PROCEDURE:
SEQUENCE RUN
ORDER EQUIPMENT NAME EQUIPMENT CODE FEEDBACK/ CONDITION PRESET RUN TIME
MATERIAL TRANSPORT GROUP
RUN ORDER #1 G-ASH SILO DEDUSTING FAN X-4 A RUN 10 SEC
G-ASH SILO LEVEL TRANSMITTER LT
SOLENOID VALVE SV
RUN ORDER #2 DIVERTER GATE LIMIT SWITCH X-6_LS1 LIMIT OPEN TO G-ASH SILO
RUN ORDER #10 DRYER DUST COLLECTOR FAN 3-5A RUN 10 SEC
RUN ORDER #11 DUST COLLECTOR FAN DAMPER 3-5AMOD CLOSE POSITION 15-20% INITIALLY OPEN
RUN ORDER #14 DRYER MAIN DRIVE & MOTOR FAN 3-4A RUN 10 SEC
MATERIAL ENTRY GROUP
LIMIT TOWARDS DRYER FEED
RUN ORDER #15 DIVERTER X-5 END
RUN ORDER #20 BURNER FUEL PUMP 3-2A RUN 30% OPEN INITIALLY
MATERIAL FEEDING GROUP UP TO 100%
RUN ORDER #21 BELT CONVEYOR 3-3M RUN