P-1068 : VOPAK_Progress Status Tankage

TK-6 (36.8 M DIA X 21.3 M HEIGHT)


%
Plan Variance Plan Finish
Completed
Foundation 100% 89.00% -11.00% 14-May-18
- Asphalt on slop of Ring Wall partially done
Fab & Erec. 31.60% 25.70% 11-Dec-18
- Shell Course 9 Erection completed
- Roof Structure Erection completed and roof plate Welding in
Progress

TK-5 (36.8 M DIA X 21.3 M HEIGHT)


%
Plan Variance Plan Finish
Completed
Foundation 100% 69.00% -31.00% 5-Jun-18
- Crushed stone laying & Asphalt on slop of Ring Wall to be done
Fab & Erec. 23.42% 9.32% 5-Feb-19
- Laying & Welding of Annular Plates completed, bottom plate
welding in progress
- Shell course 9 erection in progress

TK-4 (36.8 M DIA X 21.3 M HEIGHT)


%
Plan Variance Plan Finish
Completed
Foundation 41.3% 69.00% -27.7% 24-May-18
- Crushed stone laying & Asphalt on slop of Ring Wall to be done
Fab & Erec. 21.69% 22.92% 1.23% 23-Jan-19
- Shell Course 9 Erection completed
- Roof Structure Erection completed, Welding in Progress
TK-3 (36.8 M DIA X 21.3 M HEIGHT)
%
Plan Variance Plan Finish
Completed
Foundation 100% 44.75% -55.25% 25-Jun-18
- Top Sand Filling on HDPE layer in progress
- Asphalt below annular plate in progress
- Asphalt on Slope of Ring wall to be done
Fab & Erec. 3.81% 4.014% 1-Mar-19
- Marking and cutting of Plates completed. Rolling of SP9, SP8 &
SP7 completed
- Fabrication and rolling of Curb Angle & wind girder Completed
- Roof Structure Fabrication completed

TK-2 (26.2 M DIA X 21.3 M HEIGHT)


%
Plan Variance Plan Finish
Completed
Foundation 74.0% 45.37% -28.63% 26-Jun-18
- HDPE sheet laying & Sump erection completed
- Asphalt below annular plate & Asphalt on Slope of Ring wall to
be done
Fab & Erec. 1.38% 3.96% 2.58% 9-May-19
- Marking and cutting of Plates completed. Rolling of SP9, SP8 &
SP7 completed
- Fabrication and rolling of Curb Angle Completed
- Roof Structure Fabrication completed

TK-1 (26.2 M DIA X 21.3 M HEIGHT)


%
Plan Variance Plan Finish
Completed
Foundation 81.8% 14.23% -67.52% 31-May-18
- Ring beam 5th layer (G2) in progress
Fab & Erec. 6.59% 3.82% 3-Apr-19
- Marking and cutting of Plates completed 93.01%
- Fabrication and rolling of Curb Angle Completed
- Roof Structure Fabrication completed 81.01%
TK-8
%
Plan Variance Plan Finish
Completed
Foundation 38.5% 14.60% -23.90% 13-Aug-18
- Sand filling inside ring wall in progress

Week Look Ahead


Engineering

Target for this


Procurement Cumm. Till 21-Jun-18
week
Plan Actual ∆

Status as on Target in % of Contract


Payment Milestone Remarks
21-Jun-18 this week Value
Fire Water Pumps & Jockey Pumps
Supply of Fire Water Pumps – M14 5%
PO to be
CBE Closed Delivery - 3 Month Ex Works (37,138,578
issued
ZAR)
Expected ROS – 28-Oct-18
ESD & MOVs
Supply of ESD & MOVs – M12 6%
TBE – PO to be
Delivery - (44,566,294
in progress issued
Expected ROS – ZAR)
Construction