QC~PLAN.

Project No. & Name:


Name of Client/ Consultant: Doc. No. CIVIL QC

SL. ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA PERSON RESP.
No. DOCUMENT OF INSP./TEST AT LOCATION
1 Preparation Drawing Visual, 100% - Check prior installation Engineer /
Contract Specs. a. working/ shop drawings prepared Foremen/
b. Building fully enclosed Quality Engineer
c. All wet works completed and dried out
d. All service installation except final connections &
adjustments completed
e. The walls are to be painted with primer coat/ one
coat of paint or as agreed with Quality engineer/
customer if required
2 Installation Drawing Visual, 100% - Setting out carried out as per shop/ working drgs. Engineer /
Contract Specs. - Top fixing are to be installed with the fixing device Foremen/
I.e mechanically. Quality Engineer
- Binding structure to be verified and should be
sound to sustain ceiling load
- All Suspension rods/ hangers should be
vertical and in accordance with the Contract
specs./ Manufacturer's instructions
- Extra hangers to be provided near light fittings
- All exposed/ concealed grids should be horizontal/
levelled and fixed as per contract specs./
Manufacturer's instructions
- All members I.e. cross members, perimeter trims,
Holding down clips, infill units, splines etc. to be
fixed as per Contract specs./ Mfr's instructions.
- Light fittings placement should not affect the
structural stability of the ceiling
QC~PLAN.
Project No. & Name:
Name of Client/ Consultant: Doc. No. CIVIL QC

SL. ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA PERSON RESP.
No. DOCUMENT OF INSP./TEST AT LOCATION
2 Installation (Contd.) - All grills, diffusers is to be incorporated as per
Contract specs./ Manufacturer's instructions.
- Conducting parts of ceiling is to be connected
to the suitable earthing if required
- Access panels is to be provided and located to
facilitate the service units above the false ceiling
if required or as per Contract specifications

3 Final inspection Drawing Visual, 100% - The tiles/ panels are to be secured properly to grid Engineer /
Contract Specs. The installed tiles/ panels are undamaged Foremen/
- Trims around light fttings are in line and level Quality Engineer
- Access panels design is as per approved drawings.
QC~PLAN.
Suspended ceilings
Doc. No. CIVIL QC~Plan- 021/ REV. 0

RECORD

Inspection report
CIVIL QC~Form- 021-01/ REV 0

Inspection report
CIVIL QC~Form- 021-01/ REV 0
QC~PLAN.
Suspended ceilings
Doc. No. CIVIL QC~Plan- 021/ REV. 0

RECORD

Inspection report
CIVIL QC~Form- 021-01/ REV 0