (Figure 19). The important thing to define in the window is the run time (Figure
19). Once defined the specifications run the simulation using the play button which is located on
26
Figure 16. Arrival station 2 connected to saw station and saw station to Milling station.
27
Figure 18. Simulation option.
28
Figure 20. Defining run time in simulation option dialog box.
Process Layout
Similar to the product layout, define the parts of the industrial vice. In process layout
29
group the machining operations into workstations based upon the type of machining operation
and the machine that is used to perform it. Consider the first ten steps of manufacturing industrial
vice. The machines required for this layout are the sawing operation, lathe, and milling
operations. The next step is to model for the process layout. For this new model, give the title
Figure 22. Window with dialog box asking for details of new project.
Click build option and select the locations. Define the workstations. Since there are two
parts used in the first 10 steps considered, two arrival stations are needed. The capacities of the
arrival stations are also defined with 100 units each. Define the sawing workstation where the
sawing operations are done for the required parts. The lathe station where the operation for lead
screw are performed and a milling station for the vice body (Figure 23).
30
Figure 23. Location window with workstations.
After the locations are defined, the entities are defined. Click on the build option and
select entities (Figure 24). Since there are two parts, the two input raw materials for lead screw
and vice body are defined (Figure 25). Again click on the build options to select the arrivals. The
starting point of the raw material is defined. The frequency of the arrival of raw material and the
quantity of each also defined. For the lead screw, the raw material arrives one at a time at
frequency of 7 min. Whereas for the vice body, the raw material enters one at a time with a
frequency of 5 min.
31
Figure 24. Entities window
Next step is to define the arrivals, that is the starting point of the raw material flow (Figure 26).
32
Figure 26. Arrivals window.
The next step is to define the path of the raw materials. To define the path, select the raw
material from the left pane. Select the raw material of lead screw first and click on the arrival
station 1 and an arrow line starts (Figure 27). Click on the next station which is the sawing
station. The line between the arrival station 1 and the sawing workstation with an arrow pointing
the direction of the flow can be seen. Sawing station to the lathe station. From the lathe station
the completed part of lead screw is exited (Figure 28). Coming to the arrival station 2, the raw
material for the manufacturing of vice body enters here and moves to the sawing station. Click
on arrival station 2 and then on sawing station to represent this flow. Connect the sawing station
to the milling station where the next set of operations are carried on. Since the first 10 operations
are only considered from the operation process chart, in the model the part exits after the milling
station (Figure 29). But in real time it moves to the next station.
33
Figure 27. Processing window showing the material flow from arrival station1 to saw station.
34
Figure 28. Material flow of lead screw.
The logic for the model is constructed. The wait logics and the move logics for the flow
are defined similar to the product layout (Figure 30,31). After the logic is done, it is time to test
35
the logic by running the simulation. From the simulation command located on the top pane,
options is selected (Figure 32). The run time is defined (Figure 33) and the simulation is run (Fig
Figure 31. Processing window with wait logic and move logics.
36
Figure 32. Simulation command
Figure 33. Dialog box with defined run time for simulation.
37
Figure 34. Simulation in progress.
38
Once the simulation is run for the models, data has been collected, analyzed, and
compared. The results have been analyzed and discusses in the following chapter.
After the first 10 steps, the complete design of the process layout is modeled. The first
step is to define the locations. There are 11 stations where the raw material travels through
including the arrival station and assembly station. The first station is the arrival station where the
raw material goes to the respective work station. The next station is the lathe station with two
lathe machines and a mill station with three milling machines. There is drilling station with two
drill presses and next one is the tapping station. The final station is the assembly station where all
The next process is to define the entities which is the raw material. The raw material for
all the five parts of the vice are defined. The next procedure is to define the arrivals of the layout.
The arrival station for the raw material is defined and next process id to define the processing. In
39
processing the routes of raw material travel are defined and then the wait and move logics are
defined for the machining operations. The raw material for lead screw enters the sawing station
from arrival station and this operation continues for one min. From saw station it enters the lathe
station. After the machining is done on first lathe for nine min it moves to the next lathe station
where it waits for ten mins for machining. The lead screw exits from the lathe to the assembly
station.
Meanwhile, the raw material for vice body enters the saw station (after sawing the raw
material for lead screw) from arrival station. From saw station it moves to the milling station.
From milling station, it travels to the drill press and to tapping station. After tapping is done the
vice body reaches the assembly station where lead screw and the vice body are assembled. It
At milling station, vice body, movable jaw, upper guide plate, and lower guide plate are
machined with respect to the product specifications. The vice body is milled for ten min on one
milling machine and seven min on the second machine. The movable jaw is milled for two min
on second machine and two min on third station. The upper and lower guide plates are milled for
The next station is the drilling workstation where there are two drilling machines. Vice
body is drilled for two min and movable jaw for seven min on first drilling machine. The drilling
operation is performed on the upper guide plate for two min and two more min on the second
drilling machine. The lower guide plate is also subjected to drilling operation for eight min.
After drilling, the next station is the tapping station. The overall process time of tapping
station is seven min which constitutes of two-min tap on vice body, four-minute tap on movable
40
After the operations are performed on the individual parts, they travel to the assembly
station. The lead screw and vice body are assembled for two min, and adding the movable jaw
takes two min. Assembling the upper and lower guide plates takes one min each. After this
assembly, it takes four min to set the machine screws to the end product.
Once the routes and the processing logics are defined, it is time to run the simulation.
Before running the simulation, the run time must be defined in the simulation options. After the
simulation is run for 40 hrs., the results are compared and analyzed.
41
CHAPTER IV
In the Chapter iii, it is discussed how the layout modeling is done and built two models.
One is the product layout and the other is the process layout. The two models are simulated for a
certain period of time, in this case 40hrs, and the results are compared. Based on the results it is
observed that the process layout is more efficient than the product layout.
42
Figure 37: Process Layout of Industrial Vice
Considering the number of workstations, the product layout has 10 work stations where
In the layouts the total number of workers required is 10. But the arrangement is quite
different. In the product layout there is worker for every work station. Whereas in the process
layout, the saw station has one worker, lathe station with two workers, milling station with three
workers, drilling station with two workers and the tapping and assembly stations with one
worker each.
Coming to the facility area, the product layout needs more facility that the process layout.
Because, the product layout has 10 work stations with five saw machines, three lathe machines,
six milling machines, six drilling machines, three tapping machines ,and four assembly stations.
The overall number of machines is 23 and four assembly stations. But whereas in process layout,
there is only one saw machine, two lathe machines, three milling machines, two drilling
43
machines, one tapping machine, and an assembly station. This makes the overall number of
It takes a lot of space for 23 machines than for 9 machines. So, process layout is more
efficient when the facility area is considered. Process layout is more economical when compared
to the product layout as it needs nine machines whereas the product layout requires 23 machines.
Process layout is cost effective in terms of facility are and number of machines.
The next factor is the ideal capacity. Consider the saw machine in both the layouts. The
product layout has 5 saw machines at workstations: 1, 3, 6, 7, and 9 (Figure 36). The saw
machines work for 1 min only but at various frequencies. The frequencies depend on the capacity
of the next station. For example, the first saw station is operated for every 7 min because the
lathe is free only after every 8 min. And remaining 1 min is covered in moving of the part from
saw to the lathe. Likewise, the second saw station located at third workstation is operated for
every 4 min, third and fourth saw stations work at a frequency of 3 min and the fifth one is also
operated every 3 min. The rest of the time the machine is idle. Whereas process layout has 1 saw
and works for 5 min at a frequency of 10 min on an average. The saw here is also idle for most
of the time but important point is there is only 1 saw in the process layout and is used to the best
as per requirements. Whereas in the product layout has 5 saw machines and they are kept idle for
Similarly, 3 lathe machines are in product layout and 2 in the process layout. The raw
material first goes through the machining operations for 8 min on first lathe machine and moves
on to the second one and waits for 9 min for the machining operations and moves to the third
lathe where it is machined for 2 min. The third lathe is idle for most of the time, since it does not
have other operations to do except the 2 min operation for every ten min.
44
Coming to the milling station, there are 6 milling machines in product layout and only 3
milling machines in process layout. Out of the 6 machines, 3 of them are used for operations
performed on the vice body, one each for movable jaw, upper guide plate, and lower guide plate.
On one part, the first milling station is operated for 5 min and the second mill for 8 min. The
third and fourth milling station works for 4 min each. The fifth and sixth milling machines are
also operated for 4 min each to get one part done. However, in the process layout, first and
second milling machines are operated for 10 min each and the third machine for 9 min. Though
the overall operation times are same, the number of machines used in the product layout is more
than the machines used in process layout which is again a poor use of money and time.
Likewise, in the drilling section, there are 6 drilling machines in product layout and two
drilling machines in process layout. There is 1 drilling machine allotted to vice body, 2 for
movable jaw 1 for upper guide plate and two for lower guide plate. The first drilling machine
which is located in workstation four is operated for 2 min. The second drill press is in operation
for 4 min and the third one for 3 min. The fourth, fifth, and sixth drilling machines are operated
for 4 min each. In the process layout, first and second mills are operated for 10 min each and the
third one for 9 min. A lot of idle time is noticed on the milling machines in product layout than
process layout.
After drilling station there is tapping station. Three tapping machines are arranged in
product layout one for vice body, one for movable jaw and the other for upper guide plate. One
tapping machine is arranged in process layout which performs the tapping operations on the parts
which requires this operation. The overall process time for a tapping machine to complete one
industrial vice is 7 minutes. In product layout, the first machine is operated for 2 min, second one
for 4 min and third one for 1 min. In process layout, one tapping machine is arranged which
takes care of the tap operations of the parts. In product layout, even though the machines are
45
capable of manufacturing more number of parts, they are starved because of the prior operations
A product layout is a best choice for repetitive type of jobs. The flow time is also less
with a continuous smooth flow with stoppages in between. The time required for inspection is
less with lower work in process inventories and material handling costs. In process layout there
is a high possibility for variety in the products due to its high flexibility and adaptability. This
variety in products is not possible with the product layout. In a product layout, if a machine stops
the whole production line is stopped whereas in a process layout machine breakdown does not
affect the production line (Tompkins, 2010). The investment requires in setting up a product
layout is much higher whereas process layout requires comparatively less investment (Freemba,
2016). The equipment utilization is not to full capacity in product layout when compared to
The first component manufactured during the process is lead screw (Figure 38). Major portion of
the lead screw is threaded which converts the circular motion to linear motion. There is a groove
cut at one end so that the movable jaw is pinned to the lead screw. The other end of lead screw is
knurled and used for the purpose of tightening or loosening the screw. After cutting the raw
material to required size, the operations to make lead screw are performed on lathe machines.
46
Figure 38: Lead Screw.
The next component is the vice body (Figure 39). The vice body is a rectangular shaped
component which is the support system of the whole product. There is a hole drilled on one end
of the body and threaded inside for the assembly of lead screw. The movable jaw is fixed to the
same end from where the lead screw enters. The other end of vice bod acts as the stationary jaw.
After cutting the raw material to size, it undergoes four operations on milling machine, one
47
Figure 39: Vice Body.
After vice body, the next part is the movable jaw (Figure 40). The movable jaw is
attached to the lead screw with a pin after assembling the lead screw to vice body. After cutting
the raw material to required size, it is moved to milling station where two milling operations are
carried on. Then a hole is drilled for the assembly of lead screw. There are five more holes
drilled for the final assembly. There is a tapping operation which is performed on four holes.
48
Figure 40: Movable Jaw
The next part is the upper guide plate (Figure 41). The upper guide plate is assembled to
vice body with five screws. A drilling operation is performed to drill five holes. Before drilling,
the work piece is roughly cut and then finishing operation is done for desired cut on milling
49
Figure 41: Upper Guide Plate.
The lower guide plate (Figure 42) is assembled in between the vice body and upper guide
plate. The work piece is first cut to size and undergoes two milling operations of cutting for
desired specifications of the part. There is a drilling operation performed to drill five holes. For
lower guide plate, a counter boring operation is also performed for the five holes. The five holes
50
Figure 42: Lower Guide Plate.
Figure 43 shows all the components of the industrial vice that are manufactured and also
the screws that are used to assemble them together. Figures 44 and 45 show the front and back
51
Figure 43: Components of Industrial Vice Before Assembly.
52
Figure 44: Assembled Industrial Vice Front View.
53
Figure 45: Assembled Industrial Vice Back View.
54
CHAPTER V
CONCLUSION
Facility layout always plays a prominent role for a manufacturing industry since this layout is the
deciding factor for the major operations of the manufacturing unit. This research discusses the
importance of the facility layout and selecting an optimum layout of a facility for the production
of an industrial vice by designing two layout models. The layouts selected are product layout and
process layout. The purpose of the study is to develop a layout with the best efficiency in
Facility layout is a process which is time consuming as major factors like amount of area
in which the facility is built, number of workstations and the number of machines in each
workstation are required. It is immensely expensive to install a layout and once laid it is not
possible to redo it. So it is important to make sure that the layout selected has the best efficiency.
Any method that has a scientific approach to make smart decisions about facility layout
will help a lot by making the process more efficient. ProModel is one such scientific approaches
of modeling the layouts as per the requirements. Modeling of facility layout gives an opportunity
to examine types of layouts compares them in aspects and finally pick the one that suits us the
best.
Using ProModel, after designing the product and process layouts of industrial vice
manufacturing plant the differences between the two models are clearly visible when compared.
The pros and cons of each model is easily understood from the outputs. The visual view of how
the process takes place and how the raw material moves from one station to other is represented
by visual model, which makes the whole process presented to the user. It is easy to tabulate the
results using the software. The simulation can be run for various cycle times and compare them
55
for best outputs. ProModel generated graphs and charts are an effective tool for presenting the
It definitely takes some time to understand the software but once understood, it takes a
short time to model a layout, of course modeling time also depends upon the complexity of the
product manufactured. It becomes easy to change the process to a higher volume or lower
volume during the modeling stage before building the real layout. Again compare the results to
Modeling helps making smart decisions regarding the block layout, detail layout, and
installation. Once a model is designed, it is possible to come up with the required number of
equipment that is needed also the number of workstations and number of machines required in
each workstation. This information helps defining the block layout, that is the area required for
the facility to build in. it also provide information to estimate the cost for the installation and
equipment to be purchased.
The important factor to be considered while modeling or building a layout is the material
handling. Material handling is waste of time and space. No value added to the part by material
handling. With the help of this software, it can clearly be seen how the material moves from one
place to another place. The unnecessary movement of the material handling can be eliminated by
changing the model accordingly. Thus modeling helps in reducing or even eliminating the
material handling.
Modeling is not only useful during the facility layout of a new plant, but also assists
greatly during redesigning of a plant. The existing plant can be remodeled on ProModel and
make the necessary changes and upgrades that are required. The most efficient redesigned model
56
The philosophies like just-in-time, total quality management and constraint management
provide various approaches to the system efficiency and productivity. During modeling, it is
possible to implement these philosophies depending upon the specifications of the facility by
From this research, the process layout turned out to be best choice over product layout for
the industrial vice manufacturing plant. The process layout is more cost effective than product
layout as it requires less area for the facility whereas the later requires larger area to be used. The
process layout works the best with less number of workstations and machines when compared to
the product layout. There are six workstations with nine machines and one assembly station in
process layout. In the product layout there are 10 workstations with 23 machines and four
assembly stations.
57
REFERENCES
Phillips, J. (1997). Manufacturing plant layout fundamentals and fine points of optimum facility
design.USA.
https://www.promodel.com/Products/ProModel
Pochamarn, T., Suwadee, N & Chonthicha, C (2007). Using ProModel as a simulation tools to
assist plant layout design and planning: Case study plastic packaging factory.
https://www.arenasimulation.com
Garcia, A. D. (2008). Facility Planning and Design. New York: Pearson International Edition.
Huang, H. (2003). Facility layout using layout modules, PhD Thesis. The Ohio State University.
Askin, R. G & Standridge, C. R. (1993). Modeling and Analysis of Manufacturing Systems. New
Tompkins, J. A. (2003). Facilities planning. New York: John Willey & Sons.
Hesen, P.M.C, Renders, P. J. J & Rooda, J.E. (2001). Application of a Layout/Material Handling
58
Nica, M. (2008). Simulation of Queues in Manufacturing Systems. Fascicle of Management and
Zuhdi, A. D & Taha, Z. (2008). Simulation Model of Assembly System Design. Proceeding Asia
Rieth, D & Gerlach, S. (1996). Planning and controlling of flexible assembly systems for
Irani, S.A & Huang, H. (2000). Enhancements in facility layout tools using cell formation
Muther, R. (1994). Pant layout and flow improvement. New York: McGraw-Hill Companies.
Benjafaar, S. A & Hillier, F. S. (1963). Quantitative Tools for Plant Layout Analysis, Journal of
Tobiah, R & Francis, R. L. (1992). Facility Layout and Location: An Analytical Approach.
Thomas, L. (2010). Facilities Layout Optimization Method Combining Human Factors and SLP.
http://www.freemba.in/articlesread.php?artcode=2504
59
VITA
Sharanya Elukurthi was born in Warangal, India. She completed her master of technology degree
2012 from Jawaharlal Nehru Technological University, India. She joined Texas A&M University
‘Kingsville in fall 2015 to obtain a master’s degree in industrial management and will be
60