Professional Documents
Culture Documents
Electrical Work
Persiapan Untuk Back Feeding
No. Item pekerjaan Material On Site Installation Testing Target Day Remark
Others :
1 Power Supply for Back Feeding
will be taken from nearest PLN
line
Document
1 ITP Procedure OK - -
PLTMG SUMBAWA 50 MW
Electrical Work
Persiapan Untuk Back Feeding
No. Item pekerjaan Material On Site Installation Testing Target Day Remark
2 Installation Procedure OK - -
Switchyard
Disconnecting Switch (DS) OK - -
CT/CVT OK - -
Circuit Breaker (CB) OK - -
Lightning Arrester (LA) OK - -
Marshalling Kiosk OK OK -
GSW On going - -
AAC Cable - - -
I & C Work
1 CCTV System OK On going
2 Communication System OK
3 Control Protection & Metering OK
4 Substation Automation (SAS) -
5