BALANCE O

Location Activity
Road 1
1 Cutting of expansion gaps
2 Asphalt installation on expansion gaps
3 Lamp posts pedestals 6 units
4 Sidewalk - Right side
5 Parking area near McDo
6 Temporary Access road for equipment and materials
7 Painting works
8 Plant boxes
9 Parking area at the corner of Mcdo drive thru
Road 2
10 Sidewalk - 2 sides
13 Lamp posts pedestal - 10 units
14 Asphalt laying at expansion gaps
15 Painting works

Road 4
16 Site Preparation
17 For final grading and compaction
18 For laying of formworks
Roadway
Parking spaces
Miscellaneous works
19 Additional parking area at Shakey's side, left side of Road
20 McDo area re-routing of STP pipe
21 Electrical manhole relocation near power house
22 STP AOS Chamber relocation Road 3
BALANCE OF WORKS
Status

Completed on areas with concrete


Ongoing; Awaiting delivery of materials
Completed; Ready to receive Lamp posts
Prepared with base coarse; Ready to receive concrete
Painting of wheel stoppers pending; Manhole cover grating galvanization in-progress, for delivery mid-January
For concreting upon completion of all areas
Shakey's side completed; Mcdo side pending
Completed at the corner of Road 2
Curb, gutter & sidewalk construction is in-progress

Half of right portion left for concreting.


Excavated, reinforcement steel fabricated; reinforcement steel fabricated; Done excavation; For steel reinforcement and formworks fabrication; installation of electrical roughing-ins ongoin
Awaiting delivery of asphalt; ongoing
for finalization to paint all at once

For Field density testing; with ongoing relocation of utilities on STP; FDT tomorrow -11/14; Water-saturated area, for FDT on Monday 11/20
due to disturbed soil condition; wet soil condition
after site prepation and final grading; wet soil condition
50% Concreted 11/24/2017
For site preparation
ongoing excavation of 3 addtl lamp posts; awaiting layout of parking space; for shopdrawing and cost estimates; cost proposal for final review
ongoing excavation; materials already purchased for installation; ongoing excavation; for lay out of 6inches pvc pipe; for layout on 11/27/17
for proposal of alternative solution instead of relocation; ongoing formworks and steel reinforcement; quotation received from supplier; for purchase of water-tight manhole covers
ongoing steel reinforcement fabrication; ongoing excavation, for submission of cost proposal; with verbal approval from Chris Yatco on the 140k cost proposal; excavation done, for rebar a
Estimated Time of Completion (ETC) Remarks

In work schedule

DONE

Monday, November 27, 2017

Thursday, December 21, 2017


Monday, November 20, 2017 resolved DONE
Thursday, November 16, 2017 DONE
Monday, November 27, 2017

Monday, November 27, 2017 FDT not possible due to strong rains last week;
Monday, November 27, 2017
Monday, November 27, 2017
Monday, November 27, 2017
Tuesday, November 28, 2017
Thursday, November 30, 2017 c/o owner
Monday, November 27, 2017
Monday, November 20, 2017 c/o LBI
Tuesday, November 28, 2017
Item Location
Road 3
1 Roadway 1
2 Roadway 2
3 Bus Parking Bay 1
4 Bus Parking Bay 2
5 Bus Parking Bay 3
6 Roadway 3
7 Roadway 4
8 Car Park Right side
BALANCE OF WORKS
Status

For final grading and compaction on bus parking bay and roadway; ongoing final grading and elevation; concreted Roadway 11/15 and bus pa
FDT passed; For site preparation 11/18;
5m width x 28m length concreted 11/17
FDT passed; For site preparation 11/18;
FDT passed; For site preparation 11/18;
FDT passed; For site preparation 11/18;
For site preparation 11/18; FDT on Monday 11/20
FDT passed; For site preparation 11/18;
Estimated Time of Completion (ETC) Remarks

Tuesday, November 21, 2017 Concreted 3.075m width x 20m length; done 70%
Saturday, November 25, 2017 Done 35%
Wednesday, November 22, 2017 5m width x 28m length concreted 11/17 DONE
Thursday, November 23, 2017 Done
Friday, November 24, 2017 DONE
Thursday, November 23, 2017 CONCRETED 75%
Friday, November 24, 2017 CONCRETED 75%
Monday, November 20, 2017 DONE