You are on page 1of 10

Quiz 3:  Planning

True/False

1. The plan lays out what needs to be accomplished but not how it is to be 
accomplished.

ANSWER: F

2. It is important that the people who will be involved in performing the work are also 
involved in planning the work. 

ANSWER: T

3. The first step in the planning process is to define the project criteria.

ANSWER: F

4. The objective must be clear, attainable, specific, and measurable.  

ANSWER: T

5. For a project, the objective is usually defined in terms of scope, packages, and cost.

ANSWER: F

6. In the real world, project objectives are always be spelled out clearly at the 
beginning of a project.

ANSWER: F

7. The WBB breaks a project down into manageable pieces, or items, to help ensure 
that all of the work elements needed to complete the project work scope are 
identified.

ANSWER: F

TB9–1
8. The lowest­level item of any one branch of a WBS is called a work code. 

ANSWER: F

9. The WBS usually indicates the organization or individual responsible for each work 
item.

ANSWER: T

10. Some responsibility matrices use an X to show who is responsible for each work 
item.

ANSWER: T

11. An activity requires the expenditure of effort by people.

ANSWER: F

12. The Gantt chart is sometimes called a bar chart.   

ANSWER: T

13. In a Gantt chart, activities are listed down the left­hand side, and the person 
responsible is shown along the bottom.  

ANSWER: F

14. One of the major advantages to the traditional Gantt chart is that it shows 
graphically the interrelationships of activities.   

ANSWER: F

15. A network diagram is typically not drawn to a time scale.   

ANSWER: T

TB9–2
16. Each activity in a network diagram can be represented by one or more boxes.  

ANSWER: F

17. An activity cannot start until all of the preceding activities that are linked to it by 
arrows have been finished.   

ANSWER: T

18. In the AOA format, an activity is represented by a rectangle  in the network diagram

ANSWER: F

19. Network diagrams must flow from right to left.   

ANSWER: F

Multiple Choice

20. ________________ is the systematic arrangement of tasks to accomplish an 
objective.
a.  scheduling
b.  planning
c.  team building
d.  controlling

ANSWER: B

21. The plan becomes a benchmark against which ______ progress can be compared.
a.  actual
b. planned
c.  future
d. expected

ANSWER: A

TB9–3
22. By participating in ____________ of the work, individuals will become committed 
to accomplishing it.
a.  planning
b.  controlling
c.  discussing of
d.  timing

ANSWER: A

23. The _______ step in the planning process is to define the project objective 
a.  first
b.  second
c.  third
d.  fourth

ANSWER: A

24. The project __________ must be clear, attainable, specific, and measurable.
a. environment
b. cycle
c. objective
d. work forms

ANSWER: C

25. For a project, the objective is usually defined in terms of scope, _______, and cost.
a. plan
b. schedule
c. controls
d. packages

ANSWER: B

26. The _____________ breaks a project down into manageable pieces, or items, to help
ensure that all of the work elements needed to complete the project work scope are 
identified.
a.  work package plan

TB9–4
b.  work budget plan
c. work breakdown staff
d.  work breakdown structure

ANSWER: D

27. _________ Is a hierarchical tree of end items that will be accomplished or produced 
by the project team during the project.
a.  work package plan
b.  work budget plan
c. work breakdown staff
d.  work breakdown structure

ANSWER: D

28. A WBS subdivides the project into smaller pieces called _____________.
a.  object codes
b.  task statements
c.  work items
d.  work loads

ANSWER: C

29. The lowest­level item of any one branch is called a ___________.
a.  object item
b.  task statements
c.  work package
d.  work loads

ANSWER: C

30. The ___________________ is a method used to display, in tabular format, the 
individuals responsible for accomplishing the work items in the WBS.
a.  responsibility matrix
b.  resource map
c.  responsibility web
d. task structure

TB9–5
ANSWER: A

31. A _____________ is defined as a piece of work that consumes time.
a.   action
b.  activity
c.  element
d.  work object

ANSWER: B

32. When all the detailed activities have been defined for each of the work packages, the
next step is to graphically portray them in a __________________ that shows the 
appropriate sequence and interrelationships to accomplish the overall project work 
scope.
a. bubble diagram
b. network ladder
c. network diagram
d. responsibility chart

ANSWER: C

33. PERT stands for:
a. program evaluation and review technique
b. process examination and review technique
c. program evaluation and reward technique
d. process examination and reward technique

ANSWER: A

34. CPM stands for:
a.  critical part model
b.  critical path method
c.  criteria plan method
d.  criteria part model

ANSWER: B

TB9–6
35. Two popular formats for drawing network diagrams are:
a.  activity in the box  and activity on the arrow
b.  activity in the node and activity in the square
c.  activity in the box and activity on the box
d.  activity on the arc and activity on the node

ANSWER: A

36. In the _____ format, an activity is represented by an arrow in the network diagram
a.  AOA
b.  ABC
c.  AIN
d.  AIB

ANSWER: A

37. In the _______ format, there is a special type of activity known as a dummy activity.
a.  AOA
b.  ABC
c.  AIN
d.  AIB

ANSWER: A

38. A dummy activity consumes ______ time.
a.  zero
b.  little
c.  endless
d.  varying

ANSWER: A

57. Draw network diagrams using the activity-in-the-box format and the activity-on-the-
arrow format for the following project.

TB9–7
Activity Immediate Predecessor
A -
B A
C A
D B, C
E D
F D
G F
H E, G

ANSWER:
Activity-on-the-arrow

B
A
E
C D H
F G

Activity-in-the-box

B E

A D H

C F G

58. Draw network diagrams using the activity-in-the-box format and the activity-on-the-
arrow format for the following project.

Activity Immediate Predecessor


A -
B -
C A
D B, C
E D
F E
G E
H G

TB9–8
ANSWER:
Activity-on-the-arrow

A C D E F

G
B
H

Activity-in-the-box

A C

Start D E F
Finish
B G H

59. Draw network diagrams using the activity-in-the-box format and the activity-on-the-
arrow format for the following project.

Activity Immediate Predecessor


A -
B A
C A
D B
E C
F D
G E
H F, G
I H
J I

ANSWER:
Activity-on-the-arrow
D F H I J
B
A
G
C E

TB9–9
Activity-in-the-box

B D F

A H I J

C E G

TB9–10

You might also like