You are on page 1of 11

chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106

Contents lists available at ScienceDirect

Chemical Engineering Research and Design

journal homepage: www.elsevier.com/locate/cherd

Lead time estimation for modular production


plants

Stefan Sievers ∗ , Tim Seifert, Marcel Franzen, Gerhard Schembecker,


Christian Bramsiepe
TU Dortmund University, Department of Biochemical and Chemical Engineering, Laboratory of Plant and Process
Design, Emil-Figge-Str. 70, D 44227 Dortmund, Germany

a r t i c l e i n f o a b s t r a c t

Article history: Modular plant design is an approach for making chemical production more flexible and more
Received 23 February 2017 efficient. Different approaches for modular plant design have been developed, for example
Received in revised form 1 October in the CoPIRIDE or F3 factory project. They have in common, that lead time reductions for
2017 modular equipment are expected e.g. by utilizing design repetition or parallelization of pre-
Accepted 5 October 2017 assembly of modules. To support the decision for or against a modular concept, besides
Available online 13 October 2017 cost effects possible lead time changes compared to conventional concepts should be antic-
ipated in early economic evaluations already. In this article, a lead time estimation method
Keywords: will be presented that correlates project costs and project durations and can be applied to
Modular plant design modular and non-modular plants enabling comparative studies. An example from a previ-
Modularity ous paper was used to investigate the impact of modularization on lead time. It includes
Time-to-market modular production lines and a non-modular backbone facility that provides energy and
Lead time utility supply. A range of investment sizes (FCI of 3–95 mio. D ) was investigated and com-
Fixed capital investment pared with a conventional reference plant. Total lead time reduction was in the range from
2.6 to 5.5 month depending on investment size. For a more significant impact on the lead
time the modularization approach needs to be modified by also applying modular design to
the backbone facility. In this case depending on investment size total lead time reduction
would be between 3.9 and 18.7 months representing a very significant reduction of 23%–60%
compared to the lead time of the conventionally designed reference plant. This is consid-
ered as the maximum expectable lead time reduction that can be achieved through modular
plant design. This reduction would represent a major potential for speeding up construction
of chemical plants.
© 2017 Institution of Chemical Engineers. Published by Elsevier B.V. All rights reserved.

1. Introduction kets and an increasing demand for a flexible production (Buchholz,


2010). Additionally, there is increasing pressure on product prices and
Future development of global chemical market is characterized by a trend of increasing raw material prices in the long term. To keep
diversification and fragmentation (Lier et al., 2015). Technological up with this future development, future chemical production will also
improvements and new fields of application make customers ask for need to be more efficient.
more tailor-made products, which leads to an increasing number of Fulfillment of both, increased flexibility and efficiency is hardly
products, decreased production volumes, delocalized product demand possible applying existing production concepts. In a simplified view
and shorter product life cycles. This in turn leads to more volatile mar- the existing production concepts can be described by the benchmarks


Corresponding author.
E-mail addresses: Stefan.Sievers@tu-dortmund.de (S. Sievers), Tim.Seifert@tu-dortmund.de (T. Seifert),
Marcel.Franzen@tu-dortmund.de (M. Franzen), Gerhard.Schembecker@bci.tu-dortmund.de (G. Schembecker),
Christian.Bramsiepe@tu-dortmund.de (C. Bramsiepe).
https://doi.org/10.1016/j.cherd.2017.10.003
0263-8762/© 2017 Institution of Chemical Engineers. Published by Elsevier B.V. All rights reserved.
chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106 97

et al. (2012). Another feature that can be exploited using modular-


ization is standardization. Standardized modules and standardized
simulation models can be used for faster process development by
selecting modules from a module database rather than designing them
individually. For example, in two studies (fine chemicals and pharma
product) Grundemann et al. (2012) showed that the time-to-market
can be reduced by implementing pre-designed, continuously operated
Fig. 1 – Scheme of the modular design of the F3 factory micro-structure units.
concept. Moreover, pre-construction of modules in an off-site workshop
under ideal spatial conditions and the presence of all necessary tools
of the large-scale commodities production plant and the small-scale and expertise may lead to a reduction of field work but requires a high
specialties production plant (Bramsiepe, 2014). degree of logistics planning, additional accommodation for workers
Traditionally, the main economic driver of the continuously oper- at the site and can potentially be dependent on weather conditions.
ated large-scale commodities production plant is the economy of scale Nevertheless, construction expenses and time may be reduced.
together with high process efficiency. However, this concept usually The reduction of engineering and construction effort helps to
offers a low degree of product and capacity flexibility (Buchholz, 2010). decrease lead times and thus the time to market, which can substan-
The small scale specialties production concept, e.g. a multi-purpose tially improve the economy by generating earlier sales. As could be
batch plant, offers a higher degree of flexibility regarding capacity and shown by Bramsiepe et al. (2012) and Seifert et al. (2012), a lead time
product portfolio. Here, the ability to quickly react to seasonal or new reduction from three to one year by means of modular setup imple-
market requirements including innovations are main economic drivers mentation can result in a net present value improvement of more than
(Rauch, 1998). The disadvantage of this concept is the comparably low 25 percent, which offers the opportunity to compensate loss of econ-
efficiency due to a lack of material and heat integration (Rauch, 1998). omy of scale. The generation of earlier sales also results in a shorter
A solution proposed to combine the advantages of both production pay-back period, reducing the investment risk. This in turn allows to go
concepts are production plants that use a modular design (Buchholz, for projects that otherwise were too risky, creating an increased degree
2010). Several approaches to describe modularization are available. of business flexibility.
While Jameson (2007) describes a module as just being a mobile unit, a It becomes clear that lead time is a central element for economic
more detailed description has been developed by Burdorf et al. (2004), evaluation and comparison of modular and conventional production
Kampczyk et al. (2004) and Schmidt-Traub et al. (1999). In their defini- concepts. There are different project phases, which constitute the lead
tion a module corresponds to a main equipment item including its local time. An example of a typical differentiation of lead time phases is
pipe installation. A module description that also includes standardiza- given, for example, by Bramsiepe et al. (2011).
tion of modules has been developed in several research activities in The first economic evaluation that already includes a lead time
the recent years. European research projects to be considered are for estimate is conducted during a feasibility study in the process con-
example CoPIRIDE (Löb, 2013) or F3 factory (Buchholz, 2010; Buchholz, cept phase (Navarette, 2009). This evaluation aims at choosing one of
2013), further relevant projects have been listed by Lier et al. (2015). the process alternatives developed, e.g. a modular vs. a conventional
The concept used as a reference for modular design in this paper approach. Bramsiepe (Bramsiepe, 2014) found that for conventional
was used in the F3 factory concept. F3 stands for flexible, fast and plants in this phase only a rough estimate is conducted for lead time
future production plants and describes a modular and continuous estimation because “especially during early process design only few informa-
operating mode. The overall F3 factory plant is made up from two mod- tion about the process under investigation are available so that the decision pro
ular structures, PEAs (Process Equipment Assembly) and PECs (Process or contra a process alternative has to be made based on practical knowledge
Equipment Container), both equipped with standardized interfaces. instead of detailed calculations”. For example, in this phase Mosberger
The structure is schematically illustrated in Fig. 1. (2012) propose to estimate two to two-and-a-half years from process
In this concept, modular equipment fulfilling a full unit operation design freeze to start-up plus half a year to one year until minimum
(the PEAs) can be placed into standard containers which represent the capacity is reached that corresponds the break-even point.
modular superstructure (the PECs) and are connected to a shared back- Even rough lead time estimates need to be established on a com-
bone facility that provides housing and basic supply with utilities and mon and comparable basis to get meaningful results. Thus, comparing
energy. Aiming for high process efficiency highly automated, contin- modular and conventional design requires that the same methodologi-
uously operated processes using process intensified technologies and cal approach is applied and the same database is used for the lead time
material and heat integration can be implemented (Seifert et al., 2014; estimate of both approaches. Of course above mentioned expectable
Bramsiepe et al., 2012). lead time reductions for modular plants need to be considered in such
However, process intensified technologies are often limited in comparison. This means existing rough lead time estimates for conven-
throughput. Especially when parallelization or numbering up is tional plants need to be adjusted and for plants with modular design a
required to prepare technically relevant production capacities, loss of new estimate is required.
economy of scale can compensate improved conversion cost.
An economic evaluation is necessary to determine whether the
2. Approach
modular approach provides economic advantages over conventional
production concepts.
For such economic evaluation it is not sufficient to incorporate For lead time estimation, first, the phases of an engineering
investment costs and conversion costs only. There are further eco- project have to be defined. After that a calculation method
nomic aspects like supply chain costs, personnel costs, site-specific has to be developed that allows determining the duration of
costs, and others that are affected by implementation of a modular each of the phases.
plant design and need to be considered (Sievers et al., 2017). For further considerations, it is assumed that there is a rela-
One of the most important effects on the economy is the increase
tionship between the duration of a project and the investment
of plant flexibility. The structural flexibility obtained by the modular
sum as for any given project, accruing costs and the project
design poses the chance to build processes quickly and in multiple
duration can be expressed as a relation, i.e. different durations
small scale units (Buchholz, 2010). From lab to production scale a small
factor applies, reducing scale-up issues. Potentially, existing modules
will yield different costs (Khosrowshahi, 2002).
can already be used for product development and production of sample As a starting point for the lead time calculation thus, the
amounts while production capacity can later be increase by number- fixed capital investment (FCI) must be calculated first. The
ing up. Such integration of product and process development, leading starting parameters used for calculating phase durations are
to a reduction of development periods was shown e.g. by Brodhagen the expenses that accumulate by the engineering activities
98 chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106

Fig. 2 – Illustration of the most important phases of an investment project and assigned project costs. The period
considered in the presented method is marked by grey background. Period durations are not true to scale.
The lower part of the picture was adapted from Bramsiepe et al. (2011).

and the construction work to be conducted in an investment engineering costs should be included in the FCI estimation
project. These parameters can be derived e.g. from existing and the lead time estimation as well; the estimated period
FCI calculations as those provide descriptive parameters for should include the phases from basic engineering to commis-
investment projects. Additionally, an estimation of the FCI sioning and start-up and thus all phases after the estimate (see
including costs of construction work and engineering activ- shaded area in Fig. 2). The estimate itself should take place in
ities contributing to it has recently become available for both the concept phase.
conventional and modular plants using the same methodol-
ogy. This opens the opportunity to identify changes resulting 2.2. Definition of phases in the lead time period
from implementing modular technology and their impact on
material, engineering and construction costs on FCI (Sievers Fig. 2 shows that some phases of the lead time are conducted
et al., 2017), which is the basis for correlating project expenses in parallel. Actually, in literature the phases are separated and
and required project execution time. described differently due to their complexity and mutual links.
Input variables of the proposed method are construction Thus, a clear separation of such phases is already difficult
and engineering costs. Using correlations for project staffing today and “will become even more difficult if lead times are reduced”
and salary information the approach presented provides the (Bramsiepe, 2014).
opportunity to convert expenses for construction work and However, from a management point of view a stage-
engineering activities into time intervals and thus to calculate gate process is necessary to approve breakpoints sequentially
an estimated lead time. (Peters et al., 2003). Referring to this in our approach a clear
specification and sequential separation of lead time phases is
2.1. Application of lead time estimation developed. In the following, the lead time is broken down into
a set of sub phases based on various literature sources.
In Fig. 2 typical phases of an investment project are illus- According to Helmus (2008) a clear separation into project
trated for a conventional chemical production plant. In the planning and project execution is possible. The project
conceptual design phase, the best alternative among possible planning phase can further be separated into product devel-
production concepts developed is identified gradually, which opment, process development and implementation phase
may include modular and non-modular production concepts. (Mosberger, 2012; Festel et al., 2001; Wagner, 2003; Sattler and
In chapter 1 we have ascertained that in this phase a first eco- Kasper, 2000) (compare Fig. 3).
nomic evaluation is necessary to compare these production As described above the product development phase is not
concepts and as the lead time is a decisive factor for the eco- included in the lead time. Process development in contrast
nomic result, an estimation of the lead time is also required takes place during the conceptual design phase (compare
in the conceptual design phase. Fig. 2) and aims at selecting an optimum process alternative
In later phases of the project parallel work on several alter- including lead time estimation. Using that optimum alterna-
natives should be avoided. This is important, since the costs tive, a feasibility study can be conducted. Given a feasible
increase with the progress of project duration and here paral- process alternative, the project execution phase is initiated
lel work on alternative concepts that may be discarded later (Mosberger, 2012; Navarette, 2009). As explained above the
is particularly costly (Baerns et al., 2006). The project costs lead time estimation takes place during process development
as well as the number of process alternatives applied to the phase and includes all phases after the estimate. Conse-
project phases are shown in Fig. 2. Starting with the basic quently, the beginning of the lead time period to be estimated
engineering phase the costs substantially increase. To include is not identical with the end of the process development phase
these costs and the corresponding phase duration the basic or the start of the implementation phase respectively. For
chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106 99

Fig. 3 – Phase definition of an investment project as defined by Helmus (2008) (top row), Mosberger (2012), Festel et al.
(2001), Wagner (2003), Sattler and Kasper (2000) (middle row) and Navarette (2009) (last row). The lead time phases chosen
for the proposed approach correspond to the structure according (Navarette, 2009). Period durations are not true to scale.

clear phase separation a definition used by Navarette (2009) project team and selection of contractors are conducted. Fur-
is applied who defines a pre-project phase before the imple- thermore, basic engineering activities are intensified, building
mentation phase. The pre-project phase represents a clear the basis for more detailed cost estimation (±10 % to ±25 %)
starting point and is the first phase contributing to the lead and the final approval for expenditure estimate (AFE). Prepa-
time. Following Navarette’s (2009) nomenclature the imple- ration of AFE and a waiting time for final AFE approval for
mentation phase as defined by (Mosberger, 2012; Festel et al., construction start are also assigned to this phase (Mosberger,
2001; Wagner, 2003; Sattler and Kasper, 2000) will be called 2012). For the calculation procedure presented, we assume a
project start phase in the following (compare Fig. 3). positive AFE decision, that investment capital is released and
As a result of the process development phase at the begin- project execution is initiated.
ning of the pre-project phase basic knowledge about the Project phases until this point are assigned to the project
process is already available; e.g. reaction kinetics and a block planning period. The second superordinate phase is the
diagram of the process is available, from laboratory experi- project execution period (Helmus, 2008). This period can fur-
ments separation parameters including expectable yields are ther be separated into the phases basic engineering, detail
known and market forecasts and an analysis of the patent engineering, procurement, assembly/erection and commis-
situation are available. Before the pre-project starts, a first sioning (Madauss, 2000; Mosberger, 2012). In fact, first basic
process flow diagram including equipment list and mass engineering activities do start in the pre-project phase before
and energy balance is available, too. Investment capital for the basic engineering phase due to planning tasks that are
proceeding with the next project phase is approved after suc- necessary as basis for later activities. The same holds true
cessful check of economy i.e. the conceptual design is fixed for for detail engineering and also for construction activities. For
the follow-up phases, beginning with the pre-project phase. example, while first site preparation and excavation work is
The pre-project phase is the first phase contributing to executed, detail planning of secondary equipment, piping, fit-
the lead time and represents the transition from process tings, etc. still needs to be elaborated (Sattler and Kasper,
development to implementation phase. In this phase, basic 2000). The period between AFE approval and first construc-
engineering is initiated and the production concept and pro- tion work incorporates preparatory work that mainly includes
cess design are refined. Results of this phase are (Navarette, detail engineering tasks (Navarette, 2009). There is a mis-
2009): match between a strict differentiation of the basic and detail
engineering phase and the actual starting times of different
engineering activities to be considered. As a consequence, we
• Fixed plant location and size
concluded that it is more practical to follow Navarette’s (2009)
• Fixed product specifications
approach who just divided the project execution phase into
• Fixed material and energy balance
an “engineering lead time” and the “construction” phase.
• Definition of recycle and purge streams
The engineering lead time follows the “project start” resp.
• Definition of equipment size
implementation phase (compare Fig. 3). Before construction
• Raw material and utilities selection
can start, preparatory work necessary for first construction
• List of motors and actuators
tasks needs to be completed. In parallel to this preparatory
• P&ID and preliminary floor plan
work, the main part of detail engineering is finalized. During
• Concept for instrumentation and automation
the engineering lead time, the following actions are performed
• HAZOP and environmental pollution study
to prepare start of construction:
• Packaging and logistic concept
• Finalize long delivery equipment specification and select
Basic engineering work is ongoing at the end of the pre- vendor
project phase but the results until this time are the starting • Complete basic engineering
point for first detail engineering activities and mechanical • Complete detail engineering to approx. 90%
design (Navarette, 2009). • Contracting for site preparation, foundations and steel
After completion of the pre-project, the “project start” structure and supports
(Navarette, 2009) or “implementation phase” (Mosberger, 2012;
Festel et al., 2001; Wagner, 2003; Sattler and Kasper, 2000) is ini- Of course, engineering work is not finished after engi-
tiated. In this phase increased project planning, formation of a neering lead time. First construction work is performed
100 chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106

immediately after engineering lead time and is carried out The construction wage costs cwc are determined by dividing
in parallel to final detail engineering activities (Navarette, the annual median pay of $50,620 (Bureau of Labor Statistics,
2009). Further engineering-related activities during construc- U.S. Department of Labor) by a total of 1790 h actually worked
tion phase are procurement, site supervision and enhanced annually (OECD) and applying that the pay corresponds 69.7%
project management (Mosberger, 2012). of the total employer costs (Bureau of Labor Statistics, U.S.
Whether commissioning resp. start-up is considered as Department of Labor). Applying the 2015 average exchange
part of project execution or not is a question of definition. rate of 1.1095 $/D (European Central Bank) construction wage
While Bernecker (2001) or Sattler and Kasper(2000) summarize costs of cwc = 37 D /h (rounded) result. The annual median pay
technical acceptance testing and start-up as commissioning, used as basis is “the wage at which half the workers in an
Navarette (2009) distinguishes between these activities and occupation earned more than that amount and half earned
considers the start-up as separate phase while all acceptance less” (Bureau of Labor Statistics, U.S. Department of Labor).
tests are considered as part of construction finalization. By Compared to the arithmetic mean the median implies the
choosing Navarette’s definition of the construction phase we advantage of being robust against outliers and is applicable
decided to consider start-up as separate phase, avoiding to without incorporating additional dispersion measures. Apply-
take acceptance tests into account twice. Thus, both engi- ing the procedure to engineering wage costs, the result is
neering lead time and construction together are considered cwe = 70 D /h (rounded), based on an annual median pay of
as project execution phase. The project phases defined for $97,360 (Bureau of Labor Statistics, U.S. Department of Labor).
further use are shown in Fig. 3. Construction costs Cc are considered as all labor costs for
workshop and field work that are assigned to assembly and
3. Calculation procedure erection of the production plant. As explained in chapter 1
we use data from a previous work (Sievers et al., 2017) from
According to our approach, the lead time duration (tLT ) is the which construction costs Cc can be calculated. Details about
sum of the durations of the pre-project phase (tPP ), project start the origin of construction costs Cc are given in chapter 4.
phase (tPS ), project execution phase (tPE ) and start-up phase The project execution phase tPE is a sum of the construction
(tSU ). phase duration tc and the engineering lead time teLT . As an esti-
mation from analysis of different project schedules, Navarette
tLT = tPP + tPS + tPE + tSU (1) (2009) found that tc makes up 80% of the sum of tc and teLT but
has a minimum duration of three months. Applying that, teLT
As described in chapter 2 expenses for construction work can be calculated.
and engineering activities will be converted into time inter-
vals to determine the values of the summands. During project teLT = max [0.25 · tc ; 3] [teLT ] = month (4)
execution phase calculation interim results are generated that
will be used for calculating other phase durations. Therefore, Applying this estimation, the duration of the project exe-
the description of the phase durations’ calculation starts with cution phase tPE can be calculated.
the project execution phase.
The project execution phase (tPE ) is the sum of the con- tPE = teLT + tc (5)
struction phase duration tc and the engineering lead time teLT
(compare Fig. 3). First, the construction phase duration is cal- Next the duration of the pre-project phase (tPP ) is cal-
culated. culated. This can be done based on engineering costs Ce ,
The duration tc is calculated depending on the construc- which can be taken as a result from a previous work (Sievers
tion work hours hc . For this a result given by Navarette (2009) et al., 2017) similar to construction costs, as explained in the
is used who found a correlation between the actual construc- Appendix A. Engineering costs are considered as labor costs
tion working hours on the field and the actual field duration for basic and detail engineering, project management and site
i.e. duration of construction phase (see Fig. 4). This correlation supervision during construction phase and plant start-up.
is not linear because first, a basic amount of working hours Similar to calculating construction phase duration, engi-
is necessary nearly independently on the size of a project, neering work hours he are determined based on engineering
e.g. contractor’s job preparation scheduling, management of costs Ce and engineering wage costs cwe (the value of cwe is
workers and accommodation or equipment transport, and 70 D /h, as given above).
second the bigger the project is, the more work is performed
in parallel. he = Ce /cwe (6)
For calculation of the duration of construction phase tc the
correlation by Navarette can be described by an approximate From total number of engineering hours he usually a frac-
function determined by least square method: tion of approx. 12% is allocated to the pre-project phase
(Navarette, 2009). The duration of tPP can be calculated as soon

3 × 10−11 × hc + 5.53 × 10−5 × hc + 2.8283 ∀hc ≤ 105 ; [tc ] = month
2 as the engineering hours performed per month are known.
tc =  −3  These depend on the number of engineers working in parallel
4.5114 · ln 10 × hc − 12.102 ∀hc > 105 ; [hc ] = hours
in this phase (NePP ) and the effective monthly working hours
(2) of an engineer (h = 1790/12 = 149 h/month (OECD)).
M

0.12 · he
Construction work hours hc can be determined based on tPP = (7)
NePP · hM
construction costs Cc and construction wage costs cWC .
Obviously, NePP has to be determined to calculate tPP .
hc = Cc /cwc (3) According to the tasks to be performed the number of engi-
chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106 101

Fig. 4 – Correlation between construction work hours and field duration.


Data taken from Navarette (2009).

neers changes throughout project execution. Sattler and project phase duration tPP would result for modular plants
Kasper (2000) gives corresponding data about the typical compared to non-modular plants, if engineering costs and
number of engineers throughout the course of an invest- therewith he were lower.
ment project. He shows that the number of engineers in the To calculate the lead time duration tLT the start-up phase
pre-project phase is rather constant and corresponds to the (tSU ) and the project start phase (tPS ) need to be calculated (cf.
number of engineers at the beginning of the engineering lead Eq. (1)). For the project start phase we assume that there is
time phase. This is plausible as at the end of the pre-project no difference in phase duration between modular and non-
phase and at the beginning of the engineering lead time phase modular plant design as the tasks assigned to this phase
basic engineering activities of a similar amount take place (compare chapter 2.2) are depending on the company’s organi-
(Sattler and Kasper, 2000). During the engineering lead time zational structure rather than on the technology chosen. The
the number of engineers increases gradually. The number of project start phase duration was estimated with 4.5 months
engineers at the beginning of the engineering lead time cor- according to the time for sequentially completing following
responds to 40.4% of the number of engineers averaged over main tasks (Navarette, 2009):
the engineering lead time (Sattler and Kasper, 2000). In the
project start phase between the pre-project phase and the • Form project team (0.5 month)
engineering lead time phase (compare Fig. 3) organizational • Select contractor (1.5 month)
and economy-based tasks are performed, so no impact on the • Prepare AFE estimate (0.5 month)
number of engineers is observed (Sattler and Kasper, 2000). • Wait for AFE approval (2 month)
Concluding, we assume that NePP can be described in depen-
dency of the number of engineers NeLTA averaged over the Finally, the duration of start-up needs to be considered.
engineering lead time (see Eq. (8)), which will be calculated It depends on the training of the responsible team and on
in the next step. smooth operation of the plant. Moreover, this phase strongly
depends on the conditions and complexity of the process to
NePP = 0.404 · NeLTA (8) be performed. Due to these reasons we do consider the dura-
tion of the start-up phase tSU as a cost-independent, fix value
Navarette (2009) found that the average number of engi- and assume a duration of 1 month as proposed in literature
neering hours raised in the engineering lead time corresponds (Navarette, 2009; Sattler and Kasper, 2000).
to 35% of the total engineering hours (he ). Applying this, NeLTA
can be calculated using the result for the calculated engineer- 4. Results
ing lead time (teLT , for procedure see Eq. (4)).
Input variables of the proposed method are construction
0.35 · he and engineering costs. The approach presented provides the
NeLTA = (9)
teLT · hM opportunity to convert these costs into corresponding periods
and thus to calculate an estimated lead time.
Applying Eq. (7) the pre-project phase duration tPP can The necessary cost information is taken from a previous
be calculated. We assume that the staffing and structure of work where we propose a method capable of taking the impact
companies which provide engineering activities will be inde- of modular design on FCI into consideration (Sievers et al.,
pendent of the plant structure (modular or conventional) to 2017). The FCI estimation bases on a cost factor method pro-
be considered. Based on that assumption we conclude that the posed by Peters et al. (2003) developed for conventional plants
number of engineers working on the investment project would and transfers the “delivered purchased equipment costs” of
not be affected and therefore would not differ between plan- the plant components into FCI using cost factors. The cost fac-
ning modular and non-modular plants. As described above, tors used were adjusted to consider different site conditions.
the lead time estimation method is meant to be applicable This was necessary to take into account that construction site
for both modular and non-modular design. For non-modular conditions change for plant erection with step-wise imple-
plants, a minimum duration of this phase of three months is mentation of a modular plant. For example, while the first
proposed and an upper limit of four months (Navarette, 2009). module is installed under greenfield conditions, the construc-
By keeping the number of engineers constant, a reduced pre- tion site is already prepared for follow-up modules, which has
102 chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106

Fig. 5 – Resulting cost data according to Sievers et al. (2017) for different values of delivered purchased equipment costs,
used as input parameters for further lead time consideration.

an impact on costs. In the FCI estimation procedure, engineer- non-modular backbone facility that provides energy and util-
ing and construction costs are calculated separately for the ity supply. The process used is a generic example that is based
backbone facility, the first module and follow-up modules. The on a reference process and a modular process both developed
cost data generated by that method can be used in the lead as an example for small scale specialty chemicals production
time estimation method so that not only a cost but also a lead within the F3 factory project in 2013. The delivered purchased
time estimation can be derived for each individual stage of the equipment costs of the continuously operated reference plant
modular plant. This is shown in an example below (scenarios with one production line are 2 million D , the number of main
2 and 3). equipment items is 20 and the scale-independent “fixed
Moreover, in the FCI estimation method non-scaling costs equipment costs” are 780,000 D . Applying the rule of economy
are considered that are mostly independent on the plant’s of scale (degression exponent = 0.7), a single production line
capacity. This has to be taken into account when considering with a third of production capacity of the continuously oper-
containerized production lines limited in scale. For example, ated reference plant amounts for 927,000 D . Both plants are
the size and corresponding planning effort of a concentra- built under greenfield conditions (Sievers et al., 2017).
tion measurement is nearly independent on the stream that The results of applying the FCI estimation method were
is monitored. Additionally, there is a base effort of engineer- used for calculating lead times and comparison between con-
ing (e.g. project team assembly, contractor selection, start-up ventional and modular plant design. The resulting data for
supervision, preparation of approval for expenditure) which is construction (Cc ) and engineering costs (Ce ) used for lead time
not linearly dependent on equipment costs (Navarette, 2009). estimation can be extracted from the FCI calculation method
Like for costs this fact influences lead time, accordingly. using the procedure explained in the Appendix A.
To achieve the same production capacity like a conven- The resulting cost data (construction and engineering costs
tional plant a modular plant requires a larger number of as well as fixed capital investment for both, conventional and
individual equipment items when these are limited in size modular construction) that is the basis for lead time calcu-
(Bramsiepe, 2014). This leads to an increased complexity for lation for the example chosen are shown in Fig. 5. To cover
engineering and construction and thus increased costs con- a range of investment sizes and to evaluate the resulting lead
sidered in the FCI estimation method and corresponding times the FCI calculation was done for different plant sizes and
impact on lead times. resulting values of delivered purchased equipment costs rang-
On the other hand, there are changes induced by mod- ing from the given initial value up to 20 million D . Thereby the
ularization that lead to a reduction of engineering and number of equipment items and fixed equipment costs were
construction effort. For a modular plant setup construction kept constant, no numbering up was considered.
cost reduction is expected by using standardized compo- Based on the cost data given the lead time calculation pro-
nents and installation procedures in the modular plant (Lier cedure presented in chapter 3 was applied. The resulting lead
et al., 2015; Behr et al., 2003). Furthermore, construction can times are shown in Fig. 6. In this “scenario 1”, resulting lead
take place under workshop conditions and less field labor is times for the conventional plant range from 16.5 to 32 months
required for module assembly (Lier et al., 2015), which was for investment sizes (FCI) of 3 to 95 million D , which is a good
considered in the FCI estimation method (Sievers et al., 2017). agreement with literature data (Rauch, 1998; Brodhagen et al.,
Engineering costs are expected to be reduced using a modular 2012).
approach due to pre-designed structures and design repetition Resulting lead times for corresponding modular plants are
(Buchholz, 2010; Lier et al., 2015), which was also investigated 13.9–26.4 months. This corresponds to a lead time reduction
and considered in the FCI estimation method (Sievers et al., of 15.5%–17.3%. Whereas in the case of small investment the
2017) and takes effect for lead time estimation. reduction of pre-project phase is determining for lead time
Sievers et al. (2017) demonstrated the FCI estimation reduction (1.5 vs. 3 months), for large investments the major
method using a brief example of a modular production plant leverage comes from reducing the project execution phase
that includes three identical modular production lines and a
chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106 103

Fig. 6 – Scenario 1 — resulting lead times and project phase durations for conventional and modular construction of
different sizes of the investment project.

(18.6 vs. 22.6 months), due to a significant reduction in con- of the project execution phase. Moreover, for modular plant
struction effort. lead time calculation the available number of engineers cor-
For this result a scale-up of each single equipment item responds to the number of engineers of the conventional plant
was assumed for different production capacities, leading it is compared with (see NeLTA , chapter 3), leading to a reduc-
to increasing delivered purchased equipment costs without tion of the pre-project phase. As a result, the lead time of
changing the actual setup of the plant. The idea of modular the production modules is essentially determined by the cost-
production plants of course is to use segmented construction independent periods considered in lead time calculation and
elements to gain flexibility concerning capacity and product do rarely correlate with the plant capacity in the range inves-
variability, as described in chapter 1. Regarding the lead time, tigated. Due to the same reason, the difference between the
the construction elements to be distinguished in the F3 fac- first production module and follow-up modules is negligible.
tory approach taken as example for modularization are the In scenario 3 a fixed production module size is assumed.
backbone facility and the production modules. In the FCI cal- Different plant capacities are represented by a corresponding
culation methodology used as starting point for lead time number of identical production modules. This approach would
estimation learning effects originating from module design allow preproduction of modules and thus a significant reduc-
repetition are considered (Sievers et al., 2017). Therefore, the tion of lead time regarding capacity expansion. Nevertheless,
first production module and follow-up modules are distin- to compare such an approach with a conventional plant setup
guished as well. the same capacity needs to be considered, which is the design
Hence, two further scenarios should be evaluated. In sce- capacity of the conventional plant and the design capacity
nario 2, the size of the production modules and the backbone of the final expansion stage of the modular plant. According
facility are scaled as before but a breakdown of lead time pro- to the FCI calculation approach the backbone facility is not
portions of each individual construction element is used to considered as a modular setup (Sievers et al., 2017). Thus it
determine which element adds which portion to the total lead needs to be designed to host the number of production mod-
time. In scenario 3 the module size is kept constant but the ules according to the final expansion stage of the complete
number of modules is varied according to the plant capac- modular plant.
ity. In this case the size of the backbone facility again scales It is expected that a backbone facility designed to host a
with the plant capacity as it needs to be able to host the total higher number of production modules is more complex than a
number of production modules. facility hosting a lower number of production capacity offering
Fig. 7 (scenario 2) shows resulting lead times separately for an identical total capacity. Hence this should also be reflected
the backbone facility, the first production module and follow in costs and lead time of the backbone facility, which would
up modules for different plant sizes. The number of mod- diminish the advantages expected of the approach of a mod-
ules was fixed to three, which means the backbone facility is ular plant.
constructed to host a maximum of three modules. Assuming In Fig. 8 the lead time calculation results for scenario 3 are
parallel planning and construction of the production modules shown. The grey dots show the maximum number of produc-
and the backbone facility the longest lead time determines the tion modules hosted by the corresponding backbone facility.
total lead time which in this example is the lead time of the The resulting delivered purchased equipment costs of the pro-
backbone facility and ranges between 13.7 and 23.3 months. duction modules amounts to 0.5 million D per module. Due
Compared to the conventional plant this corresponds to a lead to the higher complexity and costs of the backbone facility
time reduction between 2.8 and 8.7 months. the lead time increases compared to scenario 2. It amounts
According to the FCI calculation procedure (Sievers et al., to 12.6–28.7 months. Assuming parallel processing of all con-
2017) the backbone facility is not considered as a modular struction elements the lead time of the complete modular
unit but as a conventionally built construction in which the plant is determined by the backbone facility’s lead time as
modular production lines are hosted. As a consequence, the it needs to be finished before start-up of the modular plant.
construction and engineering costs of the backbone facility Compared to the conventional plant this leaves a lead time
are directly correlated with the production capacity and the saving potential between 2.6 and 3.9 months, which is less
lead time accordingly. For the production modules cost reduc- than in scenario 2.
tions from modularization take effect resulting in a reduction
104 chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106

Fig. 7 – Scenario 2 — lead times for conventional and modular construction of different plant sizes represented by delivered
purchased equipment costs.

Fig. 8 – Scenario 3 — lead times for conventional and modular construction of different sizes of the investment project with
a backbone facility that needs to host a maximum number of modules that corresponds to the capacity of the conventional
construction (grey dots).

This result shows a demand to decrease the lead time the phase durations and the overall lead time can be calcu-
of the backbone facility as its reduction offers the largest lated using the expenses for engineering activities and the
lever to decrease total lead time for the modular plant. construction work to be conducted in an investment project
Such a reduction could be achieved e.g. by modularization of as starting parameters. To convert expenses for construction
the backbone facility. Assuming that the backbone facility’s work and engineering activities into time intervals correla-
capability for hosting production modules could be adapted tions for project staffing and salary information were used.
stepwise according to the desired number of production mod- Certainly, the parameter values used are worth being dis-
ules to be hosted, the total lead time of the plant might no cussed in detail, but we expect them to be in the right order.
longer be determined by the backbone facility’s lead time and Since the method is generic the factors may be adjusted when
could be reduced significantly. If the lead time of such mod- new knowledge is available.
ular backbone facility was comparable to the modules’ lead The proposed method can be applied to non-modular
time (12.6 months), depending on the plant’s capacity total conventional plant design and modular plant design, which
lead time reduction compared to the conventional plant would enables comparative studies. For such comparison the cost
be between 3.9 and 18.7 months (compare Fig. 8) or 23%–60%, basis provided by Sievers et al. (2017) for modular and non-
representing a very significant reduction. From this result we modular plant design was used, which considers the impact
can conclude that an approach for modular plant setup like of modular design on construction and engineering costs.
the F3 factory approach taken as example needs to include The approach of modularization used as an example was
the modularization of the backbone facility as well. Alter- also used in the F3 factory project. By that approach, the mod-
natively, a non-modular but standardized backbone facility ular plant is composed of modular production lines which are
design could be useful. This way engineering and construction housed by a non-modular backbone facility. Because the back-
of the backbone facility could be done once, independently bone facility is non-modular, it has to be designed according
from the process to be performed or specifically for a class of to the final (maximum) capacity of the production plant and
processes, which would allow to reduce lead time especially if cost reductions from modularizations cannot take effect.
a numbering up approach for the backbone facility itself would As a consequence, the backbone facility adds the biggest
also be considered. proportion to the lead time. Compared with a conventional
plant total lead time reduction is between 2.6 and 5.5 month
depending on the size of the investment. If the lead time of the
5. Conclusion
backbone facility would be significantly shorter, total lead time
of the modular plant design could be reduced substantially
A method for calculating lead times of modularly designed
assuming parallel assembly of the modules and the backbone
plants is presented. Phases that have to be considered for lead
facility.
time estimation were identified. Using the method presented,
chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106 105

For that the backbone facility would need to follow a stan- fraction, ci for the construction cost fraction of the correspond-
dardized design or ideally a modular design as well so that a ing cost item (columns three and four, Table 1).
step-wise expansion of the backbone facility would be pos-

sible. By that the investment into the first production line CMat\OVC = ai · mi where i = COCW , COB , . . ., CAEI , FFEC (10)
providing initial production capacity would represent a com- i
parably small investment with a short lead time. If the lead
time of such modular backbone facility was comparable to 
CConstr\OVC = ai · ci (11)
the production lines’ lead time, depending on investment
i
size total lead time reduction would be between 3.9 and 18.7
months representing a very significant reduction of 23%–60% Then the material cost fraction (mOVC ) and the construction
compared to the lead time of the conventionally designed ref- cost fraction (cOVC ) of the contingency costs can be calculated:
erence plant. This is considered as the maximum lead time
reduction that can be achieved through modular plant design CMat\OVC
and would represent a major potential for speeding up con- mOVC = (12)
CMat\OVC + CConstr\OVC
struction of chemical plants.
The results may be validated when further data gets avail- cOVC = 1 − mOVC (13)
able, e.g. by future construction of plants according to the
modular F3 factory design. However, the identified lead time Finally, the sum of construction costs CC can be deter-
reductions would substantially improve the economy by gen- mined:
erating earlier sales resulting in a shorter pay-back period.
This in turn helps reducing the investment risk and allows CC = COVC · cOVC + CConstr\OVC (13)
going for opportunities that otherwise were too risky. Ulti-
mately this creates an increased degree of business flexibility.
The engineering costs Ce are calculated as a separate cost
item COVE in (Sievers et al., 2017)
Acknowledgment
Ce = COVE (15)
The research leading to these results has received funding
from the European Community’s Seventh Framework Pro-
References
gramme (FP7/2007-2013) under grant agreement no. 228867.

Baerns, M., Behr, A., Brehm, A., Gmehling, J., Hofmann, H.,
Appendix A. Onken, U., Renken, A., 2006. Technische Chemie. Wiley-VCH
Verlag GmbH & Co. KGaA, Weinheim(DE).
In the following, the calculation of the construction costs Behr, A., Brehme, V.A., Ewers, C.L.J., Grön, H., Kimmel, T.,
Cc and engineering costs Ce based on data generated in the Küppers, S., Symietz, I., 2003. Neue Entwicklung bei Anlagen
und Verfahren för die Produktion von Pharmawirkstoffen.
established FCI calculation procedure (Sievers et al., 2017) is
Chem. Ing. Tech. 75 (4), 417–427.
explained. Basis for calculating Cc and Ce are the single cost Bernecker, G., 2001. Planung und Bau verfahrenstechnischer
items shown in Table 1, which are considered in the FCI esti- Anlagen: Projektmanagement und Fachplanungsfunktionen.
mation method described in a previous work (Sievers et al., Springer Verlag.
2017). Bramsiepe, C., Kussi, J., Schembecker, G., 2011. Projektierung von
First, using the calculation procedure described by Sievers Chemieanlagen: Mit der 50%-Idee vom Produkt zur
Produktionsanlage. Chem. Tech. 40, 50–52.
et al. (2017) the values of the single cost items (listed in the
Bramsiepe, C., Sievers, S., Seifert, T., Stefanidis, G., Vlachos, D.,
Table 1) and – accordingly – the sum of material costs (CMat \OVC )
Schnitzer, H., Muster, B., Brunner, C., Sanders, J., Bruins, M.,
and construction costs (CConstr \OVC ) without contingency costs Schembecker, G., 2012. Low-cost small scale processing
(COVC ) can be determined. In the following equations, ai stands technologies for production applications in various
for the costs of each cost item (COCW , COB ,. . .) listed (see first environments — mass produced factories. Chem. Eng.
and second column, Table 1), mi stands for the material cost Process. Process Intensif. 51, 32–52.

Table 1 – Extract from results elaborated in a previous work, giving an overview about the cost items considered (Sievers
et al., 2017).
Cost item ai Material costs fraction mi Construction costs fraction ci

Outside battery limits construction work COCW 60.4% 39.6%


Outside battery limits buildings COB 58.8% 41.2%
Outside battery limits facilities COF 58.8% 41.2%
Delivered purchased equipment costs BdPEC 100% 0%
Piping material CCPM 100% 0%
Material for electrical installations CCME 100% 0%
Supports, platforms, etc. CCSP 50% 50%
Equipment insulation and painting CCIP 36.3% 63.7%
Inside battery limits buildings, HVAC CCIB 50.4% 49.6%
Auxiliary work CAAW 0% 100%
Equipment assembly CAEA 0% 100%
Piping assembly CAPA 0% 100%
Electrical installation CAEI 0% 100%
Instrumentation BFEC 75% 25%
106 chemical engineering research and design 1 2 8 ( 2 0 1 7 ) 96–106

Bramsiepe, 2014. Information technologies for innovative process Khosrowshahi, F., 2002. Project cost-time optimal solutions. In:
and plant design. Chem. Ing. Tech. 86 (7), 966–981. Greenwood, D. (Ed.). 18th Annual ARCOM Conference, 2–4
Brodhagen, A., Grünewald, M., Kleiner, M., Lier, S., 2012. September 2002, University of Northumbria. Association of
Increasing profitability by accelerated product- and process Researchers in Construction Management, Vol. 2, 839–848.
development with modular and scalable apparatuses. Chem. Löb, P., 2013. EU FP7 Project CoPIRIDE — towards new production
Ing. Tech. 84 (5), 624. and factory concepts for a sustainable and competitive
Buchholz, S., 2010. Future manufacturing approaches in the European chemical industry. Green Process. Synth. 2 (5),
chemical and pharmaceutical industry. Chem. Eng. Process. 379–380.
Process Intensif. 49, 993––995. Lier, S., Wörsdörfer, D., Grünewald, M., 2015. Wandlungsfähige
Buchholz, S., 2013. Bayer Technology Services GmbH (project Produktionskonzepte: Flexibel, Mobil, Dezentral, Modular,
coordinator), Final report F3 Factory project. F3 Factory project, Beschleunigt. Chem. Ing. Tech. 87 (9), 1147––1158.
http://www.f3factory.com/scripts/pages/en/newsevents/F3 Madauss, B., 2000. Handbuch Projektmanagement.
Factory final report to EC.pdf. (Accessed 30 January 2016). Schaffer-Poeschel, Stuttgart.
Burdorf, A., Kampczyk, B., Lederhose, M., Schmidt-Traub, H., Mosberger, E., 2012. Chemical plant design and construction. In:
2004. CAPD — computer-aided plant design. Comput. Chem. Ullmann’s Encyclopedia of Industrial Chemistry. Wiley-VCH,
Eng. 28 (1–2), 73–81. Weinheim.
Bureau of Labor Statistics, U.S. Department of Labor. Organization for economic co-operation and development
Occupational Outlook Handbook, 2016-17 Edition, Plumbers, (OECD). Average annual hours actually worked per worker
Pipefitters, and Steamfitters, on the Internet at (basis: total employment).
http://www.bls.gov/ooh/construction-and-extraction/plumbers https://stats.oecd.org/Index.aspx?DataSetCode=ANHRS. (Data
-pipefitters-and-steamfitters.htm. (Visited 15 October 2016). extracted at 16 October 2016).
Bureau of Labor Statistics, U.S. Department of Labor. Employer Navarette, Pablo F., 2009. Planning, Estimating, and Control of
Costs For Employee Compensation — June 2016, Private Chemical Construction Projects.
industry workers, Peters, M.S., Timmerhaus, K.D., West, R.E., 2003. Plant Design and
http://www.bls.gov/news.release/pdf/ecec.pdf. (Visited 15 Economics for Chemical Engineers, 5th edition. The
October 2016). McGraw-Hill Companies, Inc.
Bureau of Labor Statistics, U.S. Department of Labor. Rauch, J., 1998. Mehrproduktanlagen. Wiley-VCH, Weinheim.
Occupational Outlook Handbook, 2016-17 Edition, Chemical Sattler, K., Kasper, W., 2000. Verfahrenstechnische Anlagen:
Engineers, on the Internet at Planung, Bau und Betrieb. Wiley-VCH Verlag GmbH & Co.
http://www.bls.gov/ooh/architecture-and-engineering/ KGaA, ISBN 9-783-52728459-7.
chemical-engineers.htm. (Visited 15 October 2016). Schmidt-Traub, H., Holtkötter, T., Lederhose, M., Leuders, P., 1999.
European Central Bank. Euro exchange rates USD, Average An approach to plant layout optimization. Chem. Eng.
2015-01-01 to 2015-12-31. Technol. 22 (2), 105––109.
https://www.ecb.europa.eu/stats/exchange/ Seifert, T., Sievers, S., Bramsiepe, C., Schembecker, G., 2012. Small
eurofxref/html/eurofxref-graph-usd.en.html. (Data extracted scale, modular and continuous: a new approach in plant
on 16 October 2016). design. Chem. Eng. Process. Process Intensif. 52, 140–150.
Festel, G., Hassan, A., Leker, J., 2001. Betriebswirtschaftslehre für Seifert, T., Fakner, P., Sievers, S., Stenger, F., Hamers, B., Priske, M.,
Chemiker: eine praxisorientierte Einführung. Springer Verlag. Becker, M., Franke, R., Schembecker, G., Bramsiepe, C., 2014.
Grundemann, L., Schoenitz, M., Scholl, S., 2012. Shorter Intensified hydroformylation as an example for flexible
time-to-market with micro-conti processes. Chem. Ing. Tech. intermediates production. Chem. Eng. Process. Process
84 (5), 685. Intensif. 85, 1–9.
Helmus, F.P., 2008. Process Plant Design. Wiley VCH, Weinheim. Sievers, S., Seifert, T., Franzen, M., Schembecker, G., Bramsiepe,
Jameson, P.H., 2007. Is modularization right for your project? C., 2017. Fixed capital investment estimation for modular
Hydrocarbon Process. (December), 67–71. production plants. Chem. Eng. Sci. 158, 395–410.
Kampczyk, B., Hicking, B., Schmidt-Traub, H., 2004. More efficient Wagner, W., 2003. Planung im Anlagenbau, 2nd edition. Vogel
plant design by modularization? Chem. Eng. Technol. 27 (5), Business Media/VM.
481––484.

You might also like