Bill of Quantities (Estimated)

Ventilation and Air Conditioning System


Project Hubco, Pakistan
S. No. Description

1.1.6 Ventilation Equipment Installation

Crane transportation for All HVAC Equipment includes the cost of Re-assambling of
a
Air-Handling units in non access area and Certified crane arrangments..

b Assembly Planning
c Commissioning of HVAC System
d Lettering and Marking
e Preparation of revision plans
1.2 Air lines and installation parts

a Calculating the pressure loss by re-calculation of duct sizes

b Supply & Installation of Rectangular channels as per following detail:


a) Duct Work :1490 Sq.m using lockforming prime quality
24, 22 and 20 Gauge.(Machine made)
b) Duct Insulation. : 1500 Sq. m. 24 kg/m3 with aluminum foil.
c) Hilty Brand Anchores
d) Galv. Imported threaded Rod for Supports.
e) Canopies for vent with back draft dampers..

Supply & Installation of Spiral seam pipes of Aluminum Imported pipe: 24 Mtr with
c
(Imported)

Supply and Installation of Imported Insulated Flexible air pipe 75 Mtr Aprox. with Jublee
d
clamps and round dampers.
Supply and Installation of Airtight shut-off flap in accordance with DIN 1946 : 16.7 Sq.
e
Mtr. And as per qty shown on daring (Imported).
Supply and Installation of Louver flaps: 25 Sq. Mtr and Protective gratings: 17 Sq. Mtr
f
and as per Qty shown on drawing (Imported).
Supply and Installation of Ceiling ducts rectangular/circular: 22 Sq. Mtr Aproz.
g
Lockformer Prime quality machine made for Extract system
Supply and Installation of Fire protection element/BEK-K90 and Fire protection flap FK-
h K90 motorized type (Quantity as per fire damper) with Fusable link certificate complete
in all respect.
i Supply and Installation of Excess pressure louvers: 9 Sq. m.

j Supply and Installation of Disc valves (6 Nos.) Imported

Supply and Installation of Ceiling air outlet: 25 Sq. Mtr Aprox.and Ventilation gratings: 5
k
Sq.Mtr Aprox. As per specifications and stadard. (Imported)

1.3.2 Cooling system: Installation and Comissioning


Installation of Equipment: Split-model cooling unit, Air-cooled axial condenser including
a
Levelling & Vibration isolators fixing.

b Installation of all Air-Handling & Ventilation equipmemnt

c Supply and Installation of cold water buffer tank with all following accessories.

a) Buffer Tank
b) Inlet & Out Let Valves
c) Balancing Valves
d) Heat Exchanger (Plate Type) Imported.
e) Buffer tank insulation.
f) Buffer tank cladding.
g) Pressure gauges.115mm dial, 4 Nos, Make USA
h) Pipe Line Thermometers. Min 90mm stem, 225mm scale, 4 Nos. USA
b Cooling agent filling: as per recommendation of "Rhoss"
c Cooling agent line copper pipe with following accessories:
a) Copper Pipe Dia 50mm to 75mm as per "Rhoss Recommendation.
b) Installation of Other components supplied by manufacturer.
c) Galv. Hangers & Supports.
d) Nitrogen Pressure Testing.
e) Flushing with Nitrogen..
f) Refrigerent Charging as per "Rhoss Recommendation..
Supply and Installation of M.S Pipe line & valves for Cooler Cooling machine as per
d
following detail:

a) MS Seamless Pipe Seamless 32mm to 150mm Dia: 1 Lot


b) All chilled water pipe insulation 64kg/Mtr density. : 1 Lot
c) Isolating valves 2 for Each AHU, Eurpeon Brand
d) Balancing valves 1 for each AHU, Eurpeon Brand.
e) Pipe Thermometer 75mm stem/225mm scale, 2 Nos.for Each AHU etc.
f) Pressure Gauges 115mm dial size, 2 for Each AHU.
g) Binder test point as indicated on pipe line schematic.
h) Drain Cock 1 for each AHU or Pump.
i) Air Vents, 2 for each AHU.

e Supply and Installation of Cooling/Heating circuit pumps Fittings as per following:

a) Pumps 14 Nos for chilled water and cooling media circulation, S.S type and for
primary/secondary circuit.
b) Isolating valves 2 for each pump.
c) Drain Cock
f Heat transfer medium mixture

g Supply and Installation of Drain pipe


Supply and Installation of Closed Cell as per manufacturer recommendation Insulation
h
cooling lines for Rhoss Split Chillers .

1.4 Control equipment: Installation and Comissioning


Technical data: (see page 90 of the techniical specification)
Colour
Width
Height
Depth
Commercial:

a Supply and Installation of ISP1 control system & Electrical switch board.

b1 Installation of Fire dampers

b2 Functional Tests Fire damper

c Preparation

d Comissioning of Power & Control system

e Cable system (Power & Control)

f Stripping, lead-in and installation

g Labelling and marking

Total Amount (Rs.):

Payments : 25% advance against EFU/Adamjee Insurance Gurantee.


50% advance against material delivery at site.
25% during installation.

Gurantees: Insurance gurantees

Offer Validity : 15 days.

Completion time: 6 Months.

Exvclusion : Free of charge power supply and worker accomodation shall be arrange by client.
Amount (Rs.)

500,000

300,000
450,000
80,000
145,000

150,000

6,775,000

340,000

120,000

880,000

1,555,000

675,000

1,350,000

340,000

85,000

1,937,500
300,000

400,000

1,065,000

140,000
2,150,000

3,650,000

2,385,000

235,000
1,620,000

11,900,000

45,000

50,000

25,000

125,000

1,350,000

225,000

65,000

41,412,500