PLANILLA DE METRADOS

METRADO ESPECIALIDAD DE ESTRUCTURAS


OBRA: Construccion de Vivienda HOJA N°:
PROPIETARIO: Andres Garcia PLANO :
FECHA: HECHO POR:
REVISADO:

MEDIDAS
PARTIDA N° ESPECIFICACIONES N° VECES
LARGO ANCHO

OBRAS PROVISIONALES,
OE 1 TRABAJOS PRELIMINARES,
SEGURIDAD Y SALUD
OBRAS PROVISIONALES Y
OE 1.1
TRABAJOS PRELIMINARES
OE 1.1.1 CONSTRUCCIONES PROVISIONALES
OE 1.1.1.1 OFICINA 1 5.50 4.00
1 2.50 4.00
OE 1.1.1.2 ALMACENES 1 10.00 10.00
1 7.00 4.00
OE 1.1.1.3 CACETAS DE GUARDANIA 1 2.00 2.00
OE 1.1.1.4 COMEDORES 1 8.00 11.00
OE 1.1.1.5 VESTUARIOS 1 2.00 9.00
OE 1.1.1.6 SSHH 1 3.20 8.00
OE 1.1.1.7 CERCO metalico h=2.40 417.60 197.60
OE 1.1.1.8 CARTEL DE MADERA DE 2.6 X 3.4
OE 1.1.2 INSTALACIONES PROVISIONALES
OE 1.1.2.1 AGUA PARA LA CONSTRUCCION
OE 1.1.2.1.1 OBTENCION DEL SERVICIO
OE 1.1.2.1.2
ALMECENAMIENTO Y DISTRIBUCION

OE 1.1.2.2
DESAGUE PARA LA CONSTRUCCION

OE 1.1.2.3 ENERGIA ELECTRICA PROVISIONAL


OE 1.1.2.3.1
CONEXIÓN E INSTALACION

OE 1.1.2.3.2 CONSUMO Y MANTENIMIENTO


INSTALACION TELEFONICA Y
OE 1.1.2.4
COMUNICACIÓN PROVISIONAL
OE 1.1.2.4.1 CONEXIÓN E INSTALACION
OE 1.1.2.4.2 CONSUMO Y MANTENIMIENTO
OE 1.1.3 TRABAJOS PRELIMINARES
OE 1.1.3.1 LIMPIEZA DEL TERRENO
OE 1.1.3.1.1 ELIMINACION DE BASURA Y
ELEMENTOS SUELTOS Y LIVIANOS 2 98.80 98.80
OE 1.1.4
MOVILIZACION DE CAMPAMENTO,
MAQUINARIA Y HERRAMIENTAS
OE 1.1.5 TRAZOS, NIVELES Y REPLANTEO
OE 1.1.5.1. TRAZOS, NIVELES Y REPLANTEO
PRELIMINAR 2 98.80 98.80
OE 1.1.5.2 REPLANTEO DURANTE EL PROCESO

OE 1.2 SEGURIDAD Y SALUD


OE 1.2.1
ELABORACION, IMPLEMENTACION Y
ADMINISTRACION DEL PLAN DE
SEGURIDAD Y SALUD EN EL TRABAJO

OE 1.2.1.1
EQUIPOS DE PROTECCION INDIVIDUL

OE 1.2.1.2
EQUIPOS DE PROTECCION COLECTIVA

OE 1.2.1.3 SEÑALIZACION TEMPORAL DE


SEGURIDAD
OE 1.2.1.4 CAPACITACION EN SEGURIDAD Y
SALUD
OE 1.2.2
RECURSOS PARA RESPUESTAS ANTE
EMERGENCIAS EN SEGURIDAD Y
SALUD DURANTE EL TRABAJO
ADOS
DE ESTRUCTURAS
HOJA N°: 1
PLANO :
HECHO POR:
REVISADO:

MEDIDAS
PARCIAL TOTAL UND
ALTO

22.00
32.00 m2
10.00
100.00
128.00 m2
28.00
4.00 4.00 m2
88.00 88.00 m2
18.00 18.00 m2
25.60 25.00 m2
615.20 615.20 m
1.00 Glb

1.00 Glb

1.00 Glb

1.00 Glb

1.00 Glb
1.00 Glb

1.00 Glb
1.00 Glb

0.50 4880.72 9761.44 m3

1.00 Glb
9761.44 19522.88 m2
1.00 Glb

1.00 Unidad

1.00 Glb

Glb

Glb

1.00 Glb
PLANILLA DE METRADOS
METRADO ESPECIALIDAD DE ESTRUCTURAS
OBRA: Construccion de Vivienda HOJA N°:
PROPIETARIO: Andres Garcia PLANO :
FECHA: HECHO POR
REVISADO:

MEDIDAS
PARTIDA N° ESPECIFICACIONES N° VECES
LARGO ANCHO

OE 2 ESTUCTURAS

OE 2.1 MOVIMIENTO DE TIERRA

OE 2.1.1 NIVELACION DEL TERRENO


OE 2.1.1.1 NIVELACION
OE 2.1.1.2 NIVELADO APISONADO
OE 2.1.2 EXCAVACIONES
OE 2.1.2.1 EXCAVACIONES SIMPLES
Z-1 13 1.00 1.00
Z-2 2 1.50 1.50
Z-3 3 1.40 1.40
Z-4 1 1.20 1.20
Z-5 1 1.00 0.50

EJE 3-3 ENTRE 5-9 1 7.00 0.50


EJE 8-8 ENTRE 1-4 1 1.37 0.50
EJE 8-8 ENTRE 4-3 1 1.60 0.40
EJE 7-7 ENTRE 1-4 1 3.32 0.50
EJE 6-6 ENTRE 1-4 1 3.32 0.50
EJE 5'-5' ENTRE 3'-3 1 1.15 0.40
EJE 5-5 ENTRE 1-2 1 0.50 0.50
EJE 5-5 ENTRE 2-3 1 2.37 0.50
EJE 9-9 ENTRE 1-2 1 0.50 0.50
EJE 9-9 ENTRE 2-3 1 2.37 0.50
BASE ESCALERA 1 0.85 0.50
PATIO 1 2.85 1.60
BAÑO 1 1.35 1.15
POZO TIERRA
ZANJAS SANITARIAS
OE 2.1.3 RELLENOS
OE 2.1.3.1 RELLENOS CON MATERIAL PROPIO
EJE 1-1 ENTRE 8-7 1 3.48 0.87
EJE 1-1 ENTRE 7-6 1 5.30 1.37
EJE 1-1 ENTRE 6-5 1 2.96 1.27
EJE 1-1 ENTRE 5-9 1 6.80 1.07
EJE 2-2 ENTRE 5-9 1 7.00 0.37
EJE 4-4 ENTRE 8-7 1 3.23 -0.13
EJE 3´-3' ENTRE 5´-5 1 1.73 -0.13
EJE 3-3 ENTRE 8-7 1 3.23 -0.13
EJE 3-3 ENTRE 7-6 1 5.33 -0.13
EJE 3-3 ENTRE 6-5 1 2.91 -0.13
EJE 3-3 ENTRE 5-9 1 7.00 0.37
EJE 8-8 ENTRE 1-4 1 1.37 0.37
EJE 8-8 ENTRE 4-3 1 1.60 0.27
EJE 7-7 ENTRE 1-4 1 3.32 0.50
EJE 6-6 ENTRE 1-4 1 3.32 0.50
EJE 5'-5' ENTRE 3'-3 1 1.15 0.37
EJE 5-5 ENTRE 1-2 1 0.50 0.27
EJE 5-5 ENTRE 2-3 1 2.37 0.50
EJE 9-9 ENTRE 1-2 1 0.50 0.37
EJE 9-9 ENTRE 2-3 1 2.37 0.37

OE 2.1.4 NIVELACION INTERIOR Y APISONADO


MANUAL
COCINA 1 1.87 3.36
PATIO 1 2.00 2.53
COMEDOR-SALA 1 5.30 4.02
FRENTE A ESCALERA 1 1.50 1.00
ATRÁS A ESCALERA 1 1.00 2.00
BAÑO 1 1.60 1.60
FRENTE A BAÑO 1 2.27 1.45
PASADIZO 1 6.90 1.00
TIENDA 1 6.72 2.87

OE 2.1.5 ELIMINACION DE MATERIAL EXCEDENTE

VOLUMEN EXCAVACION
VOLUMEN RELLENO
VOLUMEN ELIMINACION COMPACTADO

OE 2.2. OBRAS DE CONCRETO SIMPLE


MEDIDAS
OE 2.2.1. CIMIENTOS CORRIDOS N° VECES
LARGO ANCHO
EJE 1-1 ENTRE 8-7 1 3.48 0.50
EJE 1-1 ENTRE 7-6 1 5.30 0.50
EJE 1-1 ENTRE 6-5 1 2.96 0.50
EJE 1-1 ENTRE 5-9 1 6.80 0.50
EJE 2-2 ENTRE 5-9 1 7.00 0.45
EJE 4-4 ENTRE 8-7 1 3.23 0.45
EJE 3´-3' ENTRE 5´-5 1 1.73 0.40
EJE 3-3 ENTRE 8-7 1 3.23 0.40
EJE 3-3 ENTRE 7-6 1 5.33 0.50
EJE 3-3 ENTRE 6-5 1 2.91 0.50
EJE 3-3 ENTRE 5-9 1 7.00 0.50
EJE 8-8 ENTRE 1-4 1 1.37 0.50
EJE 8-8 ENTRE 4-3 1 1.60 0.40
EJE 7-7 ENTRE 1-4 1 3.32 0.50
EJE 6-6 ENTRE 1-4 1 3.32 0.50
EJE 5'-5' ENTRE 3'-3 1 1.15 0.50
EJE 5-5 ENTRE 1-2 1 0.50 0.40
EJE 5-5 ENTRE 2-3 1 2.37 0.50
EJE 9-9 ENTRE 1-2 1 0.50 0.45
EJE 9-9 ENTRE 2-3 1 2.37 0.50
BASE DE ESCALERA 1 1.00 0.50

MEDIDAS
OE 2.2.2 SOBRECIMIENTO N° VECES
LARGO ANCHO
OE 2.2.2.1 PARA EL CONCRETO
EJE 1-1 ENTRE 8-7 1 2.95 0.13
EJE 1-1 ENTRE 7-6 1 4.95 0.13
EJE 1-1 ENTRE 6-5 1 2.70 0.13
EJE 1-1 ENTRE 5-9 1 6.02 0.13
EJE 2-2 ENTRE 5-9 1 6.15 0.13
EJE 4-4 ENTRE 8-7 1 2.80 0.13
EJE 3´-3' ENTRE 5´-5 1 1.05 0.13
EJE 3-3 ENTRE 8-7 1 2.82 0.13
EJE 3-3 ENTRE 7-6 1 4.95 0.13
EJE 3-3 ENTRE 6-5 1 2.70 0.13
EJE 3-3 ENTRE 5-9 1 6.10 0.13
EJE 8-8 ENTRE 1-4 1 1.89 0.13
EJE 8-8 ENTRE 4-3 1 1.73 0.13
EJE 6-6 ENTRE 2-3 1 2.78 0.13
EJE 5'-5' ENTRE 3'-3 1 1.60 0.13
EJE 5-5 ENTRE 4-3 1 1.87 0.13

OE 2.2.2.2 PARA EL ENCOFRADO


EJE 1-1 ENTRE 8-7 2 2.95
EJE 1-1 ENTRE 7-6 2 4.95
EJE 1-1 ENTRE 6-5 2 2.70
EJE 1-1 ENTRE 5-9 2 6.02
EJE 2-2 ENTRE 5-9 2 6.15
EJE 4-4 ENTRE 8-7 2 2.80
EJE 3´-3' ENTRE 5´-5 2 1.05
EJE 3-3 ENTRE 8-7 2 2.82
EJE 3-3 ENTRE 7-6 2 4.95
EJE 3-3 ENTRE 6-5 2 2.70
EJE 3-3 ENTRE 5-9 2 6.10
EJE 8-8 ENTRE 1-4 2 1.89
EJE 8-8 ENTRE 4-3 2 1.73
EJE 6-6 ENTRE 2-3 2 2.78
EJE 5'-5' ENTRE 3'-3 2 1.60
EJE 5-5 ENTRE 4-3 2 1.87

MEDIDAS
OE 2.2.3 FALSO PISO 1:8 e= 0.10 m N° VECES
LARGO ANCHO
COCINA 1 1.87 3.36
PATIO 1 2.00 2.53
COMEDOR-SALA 1 5.30 4.02
FRENTE A ESCALERA 1 1.50 1.00
ATRÁS A ESCALERA 1 1.00 2.00
BAÑO 1 1.60 1.60
FRENTE A BAÑO 1 2.27 1.45
PASADIZO 1 6.90 1.00
TIENDA 1 6.72 2.87

OE 2.3 OBRAS DE CONCRETO ARMADO

MEDIDAS
OE 2.3.1 COLUMNA N° VECES
LARGO ANCHO
OE 2.3.1.1 PARA CONCRETO
C-1(COCINA) 3 0.40 0.15
C-1(PASADIZO) 1 0.40 0.15
C-2 6 0.25 0.25
C-3 4 0.30 0.30
C-4 5 0.25 0.15
ENDENTADO
C-1 4 0.12 0.15
C-2 6 0.06 0.15
C-3 4 0.12 0.15
C-4 5 0.08 0.15
OE 2.3.1.2 PARA EL ENCOFRADO
C-1 (8-1,8-4) 2 1.28
C-1 (7-4) 1 1.19
C-1 (9-1) 1 1.19
C-2 (5-1,9'-1,9'-3) 3 1.17
C-2 (5-3) 1 1.27
C-2 (9-2,9-3) 2 1.09
C-3 (7-1,7-3,6-1) 3 1.38
C-3 (6-3) 1 1.47
C-4 (5-2) 1 0.89
C-4 (8-4,7-3) 2 0.74
C-4 (9'-2) 1 0.98
C-4 (8-3) 1 0.98

N° PZAS POR
OE 2.3.1.3 PARA LA ARMADURA DE ACERO N° VECES ø ELEM.

C-1 FIERRO LONG 4 1/2" 4


4 3/8" 2
C-1 ESTRIBOS 1 1/4" 27
3 1/4" 28
C-2 FIERRO LONG 6 1/2" 6
C-2 ESTRIBOS 6 1/4" 23
C-3 FIERRO LONG 4 5/8" 4
C-3 ESTRIBOS 4 1/4" 23
C-4 FIERRO LONG 3 3/8" 4
2 3/8" 4
C-4 ESTRIBOS 3 1/4" 18
2 1/4" 23

LONGITUD TOTAL

MEDIDAS
OE 2.3.2 VIGAS N° VECES
LARGO ANCHO
OE 2.3.2.1 PARA CONCRETO
VIGA S, EJE 1, ENTRE 6-9 1 8.86 0.25
VIGA S, EJE 3, ENTRE 5-9 1 6.05 0.25
VIGA S, EJE 8, ENTRE 1-4 1 1.68 0.25
VIGA P, EJE 9, ENTRE 1-3 1 4.32 0.25
VIGA P1, EJE 5 Y 9', ENTRE 1-3 2 4.32 0.25
VIGA P2, EJE 6, ENTRE 1-3 1 4.32 0.25
VIGA P3, EJE 1 Y 3, ENTRE 6 Y 7 2 5.30 0.30
VIGA P4,EJE 3, ENTRE 5-6 1 2.70 0.15
VIGA P5, EJE 2 ENTRE 5-9 1 6.07 0.15
VIGA V1, EJE 7, ENTRE 1-3 1 4.32 0.25
VGA V1, EJE 1 Y 4, ENTRE 8-7 2 3.50 0.25
VIGA CH, EJE4, ENTRE5-6 1 2.70 0.40

OE 2.3.2.1 PARA CONCRETO


VIGA S, EJE 1, ENTRE 6-9 1 8.86 0.30
VIGA S, EJE 3, ENTRE 5-9 1 6.05 0.30
VIGA S, EJE 8, ENTRE 1-4 1 1.68 0.30
VIGA P, EJE 9, ENTRE 1-3 1 3.67 0.45
VIGA P1, EJE 9', ENTRE 1-3 1 3.67 0.45
VIGA P1, EJE 5, ENTRE 1-3 1 1.85 0.30
1 1.80 0.45
VIGA P2, EJE 6, ENTRE 1-3 1 2.82 0.30
1 0.90 0.45
VIGA P3, EJE 1 Y 3, ENTRE 6 Y 7 2 4.90 0.55
VIGA P4,EJE 3, ENTRE 5-6 1 2.70 0.40
VIGA P5, EJE 2 ENTRE 5-9 1 6.07 0.20
VIGA V1, EJE 7, ENTRE 1-3 1 3.57 0.25
VGA V1, EJE 1 Y 4, ENTRE 8-7 2 3.10 0.45
VIGA CH, EJE4, ENTRE5-6 1 1.05 0.25
1 1.70 0.40
S
ESTRUCTURAS
HOJA N°: 2
PLANO :
HECHO POR
REVISADO:

MEDIDAS
PARCIAL TOTAL UND
ALTO

1.30 16.90
1.30 5.85
1.30 7.64
1.30 1.87
1.30 0.65

1.00 3.50
1.00 0.69
1.00 0.64
1.00 1.66
1.00 1.66
1.00 0.46
1.00 0.25
1.00 1.19
1.00 0.25
1.00 1.19
0.65 0.28
0.15 0.68
0.15 0.23

45.58 m3
SC = 0.13

0.25 0.76
0.25 1.82
0.25 0.94
0.25 1.82
0.25 0.65
0.25 -0.10
0.25 -0.06
0.25 -0.10
0.25 -0.17
0.25 -0.09
0.25 0.65
0.25 0.13
0.25 0.11
0.25 0.42
0.25 0.42
0.25 0.11
0.25 0.03
0.25 0.30
0.25 0.05
0.25 0.22 7.86 m3

6.28
5.06
21.31
1.50
2.00
2.56
3.29
6.90
19.29 68.19 m3

32.25
6.00
26.25 m3
MEDIDAS
PARCIAL TOTAL UND
ALTO
0.75 1.31
0.75 1.99
0.75 1.11
0.75 2.55
0.75 2.36
0.75 1.09
0.75 0.52
0.75 0.97
0.75 2.00
0.75 1.09
0.75 2.63
0.75 0.51
0.75 0.48
0.75 1.25
0.75 1.25
0.75 0.43
0.75 0.15
0.75 0.89
0.75 0.17
0.75 0.89 23.62 m3
0.65 0.33

MEDIDAS
PARCIAL TOTAL UND
ALTO

0.55 0.21
0.55 0.35
0.55 0.19
0.55 0.43
0.55 0.44
0.55 0.20
0.55 0.08
0.55 0.20
0.55 0.35
0.55 0.19
0.55 0.44
0.55 0.14
0.55 0.12
0.55 0.20
0.55 0.11
0.55 0.13 3.79 m3
0.55 3.245
0.55 5.445
0.55 2.97
0.55 6.622
0.55 6.765
0.55 3.08
0.55 1.155
0.55 3.102
0.55 5.445
0.55 2.97
0.55 6.71
0.55 2.079
0.55 1.903
0.55 3.058
0.55 1.76
0.55 2.057 58.37 m2

MEDIDAS
PARCIAL TOTAL UND
ALTO
6.28
5.06
21.31
1.50
2.00
2.56
3.29
6.90
19.29 68.19 m3

MEDIDAS
PARCIAL TOTAL UND
ALTO

3.08 0.55
2.98 0.18
2.98 1.12
2.98 1.07
2.98 0.56

2.53 0.17
2.53 0.14
2.53 0.18
2.53 0.15 4.13 m3
3.08 7.88
3.08 3.67
2.98 3.55
2.98 10.46
2.98 3.78
2.98 6.50
2.98 12.34
2.98 4.38
2.98 2.65
2.98 4.41
2.98 2.92
2.98 2.92 65.46 m2

LONG. POR LONGITUD POR ø


PIEZA 1/4" 3/8" 1/2" 5/8"
4.50 72.00
4.50 36.00
1.10 29.70
1.10 92.40
4.50 162.00
1.00 138.00
4.50 72.00
1.20 110.40
3.93 47.16
4.50 36.00
0.80 43.20
0.80 36.80

450.5 119.16 234.00 72.00

MEDIDAS
PARCIAL TOTAL UND
ALTO

0.20 0.44
0.20 0.30
0.20 0.08
0.30 0.32
0.30 0.65
0.30 0.32
0.30 0.95
0.30 0.12
0.30 0.27
0.20 0.22
0.20 0.35
0.20 0.22 4.26 m3

2.66
1.82
0.50
1.65
1.65
0.56
0.81
0.85
0.41
5.39
1.08
1.21
0.89
2.79
0.26
0.68 23.21 m2