You are on page 1of 154

ELECTRICITY OF VIETNAM

SOUTHERN POWER CORPORATION

SCADA SYSTEM AND 110KV SUBSTATIONS


WITHOUT OPERATORS

Feasibility Study

June 2012
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 2/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

EDF/CIST
Project Director Deputy Project Director
SCADA/ Telecontrol Expert Telecommunication Expert

Pierre-Jacques Le Quellec Jacques Le Minor

ERDF EDF/CIST

SCADA Expert Adaptation Work Expert

Olivier Carré Christophe Gauthier


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 3/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Contents
1 Executive summary 6

2 Main outlines of the Project 7

3 Scope of Feasibility Study 7

4 Data collected (summary of the inception report) 8

5 Organisation around unmanned substations 9


5.1 Security 9
5.1.1 People security 9
5.1.2 SPC teams security 11
5.2 Visit for Operating Tasks 11
5.3 Visit for Maintenance Tasks (periodic visit) 12
5.3.1 Short visits 12
5.3.2 Long visits 12
5.4 Periodicity 12
6 Substations Works and Telecontrol 12
6.1 Teleinformation Plan 13
6.1.1 110kV bays 15
6.1.2 22/35kV bays 17
Low Voltage 20
6.1.3 Reclosers (880) 20
6.2 Adaptation Works 21
6.2.1 Table 1 (Mini SCADA Project not considered) 22
6.2.2 Table 2 (SPC Mini-SCADA Project considered) 23
6.3 Telecontrol 23
6.3.1 Table 1 (SPC Mini-SCADA Project not considered) 24
6.3.2 Table 2 (SPC Mini-SCADA Project considered) 25
6.4 Telecommunication links between SS and Provinces 25
6.4.1 Telecommunication Network between substations, HVGB and PLDCs 26
6.4.2 Telecommunication Network equipment 28
6.4.3 Telecommunication Network between 26 substations and A2 Critical Substations 30
7 SCADA system implementation Alternatives 32
7.1 Analysis of SPC context and objectives 33
7.1.1 Analysis of SPC and A2 operating context 34
7.1.2 The organisational factor and its impact on SCADA Architectures 37
7.2 Analysis of the suitability of SPC headquarters premises 44
7.3 Telecontrol Protocols 45
7.3.1 IEC60870-5-101 45
7.3.2 IEC60870-5-104 46
7.3.3 IEC60870-6-503 alias TASE.2 46
7.4 Description of the various feasible alternatives for the SCADA architecture 47
7.4.1 One SCADA system per Province (SCADA Architecture 1) 47
7.4.2 One SCADA system in some strategic Provinces (SCADA Architecture 2) 52
7.4.3 One remote console connected to the main System within each Province (SCADA
Architecture 3) 57
7.4.4 Economical consideration for the SCADA systems 61
7.4.5 One and only one SCADA system within SPC head offices (SCADA Architecture 4) 62
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 4/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.4.6 Backup system in another location 64


7.4.7 Global comparison of the SCADA architectures 65
7.4.8 DMS functions implementation 67
8 Telecommunications 68
8.1 Telecommunication Network between PLDCs and SPC Head Office 68
8.1.1 Network based on leased links 69
8.1.2 SPC SDH Network 69
8.1.3 Return of investment calculation for SCADA Telecommunication Network only 75
8.1.4 Return of investment calculation for Operational and Corporate Telecommunications
Networks 76
8.2 Telecommunication Options 77
8.2.1 Operational Telephone Network: 77
8.2.2 Video Monitoring System 78
8.2.3 Tele-metering 78
8.2.4 Electricity Quality Monitoring 78
8.2.5 Technical solutions: 78
8.2.6 Options comparison 85
8.2.7 Return of investment comparison for a SDH Telecommunications Network with
multiplexors and a TCP/IP Telecommunications Network 85
8.2.8 New Substations Connection to A2 through SDH Network 86
9 Training 88
9.1 Principles 88
9.1.1 Staff requirements 88
9.1.2 Operating training 88
9.1.3 Maintenance training 88
9.2 Maintenance training 88
9.2.1 General 88
9.2.2 Contents of the courses 90
9.2.3 Specific telecommunication and telecontrol training 90
9.3 Operation training 91
9.3.1 General 91
9.3.2 Contents of the courses 91

10 Summary COST – ESTIMATES 93


10.1 Adaptations works and Telecontrol 93
10.2 SCADA 93
10.2.1 Artchitecture 1 (One SCADA system per Province) 93
10.2.2 Architecture 2 (One SCADA system in some strategic Provinces) 94
10.2.3 Architecture 3 (One remote console connected to main System within each Province) 94
10.2.4 Architecture 4 (One and only one SCADA system within SPC head offices) 95
10.3 Telecommunication with A2 connection by Optical Fiber 96
10.4 Telecommunication with A2 connection by SDH – TCP/IP Network 99
10.5 Training 101
11 Economic and Financial Analysis 102
11.1 Expected Benefits 102
11.1.1 Staff reduction 103
11.1.2 Improved Operator Training 104
11.1.3 Maintenance 104
11.1.4 Outages 105
11.1.5 Technical losses 105
11.1.6 Unserved Energy 105
11.1.7 Better Information Management 105
11.1.8 Organization improvement 106
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 5/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

11.2 Basis of the analysis 106


11.2.1 Telecontrol System Technical choices 106
11.2.2 Calculation data 107
11.2.3 Calculation of the payback period 110
11.2.4 Calculation of the Net Present Value (NPV) 110
11.2.5 Calculation of the Internal Rate of Return (IRR) 110
11.2.6 The Financial Net Present Value (FNPV) 110
11.2.7 The Economic Net Present Value (ENPV) 110
11.2.8 Calculation of the benefit/cost Ratio 111
11.3 Economic and financial study with control of MV devices 111
11.4 Economic and financial study without control of MV devices 119
12 Implementation schedule of the project 126

13 Consortium Recommendations 127


13.1 Technically 127
13.1.1 Substations adaptation 127
13.1.2 Telecommunication 127
13.1.3 SCADA architecture 128
13.1.4 MV Devices Control 128
13.1.5 Organizational 129
14 Glossary 130

ANNEXES 131

Annexe A: Sizing 131

Annexe B: Scope of RTU installation 141

Annexe C: AW and TCD Cost per substation (total) 145

Annexe D: TOTAL INVTSTMENT 151


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 6/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

1 Executive summary
The objective of a feasibility study is to compare different alternatives from technical
but also economic points of view in order to determine the best solution for a project.
Therefore, this report studies accurately the different alternatives, which have already
been suggested in the inception report.
The first part of the present report describes the teleinformation plan which lists all
the information that will be exchanged between substations and control centres. This
is from the teleinformation plan that the telecommunication network and the SCADA
system are built and the costs of RTUs and associated Adaptation Works are
estimated. This is why it is recommended to optimize the list of teleinformations in
order to facilitate the operation of the system by operators and to reduce the number
of I/O cards and associated adaptation works.
Three alternatives have been scrutinised in the study. The first one does not consider
the A2 project (installation of RTU in 80% of primary substations) requiring the
upgrading of all Primary substations for both HV and MV levels. The second one
takes into account the so-called A2 project and the last one considers the SPC mini
SCADA Project.
The second part of the report studies four architectures already presented in the
inception report:
 Architecture no 1: “One SCADA system per Province”
 Architecture no 2: “One SCADA system in some strategic Provinces”
 Architecture no 3: “One remote console connected to the main System within
each Province”
 Architecture no 4: “One and only one SCADA system within SPC head offices”
The Architecture no 3, “One remote console connected to the main System within
each Province”, turns out to meet SPC needs and has the advantage to present the
lowest cost and the most flexible solution in terms of adaptation capability. All types
of control organisation (i.e. centralised, decentralised or mixed) can easily be
implemented with the Architecture 3 ensuring its sustainability for SPC.
From the Consortium point of view, the most efficient organisation should be to
centralise one operating team (24/24) within SPC head offices in order to monitor
and operate the MV network and 110kV substation from this only one site.
Regarding the telecommunication point of view, the best way seems to use an optical
fiber network in order to implement an SDH network with a TCP/IP technology and to
use it for both telecontrol and corporate needs. This telecommunication network will
also allow implementing video surveillance, telemetering, telephone systems over IP
and future applications based on the TCP/IP protocol.
Finally, the third architecture has been chosen to carry out the economic and
financial study. Nevertheless, two cases have been studied: the first one assumes
that the control of MV devices (reclosers) will be in charge of Control Centres but not
in the second case. Eventually the solution including the MV devices control is the
alternative recommended by the Consortium taking technical and also economical
and financial aspects into consideration.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 7/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

2 Main outlines of the Project


As a subsidiary of Vietnam Electricity (EVN), Southern Power Company (SPC) has
been doing business in 21 Southern provinces, excluding Ho Chi Minh City. Its major
function is distribution and sales of electricity up to 110 kV to its customers. In
addition, SPC has diversified other activities such as power generation (small-hydro
and diesel), power design/consulting, testing, import and export of electrical materials
and equipment.
In order to meet the demand for electricity to its customers SPC needs to enhance
reliability, security, stability and power quality of the power system of which SPC is in
charge of. Therefore, SPC decided to implement a SCADA system.
SPC contracted with EDF-ERDF consortium to provide consultancy services for the
above mentioned project which initially consisted carrying out a feasibility study, a
conceptual design and drafting the EPC Tender Documents, following up the
contractor’s project implementation and preparing a training plan for SPC’s staff.
The present feasibility study document follows the first stage of the consultancy
services, i.e. data collection and sites survey. First, it summarises the Inception
Report, and gives the major principles of telecontrol from the operating point of view.
Then, it depicts the common aspects of the various SCADA architectures alternatives
(i.e. adaptation works) before scrutinizing each of them in details. The training plan
follows this analyse, precedes the global analysis (including cost estimate) and the
financial and economic analysis and finally the Consortium advice.
Note: Most of acronyms are listed in a glossary at the end of this document (ref.
chapter 14 - Glossary).

3 Scope of Feasibility Study


Pursuant to Terms of References (TOR), the objectives of this feasibility study are:
(1) To prepare a feasibility study report on the SCADA system and 110kV
unmanned substations for the entire SPC’s 110kV network. This report will
include specific contents as the needs and objectives to invest the project;
a technical analysis to select the best solutions to the model,
configurations, technology, and communication links for SPC’s SCADA
system; a total cost estimate; an economic and financial analysis; an
implementation plan, etc.
(2) To prepare a training plan to build SPC’s personnel knowledge and
capability to design, install, manage, operate, and maintain the SCADA
system and 110 kV substations of SPC, including training budget and
timetable.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 8/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

4 Data collected (summary of the inception report)


The data collection has been conducted in 2 phases, a survey mission of 12 days in
the region under SPC responsibility and a phase of assessment of collected data
with a very first view of possible architectures of the future telecontrol network and a
first cost estimate. The following domains were covered: adaptation works, RTU,
telecommunications, SCADA and operating organisation.
Regarding substation (ref. Inception report - chapter 3.3) all visits done by the
Consortium has shown that the different components were well maintained and in
good working conditions. Around 30% of substations were equipped with RTU (ref.
Inception report - chapter 3.4), which, for most of them, concern 110kV bays. So,
they could be already used after I/O cards upgrading and relevant adaptation works
to take into account 22kV feeder bays.
Regarding telecommunication (ref. Inception report - chapter 3.5), two levels have to
be considered: substation and Province Load Dispatch Centre. Both of them are
based on radio, CDMA or Public phone. But as not any transmission link is installed
because not any RTU has to communicate with a SPC SCADA at the present stage,
the operational network cannot be considered as useable as it is and shall be
adapted and enhanced to do so.
So, these telecommunication network link different staffs working in different SPC
sites, from head office to substations. Normally, they also link substation RTU with
SCADA (ref. Inception report - chapter 3.6) within Control Centres. At present, it is
estimated that not any present SCADA systems could be reused for the present
project.
Dealing with SPC SCADA system leads “de facto” to get onto operating organisation
(ref. Inception report - chapter 3.7). This organisation is based on hierarchical
principles:
 On the 110kV network side, A2 supervises and operates the network whereas
SPC performs manoeuvres on request, in the non-remote controlled
substations, and thus, even if SPC is the owner of the 110kV networks.
 On the 22kV networks side, SPC supervises, operates and control from a
centralised entity (PLDC) with the help of the operators in the primary
substations. However this organisation without any SCADA system leads SPC
to operate the 22kV network uneasily and few efficiently.
A very rough financial estimation is also done and a particular focus is done
regarding different SCADA architectures.
Concerning Adaptation works and RTU (ref. Inception report - chapter 4.1), the
Scope does not change and leads that all 110kV bays and all 22kV feeders should
be connected to future RTU.
From a telecommunication point of view (ref. Inception report - chapter 4.2), the using
of an optical fibre network seems to be the most efficient way.
Regarding the SCADA four architectures (ref. Inception report - chapter 4.4.2) are
suggested with rough cost estimation.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 9/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Whatever the SCADA architecture, the operation or maintenance organisation (ref.


Inception report - chapter 4.5) has to be considered to take into account the future
new operating means and to take advantage of this new environment. For instance
teams dedicated for real time operation, Post-operation analysis and operational
planning shall be created. It will be also the case for maintenance of
telecommunication, telecontrol, and computer for hardware as well as for Software or
Databases.
At last, just before to suggest a new work plan, the Consortium concluded (ref.
Inception report - chapter 5) that the A2 project is a real opportunity and suggests a
very strong cooperation between SPC and A2 in order to make the most of this
opportunity.

5 Organisation around unmanned substations


The very first consequence when a substation becomes “unmanned” is, that not any
person does stay inside during the day and the night. This obviousness leads that all
of daily tasks usually performed by substation operators have to be analysed in order
to define:
 How to execute it.
 At what time to execute it.
 What is the periodicity to execute it.
This analysis should allow distinguishing what has to be included in periodic visit and
what is linked with operating. Then, a specific document could be written in order to
describe all tasks to be performed during periodic visits. But, in any case, the very
first point on which it is important to work is security.

5.1 Security
As owner of unmanned substation, the Utility has the security responsibility around
this kind of substation.

5.1.1 People security


First of all the Utility has to ensure that not any person has to be able to come into
the substation. To do it, it is compulsory to check for each substation: doors, walls
and every possible access. All detected weakness shall lead the right adaptation
(reinforce a door, raise a wall…).
- In the same idea, a fire detection system (ref. - - Primary active power,
Primary reactive power,
Primary Current
Secondary active power,
Secondary reactive power,
Secondary Current,
Oil Temperature,
Winding Temperature,
Tap position (with D/A converter)
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 10/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

General purpose bay) could be installed as person detection and video monitoring
system (ref. 8.2.2 -
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 11/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Video.

5.1.2 SPC teams security


It is assumed that all manager, engineer or technician going inside a substation shall
follow a minimum of security training. Moreover, no one can go inside a substation if
he is not empowered to do it. That means that a person having to come into a
substation shall have an official permit (an official document) describing his ability
and his mission.
Then the principle, for each authorised person coming into or going out such a
substation, is to inform the Control Centre in charge of the substation concerned. At
least, the procedure should be:
1. To call the operator to indicate the permit number, to describe shortly the job
and how long it will be.
2. To carry out the job.
3. To call back the Control Centre in order to inform the job is done.
The reason of this procedure is due to the fact that to monitor a substation the
operator has only the alarms list. When he notices an alarm such as “substation door
opened” he has to know if it is normal or not. During the intervention, he has to be
aware that a person is inside the substation. And when it is finished he has to know
the situation is normal again.

5.2 Visit for Operating Tasks


Several operating reasons can lead a visit of a substation. Hereafter some examples
for such a visit:
 HV and MV devices may be not motorised (e.g. earthing switch).
Consequently, it is necessary that a technician come into the substation to
manually operate such a device.
 In case of CB trip, it is necessary that a person comes into a substation in
order:
o To notice some possible damage
o To download protection relay records
o To begin the analysis of the fault…
 A substation and generally speaking a grid is living. That means substations
change (bay addition, transformer changing…) consequently databases into
RTU have to be changed to take into account these modifications.
 In case of transmission problems between RTU and SCADA, it is often useful
that a person comes into the substation to analyse, with a protocol analyser,
exchanges between both equipments.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 12/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

5.3 Visit for Maintenance Tasks (periodic visit)


As said above, a specific document should be written to describe what is a periodic
visit. The main reason is simply to check security and the good “health” of the
substation. First, let us consider two types of visits: short and long.

5.3.1 Short visits


During short visits, it is not necessary that the technician come into the substation.
This visit can be called “security visit” and allows checking the perimeter of the
substation (state of walls, closed doors…).

5.3.2 Long visits


During long visits everything in the substation has to check:
 On the switchgear:
o HV Transformer, CT, VT, CB, Isolator…
o Cabinets, cables, poles…
o Reading of circuit breakers
o All places where snake, rats, mice, birds… like to build their house
o Cables for mice (mice love cables)
 Into the building
o Cubicles, cables, telecommunication and telecontrol equipments, battery,
light, paper for printer…

5.4 Periodicity
To conclude this chapter, it is important to note that only the analysis mentioned
above (ref. chapter 5 - Organisation around unmanned substations) will allow
determining which periodicity is the best for short and long visit.

6 Substations Works and Telecontrol


This chapter gives teleinformation plan, adaptation works, telecontrol and
telecommunication details, which are common whatever the final architecture choice.
The principle of its organisation is to describe which information have to be
transmitted (teleinformation plan), what kind of adaptation works that leads, which
type of standards should be used for the communication between Substations and
Control Centres but also within substations and finally which telecommunication have
to considered to communicate with substations.
The ultimate aim is to evaluate the cost.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 13/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.1 Teleinformation Plan


Two kinds of data lists are considered in this chapter: 110kV and 22/35kV. The
110kV one was elaborated from A2 documents (ref. Attachment_2 -
MinimumStandardDatalist.xls). The 22/35kV one was elaborated from the previous
SPC SCADA Project and also from the A2 data list.
From the IEC (International Electrical Commission) “bay consists of closely
connected sub parts with some common functionality”. The following data list applies
this principle. For instance, an Over Head Line bay (line feeder) gathers the circuit
breaker, busbar isolators, the earthing isolator and associated alarms. The following
scheme shows which is applied in this document.

Shunt
Over Head Line
Compensator

Transformer Busbar
Coupling Feeder

Section

Telecommunication

Transformer

General
Shunt
Compensator

Busbar

Transformer
Tie
Feeder

Figure 1 - Bay list


Thus this chapter describes, for each voltage level – 110kV or 22/35kV - and for
every type of bays, the complete data list. Afterwards transformer bay, general
purpose bay and telecommunication bay, which are common for a substation
whatever the voltage level, are described. The consecutive data quantities per
substations are given in annexe (ref. Annexe A: Sizing).
To design the following data lists, following options were considered:
1. All HV and MV devices are or will be equipped to be telecontroled.
2. Tap changers are considered as a part of the transformer bay.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 14/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

3. All transformer measurements (primary or secondary) are a part of the


transformer bay.
4. There is not any Series Compensator.
5. There is not any generator to telecontrol.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 15/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.1.1 110kV bays


Overhead line (ohl) consisting of:
- 4 DS circuit breaker,
busbar isolator,
line isolator,
Earthing Switch,
- 24 SS CB remote/local,
Busbar Isolator remote/local,
Line Isolator remote/local,
Earthing Switch remote/local,
CB Not Ready,
CB Alarm (SF6 low pressure),
OverVoltage,
UnderVoltage Protection,
Distance Protection Zone 1,
Distance Protection Zone 2,
Distance Protection Zone 3
Distance Protection Zone 4
Line Differential Protection,
Line directional Overcurrent 67/67N,
Overcurrent instantaneous 50/50N,
Overcurrent time delay 51/51N,
InterTrip Sent,
InterTrip Received,
Autoreclose order,
Equipment Overload Protection >Trip,
Equipment Overload Protection >Alarm,
Equipment Trip,
Breaker Failure protection 50BF,
Circuit supervision relay.

- 4 DC circuit breaker,
busbar isolator,
line isolator,
Earthing Switch,
- 4M active power,
reactive power,
Voltage,
Current.

Shunt Compensator (reactor or capacitor) consisting of:


- 3 DS circuit breaker,
busbar isolator,
Earthing Switch,
- 9 SS Equipment Fault,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 16/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

InterTrip Sent,
Equipment Overload Protection Trip,
Equipment (Voltage) Unbalance Protection (capacitor),
Equipment Differential Protection,
Equipment OverCurrent Protection,
Equipment Restricted Earth Fault Protection,
Winding Temperature Alarm (reactor),
Equipment Trip,
- 2 DC circuit breaker,
busbar isolator,
- 1M Reactive power,

Series Compensator (reactor or capacitor) consisting of:


- 7 SS Equipment Fault,
Breaker Failure Protection,
InterTrip Sent,
Equipment Overload Protection Trip,
Equipment (Voltage) Unbalance Protection (capacitor),
Equipment OverCurrent Protection,
Equipment Trip,

Transformers feeder consisting of:


- 3 DS circuit breaker,
busbar isolator,
Earthing Switch,
- 5 SS CB remote/local
Busbar Isolator remote/local,
CB Not Ready,
CB Alarm (SF6 low pressure),
Busbar Isolator Not Ready,
- 2 DC circuit breaker,
busbar isolator,
TIE consisting of:
- 3 DS circuit breaker,
2 busbar isolators,
Earthing Switch,

- 7 SS CB remote/local
2 Busbar Isolators remote/local,
CB Not Ready,
CB Alarm (SF6 low pressure),
2 Busbar Isolators Not Ready,
- 3 DC circuit breaker,
2 busbar isolators,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 17/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

- 2M active power,
reactive power,
Busbar section consisting of:
- 2 DS busbar isolator,
Earthing Switch,
- 2 SS Busbar Isolator remote/local,
Busbar Isolator Not Ready,
- 1 DC busbar isolator,
Control busbar Consisting of:
- 3 DS circuit breaker,
busbar isolator,
Earthing Switch,
- 5 SS Busbar Protection – Main,
Busbar Protection – Back Up,
Breaker Failure Protection,
OverVoltage Protection,
Undervoltage Protection,
- 2M busbar voltage,
busbar frequency.

6.1.2 22/35kV bays


Overhead line (ohl) consisting of:
- 5 DS 1 circuit breaker,
local/remote switch,
busbar isolator,
line isolator,
Earthing Switch
- 7 SS OverCurrent,
Earth fault,
load shedding trip,
trip circuit alarm,
Auto reclosing in progress (when existing),
Auto reclosing Enabling/Disabling,
Breaker Failure Protection,
- 1 DC 1 circuit breaker,
- 2M current,
CosPhi

Shunt Compensator (reactor or capacitor) consisting of:


- 3 DS circuit breaker,
busbar isolator,
Earthing Switch
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 18/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

- 9 SS Equipment Fault,
InterTrip Sent,
Equipment OverLoad Protection Trip,
Equipment (Voltage) Unbalance Protection (capacitor),
Equipment Differential Protection,
Equipment OverCurrent Protection,
Equipment Restricted Earth Fault Protection,
Winding Temperature Alarm (reactor),
Equipment Trip,
- 2 DC circuit breaker,
busbar isolator,
- 1M Reactive power,

Transformers feeder consisting of:


- 3 DS circuit breaker,
busbar isolator,
Earthing Switch
- 4 SS CB remote/local
Busbar Isolator remote/local,
CB Not Ready,
Busbar Isolator Not Ready,
- 2 DC circuit breaker,
busbar isolator,
TIE consisting of:
- 4 DS circuit breaker,
2 busbar isolators,
Earthing Switch
- 6 SS CB remote/local
2 Busbar Isolators remote/local,
CB Not Ready,
2 Busbar Isolators Not Ready,
- 3 DC circuit breaker,
2 busbar isolators,
- 2M active power,
reactive power,
Busbar section consisting of:
- 2 DS busbar isolator,
Earthing Switch
- 2 SS Busbar Isolator remote/local,
Busbar Isolator Not Ready,
- 1 DC busbar isolator,
Control busbar Consisting of:
- 3 DS circuit breaker,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 19/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

busbar isolator,
Earthing Switch,
- 4 SS Busbar Protection – Main,
Breaker Failure Protection,
OverVoltage Protection,
Undervoltage Protection,
- 3M busbar voltage,
CosPhi,
busbar frequency.

Transformer general bay


- 22 SS Equipment OverLoad Protection Trip,
Equipment OverLoad Protection Alarm,
Equipment (Voltage) Unbalance Protection,
Equipment Differential Protection,
Equipment OverCurrent Protection,
Equipment Restricted Earth Fault Protection,
Buccholtz Alarm,
Winding Temperature Trip,
Winding Temperature Alarm,
Oil Temperature Trip,
Oil Temperature Alarm,
Oil Flow Transformer Trip,
Oil level Min
Pressure Relief Relay,
Equipment Trip,
Pressure Relief Relay (Tap Changer),
Tap Changer remote/local,
Tap Changer Oil level min,
Equipment Fault (Tap Changer),
Automatic/manual mode (Tap Changer) 1,
Buccholtz of PLTC (Tap Changer) Trip,
Automatic fire system alarm.
- 2 SC Raise and
Lower,
- 9M Primary active power,
Primary reactive power,
Primary Current
Secondary active power,
Secondary reactive power,
Secondary Current,
Oil Temperature,
Winding Temperature,
Tap position (with D/A converter)

1
Extra SS to A2 data list
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 20/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

General purpose bay


- 11 SS RTU Fault,
DC system 48V fault,
DC system 110V fault or DC system 220V fault,
Rectifier 48V fault,
Rectifier 110 V fault,
AC system 220V/ 380 fault,
MCCB DC (Switchgears)
Fire Alarm,
RTU remote control,
Control room door alarm,
Substation door.

Telecommunication equipment alarm


- 1 SS Telecommunication Fault,

Low Voltage
6.1.3 Reclosers (880)
- 1 DS Recloser status,
- 5 SS Non-reclosing status,
Alt minimum trip status,
Ground trip block status,
Mal function status,
Power status.
- 1 DC Remote trip and loc out / supervision close,
- 3 SC Supervision non-reclosing,
Supervision alt.min.trip,
Supervisory ground trip block.
- 2M Current,
Voltage.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 21/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.2 Adaptation Works


Two aspects have to be taken into account, adaptation of HV devices and link
between HV devices and cubicles where equipments, like transducers and relays,
are installed.
Furthermore, to be able to telecontrol substation devices means these latter are
equipped for that. Consequently, switching devices have to be motorised and all of
bays have to be equipped with sensors and captors to gives status, measurements
and alarms.
Regarding motorisation, bays concerned are: Over Head line feeders, Transformer
Feeders, Shunt Compensator, Busbar Section and Tie. It is assumed that all of HV
devices are motorised. Thus, the list, which is given in Annexe (ref. Error! Reference
source not found.), only indicates how many MV bays should be motorised and
within which substation.
The next tables give a global price per province including:
 Cables, relays, transducers, terminal blocks and cubicles,
 Wiring between HV devices, transformers and marshalling kiosks,
 Wiring between marshalling and interface cubicles,
 Wiring between interface cubicles and RTU.
 Motorisation of all MV switching devices (where it has to be performed).

Next tables suggest two alternatives:


1. To do not take into account substations already equipped during “SPC MINI
SCADA PROJECT. That means to be equipped all of substations.
2. To do equip substations already equipped during “SPC MINI SCADA
PROJECT”
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 22/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.2.1 Table 1 (Mini SCADA Project not considered)

Adaptation Works – Total Cost (USD)

Provinces 110kV 22/33kV Total


An Giang 56 199 319 312 375 511
Bà Rịa - Vũng Tàu 97 940 138 824 236 764
Bạc Liêu 41 692 234 157 275 849
Bến Tre 57 213 214 514 271 727
Bình Dương 162 152 411 289 573 441
Bình Phước 80 569 174 565 255 134
Bình Thuận 75 489 299 894 375 383
Cà Mau 27 295 38 486 65 781
Cần Thơ 93 006 396 632 489 638
Đồng Tháp 82 675 229 131 311 806
Hậu Giang 25 610 28 568 54 178
Kiên Giang 60 972 227 809 288 781
Lâm Đồng 55 190 64 920 120 110
Long An 85 771 329 396 415 167
Ninh Thuận 48 675 185 765 234 440
Sóc Trăng 47 846 217 404 265 250
Tây Ninh 95 042 528 496 623 538
Tiền Giang 33 950 216 762 250 712
Trà Vinh 26 736 183 666 210 402
Vĩnh Long 43 512 249 256 292 768

Total per item 1 297 534 4 688 846

Total 5 986 380


Table 1 - Adaptation Works – Cost per Province - SPC Mini SCADA Project not considered
The detail for each substation can be found in annexe (ref. Annexe C: AW and TCD
Cost per substation (total)).
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 23/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.2.2 Table 2 (SPC Mini-SCADA Project considered)

Adaptation Works – Total Cost (USD)

Provinces 110kV 22/33kV Total


An Giang 56 199 319 312 375 511
Bà Rịa - Vũng Tàu 97 940 111 197 209 137
Bạc Liêu 41 692 234 157 275 849
Bến Tre 57 213 214 514 271 727
Bình Dương 162 152 411 289 573 441
Bình Phước 80 569 174 565 255 134
Bình Thuận 75 489 299 894 375 383
Cà Mau 27 295 38 486 65 781
Cần Thơ 93 006 244 992 337 998
Đồng Tháp 82 675 229 131 311 806
Hậu Giang 25 610 28 568 54 178
Kiên Giang 60 972 227 809 288 781
Lâm Đồng 55 190 49 054 104 244
Long An 85 771 329 396 415 167
Ninh Thuận 48 675 185 765 234 440
Sóc Trăng 47 846 217 404 265 250
Tây Ninh 95 042 528 496 623 538
Tiền Giang 33 950 216 762 250 712
Trà Vinh 26 736 183 666 210 402
Vĩnh Long 43 512 249 256 292 768

Total per item 1 297 534 4 493 713

Total 5 791 247


Table 2 - Adaptation Works – Cost per Province - SPC Mini SCADA Project considered

6.3 Telecontrol
Next tables suggest two alternatives:
1. To do not take into account substations already equipped during “SPC MINI
SCADA PROJECT. That means to be equipped all of substations.
To do equip substations already equipped during “SPC MINI
SCADA PROJECT”2 (ref.
 Annexe B: Scope of RTU installation).
Whatever the final choice, all of next tables give a global price including:
 Wiring between interface cubicles and RTU,
 All types of I/O cards,

2
Considering the total cost of the present Project, the upgrading cost is not taken into account.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 24/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 Rack and extra rack (note that SPC should have its own rack even though
SPC and A2 share information).
 Power Supply system,

6.3.1 Table 1 (SPC Mini-SCADA Project not considered)

RTU – Total Cost (USD)

Provinces 110kV 22/33kV Total


An Giang 8 800 46 366 55 166
Bà Rịa - Vũng Tàu 29 955 71 003 100 958
Bạc Liêu 12 780 20 141 32 921
Bến Tre 17 480 29 311 46 791
Bình Dương 36 343 104 842 141 185
Bình Phước 21 575 44 086 65 660
Bình Thuận 24 674 44 105 68 779
Cà Mau 4 953 21 977 26 930
Cần Thơ 34 064 52 614 86 678
Đồng Tháp 21 150 46 925 68 075
Hậu Giang 8 520 15 304 23 824
Kiên Giang 18 426 36 854 55 280
Lâm Đồng 21 295 33 621 54 916
Long An 28 934 49 514 78 449
Ninh Thuận 23 556 23 240 46 796
Sóc Trăng 14 166 28 339 42 505
Tây Ninh 26 693 55 682 82 375
Tiền Giang 12 914 28 504 41 418
Trà Vinh 11 905 13 303 25 208
Vĩnh Long 15 886 28 917 44 803

Total per item 394 069 794 646

Total 1 188 715


Table 3 - RTU - Cost per Province – SPC Mini SCADA Project not considered

As the previous chapter, the detail for each substation can be found in annexe (ref.
Annexe C: AW and TCD Cost per substation (total)).
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 25/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.3.2 Table 2 (SPC Mini-SCADA Project considered)

RTU – Total Cost (USD)

Provinces 110kV 22/33kV Total


An Giang 8 800 46 366 55 166
Bà Rịa - Vũng Tàu 29 955 58 405 88 360
Bạc Liêu 12 780 20 141 32 921
Bến Tre 17 480 29 311 46 791
Bình Dương 36 343 104 842 141 185
Bình Phước 21 575 44 086 65 660
Bình Thuận 24 674 44 105 68 779
Cà Mau 4 953 21 977 26 930
Cần Thơ 34 064 41 558 75 622
Đồng Tháp 21 150 46 925 68 075
Hậu Giang 8 520 15 304 23 824
Kiên Giang 18 426 36 854 55 280
Lâm Đồng 21 295 26 109 47 405
Long An 28 934 49 514 78 449
Ninh Thuận 23 556 23 240 46 796
Sóc Trăng 14 166 28 339 42 505
Tây Ninh 26 693 55 682 82 375
Tiền Giang 12 914 28 504 41 418
Trà Vinh 11 905 13 303 25 208
Vĩnh Long 15 886 28 917 44 803

Total per item 394 069 763 481

Total 1 157 550


Table 4 - RTU - Cost per Province – SPC Mini SCADA Project considered

As the previous table, the detail for each substation can be found in annexe.

6.4 Telecommunication links between SS and Provinces


Whatever the selected SCADA architecture, the Operational Network to be
commissioned in the scope of the “SCADA Systems and 110 KV substations without
operators” project, could be split in two clearly separated parts:
 Links between Substations and PLDC and /or HVGB,
 Links between PLDC and/or HVGB and the Main SCADA at SPC Head Office.
The first part, the telecommunication Network between Substations and PLDC will be
always the same, whatever the selected SCADA architecture.
But the second part, the telecommunication Network between PLDC and Main
SCADA at SPC Head Office will depend on the SCADA architecture.
So, the following study, taking into account the SPC operational needs and the
outgoing Corporate Network project from the IT department, proposes some
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 26/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

alternatives for each part, Substation to PLDC and/or HVGB and PLDC and/or HVGB
to Main SCADA at SPC Head Office.
It also proposes some options, which are not included in the scope of this study.

6.4.1 Telecommunication Network between substations, HVGB and PLDCs

6.4.1.1 Optical fibre Architecture


As it is necessary to build a Telecommunication Network for the SCADA Project, and
taking into account:
 The compared cost of optical fiber and copper cable,
 The costs of rented links,
 The necessary availability of an Operational Telecommunication
Network for a SCADA system,
The best solution for SPC consists of building optical fiber links between all SPC sites
in each province (substations, PLDC, HVGB).
These optical fibers shall be single-mode optical fiber, each cable shall contained 12
(twelve) optical fibers, its installation technology shall be “F8” technology.
Whatever the SCADA architecture selected by SPC, the connection links between
substations and PLDCs and/or HVGB will be always built.
So, these links will be realised by using optical fibre as showed in the scheme below:

PC
PC 222
PLDC
PC HVGB
HVGB
Provincial
Provincial
Provincial
HVGB
HVGB
Scada
ScadaSystem
ScadaSystem
System

Optical Fibres

SS SS SS SS

Figure 2 - Telecommunication Architecture between substations and PLDCs and/or HVGBs


To build these links in F8 technology, the estimated price is 1.400 $ per kilometre for
F8 optical fibre, including the commissioning.
Price ($)
Leased link 64 Kb/s $1750 per year
ADSS (F8) technology $1.400 per kilometre
Table 5 - F8 costs
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 27/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The optical fibers to be installed in order to build the links between the substations,
the HVGB and the PLDCs are described below:

Number Province Quantity (km)

1 AN GIANG 214

2 BA RIA VUNG TAU 43

3 BAC LIEU 81

4 BEN TRE 243

5 BINH DUONG 176

6 BINH PHUOC 270

7 BINH THUAN 238

8 CA MAU 287

9 CAN THO 205

10 DONG NAI 212

11 DONG THAP 209

12 HAU GIANG 158

13 KIEN GIANG 335

14 LAM DONG 288

15 LONG AN 308

16 NINH THUAN 118

17 SOC TRANG 190

18 TAY NINH 278

19 TIEN GIANG 293

20 TRA VINH 212

21 VINH LONG 210

Total 4565
Table 6 – Provincial missing Optical Fiber
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 28/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Thus, the investment in the optical fiber architecture between substations, HVGBs &
PLDCs will be the following:
Optical Fiber (F8 technology)
Unit Price ($) 1400 per kilometer
Quantity of optical fiber 4565
Total ($) 6.391.000
Table 7 – Provincial Optical Fiber investment

To build the Operational Telecommunication Network, the optical cable(s) and the
optical main frame distribution have to be installed in safety and property conditions
(in a cabinet for example) in each substation. The investment will be the following:

Cabinet (42U) Manpower (per Site)


Unit Price ($) 1000 250
Substations, HVGB & 144 144
PLDC
Sub Total ($) 144.000 36.000
Lump Sum ($) 180.000
Table 8 - Cabinet Investment

6.4.2 Telecommunication Network equipment


The main purpose of the project “SCADA System and 110 KV substations without
operators” is to connect the RTUs in the substations to the SCADA system(s). If the
needs are strictly limited to this item, only optical/electrical converters shall be
installed in the substations and in the PLDCs and/or HVGBs, as showed below:
PLDCs

Converter Converter
Optical/Electrical Optical/Electrical

OF OF

Converter Converter
Optical/Electrical Optical/Electrical

RTU RTU

Figure 3 - Telecommunication equipment on optical fibre


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 29/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Optical/electrical converter description:


An optical/electrical converter is a telecommunication equipment named Data Circuit
Equipment (DCE) which is in charge to adapt the electrical signal outgoing from the
Data Terminal Equipment (DTE) to the media (optical fibre in this case).
The simple kind of DCE is a point-to-point equipment as shown in the figure above.
Two kind of DCE optical interface are available:
 Multimode, dedicated for shorts distances (no more 1 kilometre),
 Single mode for long distances (maximum of around 80 kilometres, according
to the provider technology)
The type of interface shall be chosen according to the RTU interface (RS232,
RS485…).

As SPC will use only optical fibre, the necessary investment will be the following:
Optical/Electrical Manpower (per
Converter link)

Unit Price ($) 1000 100


Substations, HVGB & 250 125
PLDC
Sub Total ($) 250.000 12.500
Lump Sum ($) 262.500
Table 9 - Optical Fibre Investment
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 30/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

6.4.3 Telecommunication Network between 26 substations and A2 Critical


Substations

6.4.3.1 Optical fibre Architecture


As it is compulsory for SPC to connect the 26 substations not currently connected to
the A2 Control Centres and according to the fact that SPC shall built an optical fiber
architecture for its own needs, two solutions are possible:
 The first solution is to extend the optical fiber architecture in order to connect
these substations to the A2 critical substations,
 The second solution is to connect the A2 Control Center to the SPC SDH
Network (this solution is described in the Chapter 8)

The optical fibers to be installed in order to build the links between the 26 substations
and the A2 Critical substations are described below:
Distance
No. SUBSTATON TRANSMISSION LINE Note
(km)
1 Cho Lach 110kV Cho Lach SS to 110kV Mo Cay SS 27,0 OPGW available: SPC own 4 fiber optics
2 Mo Cay 110kV Mo Cay SS to 220kV Ben Tre SS 18,0 OPGW not available
3 My Tho 110kV My Tho SS to 110kV Binh Duc SS 6,5 OPGW not available
4 Tra Vinh 110kV Tra Vinh SS to 110kV Duyen Hai SS 28,0 OPGW not available
5 An Hoa 110kV An Hoa SS to 110kV Thanh Hung SS 24,0 OPGW not available
6 Thanh Hung 110kV Thanh Hung SS to 220kV Cao Lanh SS 26,0 OPGW available: SPC own 4 fiber optics
7 Moc Hoa 110kV Moc Hoa SS to 110kV Thanh Hoa SS 36,8 OPGW available (18.5km) and OPGW not available (18.3km)
8 Thanh Hoa 110kV Thanh Hoa SS to 220kV Cai Lay SS 46,0 OPGW available (18.5km) and OPGW not available (27.5km)
9 Can Duoc 110kV Cai Nuoc SS to 110kV Ca Mau SS 48,0 OPGW available: SPC own 4 fiber optics
10 Tran De 110kV Tran De SS to 110kV Dai Ngai SS 30,0 OPGW available: SPC own 4 fiber optics
11 My Tu 110kV My Tu SS to 220kV Soc Trang SS 16,0 OPGW available: SPC own 4 fiber optics
12 An Bien 110kV An Bien SS to 110kV Minh Phong SS 20,0 OPGW available: SPC own 4 fiber optics
13 Chung Su 110kV Chung Su SS to 220kV Rach Gia SS 0,3 OPGW not available
14 Tri Ton 110kV Tri Ton SS to 220kV Chau Doc SS 36,8 OPGW available: SPC own 4 fiber optics
15 Tan Bien 110kV Tan Bien SS to 110kV Tan Hung SS 16,6 OPGW not available
16 Tan Hung 110kV Tan Hung SS to 110kV Tay Ninh SS 32,0 OPGW not available
17 Thanh Duc 110kV Thanh Duc SS to 110kV Tay Ninh SS 26,3 OPGW available: SPC own 4 fiber optics
18 Da Tieng 110kV Dau Tieng SS to 110kV Tay Ninh SS or 30,3 OPGW not available
110kV Dau Tieng SS to 220kV Binh Long SS 76,2 OPGW not available
19 Tan Dong Hiep 110kV Tan Dong Hiep SS to 220kV Binh Hoa SS 7,5 OPGW available: SPC own 4 fiber optics
20 Bau Beo 110kV Bau Beo SS to 500kV Tan Dinh SS 2,0 OPGW available: SPC own 4 fiber optics
21 Phuoc Long 110kV Phuoc Long SS to Thac Mo Hydropower 11,8 OPGW not available
22 Binh Long 110kV Binh Long SS to 220kV Binh Long SS or 19,5 OPGW not available
110kV Binh Long SS to 110kV Tay Ninh SS 68,0 OPGW not available
23 Duc Linh 110kV Duc Linh SS to 220kV Ham Thuan SS 53,0 OPGW not available
24 Thuan Nam 110kV Thuan Nam SS to 110kV Ham Tan SS 34,0 OPGW available: SPC own 4 fiber optics
25 Di Linh 110kV Di Linh SS to 110kV Duc Trong SS 39,0 OPGW available: SPC own 4 fiber optics
26 Don Duong 110kV Don Duong SS to 110kV Duc Trong SS 19,5 OPGW not available
26 Substation 799,1

Table 10 – A2 Connection Optical Fiber

The total missing Optical Fiber in order to connect the 26 substations to A2 is 427
kms.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 31/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Thus, the investment in the optical fiber architecture between substations and the A2
Critical Substations will be the following:
Optical Fiber (ADSS technology)
Unit Price ($) 1.700 per kilometer
Quantity of optical fiber 427
Total ($) 725.900
Table 11 – A2 Connection Optical Fiber investment

6.4.3.2 Telecommunication Network equipment


As the needs are strictly limited to the connection of RTUs using the 101 Protocol
installed in substations to the A2 critical substations, only optical/electrical converters
shall be installed in the substations and in the A2 critical substations.

Optical/Electrical Manpower (per


Converter link)

Unit Price ($) 1000 100


26 Substations 48 48
Sub Total ($) 48,000 4,800
Lump Sum ($) 52,800
Table 12 – A2 Connection Optical Fibre Investment

6.4.3.3 Total Investment for Telecommunication Network between 26


substations and A2 Critical Substations

Item
Optical Fiber Architecture 725,900
Optical/Electrical Converter 52,800
Total ($) 778,700
Table 13 – Total Investment for 26 Substations A2 Control Center Connection
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 32/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7 SCADA system implementation Alternatives


Generally speaking and everywhere over the world, telecontrol architectures,
telecommunication architectures but also operating organisation can be considered
as distributed, hierarchical or as a combination of both.
Distributed means everybody receives information at the same time whereas
hierarchical means that a first one receives or has the information and then transmits
this information to another one.
In the telecontrol field, distributed architectures are used between different Control
Centres without any hierarchical link but concerned by information located on the
area not under their responsibility but with a possible impact on their own. That is
typically the case between countries, regions, provinces, districts and so on. In the
other hand, hierarchical architectures are often used between sites managed by one
and only one entities, for instance a local control Centre and a Regional one.
Within a country there is a combination of both. Local Control Centres are under the
responsibility of Regional Control Centres, which are under responsibility of the
National Control Centre. Regional Control Centres exchange information between
each other as Local Control Centre between them. The SPC project is in this case.
Now, the data are the following:
 One SCADA system has to be installed in SPC head Offices,
 One SCADA system could be installed in each Provinces,
 Substations without RTU have to be equipped with one,
 Future RTU and those already installed shall use or have to use one link of
two to communicate with A2 Control Centre (meaning only one remains
available) (ref. Inception Report - Annexe 2 Questionnaire regarding A2
project – 1.5 RTU – item 4).
Thus, we have three kinds of sites: SPC Head Offices, Provinces and Substations.
As mentioned above, we are in the case of a combination.
Consequently the different architectures are the following:
 SCADA systems are installed in Provinces or not.
 Substations communicate with the SCADA in SPC Head Offices (MCC) or
SCADA in provinces (LCC).
The table hereafter shows all combinations:
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 33/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

LCC – SS LCC with remote LCC without


MCC – SS
(SCADA) consoles SCADA
Not possible
because RTU
MCC – SS have only one A B
available link to
communicate
Not possible
because RTU Useless from
LCC – SS
have only one C telecontrol point
(SCADA)
available link to of view
communicate
LCC with remote
A C Not possible
consoles
Useless from
LCC without SCADA B telecontrol point Not possible
of view
Table 14 - Possible Architectures
Consequently only three architectures can be studied:
A. The MCC SCADA system communicates with Substations and transmits
information to Provinces equipped with remote consoles,
B. The MCC SCADA system communicates with substations without any
communication to Provinces,
C. The LCC SCADA systems communicate with substations and transmit to the
MCC SCADA system,
The different architectures suggested in the Inception Report are the following:
1. One SCADA system per Province – case C,
2. One SCADA system in some strategic Provinces – case C,
3. One remote console connected to the main System within each Provinces –
case A,
4. One and only one SCADA system within SPC head offices – case B.
The second architecture is a variation of the first one but all the same is studied due
to the cost, which is quite different.

7.1 Analysis of SPC context and objectives


Before depicting the various SCADA architecture alternatives, it is worth discussing
and analysing SPC operating context and SPC objectives in the frame of the SCADA
project. The goal of this analysis is to elaborate on the viable solutions and
alternatives and to eliminate -on a justified basis- those, which are not worth to be
more deeply analysed.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 34/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.1.1 Analysis of SPC and A2 operating context


110 and 22kV networks have definitely to be considered separately as far as
operation is concerned:
 110kV network is supervised by A2 and operated by SPC through the PLDCs
(SPC owns, manages the security accesses to the network and this latter
maintenance) in the frame of a dedicated entity gathering operators in the
primary substation and a maintenance team; A2 faces huge troubles in
network supervision since only few 110kV substations (approx. 30%) are
presently remote controlled. This drastically limits the network control and
operation efficiency. Moreover, this has a wide negative impact on SPC
network maintenance efficiency since the absence of supervision tool on A2
side does not allow to correctly evaluating the maintenance reconfiguration
schemes (from the security point of view). A2 SCADA project will improve this
situation provided the 110 kV network control is still devoted to A2 as it is
presently.
 22kV network is supervised and operated by SPC through the PLDCs, which
manage field crews and request operator teams manoeuvres in the 110kV
stations. Except in Can Tho, Da Lat and Vung Tau Cities, no SCADA facilities
are available yet in the provinces, rendering the 22kV network operation and
supervision uneasy and hardly efficient. In this frame, SPC SCADA project
initial objective is to remote control the 22kV part of the 110kV stations so as
to change them into unmanned stations. Due to the fact that this strategy will
only slightly participate in the 22kV network performance improvement (this
aspects is being discussed bellow in § 7.1.1.3) a complementary study has
been made so as to evaluate the opportunity (comparison of technical /
financial impacts vs. benefits) of remote controlling the reclosers on the 22 kV
network.
The difference in nature of the 2 networks (meshed participating in the feeding
security and somehow to the consumption/generation balance for the 110kV network
and radial for the 22kV network) implies different operation rules and practices, which
influence the network control.
For 110 KV network, the security assessment is the major objective while on the
22kV network, the continuity of supply is the essential goal. From this perspective,
there is a close connection between 110kV and 220kV networks supervision and
control. This fully justifies the existing EVN organisation that dedicates this task to
A2. The sustainability of this organisation is a must.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 35/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.1.1.1 110kV maintenance


The splitting of 110kV network maintenance and control responsibilities between two
entities (i.e. SPC and A2 respectively) is worth to be analysed in a medium term
perspective:
 On the preventive maintenance domain, programs and actions are driven on
one side by data and statistics, which are totally under SPC, control until now
while on the other side A2 masters operating constraints. As soon as A2 and
SPC are equipped with a SCADA supervision tool covering most of the 110kV
substations, these SCADA will feed to a large extend and in a most efficient
manner the 110kV substations preventive maintenance programs inputs (data
and constraints).
 On the curative maintenance side, the implementation of the A2 SCADA
system will also decrease SPC role in the detection of failures;
 Concerning the evolutive maintenance, SPC owns the networks what
theoretically entitles SPC to master the relevant investments. Once the A2
SCADA in operation on the 110kV network, only A2 will master the line
constraints evolutions that shall initiate network reinforcement. This issue has
to be considered by SPC.
This will definitely conduct SPC 110kV branch to a specialisation in the maintenance
activity as far as 110kV networks are concerned.

7.1.1.2 22kV operation


As far as SPC SCADA project is concerned, SPC major objective is to remote control
the primary substations so as to change them into unmanned substations.
It is worth noticing that the benefits drown from SPC SCADA investment will depend
on its efficiency from the technical and economical viewpoints. Under “technical
aspects”, electricity delivery quality, network operation, assets management, network
planning and maintenance will be impacted by the implementation of the SCADA
system; while under “economical aspects”, operation and maintenance costs will be
influenced.

7.1.1.3 Technical analysis

1. Electricity delivery quality


In comparison with the present situation, the introduction of a SCADA system
supervising and controlling the primary substations (110/22kV) will allow SPC to get a
more “real time” overview of the 22kV networks operation. However this will
marginally influence the electricity delivery quality in terms of customers continuity of
supply and voltage quality. As shown on the following diagram, only a coordinate
control action on both primary substations 22kV feeders and remote controlled
switches spread on the network allows improving to a large extend the electricity
delivery Quality.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 36/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

m e a n d u ra tio n * o f o u ta g e s (in m in /cu sto m e r/ye a r)

100

90

80

70

60

50

40

30

20

10

0
m a n n e d su b sta tio n s u n m a n n e d su b sta tio n s m a n n e d w ith 1 .5 *** R C u n m a n n e d w ith 1 .5 R C m a n n e d w ith 2 .5 *** R C u n m a n n e d w ith 2 .5 R C
w ith o u t R C ** d e vice s o n w ith o u t R C d e vice s o n d e vice s a n e a ch 2 2 kV d e vice s a n e a ch 2 2 kV d e vice s a n e a ch 2 2 kV d e vice s a n e a ch 2 2 kV
th e 2 2 kV n e tw o rk th e 2 2 kV n e tw o rk fe e d e r fe e d e r fe e d e r fe e d e r

Figure 4 - SCADA implementation strategy influence on electricity delivery quality


* mean durations are typical average figures found for similar 22kV networks as SPC’s around the
world
** RC: Remote Controlled;
*** 1.5 and 2.5 RC devices per feeder correspond respectively to the implementation of 1 RC
device at the feeder end (boundary switch between 2 feeders counted as a half for each feeder)

2. Network operation
The implementation of a SCADA system for the 22kV networks supervision and
control will improve the real time accuracy of the network overview and help to
coordinate field crews’ management. The knowledge of the measurements at the
feeder heads, along with the manual updates of the network topology (manual
devices on the network) and knowledge of network transits via DMS computation
functions, will help to secure the field crews actions (network reconfiguration actions
dedicated to works or restoration after outages on the networks) in a better efficiency.
The related improvement is mostly qualitative and cannot easily be quantified.

3. Assets Management
Through the SCADA implementation, the assets management quality will be
continuously improved due to the necessary substation standardisation imposed by
telecontrol adaptation and the accurate knowledge of MV network topology and
characteristics, which are a prerequisite to DMS functions implementation.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 37/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

4. Network planning and maintenance


In these matters, the implementation of the SCADA system will have a positive
impact on the improvement of planning and maintenance activities since it will
increase loads and maintenance data reliability through an automatic storage and
archiving facility.

7.1.1.4 Economical aspects analysis and Evolution of operational costs


The introduction of a SCADA system along with unmanned stations will have two
opposite operational costs impacts:
 New expenses on one hand:
1. For maintenance: it will impose the setting up, within SPC, of:
a. A centralised SCADA maintenance team (3 engineers and 3
technicians) – this being the only proven way to guarantee the
SCADA related investments sustainability. Whatever the SCADA
architecture chosen (centralised, decentralised or mixed), the
centralised structure will deal with SCADA system first level
maintenance (diagnosis and repair via simple procedures i.e.
restarting or hardware modules exchanges either for RTUs,
telecommunication equipments and central system) and manage the
exchanges with the SCADA manufacturer for second maintenance
level.
b. A data maintenance team (2 people engineer or technician)
attached to each control centre;
c. A RTU and telecommunication maintenance team.
2. For network operation: a group of operators shall be set up (6 operators on
24h shift +6 on 14h in a centralised organisation, 6-7 operators in 24h shift
in a decentralised organisation);
3. For the Control System Management; a management team (manager,
deputy manager, group of 2 “works preparation engineers in a centralised
organisation, manager and deputy manager in a decentralised
organisation);
 Reduction in costs on the other hand:
For primary substations operation: suppression of the relevant teams (around
700 people to be reallocated – their skills being appreciated for the new
related SCADA operation jobs); Due to the status of SPC personnel, these
costs reduction will only be effective on medium and long terms (10-20 years)
while the expenses increase will be immediate and hardly balanced.

7.1.2 The organisational factor and its impact on SCADA Architectures


Taking into account SPC willingness (expressed in the TOR) to deploy decentralised
Control Centres (in the provinces) along with a centralised supervision entity in
HCMC headquarters, the consortium feasibility study focussed on the viable
architectures matching SPC needs and those, which might have an interest for SPC.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 38/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

In this concern architectures viability is mostly governed by the satisfaction of a


security rule that imposes at all times - on a specific area - that a unique Control
Centre is in charge of network control.
Considering this latter intangible rule, SPC requirements and the possibilities offered
by the actual technology (performances and capacity), following organisations would
be possible:
i) MCC has a supervision role only, PLDCs have a control role on their province
at all times,
ii) MCC has a back up role from the control and system point of view for one or
several PLDCs in case of crisis and/or PLDC System failure; apart from this
situation, PLDCs have a control role on their province at all times,
iii) MCC has a supervision role only, selected PLDCs (so called Major PLDCs)
have a control role on their province at all times and take over the control of x
neighbouring PLDCs (called “Sub” PLDCs) at definite moments (i.e. at night,
week ends and/ or during major events) as well as in emergency situations
(loss of one neighbouring PLDC),
iv) MCC has a back up role from the control and system point of view for one or
several Major PLDCs in case of crisis and/or Major PLDC System failure;
apart from this situation Major PLDCs have a control role on their province at
all times and take over the control of neighbouring PLDCs at definite moments
(i.e. at night and/ or during major events) as well as in emergency situations
(loss of one neighbouring PLDC),
v) MCC has a control role for the entire network at nights, week-ends, during
crises and/or PLDC System failure, PLDCs have a control role on their
province during daytime on the normal working days,
vi) MCC has the control of the entire network at all times; PLDCs have a
supervision role only (i.e. via web accesses),
vii) MCC has the control of the entire network at all times; PLDCs have a
supervision role only (i.e. via web accesses) one PLDC location houses a
back up site for the MCC.
These are the major feasible alternatives, several sub-alternatives of each of them
can also be thought but without structuring impact. Therefore, these later seven
alternatives only gave rise to an efficiency analysis scrutinising their respective
advantages and drawbacks and their global viability.
The result of this analysis is to be found in following table (see next page).
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 39/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The following table gathers the various possible organisations and analyses their viability.

Organisation for Advantages Drawbacks Comments/ advice


Network Control
i) MCC has a - Easy to settle due to the proximity with - High need in skilled and trained human Analytic outcomes of the
supervision role existing operation organisation resources (for setting up all PLDCs control Alternative:
only, PLDCs have a teams), - Level of Performance of network
control role on their - Control coordination problems for the MV operation and control: +/-
province at all times feeders crossing the provinces boundaries - Level of control reliability: - -
- Organisation not efficient for crises - Level of investment (CAPEX): -
management (crisis management needs a was not considered
global synthesis control coordination level
- Level of operational costs
above the provincial level)
(OPEX): - - - (very high)
- When limited to a supervision role, a control
centre is generally hardly economically
justified; moreover, all state of the art control
systems allow for web-reporting facilities,
which are more efficient and less, expensive
than a complete control centre architecture.
ii) MCC has a back up - Easy to settle due to the proximity with - High need in skilled and trained human Analytic outcomes of the
role from the control existing operation organisation, resources (for setting up all PLDCs control Alternative:
and system point of - Back up facility achieved teams), - Level of Performance of network
view for one or - Back up role efficiency necessitates a high operation and control: +/-
several PLDCs in level of proficiency and network knowledge - Level of control reliability: +/-
case of crisis and/or of the operators (in particular when a control
PLDC System - Level of operational costs
centre is only dedicated to this latter role);
failure; apart from (OPEX): - - - (very high)
the related proficiency level is hardly
this situation, obtainable without experienced operators;
PLDCs have a
control role on their
province at all times
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 40/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Organisation for Advantages Drawbacks Comments/ advice


Network Control
iii) MCC has a - Easy to settle due to the proximity with - Medium need in human resources (for Analytic outcomes of the
supervision role existing operation organisation setting up all PLDCs control teams), the shift Alternative:
only, selected - Coordination efficiency at boundaries operation is limited to the “major PLDCs” - Level of Performance of network
PLDCs (so called between “normal PLDC” control areas what decreases the costs and the human operation and control: +
Major PLDCs) have achieved resources needs
- Level of control reliability: +
a control role on - Control coordination problems for the MV
- Fair Control efficiency during crises- - Level of operational costs
their province at all feeders crossing the provinces boundaries
(during these periods, a concentration of (OPEX): - - - (very high)
times and take over between major PLDC operation areas
control is more efficient)
the control of (including “sub” PLDCs)
neighbouring - Fair Reliability level
PLDCs at definite Global Appraisal
moments (i.e. at This organisation has a “drawback
night, week ends level” which is hardly balanced by only
and/ or during major few advantages.
events) as well as in
emergency
situations (loss of
one neighbouring
PLDC),
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 41/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Organisation for Advantages Drawbacks Comments/ advice


Network Control
iv) MCC has a back up - Easy to settle due to the proximity with - high need in skilled and trained human Analytic outcomes of the
role from the control existing operation organisation, resources (for setting up all PLDCs control Alternative:
and system point of - Coordination easy to achieve and teams), - Level of Performance of network
view for one or efficient during crises situations - Back up role efficiency necessitates a high operation and control: ++
several Major level of proficiency and network knowledge
- Back up facility achieved - Level of control reliability: ++
PLDCs in case of of the operators (in particular when a control
crisis and/or Major - High reliability level - Level of operational costs
centre is only dedicated to this latter role);
PLDC System (OPEX): - - - (very high)
the related proficiency level is hardly
failure; apart from obtainable without experienced operators;
this situation Major
PLDCs have a
control role on their
province at all times
and take over the
control of
neighbouring
PLDCs at definite
moments (i.e. at
night and/ or during
major events) as
well as in
emergency
situations (loss of
one neighbouring
PLDC),
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 42/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Organisation for Advantages Drawbacks Comments/ advice


Network Control
v) MCC has a control - Coordination easy to achieve and highly - Highly skilled people needed Analytic outcomes of the
role for the entire efficient during crises situations - Control coordination problems for the MV Alternative:
network at nights, - Back up facility achieved feeders crossing the provinces boundaries - Level of Performance of network
week ends, during operation and control: +++
- Good reliability level - Organisation not efficient for crises
crises and/or PLDC
- Lowest need in quantity of skilled and management (crisis management needs a - Level of control reliability: ++
System failure,
trained human resources (for setting up global synthesis control coordination level - Level of operational costs
PLDCs have a
all PLDCs control teams), above the provincial level) (OPEX): ++
control role on their
province during - No real backup facility for each PLDC even
daytime on the with higher level of investment in each
normal working system architecture
Global Appraisal
days, - Provincial control needs might be satisfied
with minimised architecture costs Apart from the economical viewpoint
which does not militate in favour of this
- Need for DTS investment to maintain a high
alternative, this latter has several
level of skills amount MCC operators
important advantages such as a good
level of control performance and
reliability
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 43/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Organisation for Advantages Drawbacks Comments/ advice


Network Control
vi) MCC has the - Need for DTS function not obvious (fault - Back up facility achieved via higher Analytic outcomes of the
control of the entire rate encountered will be an efficient “on infrastructure /system costs at the Control Alternative:
network at all times; the job continuous training) Centre - Level of Performance of network
PLDCs have a - Coordination easy to achieve and highly operation and control: +++
supervision role efficient during crises situations - Level of control reliability: ++
only (i.e. via web
- Good reliability level - Level of operational costs
accesses)
(OPEX): +

Global Appraisal
Apart from the economical viewpoint
which does not militate in favour of this
alternative, this latter has several
important advantages such as a good
level of control performance and
reliability
vii) MCC has the - Coordination easy to achieve and highly Analytic outcomes of the
control of the entire efficient during crises situations Alternative:
network at all times; - Back up facility achieved - Level of Performance of network
PLDCs have a operation and control: +++
- High reliability level (needed due to the
supervision role
higher sensitiveness of the control centre) - Level of control reliability: +++
only (i.e. via web
accesses) one - Need for DTS function not obvious (fault - Level of operational costs
PLDC location rate encountered will be an efficient “on (OPEX): +
houses a back up the job” continuous training)
site for the MCC
Table 15 - Various Organisation Analysis
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 44/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.2 Analysis of the suitability of SPC headquarters premises


Depending of the organisation retained, the needs for control centre premises at SPC
headquarters might be highly different.
The following table analyses this issue.
Organisation for Network Need for SPC HQ premises Suitability of SPC proposed
Control premises
i) MCC has a supervision role Supervision room: 50sqm Yes even oversized
only, PLDCs have a control Equipment room: 20sqm
role on their province at all
times
ii) MCC has a back up role Control room: 150sqm No
from the control and Equipment room: (2 rooms of
system point of view for 50Sqm each)
one or several PLDCs in
Kitchen: 30sqm
case of crisis and/or PLDC
System failure; apart from Rest room: 30sqm
this situation, PLDCs have Meeting+crisis room: 150sqm
a control role on their
province at all times
iii) MCC has a supervision role Supervision room: 50sqm Yes even oversized
only, selected PLDCs (so Equipment room: 20sqm
called Major PLDCs) have
a control role on their
province at all times and
take over the control of x
neighbouring PLDCs at
definite moments (i.e. at
night, week ends and/ or
during major events) as
well as in emergency
situations (loss of one
neighbouring PLDC),
iv) MCC has a back up role Control room: 150sqm No
from the control and Equipment room: (2 rooms of
system point of view for 50Sqm each)
one or several Major
Kitchen: 30sqm
PLDCs in case of crisis
and/or Major PLDC System Rest room: 30sqm
failure; apart from this Meeting+crisis room: 150sqm
situation Major PLDCs
have a control role on their
province at all times and
take over the control of x
neighbouring PLDCs at
definite moments (i.e. at
night and/ or during major
events) as well as in
emergency situations (loss
of one neighbouring
PLDC),
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 45/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Organisation for Network Need for SPC HQ premises Suitability of SPC proposed
Control premises
v) MCC has a control role for Control room: 200sqm No
the entire network at nights, Equipment room: (2 rooms of
week ends, during crises 50sqm each)
and/or PLDC System
Kitchen: 30sqm
failure, PLDCs have a
control role on their Rest room: 30sqm
province during daytime on Meeting+crisis room: 150sqm
the normal working days,
vi) MCC has the control of the Control room: 200sqm No
entire network at all times; Equipment room: (2 rooms of
PLDCs have a supervision 50sqm each)
role only (i.e. via web
Kitchen: 30sqm
accesses)
Rest room: 30sqm
Meeting+crisis room: 150sqm
vii) MCC has the control of the Control room: 200sqm No
entire network at all times; Equipment room: (2 rooms of
PLDCs have a supervision 50sqm each)
role only (i.e. via web
Kitchen: 30sqm
accesses) one PLDC
location houses a back up Rest room: 30sqm
site for the MCC Meeting+crisis room: 150sqm
Table 16 - Organisation Suitability Analysis

7.3 Telecontrol Protocols


This chapter gives some basic information regarding telecontrol protocols, which are
named throughout the following lines.
Two kinds of protocols are usually used for a telecontrol network: to exchange
between Substations and Control Centres and to exchange between Control
Centres. The 3 following protocols: 60870-5-101, 60870-5-104 and TASE.2 cover this
type of exchange and are mostly common among utilities. This chapter gives a brief
description using the OSI 7-layers (physical, link, network, transport, session,
presentation, and finally application).
Note: That there is also a specific companion standard for integrated totals (the 102) but
very little or not used and a specific companion standard for the interface with
protection equipment (the 103). Both based on the same series as the 101 regarding
formats and transmission rules.

7.3.1 IEC60870-5-101
This protocol is officially born in 1995. It is called point to point because it defines the
transmission over serial links. In fact, the 101 is the visible part of the standard that
consists of 5 base documents (60870-5-1.5), which specify the structure of frames
and data to the description of the fundamental exchanges. If we compare this
protocol to a language that has a lexicon, grammar and conventions, we could say
that grammar and conventions are described in the first documents and the 101
document describes the specific lexicon for telecontrol.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 46/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

From OSI point of view, only layers Link (60870-5-1 & 2) and application (60870-5-3
& 4) are covered by the standard.
It allows the transmission of all information required for telecontrol, which mainly
means signals, measurements, counting, commands and setpoints. There are also
elements supporting the management of transmission: timing, test command and the
ability to transfer files and set.

7.3.2 IEC60870-5-104
This protocol is a porting of 101 for a communication network based on TCP/IP.
Thus, the two first documents, 60870-5-1 & 2 dedicated for the link layer, becomes
useless.
He almost offers the same features as the 101; almost, because TCP/IP. In fact,
TCP/IP is non-deterministic, that means we know when we send a message, but it is
hard to say exactly when it will reach the relevant device. In telecontrol, this presents
some difficulties, especially regarding telecommands. It is clearly unthinkable that an
operator in an emergency situation, sending an order to open or close a circuit
breaker, waits quietly until the telecommand wants to arrive. This would call into
question the interest of using a telecontrol network expected to provide reliability and
reactivity essential to operate a power grid.
To overcome this non-determinism the 104 adds some specific information for
communication from the Control Centre to sites. The characteristic of these
information is to be time tagged. Thus, when the RTU receives them it can check if
the information is still on time and can be transmitted to the HV device. This
obviously implies a perfect time synchronization; other point to which the 104
companion standard advises the implementation of mechanisms other than those
originally used for the 101.
This non-determinism leads also that the clock synchronization procedure defined in
IEC 60870-5-5 cannot be used (ref. IEC60870-5-104) because the link layer
according to IEC60870-5-2, which provides the exact time of sending the clock
command, is no longer available. But this synchronization is more than useful.
Consequently, there is a necessity of installing clock synchronization receivers or
similar equipment in each substation.

7.3.3 IEC60870-6-503 alias TASE.2


It is completely independent of the communication medium and is based on the OSI
application layer. Communication with the lower layer is managed by MMS and
ACSE also located on the application layer. It was also designed to transmit all types
of information: signal, measurement, command, setpoint, counting, events, reports,
accounting data, load shedding plan, producer walking program. It can also remotely
manage executable program, transmit information sampling (typically from protection
relay). All these facilities are described in 9 blocks. Note that only block 1, 2, 5 and 7
are really necessary for telecontrol needs.
The principle of communication is quite different from that described for the two
previous protocols, it is called "Client Server". This means that any exchange starts
by sending a request from the client. A first communication, real contract, between
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 47/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

the client and the server is used to define the information to be transmitted but also
the method of transmission (exception, periodic...). It even offers the opportunity to
hot redefine conditions of transmission but also the data transmitted.
Without going into details of the TASE.2 working, we note that the principles on which
it relies involve a total independent with the SCADA system. This no-adherence
explains the ability of this protocol to communicate between heterogeneous systems.
That is the reason why this protocol is is universally required for the transmission
between Control Centres.

7.4 Description of the various feasible alternatives for the SCADA


architecture
Note: This Chapter does not depict the detailed SCADA issues. These latter are detailed in
the SCADA DMS document handed over to SPC during the training session.

A2 SPC
Within all schemes describing

the different architectures, the


3U
includes what the
SS
icone
Telephone Video
RTU PC
Surveillance

next figure describes. Substation


Communication
Components

7.4.1 One SCADA system per Province (SCADA Architecture 1)


This architecture corresponds to the “organisation” architectures i), ii), v) depicted in
the previous chapter.
With this architecture the main SCADA system located into SPC offices is supplied
by provincial SCADA themselves supplied by RTU located into 110kV substations
under their responsibility (ref. Figure 5).
The failure of one of the provincial SCADA systems will have a limited consequence
on the province’s MV network control capability: only the relevant province MV
network control and monitoring will be unavailable. The 110kV network monitoring
and control of the said province would still be possible (if designed so) on the MCC
SCADA system via the TASE 2 link.
Therefore, considering the low occurrence rate of such a SCADA system failure and
its limited consequence, as shown above, the consortium would not recommend to
implement a backup system neither for the provincial SCADA systems nor for the
MCC SCADA system.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 48/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

None “back up” has thus been considered in the SCADA Architecture 1 technical
description nor in the relevant cost estimation.

A2 TASE.2
Scada System (ICCP)

101 SPC
MV
GPRS Main
Reclosers Main Control Centre(MCC)
Scada System
SS or

Main Load Dispatch Centre


(MLDC)

TASE.2 TASE.2 TASE.2


(ICCP) (ICCP) (ICCP)
Double links

1st SPC 2nd SPC 20th SPC


MV
GPRS Provincial GPRS Provincial GPRS Provincial
Reclosers
Scada System Scada System Scada System

104 104 104 104 104 104 Provincial Control


Centres (PCCs)
or
Provincial Load Dispatch

Centres (PLDC)
RTU RTU RTU RTU RTU
RTU
RTU RTU
RTU
RTU

Figure 5 - One SCADA per Province

7.4.1.1 Functional Issues


This paragraph analyses the functional impacts of the architecture on the SCADA
system.
All the SCADA manufacturers present on the market master the relevant architecture,
therefore, due to a potential enlarged competition, SCADA costs would be kept at a
low level for each system (SPC will above that beneficiate from a purchase “quantity
effect” that will definitely decrease the individual costs- since all the systems will be
similar). In a first step and due to the fact that only the primary substations and not
the MV network will be remote controlled, the relative “easiness” of control operation
does not require the implementation of elaborated isolation and restoration DMS
functions. However, the return on investment being essentially linked to the MV
network automation level (via remote controlled facilities), SPC will necessarily have
to invest on network automation and consequently on fault location and restoration
functions on the medium-long term. Therefore it is advisable in this case to pre-select
only the bidding manufacturers among those, which might propose these functions,
so as to be sure of their integration possibility.
In addition, Computation function on the network could optionally be implemented so
as to help the operator to build the works and outages reconfiguration schemes more
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 49/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

efficiently. This option will be worth to be firmly requested in order to increase the
performance of control efficiency.
This latter option estimated cost will be around 50,000 USD per Control System site.
In any case, a full description of the MV network operated is worth to be integrated in
the SCADA systems so as:
 To enter in a virtuous circle of data quality improvement that will guarantee the
system sustainability and a global improvement of the Distributor efficiency,
 So as to be sure of the possible management of high quantity of network
descriptive data and guarantee the further integration of the highly demanding
DMS functions in this concern,
 So as to improve works management efficiency and further implementation of
WFM (Work Force Management Tools in a near future or as an option in the
early tendering phase)
In addition to the conventional SCADA functions, the efficiency of WFM would also
be achieved via the integration of following functions:
 SMS exchanges with field crews

7.4.1.2 Control Systems characteristics and Sizing,


It is advisable, to specify a wide integration of standards (IEC, TCP/IP, Linux) within
the control systems architecture so as to ensure its sustainability (this is true for all
the various architectures) .
On top of this “basic requirements, the following shall prevail in the hardware and
software architectures:
 Duplicate Ethernet LAN (preferably separated for process and operator
positions)
 Linux or eventually Windows (in case the manufacturer proves its perfect
handling of Microsoft OS over a long period of time) servers (or a mix of both)
 Linux or Windows workstations
 2 - 3 monitors ((2 as long as the MV network is not automatised; preferably 3
as soon as remote control facilities are implemented on the MV network)) per
operator workplace; moreover
 Redundant SCADA servers (so as to achieve a “reasonable reliability level
for this type of architecture)
 Standard real time APIs
 Standard CIM interfaces
Sizing concerns
Due to the fact that the life expectancy of a control system is around a decade
(10years)-(the life expectancy corresponding to the commonly admitted average
return on investment duration for control systems) the system shall be sized so as to
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 50/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

cover at least the network increase within the next decade with an additional margin
of 50% so as to ensure good performances throughout the system life.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 51/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.4.1.3 Telecommunication
In this SCADA architecture, as a SCADA system is installed in each PLDC, the RTU
links are directly connected on the Provincial SCADA Front End. Consequently,
Telecommunication concentrators are not necessary.

Exchanges aspects
The Telecommunication Network has to take into account the necessary exchanges
between:
 RTU located in Substation and SCADA systems in PLDC,
 SCADA systems located in PLDC and the Main SCADA system located in
SPC Head Office,
 SCADA systems located in PLDC and the SCADA systems located in
neighbour PLDC, to exchange bordering information.

Protocol Telecom Protocol Speed rate (b/s)


Exchanges between RTU and
IEC60870-5-104 RS-XXX 9.600 min
SCADA in PLDC
Exchanges between SCADA
TASE 2 E1 64.000
in PLDC and Main SCADA
Exchanges between
TASE 2 E1 64.000
neighbour SCADA in PLDC
Table 17 - Necessary Protocols - Architecture 1

7.4.1.4 Economical consideration for the SCADA systems


a) Basic costs
Investment SCADA Systems Costs
Hardware $200,000
SCADA Software $4 -6M
DMS software $2-3 M
System configuration and project management $1-2 M
Total CAPEX $7.2-11.2 M
Operation cost SCADA Systems Costs
Curative Maintenance over 10 years* $2 M
Evolutive Maintenance over 10 years* $2 M
Total OPEX $4 M
Grand Total (CAPEX+OPEX) $11.2-15.2 M
Table 18 - SCADA Cost - Architecture 1
* The maintenance contract over a period corresponding to the system life
expectancy is a guarantee of system sustainability and is a must.
Note that these figures are slightly under the ones given in the inception report
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 52/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

b) Options
Optional control of devices on the 22kV network:
The following table evaluates the related expenses.
Investment Amount
Hardware (additional hardware in the control centre induced by $15,000
the reclosers implementation
Adaptation of reclosers to remote control $1.5 -2M
DMS software adaptation dedicated to the use of reclosers $0.1 M
System configuration and project management $0.3 M
Total CAPEX $1.915-2.415 M
Operation cost Amount
No specific OPEX costs have to
be considered compare to the
present situation
Total OPEX $0 M
Grand Total (CAPEX+OPEX) $1.915-2.415 M
Table 19 - MV Option Costs - Architecture 1
Following assumptions have been made:
- Reclosers only shall be remote controlled since most of the LBS are not
motorised.
- 80% of the 795 existing reclosers will be easily adapted to remote control via the
connection of RTUs or SCADA adaptation cards, the 20% left will for some of
them (around 5%) necessitate the replacement of the Control cubicle or the
implementation of specific I/O cards allowing for teleindication retrieval.
- Considering the telecommunication architecture allowing the connection of the
reclosers RTUs or SCADA modules, two alternatives are possible:
1. GPRS the easiest and less expensive one,
2. A mix of GPRS and optic fibre when the F8 network is available in the
vicinity of the Reclosers. In this latter case, the architecture reliability will
slightly increase while the price will considerably increase due to the fact
that it imposes the building of an IP network.
Considering the above, the second alternative has not been taken into account in
the detailed quotation of the alternative

7.4.2 One SCADA system in some strategic Provinces (SCADA Architecture


2)
This architecture corresponds to the “organisation” architectures iii), iv) depicted in
the previous chapter.
As previously, with this architecture the main SCADA system located into SPC offices
is supplied by provincial SCADA themselves supplied by RTU located into 110kV
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 53/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

substations under their responsibility (ref. Figure 6). Only the final number of PLDC
changes. The PLDCs where SCADA systems are implemented are called “Major
PLDCs. In order to cope with SPC requirements to keep a control capability in all
PLDCs, remote consoles can also be implemented in each PLDC.
The failure of one of the “Major” provincial SCADA systems will have an impact on
the MV network control capability of 4 provinces what is not negligible. To overcome
this situation in the most efficient manner (technically and economically), each
SCADA could be sized to twice its “normal” capacity so as to take over the control of
the zones connected to the Provincial Telecom concentrators of the lost SCADA.
This solution requires duplicated telecommunication links from each Provincial
Telecom concentrator to Two Major provincial SCADA systems or alternatively to one
Provincial SCADA and the MCC. This latter solution would be easier to implement
(due to the existence of the Fibre optics communication links) but would require
additional routers. Globally, the securisation of SCADA architecture 2 would
represent 25% of the cost of the “basic” depicted architecture.

A2 TASE.2
Scada System (ICCP)

101
MV
SPC
Reclosers
GPRS Main
SS Scada System

Double links TASE.2 TASE.2 TASE.2


(ICCP) (ICCP) (ICCP)

1st SPC 2nd SPC 5th SPC


MV Strategic Strategic Strategic
Reclosers
GPRS GPRS GPRS
Provincial Provincial Provincial
Scada System Scada System Scada System

Telecom Telecom Telecom


104 104 104 104 104
Protocol Protocol Protocol

Provincial RTU RTU RTU Provincial RTU


RTU
RTU Provincial RTU
RTU
RTU
Telecomm Telecomm Telecomm
Concentrator Concentrator Concentrator

104 104 104

RTU RTU RTU

Figure 6 - One SCADA for Strategic Province

7.4.2.1 Control Centre functions


This paragraph analyses the functional impacts of the architecture on the SCADA
system.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 54/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The same general considerations apply as for the previous architecture, i.e.: all the
SCADA manufacturers present on the market master the relevant architecture,
therefore, due to a potential enlarged competition, SCADA costs would be kept at a
low level for each system (SPC will above that beneficiate from a purchase “quantity
effect” that will definitely decrease the individual costs- since all the systems will be
similar). In a first step and due to the fact that only the primary substations and not
the MV network will be remote controlled, the relative “easiness” of control operation
does not require the implementation of elaborated isolation and restoration DMS
functions. However, the return on investment being essentially linked to the MV
network automation level (via remote controlled facilities), SPC will necessarily have
to invest on network automation and consequently on fault location and restoration
functions on the medium-long term. Therefore it is advisable in this case to pre-select
only the bidding manufacturers among those, which might propose these functions,
so as to be sure of their integration possibility.
In addition, Computation function on the network could optionally be implemented so
as to help the operator to build the works and outages reconfiguration schemes more
efficiently. This option will be worth to be firmly requested in order to increase the
performance of control efficiency.
This latter option estimated cost will be around 50,000 USD per Control System site.
In any case, a full description of the MV network operated is worth to be integrated in
the SCADA systems so as:
 To enter in a virtuous circle of data quality improvement that will guarantee the
system sustainability and a global improvement of the Distributor efficiency,
 So as to be sure of the possible management of high quantity of network
descriptive data and guarantee the further integration of the highly demanding
DMS functions in this concern,
So as to improve works management efficiency and further implementation of WFM
(Work Force Management Tools in a near future or as an option in the early
tendering phase)
In addition to the conventional SCADA functions, the efficiency of WFM would also
be achieved via the integration of following functions:
 SMS exchanges with field crews

7.4.2.2 Control Systems characteristics and Sizing,


The same considerations apply as for the previous architecture, i.e.: it is advisable, to
specify a wide integration of standards (IEC, TCP/IP, Linux) within the control
systems architecture so as to ensure its sustainability (this is true for all the various
architectures).
On top of this “basic requirements, the following shall prevail in the hardware and
software architectures:
 Duplicate Ethernet LAN (preferably separated for process and operator
positions)
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 55/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 Linux or eventually Windows (in case the manufacturer proves its perfect
handling of Microsoft OS over a long period of time) servers (or a mix of both)
 Linux or Windows workstations
 2 - 3 monitors (2 as long as the MV network is not automatised; preferably 3
as soon as remote control facilities are implemented on the MV network) per
operator workplace
 Redundant SCADA servers (so as to achieve a “reasonable reliability level
for this type of architecture)
 Standard real time APIs
 Standard CIM interfaces
The specificities of this architecture are as follows:
3 monitors would be preferable in the “Major PLDC” as well as a large screen
(whose size might be over 90 inches) so as to help decision making during crises.
The same (large screen) would apply for the MCC, in this latter case at least 2
screens of this size should preferably be available.
Sizing concerns
Due to the fact that the life expectancy of a control system is around a decade
(10years)-(the life expectancy corresponding to the commonly admitted average
return on investment duration for control systems) the system shall be sized so as to
cover at least the network increase within the next decade with a margin of 50% so
as to ensure good performances throughout the system life.

7.4.2.3 Telecommunication
Compare with the previous architecture, there is not fundamental difference. As
SCADA systems shall not be installed everywhere, the Telecommunication Network
shall take into account the necessary implementation of concentrators to replace the
SCADA Front End.

Exchanges aspects
The Telecommunication Network has to take into account the necessary exchanges
between:
 RTU located in Substation and SCADA systems located in Foreign PLDC
through the concentrator,
 RTU located in Substation and SCADA systems in PLDC,
 SCADA systems located in PLDC and the Main SCADA system located in
SPC Head Office,
 SCADA systems located in PLDC and the SCADA systems located in
neighbour PLDC, to exchange bordering information.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 56/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Protocol Telecom Protocol Speed rate (b/s)


Exchanges between RTU and
IEC60870-5-104 RS-XXX 9,600 min
Concentrators
Exchanges between
Concentrators and Foreign / E1 2,048,000
PLDC SCADA System
Exchanges between RTU and
IEC60870-5-104 RS-XXX 9,600
SCADA in PLDC
Exchanges between SCADA
TASE 2 E1 64,000
in PLDC and Main SCADA
Exchanges between
TASE 2 E1 64,000
neighbour SCADA in PLDC
Table 20 - Necessary Protocols - Architecture 2

7.4.2.4 Economical consideration for the SCADA systems


a) Base system
Investment SCADA Systems Costs
Hardware $100,000
SCADA Software $1 –1.5M
DMS software $0.5-0.7 M
System configuration and project management $0.5-1 M
Total CAPEX $2.15-3.35 M
Operation cost SCADA Systems Costs
Corrective Maintenance over 10 years* $0.5 M
Evolutive Maintenance over 10 years* $1.5 M
Total OPEX $2 M
Grand Total (CAPEX+OPEX) $4.15-5.35 M
Table 21 - SCADA Cost - Architecture 2
* The maintenance contract over a period corresponding to the system life
expectancy is a guarantee of system sustainability and is a must.
Note: That these figures are slightly under the ones given in the inception report.
b) Options
Optional control of devices on the 22kV network:
The following table evaluates the related expenses.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 57/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Investment Amount
Hardware (additional hardware in the control centre induced by $10,000
the reclosers implementation
Adaptation of reclosers to remote control $1.5 -2M
DMS software adaptation dedicated to the use of reclosers $0.1 M
System configuration and project management $0.2 M
Total CAPEX $1.815-2.315 M
Operation cost Amount
No specific OPEX costs have to
be considered compare to the
present situation
Total OPEX $0 M
Grand Total (CAPEX+OPEX) $1.815-2.315 M
Table 22 - MV Option Costs - Architecture 2
Following assumptions have been made:
- Reclosers only shall be remote controlled since most of the LBS are not
motorised.
- 80% of the 795 existing reclosers will be easily adapted to remote control via the
connection of RTUs or SCADA adaptation cards, the 20% left will for some of
them (around 5%) necessitate the replacement of the Control cubicle or the
implementation of specific I/O cards allowing for teleindication retrieval.
- Considering the telecommunication architecture allowing the connection of the
reclosers RTUs or SCADA modules, two alternatives are possible:
1. GPRS the easiest and less expensive one,
2. A mix of GPRS and optic fibre when the F8 network is available in the
vicinity of the Reclosers. In this latter case, the architecture reliability will
slightly increase while the price will considerably increase due to the fact
that it imposes the building of an IP network.
Considering the above, the second alternative has not been taken into account in the
detailed quotation of the alternative

7.4.3 One remote console connected to the main System within each
Province (SCADA Architecture 3)
This architecture corresponds to the “organisation” architectures vi) & vii) depicted in
the previous chapter.
This architecture is fundamentally different from those here above mentioned. Not for
the main SCADA system located into SPC offices but for PLDDs. In fact, this
architecture replaces PLDDs SCADA system with remote consoles (ref. Figure ). In
this case, the SPC SCADA located in head office is supplied by RTU located into all
of 110kV substations under SPC responsibility.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 58/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Due to the essential role of the SCADA system, the securization of this architecture
with a backup system located in another site is a must. The back up system has thus
been included in the basic architecture.

A2 TASE.2
SS 101 (ICCP)
Scada System PLDC

Tcp:Ip
SPC PC2
SPC
Main
Backup Main
Scada System
Scada System Scada System Tcp:Ip PLDC
Tcp:Ip
GPRS
MV PLDC
Reclosers

Tcp:Ip
104 104 104 104

PLDC
RTU RTU RTU RTU

Figure 7 - Remote Console linked to Main SCADA (with its backup)

7.4.3.1 Control Centre functions,


This paragraph analyses the functional impacts of the architecture on the SCADA
system.
Less SCADA manufacturers present on the market master the relevant architecture –
specifically an efficient Web interface fitted with all the necessary securities (access
control, intrusion blocking mechanisms, secured exchanges, etc.) -compared with the
2 previous architectures; since this architecture really correspond to the state of the
art of SCADA systems, therefore, due to a potential reduced competition, SCADA
individual costs would be slightly higher than for the 2 previous architectures without
any possibility for SPC to beneficiate from a purchase “quantity effect”.
The rest of the considerations are kept unchanged, i.e.: in a first step and due to the
fact that only the primary substations and not the MV network will be remote
controlled, the relative “easiness” of control operation does not require the
implementation of elaborated isolation and restoration DMS functions. However, the
return on investment being essentially linked to the MV network automation level (via
remote controlled facilities), SPC will necessarily have to invest on network
automation and consequently on fault location and restoration functions on the
medium-long term. Therefore it is advisable in this case to pre-select only the bidding
manufacturers among those, which might propose these functions, so as to be sure
of their integration possibility.
In addition, Computation function on the network could optionally be implemented so
as to help the operator to build the works and outages reconfiguration schemes more
efficiently. This option will be worth to be firmly requested in order to increase the
performance of control efficiency.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 59/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

This latter option estimated cost will be around 50,000 USD per Control System site.
In any case, a full description of the MV network operated is worth to be integrated in
the SCADA systems so as:
 To enter in a virtuous circle of data quality improvement that will guarantee the
system sustainability and a global improvement of the Distributor efficiency,
 So as to be sure of the possible management of high quantity of network
descriptive data and guarantee the further integration of the highly demanding
DMS functions in this concern,
So as to improve works management efficiency and further implementation of WFM
(Work Force Management) tools in a near future or as an option in the early
tendering phase.
In addition to the conventional SCADA functions, the efficiency of WFM would also
be achieved via the integration of following functions:
 SMS exchanges with field crews

7.4.3.2 Control Systems characteristics and Sizing,


The same considerations apply as for the previous architecture; i.e.: it is advisable, to
specify a wide integration of standards (IEC, TCP/IP, Linux) within the control
systems architecture so as to ensure its sustainability (this is true for all the various
architectures).
On top of this “basic requirements, the following shall prevail in the hardware and
software architectures:
 Duplicate Ethernet LAN (preferably separated for process and operator
positions)
 Linux or eventually Windows (in case the manufacturer proves its perfect
handling of Microsoft OS over a long period of time) servers (or a mix of both)
 Linux or Windows workstations
 2 - 3 monitors (2 as long as the MV network is not automatised; preferably 3
as soon as remote control facilities are implemented on the MV network) per
operator workplace
 Redundant SCADA servers (so as to achieve a “reasonable reliability level
for this type of architecture)
 Standard real time APIs
 Standard CIM interfaces
The specificities of this architecture are as follows:
3 monitors would be preferable in the “MCC” as well as 2 large screens (whose size
might be over 90 inches) so as to help decision making during crises.
Sizing concerns
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 60/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Due to the fact that the life expectancy of a control system is around a decade
(10years)-(the life expectancy corresponding to the commonly admitted average
return on investment duration for control systems) the system shall be sized so as to
cover at least the network increase within the next decade with a margin of 50% so
as to ensure good performances throughout the system life.

7.4.3.3 Telecommunication
Compare with the previous architecture (architecture 2), there is not fundamental
difference. As SCADA shall not be installed in the PLDCs, the Telecommunication
Network shall take into account the necessary implementation of concentrators in
each PLDC. The Telecommunication Network shall take also into account the links
between the SCADA system located in the SPC Head Office and the Remote
Consoles.

Exchanges aspects
The Telecommunication Network has to take into account the necessaries
exchanges between:
 RTU located in substation and the Main SCADA system located in SPC Head
Office,
 Main SCADA system located in SPC Head Office and the Remote Consoles
located in each PLDC.
Protocol Telecom Protocol Speed rate (b/s)
Exchanges between RTU and
IEC60870-5-104 RS-XXX 9,600 min
Concentrators
Exchanges between
Concentrators and Main / E1 2,048,000
SCADA System
Exchanges between Main
SCADA system and Remote TCP/IP E1 2,048,000
Consoles in PLDC
Table 23 - Necessary Protocols - Architecture 3
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 61/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.4.4 Economical consideration for the SCADA systems


a) Basic costs
Investment SCADA Systems Costs
Hardware $90,000
SCADA Software $0.9 –1.4M
DMS software $0.3-0.5 M
System configuration and project management $0.7-1.2 M
Total CAPEX $2-3.2 M
Operation cost SCADA Systems Costs
Corrective Maintenance over 10 years* $0.3 M
Evolutive Maintenance over 10 years* $1.5 M
Total OPEX $1.8 M
Grand Total (CAPEX+OPEX) $3.8-5 M
Table 24 - SCADA Cost - Architecture 3
* The maintenance contract over a period corresponding to the system life
expectancy is a guarantee of system sustainability and is a must.
b) Options
Optional control of devices on the 22kV network:
The following table evaluates the related expenses.
Investment Amount
Hardware (additional hardware in the control centre induced by $10,000
the reclosers implementation
Adaptation of reclosers to remote control $1.5 -2M
DMS software adaptation dedicated to the use of reclosers $0.1 M
System configuration and project management $0.2 M
Total CAPEX $1.81-2.31 M
Operation cost Amount
No specific OPEX costs have to be
considered compare to the present
situation
Total OPEX $0 M
Grand Total (CAPEX+OPEX) $1.81-2.31 M
Table 25 - MV Option Costs - Architecture 3
Following assumptions have been made:
- Reclosers only shall be remote controlled since most of the LBS are not
motorised.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 62/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

- 80% of the 795 existing reclosers will be easily adapted to remote control via the
connection of RTUs or SCADA adaptation cards, the 20% left will for some of
them (around 5%) necessitate the replacement of the Control cubicle or the
implementation of specific I/O cards allowing for teleindication retrieval.
- Considering the telecommunication architecture allowing the connection of the
reclosers RTUs or SCADA modules, two alternatives are possible:
1. GPRS the easiest and less expensive one,
2. A mix of GPRS and optic fibre when the F8 network is available in the
vicinity of the Reclosers. In this latter case, the architecture reliability will
slightly increase while the price will considerably increase due to the fact
that it imposes the building of an IP network.
Considering the above, the second alternative has not been taken into account in the
detailed quotation of the alternative.

7.4.5 One and only one SCADA system within SPC head offices (SCADA
Architecture 4)
This architecture is quite similar the previous one. But in this case, not any remote
console communicates with head office (ref. Figure ). It is the simplest architecture.
Due to the essential role of the SCADA system, the securization of this architecture
with a backup system located in another site is a must. The back up system has thus
been included in the basic architecture. The cost estimation thus reflects this
situation.

PC2
A2 TASE.2
SPC
Main
(ICCP) Main
Scada System Scada System
Scada System MV
GPRS
Reclosers

101

SS 104 104 104 104

RTU RTU RTU RTU

Figure 8 - Only one Main SCADA (with its backup)

7.4.5.1 Control Centre functions


Same considerations as for architecture N°3.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 63/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.4.5.2 Telecommunication

Exchanges aspects
The Telecommunication Network has to take into account the necessary exchanges
between RTU located in Substation and Main SCADA system located in SPC Head
Office. So, only concentrators for the RTU connection shall be installed in each
PLDC.
Protocol Telecom Protocol Speed rate (b/s)
Exchanges between RTU and
IEC60870-5-104 RS-XXX 9,600
Concentrators
Exchanges between
Concentrators and SCADA / E1 2,048,000
System
Table 26 - Necessary Protocols - Architecture 4

7.4.5.3 Economical consideration for the SCADA systems


Investment SCADA Systems Costs
Hardware $70,000
SDADA Software $0.6 –0.9M
DMS software $0.3-0.5 M
System configuration and project management $0.6-1 M
Total CAPEX $1.75-2.65 M
Operation cost SCADA Systems Costs
Corrective Maintenance over 10 years* $0.3 M
Evolutive Maintenance over 10 years* $1.5 M
Total OPEX $1.8 M
Grand Total (CAPEX+OPEX) $3.55-4.45 M
Table 27 - SCADA Cost - Architecture 4
* The maintenance contract over a period corresponding to the system life
expectancy is a guarantee of system sustainability and is a must.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 64/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

b) Options
Optional control of devices on the 22kV network:
The following table evaluates the related expenses.
Investment Amount
Hardware (additional hardware in the control centre induced $5,000
by the reclosers implementation
Adaptation of reclosers to remote control $1.5 –2M
DMS software adaptation dedicated to the use of reclosers $0.1 M
System configuration and project management $0.15 M
Total CAPEX $1.75-2.25 M
Operation cost Amount
No specific OPEX costs have to be
considered compare to the present
situation
Total OPEX $0 M
Grand Total (CAPEX+OPEX) $1.75-2.25 M
Table 28 - MV Option Costs - Architecture 4
Following assumptions have been made:
- Reclosers only shall be remote controlled since most of the LBS are not
motorised
- 80% of the 795 existing reclosers will be easily adapted to remote control via the
connection of RTUs or SCADA adaptation cards, the 20% left will for some of
them (around 5%) necessitate the replacement of the Control cubicle or the
implementation of specific I/O cards allowing for teleindication retrieval.
- Considering the telecommunication architecture allowing the connection of the
reclosers RTUs or SCADA modules, two alternatives are possible:
1. GPRS the easiest and less expensive one,
2. A mix of GPRS and optic fibre when the F8 network is available in the
vicinity of the Reclosers. In this latter case, the architecture reliability will
slightly increase while the price will considerably increase due to the fact
that it imposes the building of an IP network.
Considering the above, the second alternative has not been taken into account in the
detailed quotation of the alternative

7.4.6 Backup system in another location


For both late architectures backup system should be implemented for safety raisons.
This chapter describes functions of such a system with exchange aspects and costs.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 65/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.4.6.1 Control Centre functions


Same considerations as for architecture N°4 (previous depicted one).

7.4.6.2 Telecommunication

Exchanges aspects
The Telecommunication Network has to take into account the necessary exchanges
between RTU located in Substation and Main SCADA system located in SPC Head
Office. So, only concentrators for the RTU connection shall be installed in each
PLDC.
Protocol Telecom Protocol Speed rate (b/s)
Exchanges between RTU and
IEC60870-5-104 RS-XXX 9,600
Concentrators
Exchanges between
Concentrators and SCADA / E1 2,048,000
System
Table 29 - Necessary Protocols - Backup (Architecture 3 and 4)

7.4.6.3 Economical consideration for the SCADA systems


Already included in the global estimations of SCADA architectures 3 and 4

7.4.7 Global comparison of the SCADA architectures


The table bellow analyses the different SCADA architectures
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 66/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

SCADA Advantages Drawbacks Comments/ Appraisal


Architecture
1. one SCADA in - Satisfies all SPC needs in particular - High need in skilled and trained human - Performance of network operation and control: ++
each PLDC and the control facility at the PLDC level resources for setting up PLDCs - control reliability: ++
one SCADA in maintenance teams,
- investment (CAPEX): - - -
SPC HQ - With multiple systems, the global reliability is
- operational costs (OPEX): - - -
lower and the relevant maintenance effort is
higher than with a “concentrated” Global appraisal: - -
architecture

2. one SCADA in - reduced investments vs. architecture 1 - Fair need in skilled and trained human - Performance of network operation and control: ++
Major PLDCs resources for setting up PLDCs - control reliability: +
(4-5) and one maintenance teams,
- investment (CAPEX): - -
SCADA in SPC - high Maintenance effort required
HQ - operational costs (OPEX): - - -
- Lower level of architecture reliability
Global appraisal: -
3. one remote - Low level of maintenance effort - Performance of network operation and control: +++
console - High reliability - control reliability: +++
connected to
- Highly flexible: copes with all types - investment (CAPEX): +++
the main
of control/supervision organisation - operational costs (OPEX): +++
SCADA system
within each Global appraisal: +++
province
4. one & only one - low need in skilled and trained - Does not Satisfies all SPC needs in - Performance of network operation and control: ++
SCADA system human resources for setting up particular the control facility at the PLDC - control reliability: +++
within SPC PLDCs maintenance teams, level
- investment (CAPEX): +++
Head Offices
- operational costs (OPEX): +++
Global appraisal: ++
Table 30 - SCADA Architectures Global Comparison
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 67/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

7.4.8 DMS functions implementation


The following figure gives an overview of the optimum SCADA architecture
(SCADA/DMS software modules and data bases) and for each SCADA modules well
adapted to SPC project context, details the DMS functions whose implementation is
recommended in the basic architecture and those which might be optionally
requested (due to lower encountered benefit or lower ratio benefit/cost).

DMS functions

Figure 9 - DMS Functions

Legend: DMS function to be implemented in SPC base system

 DMS function to be optionally requested


WFM: Work Force Management
OMS: Outage Management System
IVR: Automatic Answering Machine
FLISR: Fault Location, Isolation and Supply Restoration
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 68/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8 Telecommunications
8.1 Telecommunication Network between PLDCs and SPC Head Office
As described in the previous chapter, whatever the selected SCADA architecture, the
RTU shall be connected to the PLDC and/or HVGB sites with optical fibre.
Depending on the selected SCADA architecture, it shall be necessary to connect the
RTU and/or the Provincial SCADA systems to the Main SCADA system located in
SPC Head office, as shown below:
SPC
Main
Scada System

Private Network or Leased links Network

SPC
PC2
PC
PC22
Provincial
Provincial
Provincial
ScadaProvincial
Scada System
System
Scada
ScadaSystem
System

Optical Fibres (ADSS or F8 technology)

SS SS SS SS

Figure 10 – General Operational Telecommunication architecture


Depending on the selected SCADA architecture, the needed telecommunication links
and equipment between each PLDC and the SPC Head Office will be different:
 Concentrators in each PLDC if not any SCADA systems is installed,
 Large bandwidth links (2 Mbit/s) for the Remote Consoles if any,
 Small bandwidth links (64 Kbit/s) for the exchanges between SCADA systems.
Depending on the SPC selected SCADA architecture, the needed links will be the
following:
Links (64Kb/s) Links (2 Mbits/s) Concentrator
YES (1 or more,
Architecture 1 according to the NO NO
bordering SCADA)
YES (1 or more, YES (1 for the
Architecture 2 according to the NO PLDC without
bordering SCADA) SCADA system)
Architecture 3 NO YES (1) YES (1)
Architecture 4 NO NO YES (1)
Table 31 - Necessary Links depending on the different Architectures
To build this Operational Network, two alternatives are possible by:
 Using leased links from a Telecommunication Operator,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 69/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 Building a SPC private Network.


Hereafter, the two alternatives are described and compared.

8.1.1 Network based on leased links


This solution consists in renting leased links from a Telecommunication Operator. In
this solution, the main advantages are the limited investment and the facility to
spread out the Network.
As A2 is also using Telecommunication Operator services to build its links between
RTU and the SCADA system located in Ho Chi Minh, the Telecommunication
Operator must certify that the A2 and SPC links do not have mutual paths in order to
guarantee the backup between the A2 and SPC SCADA systems.

8.1.2 SPC SDH Network


This solution will consist for SPC to build its own Telecommunication Network, based
on SDH technology.
In this solution, the main advantages are the optimisation of the SPC investments
and of the SPC staff skilled expertise.
As A2 is using Telecommunication Operator services to build its links between RTU
and the SCADA system located in Ho Chi Minh, SPC is able to guarantee the
separate paths for the connection links between the different parts of its
Telecommunication architecture and so, to guarantee the back-up with the A2
system.
To build the SPC SDH Network, it is necessary to install:
 Optical fibres between Provinces and SPC Head Office,
 A SDH equipment and Concentrator in each PLDC or HVGB site,
 A SDH equipment and Concentrators in the SPC Head Office and in the Back-
up site,
That is shown hereafter:

SPC Head Office


SDH equipments
Consentrators

Loop or Double Loop or Double Loop or Double


links links links
( SDH) ( SDH) ( SDH )

1 st PLDC 2 th PLDC 21 th PLDC


SDH equipment & SDH equipment & SDH equipment &
Concentrators Concentrators Concentrators

Figure 11 – SDH architecture


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 70/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Optical fibre
As only a few optical fibers currently exist, it shall be necessary to install new optical
fibers in order to build the optical fibre Backbone between all PLDCs or HVGBs and
the SPC Head Office Control Center and Control Center Backup site.
Hereafter, the SPC optical fibre backbone is draft:
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 71/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Figure 12 - SPC Optical Fibre Backbone


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 72/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

These optical fibres have to be installed as described hereafter:


No. Province Quantity (km)
1 CA MAU - BAC LIEU 73.00
2 BAC LIEU - SOC TRANG 45.00
3 SOC TRANG - HAU GIANG 28.00
4 HAU GIANG - CAN THO 25.00
5 CAN THO - AN GIANG 98.11
6 AN GIANG - KIEN GIANG 69.27
7 KIEN GIANG - HAU GIANG 54.19
8 HAU GIANG - CA MAU 102.50
9 CAN THO - VINH LONG 15.00
10 VINH LONG - DONG THAP 17.00
11 VINH LONG - TRA VINH 68.00
12 VINH LONG - TRA VINH 2 36.00
13 DONG THAP - TIEN GIANG 83.70
14 TIEN GIANG - LONG AN 33.00
15 LONG AN - TPHCM 43.00
16 TPHCM - DONG NAI 1 32.05
17 TPHCM - DONG NAI 2 43.20
18 DONG NAI - LAM DONG 299.20
19 LAM DONG - NINH THUAN 74.91
20 NINH THUAN - BINH THUAN 127.10
21 BINH THUAN - VUNG TAU 143.49
22 VUNG TAU - DONG NAI 65.66
23 TPHCM - BINH DUONG 49.05
24 BINH DUONG - TAY NINH 35.72
25 TAY NINH - BINH PHUOC 150.30
Total 1,811

Table 32 – Regional missing Optical Fibre for SDH network


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 73/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Some of these optical fibers shall be installed under ongoing projects as described
hereafter:

Quantity
No. Province From To
(Km)
110kV Ca Mau s/s 110kV Gia Rai s/s 34
1 BAC LIEU - CA MAU
110kV Gia Rai s/s 110kV Bac Lieu s/s 39
BAC LIEU - SOC
2
TRANG 110kV Bac Lieu s/s 110kV Soc Trang s/s 45
SOC TRANG - HAU 110kV Soc Trang
3
GIANG s/s 110kV Phung Hiep s/s 28
HAU GIANG - CAN 110kV Phung Hiep
4
THO s/s 110kV Hung Phu s/s 25
110kV Hung Phu s/s 110kV Can Tho s/s 15
110kV Can Tho s/s 110kV Long Hoa s/s 7
110kV Long Hoa s/s 110kV Tra Noc s/s 18
O Mon Power 110kV Dai PT Nam Bo
5 CAN THO - AN GIANG
factory s/s 12
110kV Dai PT Nam
Bo s/s Thot Not 2 s/s 14
Thot Not 2 s/s 110kV Long Xuyen s/s 22
6 HAU GIANG - CA MAU 220kV Ca Mau s/s 110kV Ca Mau s/s 15
CAN THO - VINH PC Can Tho city Can Tho bridge 5
7
LONG Can Tho bridge PC Vinh Long 5
VINH LONG - TRA TBA 110kV Vung Liem
8
VINH 110kV Vinh Long s/s s/s 24
VINH LONG - TRA
9
VINH 2 110kV Binh Minh s/s 110kV Cau Ke s/s 36
10 DONG THAP - TIEN 110kV Cao Lanh s/s Cao Lanh 2 s/s 3
GIANG Cao Lanh 2 s/s 110kV My Thuan s/s 27
TIEN GIANG - LONG
11
AN My Tho 2 s/s 110kV Tan An s/s 33
12 LONG AN - TP.HCM 110kV Tan An s/s 500 kV Phu Lam s/s 28
220kV Long Binh s/s 110kV Ho Nai s/s 8
Dam Ri hydropower 110kV Bao Loc s/s 27
13 DONG NAI - LAM 110kV Bao Loc s/s 110kV Di Linh s/s 30
DONG 110kV Di Linh s/s 110kV Duc Trong s/s 41
110kV Duc Trong
s/s 110kV Da Lat 1 s/s 30
110kV Phan Thiet 110kV Thuan Nam s/s 27
BINH THUAN - BA RIA 110kV Thuan Nam
14
VUNG TAU s/s 110kV Ham Tan s/s 34
110kV Ham Tan s/s 110kV Xuyen Moc s/s 24
Total 657
Table 33 – Installed Optical Fiber through ongoing projectsfor SDH network
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 74/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Thus, the global quantity of optical fiber to be installed shall be around 1154 kms as
described below:

Annex 3B Global quantity of missing optical fiber


No. Province Quantity (km)
1 CAN THO - AN GIANG 10.11
2 AN GIANG - KIEN GIANG 69.27
3 KIEN GIANG - HAU GIANG 54.19
4 HAU GIANG - CA MAU 87.50
5 CAN THO - VINH LONG 5.00
6 VINH LONG - DONG THAP 15.00
7 VINH LONG - TRA VINH 44.00
8 DONG THAP - TIEN GIANG 53.70
9 LONG AN - TPHCM 15.00
10 TPHCM - DONG NAI 1 32.05
11 TPHCM - DONG NAI 2 43.20
12 DONG NAI - LAM DONG 164.20
13 LAM DONG - NINH THUAN 74.91
14 NINH THUAN - BINH THUAN 127.10
15 BINH THUAN - VUNG TAU 58.49
16 VUNG TAU - DONG NAI 65.66
17 TPHCM - BINH DUONG 49.05
18 BINH DUONG - TAY NINH 35.72
19 TAY NINH - BINH PHUOC 150.30
Total 1,154
Table 34 – Total Missing Optical Fiber SDH network

The investment will be the following:

Optical Fiber (ADSS technology)


Unit Price ($) 1700 per kilometer
Quantity of optical fiber 1154
Total ($) 1,960,000
Table 35 – Regional Optical Fiber investment
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 75/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

SDH equipment
According to the needed bandwidth in each SCADA architecture (a maximum of 4
Mbit/sec for the Remote Consoles architecture), a STM-1 (155 Mbit/sec) technology
is sufficient.
Besides, the needs for operationa land corporate Telecommunication Networks from
the IT Department has also to be taken into account, thus:
 STM-4 (622 Mb/s) will be used between PLDCs or HVGBs & SPC Controls
Centers and A2 Control Center,
 STM-16 (2,5 Gb/s) will be used between SPC Controls Centers (Main &
Backup).

A Telecommunication Management Network (TMN) has also to be installed in order


to provide:
 Configuration,
 Control and Supervision,
 Alarms management,
 Handling of information,
 Logging and maintenance hardware,
 Logging and maintenance software.
The total investment will be the following:
SDH STM – 16
SDH STM – 4 (including
(including TMN
Multiplexor)
Multiplexor)
Number 22 2 1
Cost ($) 65,000 100,000 120,000
Subtotal 1,430,000 200,000 120,000
Total ($) 1,750,000
Table 36 - Total Investment for SDH network

8.1.3 Return of investment calculation for SCADA Telecommunication


Network only
Note: This calculation does not take into account the earnings on the Corporate
Network.
For the calculation of return on investment, we consider that the costs of:
 Annual maintenance contracts,
 Telecommunications maintenance staff.
That represents 10 % of the total telecommunications investments: 170,000 $.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 76/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

According to the selected SCADA architecture, the return on investment will be the
following:
Full optical fibres Backbone:

Private SDH Network Leased Links


Return on investment
(Optical Fiber + SDH equipment)
10,500,000 870,000 12.15 years (impossible)
Table 37 - Full optical fibres Backbone (Corporate needs not considered)
Note: * these prices are the costs of leasing links from HCM PC

8.1.4 Return of investment calculation for Operational and Corporate


Telecommunications Networks
Note: This calculation takes into account the annual Corporate Network costs,
which will be an average of 100 E1 for the next 10 years for the lump sum
of 2.000.000 $ per year.
For the calculation of return on investment, we consider that the costs of:
 Annual maintenance contracts,
 Telecommunications maintenance staff,
That represents 10 % of the total telecommunications investments: 170.000 $.
According to the selected SCADA architecture, the return on investment will be the
following:
Full optical fibres Backbone:

Private SDH Network Leased Links Return on


(Optical Fiber + SDH equipment) investment
10,500,000 2,870,000 3.7 years
Table 38 - Full optical fibres Backbone (Corporate needs considered)
Note 1: * these prices are the costs of leasing links from HCM PC
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 77/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8.2 Telecommunication Options


It is a matter of fact that the main purpose of this study is to build an Operational
Telecommunication Network for the remote control but, taking into account our
experience in the Telecontrol field and the possibilities offered by the large bandwidth
of the optical fibre used, some options can also be suggested:
 Operational Telephone Network,
 Video-surveillance,
 Tele-metering,
 Electricity Quality Monitoring,
 …

8.2.1 Operational Telephone Network:


To secure and optimise the phone communications between the Telecontrol sites
(substations, PLDC, SPC Main SCADA), direct phone lines shall be installed. These
direct phone lines shall be connected on specific PAX and shall be strictly reserved
for operational communications.
According to the SPC SCADA selected architecture, the number of PAX to be
installed will change from one (1), located in the SPC Head office to twenty one (21),
One in the SPC Head Office and one in each of the twenty PLDC.
A dedicated phone of this operational telephone network will be installed in each
substation and another one near each Dispatcher SCADA workstation, to allow
phone calls in case of out of order of the RTU or of out of order of High Voltage
devices.
As this Operational telephone network shall be clearly separated from the SPC
Corporate telephone network, you shall always be sure to establish a call
communication between the Dispatching(s) and with the substations.
A voice recorder is often associated to this operational phone network and is used to
determine, for example, the reason of false operation following a phone order on the
electrical network.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 78/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8.2.2 Video Monitoring System


As almost substations will be in a next time without operators, it could be interesting
to keep watch on these sites. A solution is to install a Video Monitoring System in a
dedicated site and cameras on strategic points of each substation.
The Video Monitoring System shall fulfil with the following main objectives of:
 To enable monitoring of substations assets from remote,
 To monitor all the major equipment in the switchyard,
 To monitor the entry/exit at the main gate, Control Room and switchyard gates
of the substation,
 To get an alarm in case of an event, motion detection,
 User definable hierarchal control,
 Monitor and control of the entire VMS including client/licenses from remote
assets management centres,
 To enable live, near real time viewing, recording of images of all selected
cameras,
 The recording of the cameras will be a local substation level. The operator at
Control Center shall, on demand, be capable of viewing live streaming as well
as recorded at remote end,
 To monitor the switchyard patrolling by Security Guards

8.2.3 Tele-metering
As it is possible to download the data from all new equipment (protection,
metering…), it would be interesting to have dedicated and secured lines for these
operations.
Presently, all new protection devices allow the transfer of data to specific servers for
analysis, for example.
It is the same for all metering equipment.

8.2.4 Electricity Quality Monitoring


To monitor the Voltage sacks and Harmonics, it is very interesting to download the
files issued from the protections.

8.2.5 Technical solutions:


To provide the necessary links for these options, different solutions are available:
 Electrical/optical converters for each application,
 Concentrators (Mux),
 TCP/IP network,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 79/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8.2.5.1 Electrical/optical converters


Optical/electrical converters can be used for video-surveillance and telemetering but
not for the phone.
A phone has specific needs: 48 V DC to be energized, 80 VAC for the ring and to
establish a call. Some information as the dial has also to be transmitted to the PAX.
Presently, we do not know phone dedicated interface converter on optical fibre.
If SPC chooses to install only video-surveillance and/or telemetering, it will be
possible to install only optical/electrical converters. In this case, the cost will
decrease a lot:

Tele-metering
Video-surveillance
(1 per substation)
Number 104 104
Cost ($) 1,000 1,000
Total ($) 104,000 104,000
Table 39 - Video Surveillance and Telemetering Costs
The cost is given for only a Tele-metering link. If SPC will need more links, additional
optical/electrical converter will be installed.
With this solution (optical/electrical converter), the main disadvantage is the use of 2
fibres of the optical cable for each application: According to the number of fibre in the
optical cable in each substation, you will saturate the optical cable for applications,
which do not need high bandwidth.

8.2.5.2 Multiplexors
In this architecture, a multiplexor is installed in each Substation and each HVGB.
Furthermore, this equipment allows the connection, through the adapted interface
card of different applications:
 Phone interface,
 Ethernet interface,
 RS XXX interface
 ….
These multiplexors are directly connected on the SDH equipment located in the
PLDC. The investment would be the following:
Multiplexor
Number 124
Cost ($) 30,000
Total ($) 3,720,000
Table 40 - Multiplexor Cost
In this architecture, SPC will have only a SDH Network with:
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 80/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 SDH equipment with integrated Multiplexor in each SCADA and PLDC sites,
 Remote Multiplexor of the SDH Network in each Substation and HVGB,
The main advantage of this solution is to have only a Telecommunication Network for
all Operational and Corporate needs. Indeed, this technology implies the following:
 guarantees the critical time transmission delay,
 offers a high quality of service (QoS), suitable for Utilities Telecommunication
needs,
 offers sufficient flows for Utilities Telecommunication needs,
 offers administration facilities,
 offers flexibility for the evolution of the network with future projects,
 is a skilfully technology, used for more than 15 years,
 has a continuity of manufacturing spare parts for more than 20 years by a lot
of telecommunication manufacturers.
The main disadvantage of this solution, except the high cost, is that more and more
applications are based on TCP/IP protocol for Operational needs (for Corporate
needs, all are based on TCP/IP protocol). Thus, we will have to add switches and
perhaps Routers in each Substations and this architecture will be very similar to the
proposed architecture with Routers.
Another disadvantage of this solution is that, for few applications to be connected, we
will install a multiplexor with at minima 30 X 64kb/s channels in each Substation and
HVGB.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 81/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8.2.5.3 TCP/IP Network


A. IP Presentation
The main goal of network layer (the layer 3 of the OSI model) is to route the
data through the network.
Presently, the protocol use in the whole world is the Internet Protocol (IP).
The Internet Protocol (IP) is a data-oriented protocol used for communicating
data in a packet-switched network. It is a connectionless protocol. (each
packet of data is transferred independently into the network).
Data issued from an upper layer protocol are encapsulated inside packets with
the addresses of the sender and the receiver and go into the network, which is
composed of different kinds of links and routers.
The principal advantage of the Internet Protocol is that this protocol can be
used over a heterogeneous network (Ethernet, Wi-Fi, Token-ring, ATM…) and
it makes no difference for the upper layers.
IP provides a connectionless (or unreliable) service: IP is a “best effort”
delivery. This means that the network makes no guarantees about the packet
and none, some, or all of the following may apply:
 Data corruption,
 Out of order delivery (Given packet A is sent before packet B but packet
B can arrive before packet A),
 Duplicate arrival,
 Lost or dropped/discarded packages.
In terms of reliability, the only thing IP does is ensuring the IP packet’s header
is error free through the use of a checksum. This had the side effect of
discarding packets with bad headers on the spot, and with no required
notification to either end.
To address any of these reliability issues, an upper layer must handle it. For
example, to ensure in-order delivery the upper layer may have to buffer data
until it can be passed up in order.
The most used is TCP (Transport Control Protocol).
To route the data in the network, all terminal equipment need an IP address.
In an IP network, the equipment in charge of routing the data is a router.
A router is a computer with a wide variety of LAN (Local Area Network) and
WAN (Wide Area Network) port technologies or other connections that are
customisable.
Routers connect two or more logical subnets, which do not necessarily map
one-to-one to the physical interfaces of the router.
To route the data in the network, the routers needs a routing table. This
routing table could be static, dynamic, or a mix.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 82/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Often, the construction of the routing table is made from knowledge of the
up/down status of its local interfaces, from hard-coded static-routes and from
exchanging routing protocol information (Open Short Path First, for example)
with other routers. Routers do maintain state on the routes in the routing table
but not on individual packets that have been forwarded. The principle of the
router is “transfer the packets and forget them”.
To connect all applications installed in the substations to the PLDC and the
SPC Head Office, another solution is to use the TCP/IP protocol. This protocol
allows the merging of all applications installed in the substations.
If the applications installed in the substations are not natively working in
TCP/IP protocol, it is possible to install gateway.
To build a TCP/IP Network, it is necessary to install Routers over the
Transmission Network (SDH Network in our case).
A Router will be installed, at minimum, in:
 Each SCADA site (MCC and Back-up),
 Each PLDC,
 Some PLDC and Substations, according to the optical architecture.
The sizing of the Routers will depends of the location site.
The number of Gateway to be installed in each SCADA site will depend of the
security level SPC needs.
Concentrators (Switch) will be installed in each site and their number will
depend of the capacity of the provider’s equipment and also of the security
level SPC needs.
Gateway will be installed in each Substation for RTU and their number will
depend of the capacity of the provider’s equipment and also of the security
level SPC needs.
A Router Management and Administration server has to be installed to monitor
and administrate the Routers.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 83/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

To SPC

OF

Router or Converter

Switch

To A2

Gateway 1

101 104
PC ( intranet local
3U access)
Video Telemetering
RTU Telephone Surveillance Quality monitoring

Figure 11 - TCP/IP Substation Architecture


The Gateway 1 is in charge to provide the interfaces signals and to energize the
phone handset and to convert analogue/digital voice signal.
To SPC

PLDC
SDH Equipment

Router

Switch HVGB

Router or Router or
Converter Converter

SS SS

Figure 12 - TCP/IP PLDC Architecture


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 84/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

To
SCADA Front-end

Gateway - Telemetering Server


IP PAX
104 – TCP/IP - Quality monitoring Server

To PLDC
Switch
HVGB
Router or Converter

Switch Router Router

Gateway

Telephone SDH
Equipment

Figure 13 - TCP/IP HVGB Sites Figure 14 - TCP/IP SCADA Sites Architecture


Architecture

As the applications to be connected are not high in Substations and HVGB, this
solution is efficient. The SDH technology with its advantages (ref. chapter 8.2.5.2 -
Multiplexors) will be used for the Backbone (links between PLDC and SCADA sites).
The main advantages of this solution are the cost and the possibility to connect
immediately all applications using the TCP/IP protocol. As now and in the future,
more and more applications natively proposed this protocol on ETHERNET LAN, this
architecture is adapted to the SPC needs. The estimated cost of the TCP/IP Network
will be the following:
Router Gateway Switch TMN
Number 90 124 + (30) 124 + (60) 1
Cost ($) 3,000 400 1,000 120,000
Total ($) 270,000 70,000 184,000 120,000
Lump Sum ($) 650.000
Table 41 - TCP/IP network Costs
Remarks: In this solution, the cost of an operational phone network could be
estimated to 100.000 $, including:
 An IP PAX in each SCADA site,
 A call recorder in each SCADA site,
 A phone (with its gateway if classical phones are provided) in each substation,
each HVGB and in the maintenance sites,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 85/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8.2.6 Options comparison


According to the fact that the use of Electrical/optical converters is not a good
solution because it does not allow the connection of phone system in the substations
and will saturate the optical fibre cable if more applications will be deployed, the
comparison is limited to the Mux and TCP/IP network:

Multiplexor TCP/IP Network


Cost ($) 3,720,000 650,000
Table 42 - Comparison costs between Multiplexor and TCP/IP Network

8.2.7 Return of investment comparison for a SDH Telecommunications


Network with multiplexors and a TCP/IP Telecommunications Network
For the calculation of return on investment, we consider that the costs of:
 Annual maintenance contracts,
 Telecommunications maintenance staff,
That represents 10 % of the total telecommunications investments:
 170,000 $ for the SDH Network,
 372,000 $ for the Mux equipment,
 65,000 $ for the TCP/IP equipment,

 Return of Investment for an SDH Operational and Corporate Network with


multiplexors:

Private SDH Network Leased Links


Return on investment
(Optical Fiber + SDH equipment + Mux)
14,200,000 2,870,000 5 years
Table 43 - Return of Investment for SDH Operational and Corporate network based on Multiplexor
Note 1: * these prices are the costs of leasing links from HCM PC

 Return of Investment for a TCP/IP Operational and Corporate Network:

Private SDH Network Leased Links


Return on investment
(Optical Fiber + SDH equipment)
11,100,000 2,870,000 3.9 years
Table 44 - Return of Investment for SDH Operational and Corporate network based on TCP/IP
Note 1: * these prices are the costs of leasing links from HCM PC
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 86/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8.2.8 New Substations Connection to A2 through SDH Network

Rather direct optical fiber links between the 26 SPC substations and the critical A2
substations, it is possible to use the SPC SDH Network to connect these mentioned
substations to the A2 SCADA. This solution consists in installing aSDH Equipment in
the A2 Control Center premises as shown below.

In this case, the investment is the following:

SDH STM – 4
(including Router/Firewall Swith Gateway
Multiplexor)
Number 1 2 2 4
Cost ($) 65,000 3,000 1,000 1,000
Subtotal 65,000 6,000 2,000 4,000
Total ($) 77,000
Table 45 – 26 Substations connection to A2

The table below give the comparison costs between the 2 solutions to connect the 26
substations to A2 Control Center:

Optical Fiber SDH Network


Cost ($) 778,700 77,000
Table 46 – Comparison costs for connection to A2
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 87/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Telephone

SCADA Front End TMS


SCADA Front End *
PAX

Gateway IP/101
Gateway IP/101

Switchs
Switchs
Routers Firewall

SPC SCADA Sites


Routers Firewall A2 SCADA Site

GPS
SDH NETWORK

HVGB Router orConverter

Switch
PLDC Routers Firewall
Router or
Converter
Operator Telephone
Workstation
Switch
Router or
Converter
Operator Video-
Workstation Surveillance
Router or
Converter Substation
Telephone

Switch

Video-Surveillance
Vide
Tele-Metering
Telephone

Gateway IP/101 A2 Gateway IP/101 SPC

RTU

Figure 15 – A2 & SPC SCADA Sites Architecture


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 88/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

9 Training
9.1 Principles
The training can be divided into two separate parts: operating and maintenance. The
operating training allows learning how to operate an electrical network throw a
SCADA system. The maintenance training allows learning how to install, to configure
and to maintain SCADA, Telecommunication and Telecontrol equipments.
Generally speaking SCADA manufacturers propose these 2 kinds of training.

9.1.1 Staff requirements


SPC’s personnel chosen to operate the electrical grid or to maintain SCADA,
telecommunication or telecontrol equipments should have a Bachelor or a Master of
Science or an equivalent.

9.1.2 Operating training


To operate an electrical network requires having some scientist bases, electrical
skills are not compulsory. Thus, SPC’s personnel shall be chosen beyond those with
such a background.

9.1.3 Maintenance training


Technologically speaking, SCADA systems, telecontrol or telecommunication
equipments today are closer and closer. All of them use computer system.
Consequently, SPC’s personnel shall be chosen, in preference order, with the
following education:
1. Industrial computing
2. Electronic,
3. Electrotechnic.

9.2 Maintenance training


9.2.1 General
The training should comprise in both theoretical and practical training courses and
allow trainees to:
 detect failures and repair by detecting failing cards and replacing with spare
cards (SCADA, telecommunication equipments or RTUs),
 perform routine maintenance on substations equipment (DC systems,
acquisition and transducers, etc.),
 further integrate in the SCADA system (hardware and software) new facilities
required by development of the power system e.g.:
 modification of data base,
 generation of VDU image/display and reports,
 modification of data routing,
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 89/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 addition of complete RTU and of all new interfacing equipment in


substations,
 addition of localised modules to the SCADA application.
As particularly concerns SCADA, manufacturers should provide software training
courses that enable SPC's software staff to be self-sufficient to maintain the SCADA
software. They should be as follows.

Software administration
This course should include training in:
1. Software backup and restoration procedures.
2. Modifying, testing, and installing application software in the real-time
environment.
3. Installing software updates provided by the manufacturer or third party
software suppliers.
4. Using the software configuration management tools.
5. Maintaining and archiving software source code.
6. Maintaining software and database documentation.

Database, Displays and Reports


This course should cover generation and maintenance of the database, displays and
reports. It should include:
1. The understanding of the SCADA database structure and the software
required for database generation and modification.
2. The handling of procedures for database generation and maintenance,
including those for adding, deleting, and modifying points, point types, RTUs,
communication links to remote data sources, data tables, and power system
model components. The course shall also cover database organization for
application data.

Programming
This course should cover programming, assembling, compiling, editing, debugging,
testing, integrating, and documenting programs, subroutines, and I/O handlers
written in all programming languages supplied with the SCADA.

Application Software
Courses should provide in depth training on the design and operation of all SCADA
application programs, including data acquisition, data exchange, data processing,
user interface, electric system monitoring and supervisory control and all special
applications.
Also, this course should include a detailed discussion of each application program, a
detailed description of its uses and capabilities, input and output data parameter.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 90/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

System Hardware
The courses should provide hardware personal with a theoretical background and
hands-on experience in installation, preventing maintenance, troubleshooting, repair,
and expansion procedures.

General
Manufacturers should supply all the required documents: texts, diagrams, schemes,
description of the operation of circuits, etc.
Manufacturers should also suggest on-the-job training at their factory (outside
Vietnam) for system software, DMS applications and databases. Such on-the-job
training should consist in the inclusion of some of the SPC’s software Engineers in
the manufacturer’s development team for a period of several months, so as to enable
them to get the software maintenance skills described above.
On-the-job training is normally provided all along the various stages of the
construction of the database on site, through the active participation of Engineers in
the process.
In the same idea, other subjects as SCADA hardware and all other systems should
be a possible on-the-job training session during installation and commissioning of
equipment.

9.2.2 Contents of the courses


The following table provides an assessment regarding the duration of the training
sessions.
Training course Duration weeks
SCADA hardware maintenance 1
DMS applications and software:
 data bases management, 4
 SCADA application. 4
Substation equipment:
 RTU, 4
 interfacing equipment,
 power supplies.
Maintenance overview for Managers 2
Table 47 - Training Duration Assessment for Hardware

9.2.3 Specific telecommunication and telecontrol training


Regarding telecommunication and telecontrol, manufacturers’ courses proposal
should include the following:

9.2.3.1 Telecommunication
 Specific telecommunication needs for Electrical Grid.
 Optical Fibre.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 91/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 SDH and PDH multiplexing equipments and compliance.


 TCP/IP equipment (router, switch, gateway, firewall, ...)
 Telecontrol, teleprotection and telephone aspects

9.2.3.2 Telecontrol
 Operating management (local/remote),
 Protocol choice (which protocol for which context),
 Standard protocols (103, 101, 104, TASE.2…),
 Interoperability,
 Teleinformation (types, using…),

9.3 Operation training

9.3.1 General
The operation training allows operators to be able to:
 use a modern Control Centre for the operation of a electrical network,
 manage particularities of the control system delivered in the scope of the
contract.

9.3.2 Contents of the courses

9.3.2.1 Courses and visits


This part of the training is aimed at familiarising the operation staff to the varied
equipment they will use when operating the new control system, SCADA as well as
DMS functions. Manufacturer can also suggest visits at power utilities in order to give
to the operators more comprehensive understanding of the use of the system.

9.3.2.2 On-site training


In addition to the previous training, sufficient additional courses should be organised
on site, mainly regarding the use of Distribution Management System.

9.3.2.3 Estimation of the number of Manager, Engineers and technician

Operating
If the SPC operating organisation leads to have 40 local Control Centres (20 PLDCs
and 20 HVGBs) with on-shift organisation for each of them, then the number of
managers, engineers and technicians for 1 Control could be:
 21 on-shift operators,
 6 off-shift operators (planned operating tasks, post-mortem analysis…),
 4 managers (3 for on-shift teams, 1 for off-shift team).
Note: off-shift operators are considered only for Head Office where the SCADA
is located.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 92/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Maintenance
Regarding the number of manager, engineer and technician for maintenance, the
SCADA system will need: 4 engineers or technicians, 1 manager. Into Provinces to
maintain substations equipments it is estimated that 20 engineers or technicians and
5 managers should be enough.

9.3.2.4 Summary
The following table provides an assessment regarding the duration of the training
sessions.
Group Training site Duration weeks
On-line Operators Contractor's workshops 2
Off-line Operators “ 4
Instructor (DTS)* “ 1
Managers “ 2
On-line Operators On site 3
Off-line Operators “ 3
Instructor (DTS)* “ 1
Managers “ 2
Table 48 - Duration Training Assessment for Operating
* Note: the Instructor is one of the 4 off-line operators. He/she shall have previously
followed the off-line operators courses.

9.3.2.5 Estimation
Considering the previous data, the table here after indicate how many people should
be trained considering the future SPC organisation.
Operating Maintenance Total
Head Office Managers 3 1 4
Engineer or Technician 21 6 27
PLDC and HVGB Managers 120 4 124
Engineer or Technician 840 16 856
Total 1011
Table 49 - Staff to be trained
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 93/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

10 Summary COST – ESTIMATES


10.1 Adaptations works and Telecontrol

Option 1 - Substations not already equipped (Mini-SCADA not taken into


account).

110kV 22/35kV Total


RTU (USD) 394 069 794 646 1 188 715
Adaptation Works (USD) 1 297 534 4 688 846 5,986,380
Total (USD) 7,175,095

Option 2 – Substations not already equipped (Mini-SCADA taken into account).

110kV 22/35kV Total


RTU (USD) 394 069 763 481 1,157,550
Adaptation Works (USD) 1 297 534 4 493 713 5,791,247
Total (USD) 6,948,997

10.2 SCADA

10.2.1 Artchitecture 1 (One SCADA system per Province)

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 11.2 M
Operation cost SCADA Systems Costs
Total OPEX USD 4 M
Grand Total (CAPEX+OPEX) (maximum) USD 15.2 M


 Optional control of devices on the 22kV network
Investment SCADA Systems Costs
Total CAPEX (maximum) USD 2.415 M
Operation cost SCADA Systems Costs
Total OPEX USD 0 M
Grand Total (CAPEX+OPEX) (maximum) USD 2.415 M
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 94/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

10.2.2 Architecture 2 (One SCADA system in some strategic Provinces)

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 3.35 M
Operation cost SCADA Systems Costs
Total OPEX USD 2 M
Grand Total (CAPEX+OPEX) (maximum) USD 5.35 M

 Optional control of devices on the 22kV network

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 2.315 M
Operation cost SCADA Systems Costs
Total OPEX USD 0 M
Grand Total (CAPEX+OPEX) (maximum) USD 2.315 M

10.2.3 Architecture 3 (One remote console connected to main System within


each Province)

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 3.2 M
Operation cost SCADA Systems Costs
Total OPEX USD 1.8 M
Grand Total (CAPEX+OPEX) (maximum) USD 5 M

 Optional control of devices on the 22kV network

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 2.31 M
Operation cost SCADA Systems Costs
Total OPEX USD 0 M
Grand Total (CAPEX+OPEX) (maximum) USD 2.31 M
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 95/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

10.2.4 Architecture 4 (One and only one SCADA system within SPC head
offices)

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 2.65 M
Operation cost SCADA Systems Costs
Total OPEX USD 1.8 M
Grand Total (CAPEX+OPEX) (maximum) USD 4.45 M

 Optional control of devices on the 22kV network

Investment SCADA Systems Costs


Total CAPEX (maximum) USD 2.25 M
Operation cost SCADA Systems Costs
Total OPEX USD 0 M
Grand Total (CAPEX+OPEX) (maximum) USD 2.25 M
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 96/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

10.3 Telecommunication with A2 connection by Optical Fiber

 The estimated cost of optical fiber between substations, HVGBs & PLDCs will
be the following:

Optical Fiber (F8 technology)


Unit Price 1400 per kilometer
Quantity of optical fiber 4565
Total ($) 6,391,000

 The estimated cost of optical fiber installation in Substations, PLDC & HVGB
will be the following:

Cabinet (42U) Manpower (per SS)


Unit Price 1000 250
Substations, HVGB & 144 144
PLDC
Sub Total 144,000 36,000
Total ($) 180.000

 The estimated cost of optical fiber terminal equipment will be the following:

Optical/Electrical Manpower (per


Converter link)

Unit Price 1000 100


Substations, HVGB & 250 125
PLDC
Sub Total 250,000 12,500
Total ($) 262,500

 The estimated cost of optical fiber between 26 Substations and A2 Control


Center will be the following:

Optical Fiber (ADSS technology)


Unit Price 1700 per kilometer
Quantity of optical fiber 427
Total ($) 725,900


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 97/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 The estimated cost of optical fiber terminal equipment for the A2 connection of
26 Substations will be the following:

Optical/Electrical Manpower (per


Converter link)

Unit Price 1000 100


Substations, HVGB & 48 48
PLDC
Total ($) 52,800

 The estimated cost of optical fiber Backbone between PLDCs and SPC
SCADA sites (Main & Backup) will be the following:

Optical Fiber (ADSS technology)


Unit Price 1700 per kilometer
Quantity of optical fiber 1154
Total ($) 1,960,000

 The estimated cost of SDH, Multiplexor and Telecommunication Management


Network (TMN) for the communication between SPC Head Offices.equipment
will be the following:

SDH STM – 16
SDH STM – 4 (including
(including TMN
Multiplexor)
Multiplexor)
Number 21 2 1
Cost 65,000 100,000 120,000
Subtotal 1,365,000 200,000 120,000
Total ($) 1,685,000

 The estimated cost of the TCP/IP equipment will be the following.

Router Gateway Switch TMN


Number 90 124 + (30) 124 + (60) 1
Cost 3,000 400 1,000 120,000
Total 270,000 70,000 184,000 120,000
Total ($) 650,000
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 98/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Thus, the estimated global cost of the Telecommunication Network will be the
following:

Cost
Optical Fiber Architecture (and optical equipment) between SS and HVGB
6,833,500
& PLDC
Optical/Electrical equipment & cabinets in 26 SS and A2 Control Center 778,700
Optical Fiber Architecture between PLDC and Control Centres 1,960,000
SDH Network 1,685,000
TCP/IP equipment 650,000
Total 11,907,200
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 99/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

10.4 Telecommunication with A2 connection by SDH – TCP/IP Network

 The estimated cost of optical fiber between substations, HVGBs & PLDCs will
be the following:

Optical Fiber (F8 technology)


Unit Price 1400 per kilometer
Quantity of optical fiber 4565
Total ($) 6,391,000

 The estimated cost of optical fiber installation in Substations, PLDC & HVGB
will be the following:

Cabinet (42U) Manpower (per SS)


Unit Price 1000 250
Substations, HVGB & 144 144
PLDC
Sub Total 144,000 36,000
Total ($) 180.000

 The estimated cost of optical fiber terminal equipment will be the following:

Optical/Electrical Manpower (per


Converter link)

Unit Price 1000 100


Substations, HVGB & 250 125
PLDC
Sub Total 250,000 12,500
Total ($) 262,500
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 100/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 The estimated cost of optical fiber Backbone between PLDCs and SPC
SCADA sites (Main & Backup) will be the following:

Optical Fiber (ADSS technology)


Unit Price 1700 per kilometer
Quantity of optical fiber 1154
Total ($) 1,960,000

 The estimated cost of SDH, Multiplexor and Telecommunication Management


Network (TMN) for the communication between SPC Head Offices.equipment
will be the following:

SDH STM – 16
SDH STM – 4 (including
(including TMN
Multiplexor)
Multiplexor)
Number 22 2 1
Cost 65,000 100,000 120,000
Subtotal 1,430,000 200,000 120,000
Total ($) 1,750,000

 The estimated cost of the TCP/IP equipment will be the following.

Router Gateway Switch TMN


Number 92 134 + (30) 126 + (60) 1
Cost 3,000 400 1,000 120,000
Total 276,000 74,000 186,000 120,000
Total ($) 656,000
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 101/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Thus, the estimated global cost of the Telecommunication Network will be the
following:

Cost
Optical Fiber Architecture (and optical equipment) between SS and PLDC 6,833,500
Optical Fiber Architecture between PLDC and Control Centres 1,960,000
SDH Network 1,750,000
TCP/IP equipment 656,000
Total 11,179,500

10.5 Training
The final cost will depend of the final organisation. It is estimated as 5% of the global price.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 102/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

11 Economic and Financial Analysis


As power systems grow in size and complexity so do the problems of coordination to
meet the basic objectives of costs, reliability, quality and safety. Control centres play
an important role in the achievement of these objectives because they are the main
means of coordination of system operation and above all the major source of real
time data of the utility IT system.
Economically speaking, it is a usual practice to evaluate such a project by the
economic quantifiable benefits that it offers to the Utility. Thus, this study is based on
comparing the project benefits and costs during the life expectancy period of the
control System. This analysis scrutinizes the whole of the project during its life
expectancy and consequently the total cost of the project. Benchmarks worldwide on
this issue show that control systems life expectancy is around ten years, i.e. covering
the period from 2015 to 2024 (considering a commissioning date beginning in 2013).
The study is made using four methods:
 Payback period
 Net Present Value (NPV)
 Internal Rate of Return (IRR)
 Benefit/Cost Ratio
In the case of a Power Distribution Company, the quantifiable benefits come from
reduction of technical losses and energy not served. But there are other benefits,
which are less obvious to quantify even if their influence on the distribution utility
performance is huge, those regarding information management and globally
organisation.
This chapter first describes these different benefits then gives basis used for
calculation and finally presents the results of the analysis. As the control of 22kV
devices was not planned at the very beginning of this project, both cases, with and
without, have been studied.

11.1 Expected Benefits


Usually, the benefits expected by a Telecontrol system are:
 Reduction of staff
 Improved staff training
 Reduced maintenance cost
 Reduction of technical losses
 Reduction of Energy not Served (Reduced losses on account of faster
restoration of power in case of outages)
 Better information for Management
 Organisation improvement
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 103/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

These benefits come mainly from the SCADA system. Actually, it allows operators to
identify the location and the reason for faults in the electrical grid. It gives to
operators all means to telecontrol switch devices. Moreover, the SCADA system
generates a large amount of information on the day-to-day operation of the grid,
which helps to prevent faults, to improve network reinforcement schedule and to
better plan preventive maintenance.

11.1.1 Staff reduction


The first principle of a SCADA system is to supervise and remotely control HV and
MV devices located in substations. This SCADA system allows Utilities to reduce
staff especially in substations. That is the case for this project, which according to the
Terms of Reference will allow a reduction of about 1070 staffs in 110kV substations.
To operate and remotely maintain 104 substations, 1016 people are required by
SPC.
Considering the 480 people who presently work in the 20 PLDCs, the project will lead
to a staff reduction of 534 persons (1070+480-1016). The following table indicates an
average cost for one person:

Items Individual monthly cost Individual


(VND) monthly cost ($)
Salary including tax 8,255,000 393
Insurance cost 705,000 33.5
SPC organization cost 3,800,000 181
Individual monthly global cost 12,760,000 607.5
Individual yearly global cost 153,120,000 7,290

The following table indicates the yearly total reduction cost for the 534 staff reduction:

Items Cost (VND) Cost ($)


Yearly individual cost 153,120,000 7,290
Yearly total reduction cost (534 people) 81,766,000,000 3,892,860
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 104/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Offsetting these staff reduction savings are two staff-related costs:


 The first is that the 534 people that would be reduced will need retraining for
other fields. That retraining cost is a one-time cost, unlikely to be more than
six months of salary. Once retrained, and reassigned to other useful jobs,
there is no further cost chargeable to the SCADA project. These training costs
are estimated to 50 % of the yearly staff costs. This training cost is to be
allocated during the implementation period according to the fraction of the
project complete.

Items Cost (VND) Cost ($)


Training individual cost (6 months Individual cost) 76,545,000 3,645
Training total reduction cost (534 people) 40,875,030,000 1,945,430

 The second cost relates to the 1,016 people who remained, some of whom will
command higher salaries given that their jobs require greater skills. This is
indeed an ongoing increased cost. This increase in salary is estimated to 15%.

Items Cost (VND) Cost ($)


Yearly individual cost 153,120,000 7,290
Individual increase in salary (15%) 22,980 1,094
Yearly total increase in salary (1016 people) 23,347,680 1,111,504

11.1.2 Improved Operator Training


Operator training simulators are available today. The use of simulator provides basic
training in the functions used daily by operators is ideal. The opening/closing of
breakers, tap changing of transformers, etc. can be simulated without affecting the
status/security of the actual power system. Network analysis training will also be a
guarantee a higher level of understanding of the power network features. Through
training and simulation exercises, operators will have the confidence to act decisively
and correctly in real emergency conditions.

11.1.3 Maintenance
Any mechanical system gets old and becomes susceptible to malfunctions. Whatever
it is too much or underused, the rate of use of a device is an important indicator
especially from the preventive maintenance viewpoint. In fact an apparatus
underutilized, an isolator for instance, can cause mechanical troubles, oxidation of
status contacts and make doubt regarding the integrity of the transmitted status. In
the same way, the vibrations caused by a device often used can provoke problems
with wiring especially with connected terminations going up to disconnection and
therefore the loss of information.
A SCADA system continuously collects data regarding components of the network
(e.g. circuit breaker meter).
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 105/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

These statistical data regarding switching devices facilitate maintenance planning,


fault prevention and, by the way, reduces maintenance costs.

11.1.4 Outages
In case of outage, it is necessary to:
 Detect the fault
 Limit its effect on the network
 Correct it in order to bring back a normal situation
SCADA system gives operators the possibility to locate and to indentify the fault.
Then to restore by remote control the supply of the network healthy portions and
finally to dispatch in the most efficient manner the field maintenance crews to the
right location (which reduces the global “repair” downtime). Finally, the SCADA
system reduces the time to solve an issue on the network consequently reducing the
Energy Non Served.

11.1.5 Technical losses


SCADA system permits real-time optimisation of network flows and more efficient
maintenance scheduling, consequently reducing the technical losses. Even though in
percentage (and GWh) terms this loss reduction may be quite small, the benefits can
be substantial.

11.1.6 Unserved Energy


SCADA system gives operators immediate information on the location and type of
fault, permitting maintenance crews to be more efficiently dispatched, resulting lower
repair downtimes, and hence reducing the amount of unserved energy lost during
outages.

11.1.7 Better Information Management


SCADA systems contain facilities to retrieve data required for preparation of reports
and "time tagging" of events for post mortem analysis.
These reports and data are the essential source of real time data of the utility and
participate in the improvement of:
 Utility global performance via the production of reliable indicators for the utility
management
 Network reinforcement investment schedule via constraints detection and
equipment aging signs identification
 Consolidation of middle and long term planning studies
 Reporting quality to customers regarding their supply
 Work force management
 Trouble shooting maintenance, helping operational staff in verifying that
protection equipment operated correctly in response to a fault
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 106/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 Preventive maintenance

11.1.8 Organization improvement


Establishment of a control centre means that during the implementation phase most
operation, planning and monitoring functions are critically reviewed. This often means
a complete reorganization of the entire organization that in the long run will result in
more efficient power system operations.
Technology transfer will assist the Utility in future attempts to rationalize and improve
operations by using computer technology. The experience and technology transfer
that will be achieved in a Control Centre project increase the ability to receive new
technology.

11.2 Basis of the analysis


11.2.1 Telecontrol System Technical choices
The assessment of the total cost of the retained solution integrates the following
options:
 Telecontrol and Adaptation Works
All 110kV substations and 22/35kV substations not already equipped by the
mini-SCADA previous project have been considered.
 SCADA
The Architecture 3 so called "One remote console connected to the main
System within each Province" has been chosen meaning a SCADA located in
SPC head office supplied by RTU located in all of 110kV substations under
SPC responsibility. A remote console is connected in each PLDC and
communicates with the main SCADA.
Note that the highest level of costs incurred for SCADA system was chosen in
the proposed range of prices.
 Telecommunication
The option chosen consists in the implementation of a SDH network with a
TCP/IP technology. This option presents the advantage to answer both
telecontrol and corporate needs and to give optionally the possibility to install
video surveillance, telemetering and telephone systems over IP.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 107/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

 Training
Taking into account the total cost of the project, the training cost is estimated
at 5% of the global price.

Cost in Cost in
USD USD
Items (with MV device) (without MV device)
including tax including tax

SCADA/DMS (1) 8.041 M 5.50 M


Adaptation Works and Telecontrol (2) 7.644 M 7.644 M
Telecommunication (3) 12.32 M 12.32 M
Consultancy service cost (4) 0.86M 0.877 M
Training = 0.05 * (1+2+3) 1.54 M 1.275M
Project management cost 0.275 M 0.275 M
Other Costs 0.572 M 0.537
Physical Contingency (10 %) 2.85 M 2.848 M
Total ($) 34.1 M 31,14 M

The total cost considering the different options is estimated at $34.1 M (ref. Annex D:
Total investment) with MV control option and $31.14 M without.

11.2.2 Calculation data

The change rate used for all calculations is:


1 USD = 21,000 VND
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 108/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The following tables indicate which data have been used for calculations:

According to WB data Data


BST (Bulk Supply Tariff using for financial analysis) 2013 1,065 VND/kWh
Consumer Tariff 2013 1,265 VND/kWh

According to Energy practices Data


Rate of energy losses 5% of the global energy sold
Reduction of Energy losses 5°/o
Rate of Energy Not Served 0.2%
Cost of Energy Not Served (from rules in many
Twice the Consumer Tariff
Utilities)
Reduction of Energy Not Served
20%
(with control of MV devices)
Reduction of Energy Not Served
5%
(without control of MV devices)

11.2.2.1 Calculation data without increased of salary for employees remaining


on the SCADA system

The yearly staff reduction cost is:


Cost (VND) Cost ($)
Yearly total reduction cost (534 people) 81,766,000,000 3,892,860

11.2.2.2 Calculation data with increased of salary for employees remaining on


the SCADA system

And also higher salaries for employees involved in the future operating organisation
(15%):
Cost (VND) Cost ($)
Yearly individual cost 153,120,000 7,290
Individual increase in salary (15%) 22,980 1,094
Yearly total increase in salary (1016 people) 23,347,680 1,111,504
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 109/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Therefore, the yearly reduction cost is:

Cost (VND) Cost ($)


Yearly total reduction cost (534 people) 81,766,000,000 3,892,860
Total Increased Yearly individual Salaries (15%) 23,347,680,000 1,111,504
(1016 employees)
Total cost reduction from staff 58,418,320,000 2,781,356

The period for analysis is:


2013 to 2025

Regarding ENS, the estimation uses an extrapolation of data coming from SPC.

The total energy sold, for these 10 years takes into account the data from SPC and
considers the huge increase of the last years:
8% /year

The consumer tariff for these 10 years takes into account the data from SPC and
considers an increase equivalent to the Vietnamese inflation Rate:
7% /year

The Weighted Average Cost of Capital (WACC) used for the Financial and
Economical Study is:
6% /year

Regarding the reimbursement, the terms of payment are based on usual WB


practices and follow these assumptions:
Year Reimbursement rate (%)
2013 35
2014 50
2015 15
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 110/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

11.2.3 Calculation of the payback period


The method to calculate the payback period is:
Project cost
Payback Period =
Average of Cashflow (from 2015 to 2025)

11.2.4 Calculation of the Net Present Value (NPV)


The method to calculate the Net Present Value is:

N  N = 10


Cn  n = time
NPV = =
(1+r)n  Cn = the net cash flow at the time “n”
n=0
 r = discount rate

11.2.5 Calculation of the Internal Rate of Return (IRR)


The method to calculate the Internal Rate of Return uses the same formula as the
NPV. The IRR is “r” when NPV = 0. Thus, the formula is:

N  N = 10


Cn  n = time
NPV = = n = 0
(1+r)  Cn = the net cash flow at the time “n”
n=0
 r = discount rate
When NPV = 0, then IRR = r.

11.2.6 The Financial Net Present Value (FNPV)


Following usual WB practices, the Financial Net Present Value focuses on the cash
flow taking into account benefits and staff reduction cost. In the context of this
project, benefits considered are only the reduction in distribution losses as well
energy not supplied. Then the Net cash flow using to calculate the FNPV equals to:
Financial Net cash flowyear = Cost of losses + Cost of ENS + Cost reduction from staff reduction –
Investment cost

11.2.7 The Economic Net Present Value (ENPV)


The difference between financial and economic analysis is that this latter does not
take into account staff reduction cost and, also following WB practices, focuses only
on benefits and investment costs. Then the Net benefits using to calculate the ENPV
equals to:

Net benefitsyear = Cost of losses + Cost of ENS – Investment cost


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 111/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

11.2.8 Calculation of the benefit/cost Ratio


The benefit/cost ratio compares the total expected costs against the total expected
benefits. In the context of this project, that means:

Total benefits
Ratio =
Total of investment cost

11.3 Economic and financial study with control of MV devices


Taking into account data previously described, results from the financial point of view
are the following in 2025 (10 years after the beginning of the Operation Time of the
SCADA):
 Payback period = 8.29 years
 FNPV = 1,119,659 M VND
 FIRR = 15%

The detailed analysis of the FIRR, according to the year, is given below:

Year FIRR
%
2013
2014
2015
2016
2017
2018 -19,59%
2019 -9,18%
2020 -1,92%
2021 3,36%
2022 7,31%
2023 10,35%
2024 12,72%
2025 14,62%
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 112/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

FIRR as a function of project life


20,00%

15,00%

10,00%

5,00%
FIRR (%)

0,00%
2012 2014 2016 2018 2020 2022 2024 2026
-5,00%

-10,00%

-15,00%

-20,00%

-25,00%
Year

FIRR Hurdle Rate Commissioning time Operating time

The breakdown of financial costs and benefits is given below:

Costs (M VND) Benefits (M VND)

Save on Losses 782259


Save on ENS 1376776
Save on staff reduction 1311781
Staff training cost 97970
Increase in salary 400167
Investment Cost 714420
Maintenance costs 1138601
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 113/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Breakdown of financial costs and benefits in 2025


4000000

3500000

3000000
1311781

Maintenance costs
2500000

Investment Cost
M VND

2000000
Increase in salary
1138601
Staff training cost
1500000 1376776

Save on staff reduction

1000000
Save on ENS
714420

Save on Losses
500000
782259
400167

0 97970

Costs (M VND) Benefits (M VND)

The sensitivity analysis of financial returns to losses reduction is given below:

Sensitivity of financial returns to save on losses


25%

20%
Sentivity of FIRR / save on losses

15%

10%

5%

0%
0 2 4 6 8 10 12

Save on losses (%)

Corresponding FIRR in 2025 Hurdle Rate


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 114/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The sensitivity analysis of financial returns to staff reduction is given below:

Sensitivity of financial returns to staff reduction


25%

20%
Sentivity of FIRR / save on staff reduction

15%

10%

5%

0%
0 100 200 300 400 500 600 700 800 900

Save on staff reduction

Corresponding FIRR in 2025 Hurdle Rate

The sensitivity analysis of financial returns to save on ENS is given below:

Sensitivity of financial returns to save on ENS


35%

30%

25%
Sentivity of FIRR / save on losses

20%

15%

10%

5%

0%
0 10 20 30 40 50 60

-5%

-10%
Save on losses (%)

Corresponding FIRR in 2025 Hurdle Rate


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 115/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Taking into account data previously described, results from the economic point of
view are the following:
 Ratio Benefits/Costs = 1.45
 ENPV = 1,274,077 M VND
 EIRR = 17%

The detailed analysis of the EIRR, according to the year, is given below:

Year EIRR
%
2013
2014
2015
2016
2017
2018 -15,72%
2019 -5,52%
2020 1,52%
2021 6,58%
2022 10,34%
2023 13,21%
2024 15,44%
2025 17,21%

EIRR as a function of project life


20,00%

15,00%

10,00%

5,00%
FIRR (%)

0,00%
2012 2014 2016 2018 2020 2022 2024 2026
-5,00%

-10,00%

-15,00%

-20,00%
Year

EIRR Hurdle Rate Commissioning time Operating time


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 116/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The breakdown of financial costs and benefits are given below:

Costs (M VND) Benefits (M VND)

Save on Losses 782259


Save on ENS 1376776
Save on staff reduction 1311781
Staff training cost 97970
Increase in salary 400167
Investment Cost 654885
Maintenance costs 1043718

Breakdown of financial costs and benefits in 2025


4000000

3500000

3000000
1311781
Maintenance costs
2500000

Investment Cost
M VND

2000000
Increase in salary

1043718
Staff training cost
1500000 1376776

Save on staff reduction

1000000
Save on ENS
654885

Save on Losses
500000
782259
400167

0 97970

Costs (M VND) Benefits (M VND)


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 117/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The sensitivity analysis of financial returns to losses reduction is given below:

Sensitivity of financial returns to save on losses


30%

25%
Sentivity of FIRR / save on losses

20%

15%
Corresponding EIRR in 2025
Hurdle Rate

10%

5%

0%
0 2 4 6 8 10 12

Save on losses (%)

The sensitivity analysis of financial returns to staff reduction is given below:


Sensitivity of financial returns to staff reduction
30%

25%
Sentivity of FIRR / save on staff reduction

20%

15%
Corresponding EIRR in 2025
Hurdle Rate

10%

5%

0%
0 100 200 300 400 500 600 700 800 900

Save on staff reduction

The sensitivity analysis of financial returns to save on ENS is given below:


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 118/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Sensitivity of financial returns to save on ENS


40%

35%

30%
Sentivity of FIRR / save on losses

25%

20%

15%

10%

5%

0%
0 10 20 30 40 50 60

-5%
Save on losses (%)

Corresponding FIRR in 2025 Hurdle Rate


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 119/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

11.4 Economic and financial study without control of MV devices


The only data having to be adapted is ENS reduction rate, which is considerably
reduced, can normally be assessed at 5% instead of 25% (ref. chapter 11.2.2 -
Calculation data and Figure 4 - SCADA implementation strategy influence on
electricity delivery quality). The results are the following in 2025 (10 years after the
beginning of the Operation Time of the SCADA):
From the financial point of view:
 Payback period = 30.35 years
 FNPV = - 73,195 M VND
 FIRR = -2%

The detailed analysis of the FIRR, according to the year, is given below:

Year FIRR
%
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025 -1,55%
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 120/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

FIRR as a function of project life


7,00%

6,00%

5,00%

4,00%
FIRR (%)

3,00%

2,00%

1,00%

0,00%
2012 2014 2016 2018 2020 2022 2024 2026
-1,00%

-2,00%
Year

FIRR Hurdle Rate Commissioning time Operating time

The breakdown of financial costs and benefits is given below:

Costs (M VND) Benefits (M VND)

Save on Losses 782259


Save on ENS 27209
Save on staff reduction 1311781
Staff training cost 97970
Increase in salary 400167
Investment Cost 654000
Maintenance costs 1042308
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 121/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Breakdown of financial costs and benefits in 2025


2500000

2000000

1042308
Maintenance costs

1500000
1311781
Investment Cost
M VND

Increase in salary

1000000 Staff training cost

654000 27209 Save on staff reduction

Save on ENS
500000
782259 Save on Losses
400167

97970
0
Costs (M VND) Benefits (M VND)

The sensitivity analysis of financial returns to losses reduction is given below:

Sensitivity of financial returns to save on losses


12%

10%

8%
Sentivity of FIRR / save on losses

6%
Corresponding FIRR in 2025
Hurdle Rate

4%

2%

0%
0 2 4 6 8 10 12

Save on losses (%)


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 122/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The sensitivity analysis of financial returns to staff reduction is given below:

Sensitivity of financial returns to staff reduction


14%

12%
Sentivity of FIRR / save on staff reduction

10%

8%

Corresponding FIRR in 2025


6% Hurdle Rate

4%

2%

0%
0 100 200 300 400 500 600 700 800 900

Save on staff reduction


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 123/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

From the economic point of view:


 Ratio Benefits/Costs = 1.04
 ENPV = 385,149 M VND
 EIRR = 7%

The detailed analysis of the EIRR, according to the year, is given below:
Year EIRR
%
2013
2014
2015
2016
2017
2018
2019
2020 -11,12%
2021 -5,45%
2022 -1,13%
2023 2,24%
2024 4,93%
2025 7,11%

EIRR as a function of project life


10,00%

5,00%

0,00%
FIRR (%)

2012 2014 2016 2018 2020 2022 2024 2026

-5,00%

-10,00%

-15,00%
Year

EIRR Hurdle Rate Commissioning time Operating time


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 124/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The breakdown of financial costs and benefits is given below:

Costs (M VND) Benefits (M VND)

Save on Losses 782259


Save on ENS 344194
Save on staff reduction 1311781
Staff training cost 97970
Increase in salary 400167
Investment Cost 599500
Maintenance costs 955449

Breakdown of financial costs and benefits in 2025


3000000

2500000

2000000 Maintenance costs

1311781
Investment Cost
M VND

955449
1500000
Increase in salary

Staff training cost

1000000
344194 Save on staff reduction
599500
Save on ENS

500000
Save on Losses
782259
400167

97970
0
Costs (M VND) Benefits (M VND)
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 125/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The sensitivity analysis of financial returns to losses reduction is given below:

Sensitivity of financial returns to save on losses


20%

15%

10%
Sentivity of FIRR / save on losses

5% Corresponding EIRR in 2025


Hurdle Rate

0%
0 2 4 6 8 10 12

-5%

-10%
Save on losses (%)

The sensitivity analysis of financial returns to staff reduction is given below:


Sensitivity of financial returns to staff reduction
20%

15%
Sentivity of FIRR / save on staff reduction

10%

Corresponding EIRR in 2025


Hurdle Rate

5%

0%
0 100 200 300 400 500 600 700 800 900

-5%
Save on staff reduction
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 126/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

12 Implementation schedule of the project

The following diagram presents the tentative schedule for the Project implementation.
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30
Jul 12 Aug 12 Sep 12 Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14

M5
39
40
43
44
45
46
49
50

10
14
15
18
19
22
23
26
29
31
34
35
38
39
42
44
47
48
49
50

10
14
15
16
18
19
22
23
27
28
31
32
36
37
40
41
44
45
48
51
2
5
6
9

1
2
5
6
9

1
2
5
8
Tender Issued
Tendering Period
Bid Evaluation
Financial Backer Approval
Contract Negociation
SPC Approval
Contract Award
Design Approval
Manufacturing & Shipping
First Delivery to SPC
Implementation/Tests/Commissioning
Completion of Installation
Figure 3 - Phase implementation schedule
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 127/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

13 Consortium Recommendations
This study allowed scrutinising all issues of the “SCADA SYSTEM AND 110KV
SUBSTATIONS WITHOUT OPERATORS” project: substations adaptation,
telecommunication, SCADA Architecture and consequent organisation. Each item
was carefully analysed in order to find the best choice for SPC whatever technically,
organisationally and financially.

13.1 Technically

13.1.1 Substations adaptation


It is a matter of fact that all primary substations will have to be adapted. Most of HV
level of the substations are taken into account by A2 (ADB Phase 1 & 2 Projects),
SPC keeping the remaining substations. Regarding the MV level of the substations,
which is entirely under the SPC responsibility, all feeders shall be adapted for
telecontrol. For substations, meaning 244 MV devices, motorisation will be
necessary.
The communication between RTU and SCADA shall use the IEC 870-5-104 standard
protocol even though A2 SCADA communicates with RTU in primary substations
using IEC 870-5-101.

13.1.2 Telecommunication
The Telecommunication Network is a very important part of a telecontrol system.
Without secured links between substations and Control Centres, the Electrical
network monitoring becomes difficult but the controlling and consequently the
operating makes extremely uncertain or even impossible. So, it is preferable for a
company as SPC to own and to manage itself its telecommunication Operational
Network. By mutualisation of investments for Corporate and Operational Networks, it
is possible for SPC to build this Network.

The Consortium suggests implementing an SDH network based on an optical fiber


architecture with a TCP/IP technology in order to use it for telecontrol and corporate
needs but also to allow the video surveillance, telemetering and telephone systems
over IP.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 128/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

13.1.3 SCADA architecture


After a first analysis of the operating organisation the Consortium suggests four
alternative architectures.

Architecture 1 (One SCADA system per Province)


With this architecture the main SCADA system located into SPC offices
communicates with provincial SCADA systems, themselves communicating with
RTUs located into 110kV substations under SPC responsibility (ref. Figure 5).

Architecture 2 (One SCADA system in some strategic Province)


Very close to the previous one, the main SCADA system, still located into SPC
offices, communicates with provincial SCADA systems, themselves
communicating with RTUs located into 110kV substations under SPC
responsibility (ref. Figure 6). Only the final number of PLDC changes in this
Architecture. The PLDCs where SCADA systems are implemented are called
“Major PLDCs”.

Architecture 3 (One remote console connected to the main System within each Province)
This architecture is fundamentally different from the two above mentioned
alternatives, not for the main SCADA system located into SPC offices but for
the PLDCs. In fact, this architecture replaces PLDCs SCADA system with
remote consoles (ref. Figure ). In this case, the SPC SCADA system located in
the head office communicates with RTUs located into 110kV substations under
SPC responsibility.

Architecture 4 (One and only one SCADA system within SPC head offices)
This architecture is quite similar to the previous one. But in this case, there are
no remote consoles communicating with SPC head office (ref. Figure ). It is the
simplest architecture.

The Consortium recommends the third architecture, which meets the SPC telecontrol
needs at the lowest cost and which is the most flexible solution in terms of adaptation
capability. All types of control organisation (i.e. centralised, decentralised or mixed)
can easily be implemented with architecture 3 ensuring its sustainability for SPC.

13.1.4 MV Devices Control


The benefits of MV Devices Control are an improved reliability for SPC and for the
consumer.
For SPC, there are two main consequences of poor reliability due to the MV Devices
Control:
 The loss of revenue when consumer’s supply is interrupted (easily quantified
as the kWh not served, less the corresponding purchase cost at the BST).
 The cost of finding and fixing faults (not taken into account in the Financial &
Economical Study)
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 129/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

The project should include the control of 22/35kV devices.

13.1.5 Organizational
EVN recommends putting in place 1 operating team (24/24) within each PLDC and
also within each HVGB. The first one should normally operate the MV network
whereas the second one should be in charge of the 110kV substations. Regarding
SPC head offices, EVN recommends to put in place one operating team to only
monitor during the day the grid under the SPC responsibility.

From the Consortium point of view, the most efficient organisation would be to
centralise one operating team (24/24) within SPC head offices and to monitor and
operate the MV network and 110kV substation from this only one site. Moreover,
even if this latter organisation might be considered as a middle term objective, the
implementation of provincial SCADA at a first stage shall lead to a modification of
EVN rules so as to merge PLDC and HVGB responsibilities in the PLDCs. This latter
recommendation is indispensable to follow in order to avoid security and efficiency
drawbacks for network control.

Regarding the maintenance of substation equipments (RTU, Adaptation equipments


as transducers, relay and so on…) the Consortium recommends to deploy 5
maintenance teams leading 1 team for 4 provinces.
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 130/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

14 Glossary
Terms Definitions
ADSS All Dielectric Self Hierarchy
AW Adaptation Works
CB Circuit Breaker
DC Double Command
DS Double Signal
GT Province Grid Teams
HV High Voltage
HVGB High Voltage Grid Branch
ICCP Inter Control Centre Protocol
IRR Internal Rate of return
LBS Low Breack Switch
LCC Local Control Centre
M Measurement
MCC Main Control Centre (SPC head offices)
MV/LV Medium Voltage / Low Voltage
NPV Net Present Value
OPGW OPtical Ground Wire
PB Power Branch
PDC Provincial Power Distribution Company
PDDD Provincial Distribution Dispatch Department
PLDC Power Load Dispatch Centre
RTU Remote Terminal Unit
SCADA Supervisory Control And Data Acquisition
SDH Synchronous Digital Hierarchy
SGC Southern Grid Company
SC Single Command
SS Single Signal
TASE.2 Telecontrol Application Service Element 2
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 131/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

ANNEXES
Annexe A: Sizing

The following table gives figures regarding:


 The type of bays:
o Over Head Line (OHL)
o Transformer (TR) comprising of transformer feeder and transformer
general bay
o Shunt Compensator (Sh)
o Section (Sect),
o Tie
 The type of information:
o Double Signal (DS)
o Single Signal (SS)
o Analogue Measurement (AM)
o Digital Measurement (DM)
o Double Command (DC)
o Single Command (SC)
 The type of I/O cards:
o Digital Input (DI)
o Digital Output (DO)
o Analogue Input (AI)
 The number of RTU racks.
The number of busbars (Bb) is indicated for 22/35kV voltage levels due to some
substations have 2 separate ones.

1. An Giang Province
 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Cái Dầu 3 2 1 1 26 152 34 20 4 13 3 5 2


Châu Đốc 2 1 1 15 87 23 9 4 7 2 3 1
Long Xuyên 2 2 1 19 121 28 13 4 10 2 3 1
Phú Tân 1 1 10 68 15 6 2 6 1 2 1
Tri Tôn 1 1 10 68 15 6 2 6 1 2 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bb DS SS AM DM DC SC DI DO AI Rack

Cái Dầu 8 2 1 1 1 56 83 22 17 8 3 2 1
Châu Đốc 8 2 1 1 2 59 87 25 17 9 3 2 1
Long Xuyên 12 2 2 2 1 79 118 29 22 12 3 2 1
Phú Tân 6 1 1 1 39 59 16 10 6 2 2 1
Tri Tôn 6 1 1 1 39 59 16 10 6 2 2 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 132/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

2. Bac Lieu Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bạc Liêu 2 2 1 1 22 128 30 16 4 11 3 4 1


Giá Rai 2 2 1 1 22 128 30 16 4 11 3 4 1
Hồng Dân 2 1 1 16 94 19 11 2 9 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bạc Liêu 6 2 2 1 1 49 78 19 17 8 3 2 1
Giá Rai 6 2 2 2 48 76 20 14 8 2 2 1
Hồng Dân 4 1 1 1 29 45 12 8 5 1 1 1

3. Ben Tre Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Ba Tri 1 1 10 68 15 6 2 6 1 2 1
Bến Tre 4 2 1 27 169 36 21 4 15 3 4 2
Chợ Lách 2 1 1 1 19 103 20 13 2 9 2 3 1
Mỏ Cày 2 2 1 1 22 128 30 16 4 11 3 4 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Ba Tri 6 1 2 39 54 18 8 6 1 2 1
Bến Tre 8 2 1 1 1 56 83 22 17 8 3 2 1
Chợ Lách 5 1 1 31 43 13 7 5 1 1 1
Mỏ Cày 8 2 1 2 55 81 23 14 8 2 2 1

4. Binh Duong Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bàu Bèo 2 1 1 1 19 103 20 13 2 9 2 3 1


Bến Cát 1 2 2 1 1 22 128 30 16 4 11 3 4 1
Bình An 2 2 1 1 22 128 30 16 4 11 3 4 1
Dầu Tiếng 2 1 1 1 19 103 20 13 2 9 2 3 1
Gò Đậu 2 2 1 1 22 128 30 16 4 11 3 4 1
Phú Giáo 2 1 1 16 94 19 11 2 9 2 3 1
Sóng Thần 2 2 1 1 22 128 30 16 4 11 3 4 1
Tân Đông
Hiệp 3 1 18 116 23 14 2 11 2 3 1
Tân Uyên 2 2 1 19 121 28 13 4 10 2 3 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 133/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Thới Hòa 2 2 1 1 22 128 30 16 4 11 3 4 1


Thủ Đức Bắc 2 2 1 20 126 30 15 4 11 3 4 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bàu Bèo 5 1 1 31 43 13 7 5 1 1 1
Bến Cát 1 10 2 1 1 1 66 97 26 19 10 3 2 1
Bình An 11 2 1 1 1 71 104 28 20 10 3 2 1
Dầu Tiếng 5 1 1 31 43 13 7 5 1 1 1
Gò Đậu 12 2 1 1 1 76 111 30 21 11 3 3 1
Phú Giáo 4 1 1 1 1 33 51 14 11 5 2 2 1
Sóng Thần 10 2 1 1 1 66 97 26 19 10 3 2 1
Tân Đông
6 1 1 1 10 6 2 2 1
Hiệp 39 59 16
Tân Uyên 12 2 2 1 1 79 120 31 23 12 3 3 1
Thới Hòa 12 2 2 1 1 79 120 31 23 12 3 3 1
Thủ Đức Bắc 10 2 1 1 1 66 97 26 19 10 3 2 1

5. Binh Phuoc Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bình Long 3 1 1 20 118 23 15 2 11 2 3 1


Bù Đăng 2 1 1 16 94 19 11 2 9 2 3 1
Chơn Thành 2 1 1 16 94 19 11 2 9 2 3 1
Đồng Xoài 2 2 1 1 22 128 30 16 4 11 3 4 1
Lộc Ninh 4 2 1 27 169 36 21 4 15 3 4 2
Phước Long 2 1 1 16 94 19 11 2 9 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bình Long 6 1 1 1 39 59 16 10 6 2 2 1
Bù Đăng 4 1 1 1 29 45 12 8 5 1 1 1
Chơn Thành 8 1 1 1 1 53 79 22 15 8 2 2 1
Đồng Xoài 8 2 2 2 56 76 22 14 8 2 2 1
Lộc Ninh 7 2 2 1 1 54 85 21 18 8 3 2 1
Phước Long 5 1 1 1 34 52 14 9 6 2 1 1

6. Binh Thuan Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Đức Linh 1 1 1 12 70 15 7 2 6 1 2 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 134/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Hàm Tân 2 1 1 17 99 21 13 2 9 2 3 1
Lương Sơn 1 1 10 68 15 6 2 6 1 2 1
Phan Rí 3 1 18 116 23 14 2 11 2 3 1
Phan Thiết 4 2 25 167 36 20 4 15 3 4 2
Thuận Nam 2 2 17 119 28 12 4 10 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Đức Linh 4 1 1 1 30 42 13 9 4 2 1 1
Hàm Tân 6 1 1 1 2 46 69 21 13 7 2 2 1
Lương Sơn 5 1 1 2 38 53 18 10 5 2 2 1
Phan Rí 8 1 1 1 50 70 21 13 7 2 2 1
Phan Thiết 8 2 1 1 2 59 87 25 17 9 3 2 1
Thuận Nam 8 2 1 1 53 74 21 15 8 2 2 1

7. Ba Ria – Vung Tau Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bà Rịa 3 1 18 116 23 14 2 11 2 3 1
Đông Xuyên 1 1 10 68 15 6 2 6 1 2 1
Long Đất 2 1 2 18 96 19 12 2 9 2 3 1
Mỹ Xuân A 2 2 1 20 126 30 15 4 11 3 4 1
Ngãi Giao 1 1 10 68 15 6 2 6 1 2 1
Phú Mỹ 2 2 1 20 126 30 15 4 11 3 4 1
Thắng Tam 2 1 14 92 19 10 2 8 2 3 1
Vũng Tàu 2 2 1 20 126 30 15 4 11 3 4 1
Xuyên Mộc 2 1 14 92 19 10 2 8 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bà Rịa 6 1 1 36 50 15 8 5 1 1 1
Đông Xuyên 4 1 1 1 30 42 13 9 4 2 1 1
Long Đất 4 1 1 1 1 33 51 14 11 5 2 2 1
Mỹ Xuân A 12 2 1 1 1 76 111 30 21 11 3 3 1
Ngãi Giao 4 1 1 1 30 42 13 9 4 2 1 1
Phú Mỹ 11 2 2 1 1 74 113 29 22 11 3 3 1
Thắng Tam 5 1 1 31 43 13 7 5 1 1 1
Vũng Tàu 14 2 1 1 1 86 125 34 23 12 3 3 1
Xuyên Mộc 5 1 1 1 34 52 14 9 6 2 1 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 135/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8. Ca Mau Province
 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

An Xuyên 2 1 14 92 19 10 2 8 2 3 1
Cà Mau 2 2 1 1 23 135 31 17 4 12 3 4 1
Cái Nước 1 1 10 68 15 6 2 6 1 2 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

An Xuyên 4 1 1 26 36 11 6 4 1 1 1
Cà Mau 9 2 1 1 1 61 90 24 18 9 3 2 1
Cái Nước 5 1 1 1 34 52 14 9 6 2 1 1

9. Can Tho Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bình Thủy 1 1 10 68 15 6 2 6 1 2 1
Cần Thơ 3 2 21 143 32 16 4 12 3 4 1
Đài PT NB 2 2 1 20 126 30 15 4 11 3 4 1
KCN Cần Thơ 2 1 1 16 94 19 11 2 9 2 3 1
KCN Hưng
Phú 2 1 14 92 19 10 2 8 2 3 1
Long Hòa 2 1 1 17 99 21 13 2 9 2 3 1
Thới Thuận 2 1 1 16 94 19 11 2 9 2 3 1
Thốt Nốt 1 1 10 68 15 6 2 6 1 2 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bình Thủy 6 1 1 1 39 59 16 10 6 2 2 1
Cần Thơ 10 2 2 2 68 104 28 18 11 3 2 1
Đài PT NB 4 2 1 1 33 46 13 11 5 2 1 1
KCN Cần
Thơ 5 1 1 1 34 52 14 9 6 2 1 1
KCN Hưng
Phú 5 1 1 1 34 52 14 9 6 2 1 1
Long Hòa 5 1 1 31 43 13 7 5 1 1 1
Thới Thuận 6 1 1 1 1 43 65 18 13 6 2 2 1
Thốt Nốt 3 1 1 1 24 38 10 7 4 1 1 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 136/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

10. Dong Thap Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

An Hòa 2 1 1 16 94 19 11 2 9 2 3 1
An Long 2 1 1 17 101 20 12 2 9 2 3 1
Cao Lãnh 3 2 21 143 32 16 4 12 3 4 1
Hồng Ngự 1 1 10 68 15 6 2 6 1 2 1
Sa Đéc 3 2 1 1 26 152 34 20 4 13 3 4 2
Thạnh Hưng 2 2 17 119 28 12 4 10 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

An Hòa 6 1 1 1 39 59 16 10 6 2 2 1
An Long 4 1 1 1 29 45 12 8 5 1 1 1
Cao Lãnh 9 2 1 1 1 61 90 24 18 9 3 2 1
Hồng Ngự 7 1 1 41 57 17 9 6 2 2 1
Sa Đéc 6 2 2 1 1 47 74 17 15 8 2 2 1
Thạnh Hưng 8 2 2 1 1 59 92 23 19 9 3 2 1

11. Hau Gian Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Phụng Hiệp 2 1 1 16 94 19 11 2 9 2 3 1
Vị Thanh 2 2 1 1 22 128 30 16 4 11 3 4 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Phụng Hiệp 4 1 1 26 36 11 6 4 1 1 1
Vị Thanh 10 2 1 1 63 88 25 17 9 3 2 1

12. Kien Giang Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

An Biên 1 1 10 68 15 6 2 6 1 2 1
Chung Sư 1 1 10 68 15 6 2 6 1 2 1
Giồng Riềng 2 1 1 16 94 19 11 2 9 2 3 1
Kiên Lương 2 2 2 1 1 22 128 30 16 4 11 3 4 1
Rạch Giá 2 2 1 20 126 30 15 4 11 3 4 1

 22/35kV level
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 137/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

An Biên 6 2 2 42 58 18 10 6 2 2 1
Chung Sư 7 1 2 44 61 20 9 6 2 2 1
Giồng Riềng 4 1 1 1 29 45 12 8 5 1 1 1
Kiên Lương 2 8 2 2 1 1 59 92 23 19 9 3 2 1
Rạch Giá 7 2 1 2 50 74 21 13 8 2 2 1

13. Lam Dong Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Đà lạt 1 2 1 1 17 99 21 13 2 9 2 3 1
Đà lạt 2 2 1 1 16 94 19 11 2 9 2 3 1
Di Linh 2 1 14 92 19 10 2 8 2 3 1
Đơn Dương 2 1 1 16 94 19 11 2 9 2 3 1
Đức Trọng 3 1 18 116 23 14 2 11 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Đà lạt 1 7 2 1 2 50 74 21 13 8 2 2 1
Đà lạt 2 6 1 1 1 39 59 16 10 6 2 2 1
Di Linh 5 1 1 1 34 52 14 9 6 2 1 1
Đơn Dương 6 1 1 1 39 59 16 10 6 2 2 1
Đức Trọng 5 1 2 1 1 41 67 17 14 7 2 2 1

14. Long An Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bến Lức 2 2 1 19 121 28 13 4 10 2 3 1


Cần Đước 2 2 1 20 126 30 15 4 11 3 4 1
Đức Hòa 2 2 1 20 126 30 15 4 11 3 4 1
Long An 2 1 14 92 19 10 2 8 2 3 1
Mộc Hóa 1 1 10 68 15 6 2 6 1 2 1
Tân An 2 1 14 92 19 10 2 8 2 3 1
Thạnh Hóa 1 1 10 68 15 6 2 6 1 2 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bến Lức 8 2 1 1 51 70 19 13 8 2 2 1
Cần Đước 6 2 2 42 58 18 10 6 2 2 1
Đức Hòa 9 2 1 1 1 61 90 24 18 9 3 2 1
Long An 5 1 1 1 34 52 14 9 6 2 1 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 138/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Mộc Hóa 5 1 1 1 34 52 14 9 6 2 1 1
Tân An 7 1 2 44 61 20 9 6 2 2 1
Thạnh Hóa 5 1 1 1 34 52 14 9 6 2 1 1

15. Ninh Thuan Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Ninh Hải 2 1 1 16 94 19 11 2 9 2 3 1
Ninh Phước 2 1 14 92 19 10 2 8 2 3 1
Ninh Sơn 2 1 14 92 19 10 2 8 2 3 1
Tháp Chàm 3 2 1 24 150 34 19 4 13 3 4 2

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Ninh Hải 4 1 1 26 36 11 6 4 1 1 1
Ninh Phước 4 1 1 26 36 11 6 4 1 1 1
Ninh Sơn 4 1 1 1 30 42 13 9 4 2 1 1
Tháp Chàm 7 2 1 1 1 51 76 20 16 8 2 2 1

16. Soc Trang Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Đại Ngãi 2 1 1 16 94 19 11 2 9 2 3 1
Mỹ Tú 1 1 10 68 15 6 2 6 1 2 1
Sóc Trăng 3 2 1 1 1 29 161 35 22 4 14 3 4 2
Trần Đề 1 1 10 68 15 6 2 6 1 2 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Đại Ngãi 4 1 1 1 29 45 12 8 5 1 1 1
Mỹ Tú 5 1 1 1 34 52 14 9 6 2 1 1
Sóc Trăng 9 2 1 1 1 61 90 24 18 9 3 2 1
Trần Đề 4 1 1 1 29 45 12 8 5 1 1 1

17. Tay Ninh Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bến Cầu 1 1 10 68 15 6 2 6 1 2 1
KCN Trảng
Bàng 2 1 14 92 19 10 2 8 2 3 1
Tân Biên 1 1 10 68 15 6 2 6 1 2 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 139/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Tân Hưng 2 2 1 1 1 25 137 31 18 4 12 3 4 1


Tây Ninh 4 2 1 28 174 38 23 4 16 4 5 2
Thạnh Đức 2 1 1 16 94 19 11 2 9 2 3 1
Trảng Bàng 2 2 1 1 22 128 30 16 4 11 3 4 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bến Cầu 5 2 1 2 40 60 17 11 6 2 2 1
KCN Trảng
Bàng 4 1 1 1 29 45 12 8 5 1 1 1
Tân Biên 5 1 1 31 43 13 7 5 1 1 1
Tân Hưng 9 2 1 1 1 61 90 24 18 9 3 2 1
Tây Ninh 10 2 2 1 1 69 106 27 21 11 3 2 1
Thạnh Đức 4 1 1 1 29 45 12 8 5 1 1 1
Trảng Bàng 8 2 1 1 1 56 83 22 17 8 3 2 1

18. Tien Giang Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Gò Công 2 2 1 20 126 30 15 4 11 3 4 1
KCN Mỹ Tho 2 1 2 18 96 19 12 2 9 2 3 1
Mỹ Tho 1 6 44 11 2 2 3 1 2 1
Mỹ Thuận 3 1 18 116 23 14 2 11 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Gò Công 9 4 2 1 1 2 75 113 28 25 11 4 3 1
KCN Mỹ Tho 4 1 1 1 29 45 12 8 5 1 1 1
Mỹ Tho 2 1 1 2 22 35 11 6 4 1 1 1
Mỹ Thuận 4 2 1 1 32 49 12 10 5 2 1 1

19. Tra Vinh Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Tra Vinh 2 2 17 119 28 12 4 10 2 3 1


Duyen Hai 2 1 1 17 101 20 12 2 9 2 3 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Tra Vinh 9 2 1 1 58 81 23 16 8 2 2 1
Duyen Hai 4 1 1 1 29 45 12 8 5 1 1 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 140/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

20. Vinh Long Province


 110kV level
Substations OHL TR Shunt Sect Tie DS SS AM DM DC SC DI DO AI Rack

Bình Minh 2 1 1 11 107 17 11 2 9 2 3 1


Vĩnh Long 3 2 16 160 28 16 4 12 3 4 1
Vũng Liêm 2 2 1 15 134 26 15 4 11 3 4 1

 22/35kV level
Substations OHL TR Shunt Sect Tie Bd DS SS AM DM DC SC DI DO AI Rack

Bình Minh 5 1 1 1 34 52 14 9 6 2 1 1
Vĩnh Long 10 2 2 1 1 69 106 27 21 11 3 2 1
Vũng Liêm 10 2 2 1 1 69 106 27 21 11 3 2 1
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 141/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Annexe B: Scope of RTU installation

Transformer Existing Existing ADB SPC


capacity Project Project
No. Provinces Substations RTU RTU
Phase 1
(MVA) of A2 of SPC &2
1 An Giang Long Xuyên 2x40 X
2 Châu Đốc 2x40 X
3 Cái Dầu 2x25 X
4 Phú Tân 40 X
5 Tri Tôn 40 X
6 Bạc Liêu Bạc Liêu 2x25 X
7 Giá Rai 25 X
8 Hồng Dân 25 X

9 Bến Tre Bến Tre 40+25 X


10 Mỏ Cày 2x25 X
11 Ba Tri 40 X
12 Chợ Lách 25 X

13 Bình Dương Gò Đậu 2x63 X


14 Sóng Thần 2x63 X
15 Bình An 2x63 X
16 Thới Hòa 2x63 X
17 Thủ Đức Bắc 2x63 X
18 Tân Uyên 2x63 X
19 Tân Đông Hiệp 2x63 X
20 Bàu Bèo 63 X
21 Bến Cát 1 2x63 X
22 Phú Giáo 25 X
23 Dầu Tiếng 25 X

24 Bình Phước Bù Đăng 25 X


25 Đồng Xoài 25+16 X
26 Chơn Thành 40 X
27 Lộc Ninh 2x25 X
28 Phước Long 25 X
29 Bình Long 40 X

30 Bình Thuận Đức Linh 25 X


31 Hàm Tân 40 X
32 Phan Rí 25 X
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 142/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Transformer Existing Existing ADB SPC


capacity Project Project
No. Provinces Substations RTU RTU
Phase 1
(MVA) of A2 of SPC &2
33 Lương Sơn 25 X
34 Phan Thiết 63+40 X
35 Thuận Nam 2x40 X

BR Vũng
36 Vũng Tàu 2x63 X
Tàu
37 Phú Mỹ 2x63 X
38 Xuyên Mộc 25 X
39 Mỹ Xuân A 63+40 X
40 Đông Xuyên 25 X
41 Bà Rịa 25 X
42 Long Đất 25 X
43 Ngãi Giao 25 X
44 Thắng Tam 40 X

45 Cà Mau Cà Mau 2x40 X


46 An Xuyên 25 X
47 Cái Nước 40 X

48 Cần Thơ Cần Thơ 40+25 X


49 KCN Hưng Phú 40 X
50 Long Hòa 40 X
51 KCN Cần Thơ 63 X
52 Thốt Nốt 25 X
53 Thới Thuận 63 X
54 Bình Thủy 40+20 X
55 Đài PTNB 2x16 X
56 Đồng Tháp Cao Lãnh 2x63 X
57 An Long 25 X
58 Hồng Ngự 25 X
59 An Hòa 40 X
60 Sa Đéc 2x25 X
61 Thạnh Hưng 40+25 X

62 Hậu Giang Vị Thanh 2x40 X


63 Phụng Hiệp 25 X

64 Kiên Giang Rạch Giá 2x25 X


65 Chung Sư 40 X
66 Kiên Lương 2 2x25 X
67 Giồng Riềng 25 X
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 143/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Transformer Existing Existing ADB SPC


capacity Project Project
No. Provinces Substations RTU RTU
Phase 1
(MVA) of A2 of SPC &2
68 An Biên 40 X

69 Lâm Đồng Đà Lạt 1 40 X


70 Đà Lạt 2 40 X
71 Đức Trọng 40 X
72 Di Linh 25 X
73 Đơn Dương 25 X

74 Long An Mộc Hóa 25 X


75 Đức Hòa 63+40 X
76 Bến Lức 40+25 X
77 Tân An 40 X
78 Long An 40 X
79 Cần Đước 40+16 X
80 Thạnh Hóa 40 X

81 Ninh Thuận Ninh Sơn 25 X


82 Ninh Hải 25 X
83 Ninh Phước 25 X
84 Tháp Chàm 2x25 X
85 Sóc Trăng Sóc Trăng 63+40 X
86 Đại Ngãi 25 X
87 Trần Đề 25 X
88 Mỹ Tú 25 X

89 Tây Ninh Tân Hưng 2x25 X


90 Bến Cầu 25 X
91 Tây Ninh 2x40 X
92 Trảng Bàng 2x40 X
93 Thạnh Đức 25 X
KCN Trảng X
94 Bàng
40

95 Tân Biên 25 X

96 Tiền Giang Mỹ Tho 25 X


97 Gò Công 40+16 X
98 KCN Mỹ Tho 25 X
99 Mỹ Thuận 25 X

100 Trà Vinh Trà Vinh 2x25 X


101 Duyên Hải 25 X
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 144/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Transformer Existing Existing ADB SPC


capacity Project Project
No. Provinces Substations RTU RTU
Phase 1
(MVA) of A2 of SPC &2
102 Vĩnh Long Vĩnh Long 2x25 X
103 Vũng Liêm 2x25 X
104 Bình Minh 25 X
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 145/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Annexe C: AW and TCD Cost per substation (total)

The following tables indicate the detail pricein USD per Provinces and per Substations
regarding Adaptation Works and RTU for 110kV and 22/35kV.

1. An Giang Province
110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Cái Dầu 17 504 4 965 17 613 10 496


Châu Đốc 14 590 0 110 204 10 496
Long Xuyên 16 051 0 166 517 12 319
Phú Tân 8 054 3 835 12 489 6 527
Tri Tôn 0 0 12 489 6 527

2. Bac Lieu Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bạc Liêu 15 952 4 260 158 042 7 397


Giá Rai 16 043 4 260 66 964 7 086
Hồng Dân 9 697 4 260 9 151 5 658

3. Ben Tre Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Ba Tri 7 989 3 556 13 313 5 792


Bến Tre 19 883 0 173 613 10 496
Chợ Lách 11 621 6 527 10 053 5 233
Mỏ Cày 17 720 7 397 17 535 7 791

4. Binh Duong Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bàu Bèo 11 621 6 527 10 053 5 233


Bến Cát 1 17 720 0 20 951 11 055
Bình An 16 004 4 540 22 620 11 760
Dầu Tiếng 11 621 6 527 10 053 5 233
Gò Đậu 17 720 0 232 289 12 039
Phú Giáo 9 632 4 260 10 820 6 248
Sóng Thần 17 720 0 20 951 11 055
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 146/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Tân Đông Hiệp 11 886 5 689 12 489 6 527


Tân Uyên 14 595 4 540 25 056 12 319
Thới Hòa 15 978 4 260 25 056 12 319
Thủ Đức Bắc 17 655 0 20 951 11 055

5. Binh Phuoc Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bình Long 12 770 6 807 12 489 6 527


Bù Đăng 9 697 4 260 9 151 5 658
Chơn Thành 9 645 4 260 17 496 7 791
Đồng Xoài 17 720 0 107 898 7 366
Lộc Ninh 19 883 0 16 711 10 496
Phước Long 10 854 6 248 10 820 6 248

6. Binh Thuan Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Đức Linh 8 938 4 953 10 053 5 543


Hàm Tân 11 132 4 260 15 749 7 511
Lương Sơn 8 041 3 835 13 313 6 102
Phan Rí 11 574 4 819 146 729 7 086
Phan Thiết 19 818 0 97 204 10 496
Thuận Nam 15 986 6 807 16 846 7 366

7. Ba Ria – Vung Tau Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bà Rịa 11 314 4 540 11 722 5 512


Đông Xuyên 7 937 3 556 10 053 5 543
Long Đất 9 684 4 260 10 820 6 248
Mỹ Xuân A 16 199 4 819 24 289 12 039
Ngãi Giao 0 0 10 053 5 543
Phú Mỹ 15 900 4 260 23 387 12 039
Thắng Tam 9 671 4 260 10 053 5 233
Vũng Tàu 17 655 0 0 0
Xuyên Mộc 9 580 4 260 10 820 6 248
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 147/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

8. Ca Mau Province
110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

An Xuyên 15 952 4 260 158 042 7 397


Cà Mau 16 043 4 260 66 964 7 086
Cái Nước 9 697 4 260 9 151 5 658

9. Can Tho Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bình Thủy 8 873 4 953 116 489 6 527


Cần Thơ 0 0 0 0
Đài PT NB 17 655 7 397 10 170 5 543
KCN Cần Thơ 9 853 4 540 10 820 6 248
KCN Hưng Phú 9 645 4 260 10 820 6 248
Long Hòa 11 236 4 540 10 053 5 233
Thới Thuận 9 567 4 260 14 158 6 807
Thốt Nốt 8 275 4 115 72 482 4 953

10. Dong Thap Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

An Hòa 10 854 6 248 12 489 6 527


An Long 10 243 4 260 9 151 5 658
Cao Lãnh 17 902 0 19 282 10 776
Hồng Ngự 8 054 3 835 13 391 6 102
Sa Đéc 19 636 0 156 438 7 086
Thạnh Hưng 15 986 6 807 18 380 10 776

11. Hau Gian Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Phụng Hiệp 9 710 4 260 8 384 4 953


Vị Thanh 15 900 4 260 20 184 10 351
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 148/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

12. Kien Giang Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

An Biên 8 873 4 953 52 430 6 102


Chung Sư 8 873 4 953 66 982 6 807
Giồng Riềng 9 697 4 260 9 151 5 658
Kiên Lương 2 15 874 4 260 18 380 10 776
Rạch Giá 17 655 0 80 866 7 511

13. Lam Dong Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Đà lạt 1 12 458 0 0 0
Đà lạt 2 9 658 4 260 12 489 6 527
Di Linh 10 789 6 248 10 820 6 248
Đơn Dương 10 854 6 248 12 489 6 527
Đức Trọng 11 431 4 540 13 256 6 807

14. Long An Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bến Lức 14 426 4 260 158 242 7 086


Cần Đước 16 381 4 819 13 430 6 102
Đức Hòa 16 771 5 689 19 282 10 776
Long An 10 789 0 101 820 6 248
Mộc Hóa 8 873 4 953 10 820 6 248
Tân An 9 658 4 260 14 982 6 807
Thạnh Hóa 8 873 4 953 10 820 6 248

15. Ninh Thuan Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Ninh Hải 9 697 4 260 8 384 4 953


Ninh Phước 9 723 4 540 8 384 4 953
Ninh Sơn 9 684 4 260 10 053 5 543
Tháp Chàm 19 571 10 496 158 944 7 791
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 149/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

16. Soc Trang Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Đại Ngãi 9 697 4 260 9 151 5 658


Mỹ Tú 8 873 4 953 10 820 6 248
Sóc Trăng 20 403 0 188 282 10 776
Trần Đề 8 873 4 953 9 151 5 658

17. Tay Ninh Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bến Cầu 7 989 3 556 12 528 6 527


KCN Trảng Bàng 9 632 4 260 9 151 5 658
Tân Biên 8 873 4 953 88 053 5 233
Tân Hưng 18 487 7 677 19 282 10 776
Tây Ninh 21 487 0 216 718 11 335
Thạnh Đức 10 854 6 248 9 151 5 658
Trảng Bàng 17 720 0 173 613 10 496

18. Tien Giang Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Gò Công 15 796 4 260 138 939 11 925


KCN Mỹ Tho 0 0 9 151 5 658
Mỹ Tho 6 957 4 394 59 404 4 674
Mỹ Thuận 11 197 4 260 9 268 6 248

19. Tra Vinh Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Duyên Hải 15 986 6 807 174 515 7 645


Trà Vinh 10 750 5 099 9 151 5 658

20. Vinh Long Province


110kV 22/35KV
Substations
Adaptation Works RTU Adaptation Works RTU

Bình Minh 10 048 5 130 10 820 6 248


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 150/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Vĩnh Long 17 473 6 217 216 718 11 335


Vũng Liêm 15 991 4 540 21 718 11 335
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 151/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

Annexe D: TOTAL INVTSTMENT

TOTAL INVESTMENT

No. CONTENT Sym. FORMULAR Cost Tax Cost


WITHOUT TAX INCLUDING TAX
CONSTRUCTION COST
564,024,237,000 56,402,423,700 620,426,660,700
I (VND) G

Construction cost 296,987,187,000 29,698,718,700 326,685,905,700


I.1 GC Item 10.1 & item 10.3

I.2 Equipment cost Ge Items from 10.1 to 10.4 267,037,050,000 26,703,705,000 293,740,755,000

PROJECT MANAGEMENT
5,777,771,639 5,777,771,639
II. COST (VND) G QLDA T x (Gc + Ge)

III. CONSULTANT COSTS (VND) Gtv 16,739,016,923 18,026,316,923

Preparing F/S report (including


survey cost, EIA report, FS report, Gtv1 According to Commercial contract 12,873,000,000 1,287,300,000 14,160,300,000
mathematical model), CD, BD
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 152/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

No. CONTENT Sym. FORMULAR Cost Tax Cost


WITHOUT TAX INCLUDING TAX

Cost for verifying F/S, CD report Gtv2 957/QĐ-BXD 105,720,156 105,720,156

Cost for verifying design 957/QĐ-BXD 173,660,084 173,660,084

Cost for verifying estimate cost Gtv3 957/QĐ-BXD 162,740,728 162,740,728

Cost for preparing, assessing


Gtv7 G*[coefficient of QĐ957] 82,129,522 82,129,522
tender document of costruction
Cost for preparing, assessing
tender document of installing Gtv8 Gtbtt*[coefficient of QĐ957] 104,654,786 104,654,786
equipment

Cost for supervising constructing Gtv9 G*[coefficient of QĐ957] 2,599,295,305 2,599,295,305

Cost for supervising installing


Gtv10 Gtbtt*[coefficient of QĐ957] 637,816,342 637,816,342
equipment
IV. OTHER COSTS (VND) Gk S(Gki) 12,032,754,767 12,032,754,767

Cost for verifying, approving Gk1 Total investment*[coefficient of TT19] 551,600,000 551,600,000

Cost for auditing Gk2 Total investment*[coefficient of TT19] 511,500,000 511,500,000

Cost for insurance Gk3 Estimate 667,592,625 667,592,625


ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 153/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

No. CONTENT Sym. FORMULAR Cost Tax Cost


WITHOUT TAX INCLUDING TAX

Cost for mobilization and un-


Gk4 Estimate 564,024,237 564,024,237
mobilization force and equipment

Cost for ensuring traffic safety


Gk6 Estimate 112,804,847 112,804,847
servicing constructing
Loan interest in construction
Gk8 Appendix 7,161,208,821 7,161,208,821
period
Cost for translating report to
Gk12 Estimate 150,000,000 150,000,000
english/Vietnam

Cost for verifying material and


Gk13 Estimate 150,000,000 150,000,000
construction quality

Cost for verifying and certifying


Gk14 Estimate 300,000,000 300,000,000
appropriate to construction quality

Cost for accepting, handing over Gk16 Estimate 150,000,000 150,000,000


Cost for preparing operation Gk17 Estimate 500,000,000 500,000,000
Environmental fee for dumping Gk18 Estimate 150,000,000 150,000,000
Cost for transfering money Gk19 G*0,1% 564,024,237 564,024,237
Others Gk20 Estimate 500,000,000 500,000,000
ELECTRICITY of VIETNAM SOUTHERN POWER CORPORATION 154/154

SCADA SYSTEM AND 110KV SUBSTATIONS WITHOUT OPERATORS

Feasibility Study – April 2012

No. CONTENT Sym. FORMULAR Cost Tax Cost


WITHOUT TAX INCLUDING TAX

CONTINGENCY COST (VND) Gdp S(Gdpi) 59,857,378,033 59,857,378,033


V.

Contingency for arising quatity Gdp1 (G+Gqlda+Gtv+Gk)*10% 59,857,378,033

VI. GRAND TOTAL (VND) I + II + III + IV + V 658,431,158,362 716,120,882,062

GRAND TOTAL (USD) 1USD = 21,000 VND 31,353,865 34,100,994