Professional Documents
Culture Documents
INDUSTRY
INSTITUTE
The purpose of this publication is to make available to industry the results of research
conducted by the Construction Industry Institute (CII). The publication does not necessarily
represent the views of CII member companies, but is offered as a contribution to the industry.
CII was founded in 1983 to improve the cost effectiveness of the nation’s largest industry.
The members, who represent a broad cross-section of owners and contractors, believe that
many of the problems that limit cost effectiveness are common ones, and that real
improvements can be best accomplished in a cooperative environment with the benefits
being shared by the construction industry at large.
Prepared by
The Construction Industry Institute
Cost/Schedule Controls Task Force
Publication 6-10
April 1990
TABLE OF CONTENTS
Chapter Page
1. Introduction ............................................................................................ 1
2. The Anatomy of Changes ........................................................................ 3
Contract Changes Clause .................................................................... 3
Types of Changes ............................................................................... 3
Sources of Changes ............................................................................ 4
Timing of Changes ............................................................................. 5
Traditional Methods for Costing Changes ............................................ 5
Direct and Consequential Effects of Changes ...................................... 5
Disclaimers by Clients and Engineers .................................................. 6
3. The Direct Impacts of Changes on Cost ................................................... 7
Productivity Degradation Due to Interruptions .................................... 7
Productivity Degradation Due to Sustained Overtime ....................... 10
Delays .............................................................................................. 10
Equipment and Labor Spent in Removing Existing Work ................... 11
Materials Wasted by Removal of Existing Work ................................. 11
Nonproductive Periods during Redirection of Work .......................... 11
Recovery Scheduling ........................................................................ 11
4. The Direct Impacts of Changes on Schedule .......................................... 12
Direct Effect Evaluation ..................................................................... 13
5. The Consequential Impacts of Changes ................................................. 15
Consequential Effects ........................................................................ 15
Evaluation Tools ............................................................................... 16
Evaluating Schedule Changes ........................................................... 17
Evaluating Consequential Costs ........................................................ 17
6. Summary .............................................................................................. 19
Recommendations and Ideas to Consider .......................................... 19
References ............................................................................................ 22
1
INTRODUCTION
Two things can be said about almost any engineering and construction
project: (1) there will be changes made during the course of construction, and
(2) the owner and the constructor will seldom initially agree on the total effect
those changes have on the cost and schedule of the project.
Types of Changes
Sources of Changes
Changes may originate with the owner, owner’s agent, design engineer, or
contractor. Owner changes may be occasioned by a change in scope of the
project (research has shown this to be the major source), a change in some
functional or maintenance requirement within the current project scope which
requires a design change, a change in need dates, problems with owner-fur-
nished materials, or a user desire. Design personnel are the agents for
implementing most owner-originated changes, and are the originators of
changes caused by inadequate knowledge of existing conditions at project
sites, design errors, unforeseen conditions, new regulatory requirements, or
revised design parameters as might occur on a project where construction is
initiated before design is complete. If the owner employs a separate project
manager to provide overall project management, that agent can introduce
changes, particularly schedule changes, in fulfilling management duties to
coordinate all project activity. That individual also may be responsible for
constructive changes that arise from unwarranted interpretation of specifica-
tions or personal desires. The contractor also may be a source of changes if
design errors are found or if, as a consequence of a value engineering clause
in the contract, the contractor suggests a more cost-effective design that is
subsequently adopted. Also there may be any number of minor field-originated
changes such as valve relocation to avoid interference, and other comparable
problems that are best solved without recourse to formal charge procedures.
A change may have both direct and consequential effects and these effects
can involve cost and/or time. The direct effects are those experienced within
the work package for which the change is directed. The consequential effects
are those experienced elsewhere on the project because of that change.
Chapter 3 will discuss direct cost impacts; Chapter 4, the direct schedule
effects; and Chapter 5, the consequential cost and schedule effects.
3
The direct effects of a change will range from insignificant to costly, the most
costly being if the change is issued while work is already underway or
completed. In this chapter, the direct effects will be discussed using that
situation as the setting.
A change made while work is in progress may cause cost increases at-
tributable to some combination of the following:
• Productivity degradation
l Delays
l Recovery scheduling
Productivity was measured as lineal inches per hour by task. Using actual
productivity and average productivity for each task as numerator and
denominator, respectively, a Productivity Index (PI) was calculated for each
observation of each task. Thus, a PI of 1.0 or greater is good; less than 1.0 is
poor with respect to average.
0 295 1.000
1 43 0.090
2 12 0.615
3 or more 4 0.313
* Normalized PI was determined by calculating the Mean PI for all
observations and then dividing by a constant, which made the Normalized
PI for no interruptions equal to 1.000.
Effects of Disturbances on Work. For this purpose, disturbances include
interruptions and forced changes in work flow due to discontinuities in the
piping system being insulated. These discontinuities cause the craftsman to
perform non-routine cutting and fitting. Data was recorded for 354 observa-
tions and cataloged as follows:
Some changes may require use of overtime work in order to maintain the
schedule. When such overtime is forced (as compared to voluntary) or
becomes sustained, it becomes a demotivator and results in lowered produc-
tivity. The Construction Industry Cost Effectiveness (CICE) Project Report C-3,
Scheduled Overtime Effect on Construction Projects, provides specific
guidance on this subject. (Reference 9)
Delays
Delays may add yet another cost of changes. The materials, tools, and
construction equipment required for the changed work may not be the same
as that required for the original work and may not be currently available at the
project site. If different, the procurement times involved will delay start of
changed work. In the case of tools and construction equipment, these items
are carefully scheduled because they are available in only limited quantities,
and there may be delays occasioned by their rescheduling.
Another potential delay is that between the time a hold is placed on work to
be changed and new instructions received so it can be restarted. Still other
delays may occur after work is restarted if the revised schedule creates
interference problems with other crews or contractors who are scheduled to
work in the same area at the same time.
When delays occur, crews may actually be idled, at least for short periods of
time. If an extensive delay is envisioned, crews may have to be laid off and
subsequently remobilized when work is to start. At the least, crews would be
diverted to other work. All of these options are inefficient and costly in
comparison to proceeding with work as originally planned.
If the change involves removal of work in place, labor and equipment will
be required for its removal. This can be estimated in advance, but is best
determined after the fact using actual quantity data.
The change also may have the ripple effect of changing priorities for
performance of remaining work. Shifting crews, materials, and equipment to
meet new priorities will generate nonproductive time that is properly charge-
able to the change.
Recovery Scheduling
Discussion thus far has concentrated on the cost aspects of changes. Time
factors were included in those discussions, but not in terms of effect on
schedule. This chapter addresses this subject.
Associated with each activity on a CPM network will be its planned duration,
early and late starts and finishes, and one or both of these floats:
Total Float. This float is calculated using the assumption that all preceding
activities will have been started on early start and that all succeeding
activities will start on late start. Thus, total float shows the potential for
an activity. A p o i n t o f t e n o v e r l o o k e d , h o w e v e r , is that this float
is usually shared by a number of activities so that use of total float by one
activity will deny its use by another, later activity.
Free Float. This float is calculated using the assumption that all preceding
and all following activities will be started on early start dates. Thus, free float
shows what slippage time is available to an activity, assuming all previous
activities are started and finished on early dates, without affecting project
completion.
Floats play important roles in schedule impact studies because they represent
scheduling flexibility available to handle unforeseen situations, including
changes. Unfortunately, ownership of float is a subject of some controversy on
a fixed-price project-seldom do the contract documents address the subject.
Most contracts only require the contractor to submit a schedule for owner
approval. Then when the subject of use of float comes up, a contractor will
claim float ownership, saying that float is a management tool and a contractor
must be allowed to manage his/her work. The contractor also will defend the
right to plan work on the early start schedule and claim that use of total float
because of owner changes should be the basis for schedule adjustments to
restore the float.
The owner usually claims ownership of float as well, claiming that on any
project there is always the potential for delivery problems with owner-fur-
nished materials or other owner delays, and changes can be expected. Because
of this, float should be considered available to help absorb owner-caused
schedule disruptions.
Never assume that the effects of a change will be confined to the work
package(s) directly impacted by the change. Consequential effects can occur
on later individual work packages and on the total project. Thus, it is important
that this possibility be acknowledged and a mechanism established for
evaluating consequential effects.
Consequential Effects
One of the control tools used on a large project is the Work Breakdown
Structure (WBS). This breaks out the project in hierarchical fashion, the
objective being to include within the WBS all elements of work in ever-increas-
ing detail. Resources will be allocated within each element of the WBS to
establish a detailed baseline for resource budgeting and control. The WBS will
be backed by a Work Package Catalog (in either computer dataset or long-hand
form), which provides a complete summary of each WBS element at the control
level. Elements on the WBS also are used for various levels of construction
schedules. (See References 4, 5, and 6)
The WBS is a vital tool in change management. If a change involves work not
previously included on the WBS, it can be logically added to the WBS and its
relationship to other WBS elements seen. If the change only increases or
decreases requirements associated with existing WBS elements, this is readily
tracked.
SUMMARY
19
• Risks properly the responsibility of the owner or engineer should not be
transferred to the contractor.
• On a fixed-price contract, the contract should specify that float is jointly
owned, but responsibly shared, by owner and contractor and that
available float may be used to accommodate changes.
• At the outset of a project, owner and contractor representatives should
establish the mechanisms and procedures for administering changes.
• To provide a realistic baseline for adjustments due to changes on a
fixed-price project, the owner should require the contractor to submit
prior to or shortly after mobilization:
-A WBS for the project which is resource loaded to include planned
worker-hours per control level element.
-A Control Schedule in critical path format that is consistent with the
WBS.
• A contractor must maintain thorough estimating, planning, and control-
ling records as baseline documents for any changes. When a change
occurs, additional records must be prepared to show all implications of
that change.
• Owners and contractors may consider an up-front agreement to place
original project planning documents and data of both parties in escrow
for later reference relating to changes. This will force both sides to be
Past Members
*Principal Author
Editor: Rusty Haggard
The Construction Industry Institute
Member Companies