You are on page 1of 32

ENGLISH VERSION

Human Capital Characteristic of the Superintending Officer


By
1 2
Ir. Dr. Hasnul Mohamad Salleh , Kohilavaani Skumaran

Keywords: Integrity, Contract Document, Domain, Professional Engineer, Contract,


Extension of Time, Human Capital, Interaction Plan, Superintending Officer,
Project Management, Variation of Works, Risk Profile, Risk, Conditions of
Contract, Superintending Officer’s Representative

Abstract

The Superintending Officer (S.O.) is an officer appointed by the Financial Controller to supervise and
issue works instruction in accordance with Standard P.W.D. Form 203 of the Agreement. The S.O.
must be capable and knowledgable in different fields. A knowlegable, confident, possess high moral
values, ethical, discipline, dynamic, innovative, fair and efficient S.O. will dictate the direction of the
Project to be implemented. These elements which form the backbone of the human capital
characteristic shall be nurtured and possessed by the S.O. to guide the S.O. in any decision making or
action taken during project implementation to avoid delay in project completion or project cost overrun.
There are cases where the decisions and actions taken by the S.O. has been criticised by the Auditor-
General. In ensuring the smooth implementation and to avoid wasteful and misuse of the power during
construction supervision of the Government project, the S.O. shall play an important role and
demonstrates the important of human capital characteristic of a S.O. when discharging the duties
entrusted by the Government. The major characteristic/criteria to be possessed by the S.O. includes
work within the stipulated domain or framework, emphasize on human capital development, Project
risks identification and prevention, understood and guided by interaction plan which serves as
reference/guidance, and skillful in decision making. This paper is intended to discuss on decisions and
actions taken by the S.O. to solve issues arising during projects implementation, such as Pulau
Perhentian Project, Phase 2 Beaufort WTP Project, Construction of Off-river Storage Project, Jalan
Universiti Project and Expansion of Mengkuang Dam Project. The outcomes of the S.O. decisions and
actions taken on the above projects are project cost saving, on time project completion, sick project
status be avoided, inconsistency of decision making and dispute with the Contractor and consultant be
avoided.

1.0 Introduction

The S.O. is an officer appointed by the Financial Controller of the


Implementation Agency to administer and issue works instruction in accordance with
the agreement based on the Standard P.W.D Form 203. The S.O. is also
empowered to appoint a suitable officer as the S.O.’s Representative in a formal
manner.

1
Director General, Water Supply Department, KeTTHA
2
Civil Engineer, Water Supply Department, KeTTHA
Page 1/32
ENGLISH VERSION

2.0 Background

In the Auditor-General’s Report released recently, many weaknesses related


to the S.O. decision during project implementation have been identified and reported.
These weaknesses have caused the delay in of Project completion and contributed
to Project cost overrun. The following are some of the weaknesses observed:

i) Improper financial management;


ii) Extension of time been approved repeatedly or improperly;
iii) Lack of control and monitoring on disbursement to the Contractor;
iv) Recoupment of advance payment from Contractor;
v) Lacking in monitoring the quality of material used and workmanship
against the Contract;
vi) Ignorance on safety at the project site;
vii) No proper monitoring on work progress;
viii) Notice did not issued within stipulated time;
ix) Did not impose liquidated ascertained damages on the Contractor who
has breached the Contract; and
x) Not well verse with the Conditions of Contract.

In ensuring the project be implemented prudently without wastage and misuse


of power, the S.O. shall pay an important role and possess good characteristic when
discharging his duties entrusted to.

3.0 Duties and Responsibilities of the S.O.

The following are the duties and responsibilities of the S.O.:

i) As Government’s representative to supervise and issue work


instructions in accordance with the provision of the Contract;
ii) The power of the S.O. to issue instruction is subject to Treasury’s
Instruction which requires prior approval from the parties concerned in
accordance with the provision;

Page 2/32
ENGLISH VERSION

iii) Responsible to ensure the Contractor carries out the work in


accordance with the provision in the Contract and obligation of the
Government is honoured. The S.O. shall:

a) Ensure the quality of the material used and quality of works comply
with the Contract;
b) Ensure local authority and other authorities requirements are
complied during project implementation;
c) Ensure the Contractor looks after the welfare of the workers,
especially on matters related to safety, insurance coverage and
salaries due.
d) Ensure the duration of the insurance as required in the Contract is
always valid during project construction stage, and if necessary, the
S.O. shall take necessary action to extend it;
e) Monitor the work progress and if necessary, to take early action to
approve extension of time or impose liquidated ascertained
damages or recommend to the Officer concerned to terminate the
Contractor’s work in accordance with the provision of the Contract;
f) To discharge the responsibilities as the S.O. so that the
Government could honour his responsibilities in the Contract:
• The Contractor is not prevented or restricted or prohibited
from carrying out the works in accordance with the Contract;
• Application by the Contractor on the approval and decision
shall be replied accordingly within the reasonable time
frame;
• Interim payment certificates to the Contractor shall be
prepared and issued in accordance with the provisions of
the Contract; and
• Each progress payment to the foreign Contractor shall take
into consideration withholding tax in accordance with the
prevailing rate.
iv) In addition, the S.O. shall also ensure that extension of time is only
issued based on the reasons stated in the Conditions of Contract.

Page 3/32
ENGLISH VERSION

4.0 Characteristic of the S.O.

The S.O. shall possess the following characteristic/criteria:

4.1 Work within Domain

The Implementation Agency shall ensure the S.O. is competent and priority
shall be given to candidate who is Technical Officer that could apply his
expertise/knowledge and experience when discharging his duties and dictate the
direction of the project.

The S.O. shall know and understand the legal framework related to the
Contract so that he could discharge his duties in orderly manner. In addition, the S.O.
shall understand each element as shown in Figure 1 which is inter related, i.e. legal,
Contract, technical and financial. As such, the S.O. ensures that his duties and
responsibilities are within the domain, he shall seek the advice of others such as the
Finance Ministry if situation warranted.

Figure 1: Work within domain.

4.2 Focus on Development of Human Capital

Human capital is defined as inbuilt competency stock, knowledge and


personalities in the ability to create economical value when implementing the work
entrusted to. These characteristic could be developed via training and experience.

Page 4/32
ENGLISH VERSION

Human capital is one of the important elements in the organisation and the
S.O. shall emphasis on development of human capital in the workforce. The
appointed S.O. must possess strong human capital, competent and well verse in
Contractual matters so that he could give guidance to the project team under his
supervision to supervise/ monitor the project in accordance with established circular,
guidelines and regulations.

In line with the Government’s effort to give better services to the Client and to
elevate the competency of the staff, high priority shall be given to training of staff in
area related to their daily task and also career development. The S.O. shall carry out
the planning and implementation of the above in two (2) phases, i.e. short and long
term planning to be carried out concurrently.

In short term planning, focus to be given on the following:

i) Staff with good writing skills;


ii) Improvement of understanding and knowledge;
iii) Establishment on good operating procedures;
iv) Staff with good communication skills;
v) Latest, accurate and up to date data;
vi) Upgrade the technical skills and knowledge; and
vii) Identify and give guidance to engineer to qualify as Professional
Engineer.

To ensure continuity, emphasize shall be given to the following:

i) Good working culture;


ii) Availability of vast experience, skillful and competence work force;
iii) Good career prospect and development;
iv) Upgrading of professionalism;
v) Very high sense of belonging and pride;
vi) Adopt good mindset, attitude and commitment; and
vii) All engineers are Professional Engineer.

Page 5/32
ENGLISH VERSION

It is expected that in tandem with the increase of the professionals and sub-
professionals in the organisation, the responsibilities and liabilities shall also be
increased accordingly. Adequate well trained workforce is necessary to ensure the
projects are monitored, implemented and handover with high quality within the
stipulated time frame. Opportunity shall be given to existing staff for promotion as a
mean to retain the experienced staff. Training and development and career path for
the professional and supporting staff shall be implemented as shown in Figure 2. For
example, all the professional staff in JBA is borrowed from Jabatan Kerja Raya
(JKR) and it is a common practice that the staff will have to be transferred out when
there is a promotion exercise. The vacancy left by the promoted staff will be filled up
by new engineer/ assistant engineer who warrant the training process which is very
time consuming to start all over again.

Figure 2: Training/Career.

4.3 Identification and Prevention of Risks

Risk shall have implication/ effect on each project which could be divided into:
i) External Risks
• Which is beyond the control/ influence of the project team, such as
change in Government policies and market shift.

ii) Internal Risks


• Which could be controlled or could change the situation, such as
expertise of staff and estimated cost.

In short, risks are associated with loss. Methods to identify risks are:
Page 6/32
ENGLISH VERSION

i) Checklist
• To identify the possible sources of risks.
ii) Flowchart
• To understand cause and effect of the risks.
iii) Interview
• To discuss with the related party who is capable of identifying the
risks.

Sources of risks could normally be identified as follows:


i) Change of requirements;
ii) Error or left out in the design and misunderstanding;
iii) Weakness in interpreting and understanding the roles and
responsibilities;
iv) Estimation error; and
v) Inefficient workforce.

Figure 3 shows the life cycle of each project and Figure 4 explains the risks
and prevention measures during award of tender.

PROJECT DOCUMENTATION
IMPLEMENTATION ( TENDER ADVERTISEMENT
PLANNING DOCUMENT)

DOCUMENTATION
(CONTRACT AWARD OF TENDER
DOCUMENT) TENDER EVALUATION

CONSTRUCTION HANDING OVER AND


AND SITE MAINTENANCE
SUPERVISION

Figure 3: Life cycle of project.

Page 7/32
ENGLISH VERSION

ACTIVITY RISKS PREVENTIONS


• Member of tender board shall
be on rotation basis.
Award of tender is not • Control movement of tender
transparent and confidential file.
information leak out • Department’s estimated cost to
be sealed and put into tender
box one (1) day before tender
opening date.

Award of Tender
Letter of Award is not • Ensure Letter of Award consists
complete complete details.

• Correspondences must be via


Letter of Award is not A.R. Register.
received/received late by
• Ensure acknowledge slip is
Contractor
returned by Contractor.

Figure 4: Risks and prevention measures during award of tender.

As an example for Expansion of Mengkuang Dam Project, the Risks Management


Committee will be formed and chaired by the S.O. and will be represented by two (2)
experts to ensure matters related to legal, financial, technical and Contract are in
order. Risks profile for this project during construction and operation stages are
shown in Table 1 and 2.

In this case, the S.O. shall prepare the risks profile and the project
implemented shall be monitored closely based on the risks profile as prevention
action.

Page 8/32
ENGLISH VERSION

CATEGORY POTENTIAL RISK RISK LEVEL MITIGATING


MEASURES

Low Med High

River Diversion -Overtopping of flood due ♦ *Allow safety factor in


to inclement weather cofferdam design.
condition.
Foundation -Damage to Plant and ♦ *Emergency Respond
Excavation and machinery by flood. Plan.
Treatment -Impact to stability of ♦ *Monitoring & control of
existing dam. excavation adjacent
-Unforeseen foundation ♦ existing dam.
conditions extensive *Contingency plan to
treatment required. mobilise additional
resources.
Construction of -Shortage of suitable ♦ *Allow import from
New Dam construction materials. outside project area.
Tunneling -Unforeseen geological ♦ *Contingency plan to
conditions causes delay in mobilise more tunneling
tunneling works. equipment &
manpower.
Draw off Tower -Extensive settlement of ♦ *Design to allow culvert
culvert underneath dam to articulate.
leads to cracks in culvert.

Table 1: Risks profile – construction stage.

Page 9/32
ENGLISH VERSION

CATEGORY POTENTIAL RISK RISK LEVEL MITIGATING


MEASURES

Low Med High

Hydrological Risk -Inadequate data for flood ♦ *Allow adequate


analysis. ♦ freeboard.
-Spillway under capacity
results in overtopping of
dam.
Geological -Weakness in geological ♦ *Geological mapping
structures. after areas area
-Fractures in rock or ♦ cleared to identify
underground channels problem areas.
leads to reservoir leakage.
Geotechnical -Foundation settlement. ♦ *Conservative design of
-Excessive leakage ♦ concrete cutoff &
through dam & foundation. curtain.
-Piping failure of dam ♦ *Careful design of filter
-Reservoir slope failure ♦ for control of piping.

Environmental -Reservoir eutrophication. ♦ *Water quality study.


-Water quality problem due ♦ Provide aeration
to iron and manganese system.
- Impact on downstream ♦ *Provide facility for
ecology maintenance flow.
Water -Competition For Water ♦ *Integrated Water
Abstraction from Rights between Kedah and Resources
Sg. Muda Penang State Management Policy &
Interstate Agreement

Changes to -Logging activities and ♦ *Implement catchment


Catchment land use change impact on management plan.
Conditions at Sg. Muda river regime. *Monitoring &
-Sg. Muda -Contamination of water Enforcement of Laws.
Catchment source due to uncontrolled ♦
-Mengkuang activities.
Dam Catchment

Table 2: Risks profile – operation stage.

4.4 Interaction Plan as Reference Point/ Guidance

Interaction plan is aimed to identify major project stakeholders. The


interaction plan for Expansion of Mengkuang Dam project is shown as Figure 5.

Page 10/32
ENGLISH VERSION

Figure 5: Interaction plan for Expansion of Mengkuang Dam Project.

4.5 Skill and Vision in Decision Making

The S.O. shall be capable to choose the best alternative to solve a problem
and to make decision based on Conditions of Contract and prevailing procedures.
Any decision shall be made carefully and be aware of the uncertainty and associated
risks of each project so that the effective result could be obtained, for example
projects at Pulau Perhentian, Phase 2 Beaufort WTP, Construction of Off-River
Storage, Jalan Universiti Project and Expansion of Mengkuang Dam. Major
decisions made by the S.O. on the issue arising during project implementation are to
ensure that the works could be completed within the approved duration.

4.5.1 Pulau Perhentian Project

i) Variation Order has increased the water reticulation coverage from 60%
to 100% with extra cost of RM8million only.
ii) Combination of two (2) reservoirs into one (1) reservoir at Pulau
Perhentian which has been declared as Marine Park. In the original

Page 11/32
ENGLISH VERSION

scope of works, the Contractor was required to build two (2) reservoirs at
Pulau Perhentian, i.e. 1.14 ML at Pulau Perhentian Besar and 0.6 ML at
Pulau Perhentian Kecil. The S.O. has decided to combine these two (2)
reservoirs into one (1) reservoir with equivalent capacity based on the
following:
a) To preserve the environment by reducing green area required to
make way for the construction of reservoirs and associated
pipeline. By doing so, it will reduce the erosion and suspended
solid carry over to the sea directly, and indirectly it will reduce the
possible damage to the coral reef which is sensitive to suspended
solid;
b) Speed up the construction process;
c) Reduce the construction waste; and
d) Reduce the movement of the construction material barge within
Marine Park.

Figure 6: 1.82ML reservoir at Pulau Perhentian Kecil.

iii) Pulau Perhentian project which is under design and built concept has
kept the Grade 25 concrete foundation for elevated reservoir against the
original design of Grade 35 when there was mistake made by the
Contractor. The foundation of Bukit Bubus elevated reservoir was
designed to Grade 35 concrete, however, sample taken during
concreting and core samples taken at the foundation for compressive
tests were found to be Grade 25. In this case, the S.O. could ask the
Contractor to demolish the concrete foundation; however, the S.O. has
requested the Consultant to carry out reverse analysis on the foundation
structural capability to withstand the load by using Grade 25 concrete.
Page 12/32
ENGLISH VERSION

Upon confirmation by the Consultant that the Grade 25 foundation is


able to withstand the load with some remedial measures, the S.O. has
agreed to keep the Grade 25 foundation (with additional cost for
remedial measures to be borne by the Contractor) based on the
following:

a) Natural resources is not unnecessary wasted;


b) The schedule of supplying water to Pulau Perhentian by the
Government is not disrupted; and
c) Did not cause unnecessary financial burden to the Contractor. It
will cause a huge financial losses for the Contractor if the
foundation were to be demolished, and as the consequences, the
project completion date will be delayed.

Figure 7: 0.75ML Bukit Bubus elevated tank.

4.5.2 Phase 2 Beaufort WTP Project

i) Decision on omission of part of works from original works and be


implemented under new Contract. The Contractor informed that they are
not capable to lay the submarine pipeline after encountered few failures
and compounded by subsequent instruction from the S.O. to use bigger
capacity lay barge to lay the submarine pipe. Steps taken are as follows:

a) Decision to omit the works from original scope of works.

Page 13/32
ENGLISH VERSION

Available options are:


• Option 1:
Only laying of submarine pipeline is taken out, the original
Contractor to continue with the pipe laying works at shore,
swamp and muddy plane (mud flat); or
• Option 2:
To terminate the whole original Contract and re-tender the
remaining work.
b) Decision to Opt for Option 1
Option 1 was adopted based on:
• Lower cost compared to Option 2 (about RM20million
cheaper);
• Shorter completion period because the original Contractor is
allowed to continue to complete the remaining works while
new tender exercise for submarine pipe laying works been
carried out;
• The urgency to complete the submarine pipeline before the
impending monsoon season (Oct 2010 – Feb 2011). Should
this window is missed, the next suitable period for laying the
submarine pipeline would be March to September 2011,
which will cause about 12 months delay;
• Water crisis at Labuan has reached the critical point; and
• Contractor has the capability to complete the remaining
works.
c) Omission of part of the works and re-tender of the submarine
pipeline has obtained approval from the Ministry of Finance.
d) Re-tender exercise for submarine pipeline was carried out via open
tender.

As the result, the submarine pipeline was completed one (1) month
ahead of new Contract schedule and six (6) months before the
completion of original Contract.

Page 14/32
ENGLISH VERSION

Figure 8: Pipe buckling.

ii) Due to omission of the works from the Contractor, decision shall be
made whether to apply clause 5b of the Conditions of Contract on the
Contractor (Non compliance with the S.O.’s instruction). The Contractor
has failed to comply with the S.O.’s instruction to continue the submarine

Page 15/32
ENGLISH VERSION

pipe laying works with suitable lay barge size to fulfill the requirement of
pipe laying.

Steps taken are:


a) Decision whether to apply Clause 5b of the Conditions of Contract
on the original Contractor.
Options available are:
• Option 1:
Apply Clause 5b on the premise that the Government
required other Contractor services to carry out the works and
all cost related with the works shall be claimed by the
Government from the original Contractor; or
• Option 2:
By Supplemental Agreement, where the Government agrees
not to make any claim in whatever form, against the
Contractor on the decision by the Government to omit the
submarine pipeline works, and vice-versa.
b) Decision to Opt for Option 2
Option 2 has been chosen based on:
• Complication may arise if Clause 5b (Option 1) is applied due
to the date the instruction was issued to the Contractor and
the Contractor may initiate the claim on the losses upon
decision to omit the submarine pipeline from the original
Contract. As a consequences, it would involve the arbitration
which is a time consuming process;
• The original Contractor was cooperative in solving other
issues related to other components of the works under main
Contract which include:
 Assistance render in solving the local issues such as
land acquisition for pipe laying in Sabah (onshore)
which took very long time; and
 Rescue the submarine pipeline which had been laid
with their own cost to be reused at muddy plane, by
doing so, it ensures the remaining submarine pipes are
reserved for new Contract (to be carried out by others)
Page 16/32
ENGLISH VERSION

and the needs for supplying new submarine pipes to be


kept at minimum (cost saving in the new Contract).
• The original Contractor has incurred huge financial losses as
the result of failure to continue the laying of submarine
pipelines. Any intention to fine the Contractor will cause a
very severe financial impact on the capacity of the Contractor
to continue the remaining work in the Contract. As the
consequences, it will cause further delay to the completion of
the project.

iii) Decision to allow the Contractor to proceed with onshore pipeline laying
works using push and pull method instead of conventional trench and lay
method in Sabah Land area. Due to delay in solving land matter in
Sabah Land compound, the Contractor is forced to lay the pipeline
during monsoon season.

Steps taken are:

a) Carried out assessment on the site condition and confirmed that


conventional pipe laying method is not suitable during monsoon
season due to continuous high ground water table;
b) Assessment on time and cost impacts;
c) To wait for drought season, however, it is expected that it will
cause further delay by six (6) months minimum. This scenario is
not acceptable in view of Labuan was facing acute water crisis; and
d) Additional cost of RM0.9million or 5% more than project cost
(RM18 million) for pipe laying works at Sabah Land.

The outcome of the decision is on time project completion.

Page 17/32
ENGLISH VERSION

Figure 9: Shore pulls arrangement at Labuan shore.

Figure 10: Pipe been pulled from Labuan shoreline by using wire rope.

Figure 11: Laybarge “STEALTH” for laying submarine pipes.

Page 18/32
ENGLISH VERSION

Figure 12: Pipe lowered down to seabed assisted by air bags.

Figure 13: Tie-in of pipes laid by laybarge and laybarge shore pull method near Labuan shore.

Figure 14: Float - push & pull – sink method.

Page 19/32
ENGLISH VERSION

Figure 15: Pipe laying with high water table and soft ground.

Figure 16: Difficulties encountered during laying.

iv) Decision to appeal for open cut instead of pipe jacking [three (3)
locations] for crossing JKR road. Due to high ground water table,
construction of pipe jacking and receiving pits is very difficult.

Steps taken are:


a) Contractor had tried to install 10 vertical pumps to lower down the
ground water table at jacking pit but was not successful (pumping
had caused minor settlement at adjacent lot);
b) Keep appealing to JKR with facts and proof that it is very difficult
and impossible to lay the pipe by pipe jacking method
notwithstanding the objection by JKR;

Page 20/32
ENGLISH VERSION

c) Finally JKR approved to give exemption for laying pipe by pipe


jacking method at two (2) locations ; and
d) There was a saving of RM200,000 by changing the pipe laying
method.

The outcome is on time completion of the project as scheduled and open


cut crossing JKR road been resurfaced to JKR satisfaction.

v) The S.O. had made decision to stop the operation of the pump to
facilitate investigation and to avoid further damage to the other pumps
despite the scheduled arrival of the Prime Minister on the next day.

Figure 17: Failure at flange adapter.

Figure 18: Failure at tie rod.


Page 21/32
ENGLISH VERSION

4.5.3 Construction of Off-River Storage (ORS) Project

This is an innovation project using storm water as source of raw water. The
study of this project have been completed in the period of less than two (2) months,
and the outcome is a project capable of producing raw water of 9million cubic metre
equivalent to 90 days of raw water from a new water source. Ammonia content of 4-
5mg/ℓ at the extraction point has been reduced to less than 1mg/ℓ via biological and
physical processes.

Figure 19: View of ORS.

Figure 20: View of main dam and spillway of ORS.

Page 22/32
ENGLISH VERSION

Steps taken by the S.O.:

i) Close monitoring on the S.O’s instructions and variation of quantities in


the Bills of Quantities managed to reduce the Project cost.
ii) Decision to lay diversion channel at intake reduced the ammonia effect
during dry weather flow.

Drain Diversion at JPS


inlet.

Figure 21: Inlet for JPS drain diversion.

Figure 22: Gate at JPS drain diversion.

Page 23/32
ENGLISH VERSION

Drain
Diversion at
JPS outlet.

Figure 23: Outlet for JPS drain diversion

4.5.4 Jalan Universiti Project

Measures taken by the S.O.:

i) Cost saving of RM8 million by open cut method in the middle of the road
for pipe laying.
ii) Application of hot tapping and line stopping methods reduced the water
interruption to 500,000 consumers.

Figure 24: Installed line stopping machine at Jalan 17/1.


Page 24/32
ENGLISH VERSION

Figure 25: Arrangement of stopper in line stopping machine.

Page 25/32
ENGLISH VERSION

Figure 26: Line stopping machine installed at the existing pipe.

Figure 27: Hot tapping machine 1000mm and 1500mm dia. installed on the
1000mm dia. gate valve of the existing pipe.
Page 26/32
ENGLISH VERSION

4.5.5 Expansion of Mengkuang Dam Project

Measures taken by the S.O.:

i) Cost saving by changing the design from linear spillway to labyrinth type,
it also increase the safety level of the dam. Labyrinth type of spillway
does not require very wide surface area for the same flow;

Figure 28: Labyrinth spillway and outlet structures.

ii) Higher embankment is not required by adopting labyrinth spillway to get


the same storage volume and flow;
iii) Project cost saving with crushed stone instead of sand;
iv) Water interruption been prevented by transferring water from existing
dam;

Page 27/32
ENGLISH VERSION

Stage 1:
1.1 Construct Draw-off Work No.2
1.2 Construct Upstream Cofferdam 1
1.3 Divert streamflow through Draw-off Works No.2
1.4 Construct Upstream Cofferdam 2, Downstream
Cofferdam and Detention Pond

Stage 2:
2.1 Construct new dam at left valley
2.2 Construct Draw-off Tower No.2
2.3 Construct Valve House 2
2.4 Construct perimeter road in left reservoir
2.5 Complete slope protection works and rehabilitation
of borrow areas

Stage 3:
3.1 Functionality test of Draw-off Work No.2
3.2 Remove Upstream Cofferdam 1 & 2 and Downstream
Cofferdam

Page 28/32
ENGLISH VERSION

Stage 4:
4.1 Siphon and pump water from existing reservoir to fill
new reservoir at left valley
4.2 Commission supply of water (to Sg Dua WTP) using
Draw-off Tower No.2

Stage 5:
5.1 Construct river diversion works at existing reservoir
5.2 Heighten existing dam
5.3 Demolish existing draw-off tower
5.4 Construct Draw-off TowerNo.1
5.5 Strengthen and extend existing Draw-off Culvert
5.6 Construct Valve House 1, spillway & saddle dams

Stage 6:
6.1 Siphon water from new reservoir at left valley to existing
reservoir to EL 34m.
6.2 Construct balancing channel at existing saddle dam
6.3 Commence impounding

Figure 29: Stages of dam construction.

Page 29/32
ENGLISH VERSION

v) Proposal not to close existing dam resulted in less public complaints and
it could continue be used for recreation purpose; and

Figure 30: Partial handing over of site.

vi) The S.O. understood fully on the quantities built-up and well verse with
the approaches taken by the Contractor, i.e. Contractor from China, thus
is well prepared for the price negotiation.

5.0 Major Clauses Related to the S.O. in the Conditions of Contract

The relevant clauses related to the S.O. in the Conditions of Contract are as
follows:

i) Clause 24 – Variations;
ii) Clause 25 – Valuation of Variations;
iii) Clause 28 – Payment to Contractor and Interim Payment;
iv) Clause 31 – Final Account and Payment Certificate;
v) Clause 39 – Completion of Works;
vi) Clause 40 – Damages for Non-Completion;
vii) Clause 43 – Delay and Extension of Times;
viii) Etc.

Page 30/32
ENGLISH VERSION

6.0 Conclusion

The S.O. shall understand his roles and responsibilities in supervising the
project so that he could discharge his duties effectively and ensure the project is
implemented smoothly.

Any decision and action by the S.O. will have the effect of project cost saving,
completion within the stipulated time, prevention of projects with sick status,
irregularities in decision making and disputes with the Contractors and Consultants
could be avoided and the project could be implemented in accordance with the
schedule.

Human capital development is not limited to develop a S.O. or official with


knowledge, experience and high expertise who is capable to discharge his duties
well and diligently but also possess the high moral values or norms which include
integrity.

Projects Completed Not by Chance or Accident BUT by Design

Page 31/32
ENGLISH VERSION

Reference:

1. Hasnul Mohamad Salleh, Ir. Dr., Ang Eng Kiat, Ir. and Wong Mun Tin, Ir..
Labuan Phase 2 Water Supply Project, http://www.jba.gov.my, 2011.

2. Hasnul Mohamad Salleh, Ir. Dr., Teo Koon Haw, Ir. and Zulkiflee Abdul Hamid
Ir.. Alternative Water Supply Scheme for KLIA, http://www.jba.gov.my, 2011.

3. Hasnul Mohamad Salleh, Ir. Dr., Angkasa Consulting Sevices Sdn Bhd (ACS)
and JBA Project Team. Expansion of Mengkuang Dam,
http://www.jba.gov.my, 2011.

4. Hasnul Mohamad Salleh, Ir. Dr. and Lim Soon Guan, Ir.. Construction of
Kinabenua Hybrid Water Treatment Plant, Pulau Labuan, 2011.

5. Hasnul Mohamad Salleh, Ir. Dr.. 1Malaysia - Concept and Values,


http://www.jba.gov.my, 2010.

6. Hasnul Mohamad Salleh, Ir. Dr.. Action Plan To Improve JBA Service
Delivery, http://www.jba.gov.my, 2010.

7. Hasnul Mohamad Salleh, Ir. Dr.. Approaches to Measuring Performance in


Water Services, http://www.jba.gov.my, 2010.

8. Hasnul Mohamad Salleh, Ir. Dr. and Lim Soon Guan, Ir.. Application of Green
Technology in Pulau Perhentian Water Supply Scheme,
http://www.jba.gov.my, 2009.

For further information on this paper and permission to use material contained in this
paper, request could be made via http://www.jba.gov.my. ALL COPY RIGHT IS
PROTECTED. Content of this paper protected under copy right shall not be reprinted
or used in whatsoever form without written consent from the authors.

Page 32/32

You might also like