PLTMG SUMBAWA 50 MW

Electrical Work
Persiapan Untuk Back Feeding

No. Item pekerjaan Material On Site Installation Testing Target Day Remark

1 Cable Tray OK on going -


2 Power Cable/Busduct OK - -
3 Lighting System OK on going -
4 Grounding System OK OK OK
5 Lightning Protection OK on going
6 GT Transformer OK OK on going
7 TFT Transformer OK OK on going
8 Auxiliary Transformer - - -
9 Panel MV OK OK
10 Panel LV - - -
11 Panel Lighting - - -
12 UPS System OK
13 DC Power System OK

Others :
1 Power Supply for Back Feeding
will be taken from nearest PLN
line

2 WIKA should be prepared Power


cable as required
3 All Equipment and material
related should be finish tested

Document
1 ITP Procedure OK - -
PLTMG SUMBAWA 50 MW
Electrical Work
Persiapan Untuk Back Feeding

No. Item pekerjaan Material On Site Installation Testing Target Day Remark
2 Installation Procedure OK - -

Switchyard
Disconnecting Switch (DS) OK - -
CT/CVT OK - -
Circuit Breaker (CB) OK - -
Lightning Arrester (LA) OK - -
Marshalling Kiosk OK OK -
GSW On going - -
AAC Cable - - -

I & C Work
1 CCTV System OK On going
2 Communication System OK
3 Control Protection & Metering OK
4 Substation Automation (SAS) -
5