You are on page 1of 8

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 40, NO.

5, SEPTEMBER/OCTOBER 2004 1427

Practical Design Considerations for Application of


GIS MV Switchgear
Chun Ty Lav, Member, IEEE, David B. Staley, Member, IEEE, and T. W. Olsen, Senior Member, IEEE

Abstract—In a recent biotechnology facility project, the de- controls for critical cell banks. In addition, the facility cri-
cision was made to require arc-resistant medium-voltage (MV) teria included maintaining operation through and after major
switchgear for the safety of operating personnel. The available ser- seismic events.
vice voltage was 26.4 kV, limiting the availability of proven designs
The utility service was arranged to accept two incoming
of arc-resistant switchgear. As a result, the owner considered use
of medium-voltage gas-insulated switchgear (GIS) with vacuum lines, although the utility was only able to serve the facility
circuit breakers. Once this decision was made, consideration was initially with one feeder. Backup power for emergency loads
given to using the same class of switchgear for the 4.16-kV voltage was provided by battery powered inverters, and for the standby
equipment in the facilities. This offered advantages of uniformity, loads by on-site diesel generators. Due to the high density of
commonality of spares, and simplification of operator training. standby loads and the potential need for frequent reconfigura-
This paper focuses on the rationale for selection of GIS tion, it was elected to re-feed the normal power system from
switchgear, and the design considerations that had to be addressed
as the project moved from concept to installation to operation. the standby generation system, and implement an automated
Among the issues discussed are the following: load-shedding and load restoration scheme. For reliability
• space requirements for conventional and GIS equipment; and maintainability, the distribution system was arranged in
• arc-resistant performance of GIS equipment; dual-radial primary feeder configuration, with both primary
• design commonality between 4.16- and 26.4-kV equipment; and secondary unit substations being secondary selective.
• installation (cable issues, foundations, workspace, etc.);
• environmental considerations; II. PROJECT REQUIREMENTS AND CONSIDERATIONS
• total cost of ownership;
• reliability/availability; The requirements for the project included a variety of func-
• operational experience. tional and operational elements, including the following.
Index Terms—Arc resistant, gas-insulated switchgear (GIS), 1) Space constraints: The central utility plant electrical room
vacuum circuit breaker. incorporated the primary distribution switchgear, the MV
switchgear for the chillers and the backup generation, plus
I. PROJECT OVERVIEW large secondary unit substations. The room was on the
second floor, adjacent to the generator room, further em-

A major biopharmaceutical company in the Northwestern


U.S. had grown by about 25% per year for 20 years,
eventually occupying space in nearly a dozen different leased
phasizing the need for compact switchgear.
2) Seismic capability: The facility is in an active seismic
area. The nature of the site activities required equipment
facilities. To better integrate the corporate staff and support
that could remain operational during and after a seismic
increased growth, construction of a single research and devel-
opment (R&D) site was planned and executed. As the available event.
utility service voltage was 26.4 kV, and the estimated ultimate 3) Local Codes and Regulations: The location is in a city that
load could approach 30 MVA, it was decided to distribute requires electrical equipment to be listed by an approved
26.4 kV to the site buildings rather than transform it to an testing laboratory.
intermediate distribution medium voltage (MV). The research 4) Arc Resistance: The owner considered arc-resistant con-
facility would require high reliability power in order to preserve struction an absolute requirement for the solidly grounded
critical experiments, and maintain the proper environmental 26.4-kV system, and preferred for the resistance grounded
4.16-kV system.
5) Commonality: The owner preferred equipment with
greater commonality between the 26.4- and 4.16-kV
equipment in the facility.
Paper PID-04-02, presented at the 2003 IEEE Petroleum and Chemical In- 6) Environmental Considerations: The electrical room is
dustry Technical Conference, Houston, TX, September 15–17, and approved
for publication in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS by the considered a clean environment. However, plant cooling
Petroleum and Chemical Industry Committee of the IEEE Industry Applications towers would be located on the roof directly above the
Society. Manuscript submitted for review September 18, 2003 and released for switchgear.
publication June 23, 2004.
C. T. Lav and T. W. Olsen are with Siemens Power Transmission & Dis- 7) Maintenance: Due to the configuration of the standby
tribution, Inc., Raleigh, NC 27626 USA (e-mail: Shawn.lav@siemens.com; power system, maintenance shutdowns would be infre-
t.olsen@ieee.org). quent. Preference would be given to equipment with
D. B. Staley is with Amgen Corporation, Seattle, WA 98119 USA (e-mail:
staleyd@amgen.com). a demonstrated record of performance with minimal
Digital Object Identifier 10.1109/TIA.2004.834136 maintenance.
0093-9994/04$20.00 © 2004 IEEE
1428 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 40, NO. 5, SEPTEMBER/OCTOBER 2004

8) Experience: The experience of the manufacturer would be ground faults on the 26.4-kV system that would exist if the
considered in the evaluation. primary winding of the transformer were ungrounded.
9) Total cost of ownership: Total estimated cost of owner- The 4.16-kV switchgear includes two generator buses, sep-
ship and operation over the life of the facility would be arated from each other and from the main bus sections by tie
evaluated. circuit breakers. This scheme allows great flexibility in connec-
tion of the generation to the balance of the system, whether for
III. DESIGN CONCEPT periodic maintenance and exercise, or for backup supply to the
complex.
The project requirements led to a project one line arrange-
Among the design features incorporated in the overall system
ment as shown in Fig. 6. The system configuration includes dual
are the following.
26.4-kV incoming sources from the utility (although only one is
initially installed), with distribution at the utility voltage to the 1) Utility Sources: There are provisions for two separate
various substations in the complex. The major portion of the sources from the utility (although only one initially is
load is served at 480 volts from substations located in the re- installed).
spective buildings. The largest individual loads are the chillers, 2) Automatic Operation: The system includes automatic
located in the central utility plant, for which 4.16 kV was the transfer to the second utility source in the event of loss
logical system voltage. Since this voltage level was needed for of one source. Initially, with only one utility source,
the largest loads, it was decided to also use this voltage for the the standby generation system is activated by loss of
standby generation system. the incoming utility service.
Most of the processes used in the complex can tolerate a 3) Bus Protection: Since there are multiple sources of
short-duration outage. However, the financial cost of extended power to the complex, bus differential protection is
outages requires that standby generation be provided. The ini- provided in the switchgear.
tial installation includes 6000 kW of generation, but this can be 4) Synchronism Check: Transfers between the various
expanded to 12 000 kW of standby generation, and provisions sources include synchronism-check supervision to
are included for future cogeneration. prevent paralleling of sources that are not synchro-
The 26.4-kV equipment is configured in a dual-source form nized.
with a normally open tie circuit breaker. The loads are approx- 5) Multifunction Relays: Protective relays are multifunc-
imately evenly divided between the two sources. In the event tion digital-microprocessor-type devices with commu-
of an outage on one of the utility incoming lines, the respective nications capabilities.
main circuit breaker can be opened and the tie circuit breaker 6) Building Feeders: The bulk load for most buildings is
closed to pick up the entire facility load. Upon loss of a utility served from dedicated 26.4-kV feeders in the main dis-
incoming source, the control system is arranged to wait for a tribution switchgear. These feeders serve double-ended
normal utility reclosing attempt, which occurs during the first substations in each building. Buildings with smaller
15 s of an outage. An outage in excess of 15 s is assumed loads are served with looping feeders from circuit
to be “permanent.” The system then opens the affected main breakers in the main distribution switchgear.
circuit breaker and closes the tie circuit breaker. Closing of 7) Chillers: The large chiller loads are served at 4.16 kV
tie circuit breakers is supervised by a synchronism-check relay from the 10/15.3-MVA transformers.
(device 25). 8) Standby Generation: The generators are connected to
If both 26.4-kV incoming sources experience an outage ex- generator buses in the 4.16-kV switchgear, with mul-
ceeding 15 s, the control system automatically disconnects loads tiple bus tie circuit breakers to allow for maximum flex-
and initiates the starting sequence for the backup generators. ibility in the connections.
The generator control system is designed to bring the first ma- 9) 26.4-kV Switchgear: This switchgear includes a total of
chine on line within 10 s. Additional machines are synchronized 19 circuit breakers (one main, one bus tie, 12 feeders
and connected so that all machines are on line within 20 s from for 480-V substations, two feeders for chiller and
the initiation of the start sequence. standby generation, and two capacitor bank feeders).
As the backup generation supply is established, the control It also includes provisions for future connection to
system automatically reconnects loads according to a defined external voltage regulators.
sequence. Thus, power can be restored to all critical loads within 10) 4.16-kV Switchgear: This switchgear includes two
1 min following a major outage. main buses feeding the large chillers. The chillers are
The 4.16-kV system voltage is established in a double-ended normally supplied from the transformers connected to
substation, with two 10/15.3-MVA vacuum pressure im- the 26.4-kV main distribution system. The switchgear
pregnated dry-type transformers. The transformers are also includes two generator buses, which can be con-
three-winding type, with solidly grounded wye primary, nected to the chiller main buses by bus tie circuit
resistance grounded wye secondary, and an embedded delta breakers. For increased flexibility, a bus tie breaker
tertiary winding. The – – transformer connection with is included between the two generator buses. Thus,
delta tertiary was chosen to provide effective grounding for the the equipment includes a total of 17 circuit breakers
26.4-kV system when the facility is operating from the on-site (two main, two bus ties between chiller buses and
generation. This eliminates the potential for undetectable arcing generator buses, one bus tie between generator buses,
LAV et al.: PRACTICAL DESIGN CONSIDERATIONS FOR APPLICATION OF GIS MV SWITCHGEAR 1429

five chiller feeders, six generator breakers for 2-MW found to remain operational during the test. The standby
diesel generators, and one generator breaker for a system is required to remain operational after a seismic
future cogeneration installation). event.
11) Generation Control System: Each generator is pro- 3) Local Codes and Regulations: The selected GIS equip-
vided with multifunction microprocessor control and ment was available with third-party (UL) listing, satisfac-
protection. The control system provides for automatic tory to the authority having jurisdiction as required by the
synchronism check, synchronizing and matching of NEC.
the number of machines to the demand. 4) Arc Resistance: The GIS equipment was the only equip-
ment found that met the requirement for arc resistance on
IV. CHARACTERISTICS OF EQUIPMENT SELECTED the 26.4-kV equipment. As a bonus, the 4.16-kV equip-
ment would also be arc resistant. This reduced the need
During preliminary planning, it was learned that conven- for certain kinds of personal protective equipment (PPE)
tional switchgear equipment might not meet all of the competing during maintenance and operation.
needs of the project. Accordingly, proposals were requested 5) Commonality: It was initially expected that there would
for conventional metal-clad (MC) switchgear (conforming to be few similarities between the 26.4- and 4.16-kV equip-
ANSI/IEEE C37.20.2-1999 [1]) and alternate proposals for ment, but the selection of the GIS provided a large benefit
competing gas-insulated switchgear (GIS). in terms of commonality of spare parts.
All equipment on the project was required to meet the local 6) Environmental Considerations: The selected equipment
code requirements, which require that the equipment must be provides an IP65 degree of protection (equivalent to
listed and labeled by a third-party testing laboratory acceptable NEMA 6) for the high-voltage portion of the equipment.
to the local jurisdiction. The installation is in a region of high Isolation of high-voltage conductors from the atmosphere
seismic activity (UBC seismic zone 3). eliminated the need for space heaters, reducing operating
The base bid required the following. expenses and reducing maintenance requirements.
1) 26.4-kV MC indoor switchgear, rated 25-kA interrupting 7) Maintenance: The GIS offered an extremely long interval
class, 125-kV BIL, of conventional drawout-type MV between maintenance. The nature of the activities at the
MC switchgear design to the requirements of ANSI/IEEE site makes it difficult to accommodate outages of any sig-
C37.20.2-1999 [1] was required. Provisions for utility nificant duration.
revenue metering equipment were specified. In addition, 8) Experience: The manufacturer of the selected GIS equip-
arc-resistant construction, meeting the requirements of ment had nearly two decades of successful field expe-
EEMAC G14-1-1987 [2] was specified. (EEMAC G14-1 rience worldwide, including over five years experience
is no longer supported, and ANSI/IEEE C37.20.7-2001 with installations in the U.S. The global installed base
[3] is the preferred replacement.) Provisions for attach- of the design is quite extensive. The manufacturer also
ment of safety grounds were specified at each incoming has a cadre of experienced factory-trained field service
or outgoing connection, and on each main bus section. representatives.
In addition, an electrically operated fault-making ground 9) Total Cost of Ownership: The purchase price of the
and test device conforming to ANSI/IEEE C37.20.6-1997 4.16-kV GIS equipment was higher than for conventional
[4] was also specified. MC switchgear. However, the purchase price for the
2) 4.16 kV MC indoor switchgear, nominal 350-MVA 26.4-kV GIS equipment was significantly lower than the
class (41-kA interrupting at 4.76 kV), 60-kV BIL, using price of conventional MC switchgear. After consideration
conventional drawout-type MC switchgear conforming of the other benefits associated with GIS equipment, the
to ANSI/IEEE C37.20.2-1999 [1] was also required. overall evaluation favored the use of the GIS switchgear.
Arc-resistant construction was not specified for the
4.16-kV equipment. Except for equipment arrangement,
ratings, omission of utility revenue metering provisions, V. GIS
and omission of the arc resistant feature, the 4.16-kV GIS differs greatly from traditional MV MC switchgear
equipment requirements were similar to those of the widely used in the U.S. A functional schematic view of one
26.4-kV switchgear. pole of a typical unit of GIS switchgear is shown in Fig. 1.
The alternative bid required the functional equivalent of the As in the familiar MC switchgear, vacuum circuit breakers are
base bid, with modifications to reflect the unique aspects of GIS. used for interruption.
After evaluation, it was determined that the alternate bid, with MV GIS switchgear differs from high-voltage GIS
GIS, provided the best performance and value for the project. switchgear in that the SF gas is used for its insulating
Among the factors considered in this decision are the properties, not for interruption. Conventional MC switchgear
following. relies on a combination of air and solid insulating materials,
1) Space Constraints: The GIS was significantly smaller in but GIS switchgear uses bare bus conductors on insulating
size than conventional switchgear, freeing space for main- supports, immersed in insulating gas. Hence, GIS switchgear is
tenance and additional equipment in the room. much smaller than equivalent MC switchgear.
2) Seismic Capability: The particular line of GIS selected Since SF gas provides the major insulation, it is not fea-
had been previously subjected to seismic testing and sible to incorporate drawout provisions for the circuit breaker.
1430 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 40, NO. 5, SEPTEMBER/OCTOBER 2004

Fig. 2. Use of three-position switch for outgoing circuit grounding.

designs indicates that leakage rate is of the order of 0.1%–0.5%


per year.
While the use of SF gas in this MV application poses fewer
concerns than for a high voltage application, the gas must still
be treated with care. An excellent report is available from the
IEC on the proper handling of SF gas [8].
Since the high-voltage components are enclosed in a gas en-
Fig. 1. Typical circuit breaker unit in GIS switchgear. velope, an alternative method of applying safety grounds for
maintenance is required. This is solved quite conveniently, using
the three-position switch. This switch is located between the
Accordingly, the circuit breaker is fixed-mounted, and is con- vacuum interrupter of the circuit breaker and the main bus, and
nected to the main bus system through a three-position switch. the mechanism of the switch is mechanically interlocked to pre-
A benefit of using a fixed-mounted circuit breaker configuration vent operation unless the circuit breaker is open. The switch has
is that all of the mechanical, thermal, and dielectric complexi- three positions, CLOSED, OPEN, and READY-TO-GROUND.
ties and maintenance associated with drawout provisions and Fig. 2 provides a representation of the use of the three-posi-
racking mechanisms are eliminated. tion switch to accomplish the grounding function for the out-
A major benefit of the use of SF gas is that the equipment is going circuit. With the switch in the CLOSED position, the line
isolated from most environmental effects. This allows for a long side of the interrupter is connected to the main bus, and when the
interval (20 years) between maintenance for the high-voltage circuit breaker is closed, the load is served from the main bus. In
elements. In essence, the high voltage portion of the equipment the OPEN position of the switch, the line side of the interrupter
approaches being maintenance free. The long maintenance is disconnected from the main bus, effectively serving to isolate
interval on the high-voltage components creates a corresponding the load from the main bus. In the READY-TO-GROUND po-
need for a long maintenance interval on the high voltage sition of the switch, the line side of the interrupter is connected
components of the circuit breaker, which has been met. The to a fully rated ground system. The circuit breaker is mechani-
vacuum circuit breaker in the installed equipment is designed cally interlocked so that it may be closed with the three-position
for 30 000 operations before overhaul is needed. Secondary switch in the READY-TO-GROUND position. When the circuit
and mechanical elements of the switchgear outside of the breaker is closed in this condition, it acts as a fully rated fault
gas envelope require more frequent cleaning and lubrication, making device, and connects the outgoing circuit (opposite the
typically at intervals of ten years. The very long intervals for main bus) to a fault-rated ground system. Essentially, each cir-
maintenance were a major factor in the decision to purchase cuit breaker becomes a fault-making grounding device for the
GIS switchgear. external power circuit. The circuit breaker thus provides a pos-
Use of SF gas can pose environmental questions, but these itive means to apply safety grounds during maintenance. In the
are of much less significance in MV GIS equipment than in grounded condition, electrical tripping of the circuit breaker is
high-voltage applications. Since the gas is used only for its blocked, and a padlock provision can be used to prevent me-
insulating properties, the filling pressure of the equipment is chanical opening of the circuit breaker by unauthorized persons.
relatively low. Further, since the gas is not involved in arc Most local codes require that the design of equipment in-
interruption, there are no by-products of the decomposition corporate a means to visually verify the isolating function of
of the SF gas by arcing. Early high-voltage GIS products disconnect devices. In the GIS switchgear, this requires a means
experienced significant gas leakage, but this is not the case to visually verify the position of the three-position switch. To
with modern MV GIS designs. The experience with present meet this requirement, the manufacturer installed miniature
LAV et al.: PRACTICAL DESIGN CONSIDERATIONS FOR APPLICATION OF GIS MV SWITCHGEAR 1431

video cameras, and associated lighting, both mounted external


to the SF gas enclosure. The video leads are brought to the
front panel of the switchgear, and a monitoring device is pro-
vided to view the position of the switch. The system includes a
selector switch so that the position of the three-position switch
can be verified in each phase of the switchgear.
The MV GIS switchgear also includes capacitive voltage in-
dicators on the outgoing circuits to indicate the presence of
voltage on the incoming or outgoing power conductors. This
gives the operator a convenient means to determine if the load
conductors are energized.
A mimic diagram is provided on the front of the switchgear.
This diagram shows the main current carrying circuits, and in-
cludes devices to denote the position of the various operating
components, including the three-position switch and the circuit
breaker. Thus, in addition to indicating lights, the operator has
a single-line-type mimic diagram to indicate whether the circuit
breaker is closed, and the position of the three-position switch.
Since SF gas is used as the main dielectric, the size of Fig. 3. Side-by-side size comparison: 38-kV MC switchgear (on left) and GIS
(on right).
the GIS switchgear can be standardized. SF has a dielectric
strength six times that of air, allowing higher insulation levels
to be achieved by increasing the gas pressure. Therefore, the internal arcing fault, meeting the requirements of IEC 60298,
physical size does not increase as rated voltage increases. Annex AA [5], and the functionally similar EEMAC G14-1 [2]
Thus, the 4.16- and 26.4-kV switchgear are the same physical and ANSI/IEEE C37.20.7 [3].
size. The internal components (such as the vacuum inter- MV GIS switchgear was introduced in Europe over 20
rupters) and the operating gas pressure differ according to the years ago. It was designed to IEC standards and ratings. For
system voltage and interrupting rating required. However, these introduction in the U.S., the design was tested to ANSI/IEEE
changes do not affect the major mechanical features. Hence, standards. The equipment was also investigated by a third-party
the two different voltage class of GIS share common layout, safety organization to the requirements of the standards devel-
stored-energy operating mechanism, construction features, oped for conformance testing of conventional MC switchgear,
operating procedures, maintenance requirements, arrangement ANSI C37.54 [6] (circuit breakers) and C37.55 [7] (switchgear
of protective and metering devices, etc. assemblies). These standards apply as UL does not have a
The use of gas insulation allows for a large reduction in the standard for MC switchgear. Based on these investigations,
floor space occupied by the equipment. With a basic unit width the equipment is qualified for application of the UL listing
of just 600 mm (24 in) and a depth of 1950 mm (60 in), the floor mark (UL label). The equipment meets the requirements of the
space requirements are reduced to only about 60% of conven- applicable MC standards, with due allowance for the inherent
tional MC equipment. This assumes the front aisle space shown differences associated with nondrawout construction.
in NEC for the voltage class of the equipment, and ignores rear The installation of the GIS required some changes as com-
aisle space. While rear aisle space is required with MC equip- pared with compartmentalized switchgear. Due to the compact
ment, GIS equipment can often be located directly adjacent to a GIS construction, the switchgear is normally installed over a
wall. The floor space savings are even greater if the aisle space cable gallery or cable room. As the project had only second
in front of the GIS switchgear can be reduced to 1000 mm (40 floor space available, a platform was designed and fabricated to
in) to reflect the fact that no high voltage components require provide additional space for cable handling, terminal-connected
maintenance from the front of the equipment. Depending on the voltage transformers, and zero-sequence current transformers.
configuration of the switchgear, the space savings can be even The platform was arranged to include an elevated common aisle
more dramatic. Fig. 3 shows a side-by-side comparison of a unit space, with the 26.4- and 4.16-kV switchgear assemblies facing
of 38-kV indoor MC switchgear and its functional equivalent in each other. The GIS was welded to the platform, and the plat-
GIS switchgear. form anchored and grouted to the floor to maintain the seismic
The GIS switchgear selected utilizes segregated-phase con- rating of the equipment. Fig. 4 shows the 26.4- and 4.16-kV
struction, with each phase of the switchgear enclosed in a switchgear lineups installed on the raised platform.
separate gas enclosure. Since the phases are separated by the The primary cable connections were of the plug-in inner
grounded enclosure, it is not possible to have a three-phase fault cone type, which provide a hermetically sealed maintenance
inside the switchgear. Another benefit of the segregated-phase free connection. The raised platform accommodated the worst
construction relates to arcing faults. Since the insulation is pro- case cable connection (four 1000 kcmil cables per phase, plus
vided by a gas, arcing faults are rare. If an arcing fault should a plug-in surge arrester) involved in the installation.
occur of a low current level, the arc will often be self-extin- A second issue involved the connection of the 10-MVA
guishing due the presence of the SF gas. If a high-level arcing transformer to the 4.16-kV switchgear. The transformer height
fault does occur, the equipment has the ability to withstand the was restricted to 3300 mm (130 in), and the transformer was
1432 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 40, NO. 5, SEPTEMBER/OCTOBER 2004

Fig. 4. 26.4-kV (right) and 4.16-kV (left) GIS switchgear installed on raised Fig. 5. Throat connection between 10-MVA transformer and 4.16-kV
platform. secondary switchgear.

to be directly connected to the adjacent switchgear. Since the flat to within 1.6 mm for the full length using laser level mea-
switchgear was located on the raised platform, the connection surements.
between the transformer and the switchgear was made with To provide a clean environment for the equipment, the as-
short lengths of capacitive-graded epoxy-insulated conductors, sembly area was isolated with plastic sheets, as much of the
which simply plugged into the switchgear and bolted to the building siding and windows had not been installed. Attention to
transformer bus bars. Fig. 5 shows the short “throat” that was cleanliness during the assembly of the gas enclosures was also
used to enclose the conductors between the transformer and necessary, to avoid contamination of the gas enclosure and the
the switchgear. The lower portion of Fig. 6 shows the one risk of reduced dielectric capability.
line diagram of the 4.16-kV switchgear and the close-coupled Another major difference involves cable terminations. GIS
10-MVA transformers at each end. switchgear uses plug-in inner-cone-type primary connections,
The installation required listing by a third-party organization instead of bolted cable lugs and preformed stress-relief termina-
acceptable to the local jurisdiction. The high-voltage portion tions. The installing contractor had no experience with this type
of the GIS was manufactured in one location, while the sec- of termination, but after learning to use the kits, they found they
ondary control and relaying compartments were manufactured could install them as fast as the conventional cold or heat shrink
at a second location. This made it necessary for the third-party termination kits. One significant difference in the kits that was
listing agency (UL) to inspect the assembled equipment at the discovered was the plug-in inner cone kits were closely sized
installation site before the listing mark (labels) could be applied. to the cable insulation diameter, so eleven (11) different sizes
This also provided the opportunity for the inspector for the local were available, whereas the same span of sizes is accomplished
jurisdiction to observe the process. The state agency responsible with three sizes of conventional stress relief terminations. This
for electrical worker’s safety reviewed the camera system used makes it advisable to have an exact sample of the cable that will
to provide visual evidence of isolation, and approved the system. be used when ordering these terminations.
The equipment has been in operation for approximately two
years, initially providing construction power, and subsequently
VI. ASSESSMENT AND CONCLUSIONS in regular service. In that time, the equipment has operated
without incident. The electrical workers have become proficient
The installation was performed by contractors who had no with using the video cameras and monitor to view the position
previous experience with GIS switchgear. Supervision was pro- of the three-position switch.
vided by factory-trained field engineers. The most significant The operators have come to appreciate the differences in the
installation issues involved the need for proper alignment. The lockout and tagout procedures for the GIS equipment compared
foundation must be level and in a single plane to allow for proper to those used with conventional MC switchgear. In contrast to
assembly of the shipping sections. The foundation height could conventional switchgear where the breaker is withdrawn and re-
only vary by 1 mm per meter, with a maximum deviation of placed with a ground and test (G&T) device, each unit of the GIS
2 mm over the full length of the assembly. The platform was switchgear includes the three-position switch that can be placed
constructed using standard structural shapes, and was verified in the READY TO GROUND position. With the switch in this
LAV et al.: PRACTICAL DESIGN CONSIDERATIONS FOR APPLICATION OF GIS MV SWITCHGEAR 1433

Fig. 6. Overall system one-line diagram.


1434 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 40, NO. 5, SEPTEMBER/OCTOBER 2004

position, when the circuit breaker is closed, the outgoing circuit Chun Ty (Shawn) Lav (S’92–M’94) received the
is positively grounded, and can be padlocked in the grounded B.S.E.E. degree from North Carolina State Univer-
sity, Raleigh, in 1994.
position. He joined Cutler-Hammer in 1994. In 1995, he
The use of GIS switchgear was received very differently by moved to Siemens Power Transmission & Distribu-
the various entities involved. The operations staff, consulting tion, Inc., Raleigh, NC. He has held several positions
within Siemens, including a two-year expatriate
engineers, and utility engineers were split between being satis- assignment in Germany involving gas-insulated
fied with the equipment, and being apprehensive about their lack switchgear. He is currently the Business Unit Man-
of familiarity with the product. The contractors were enthusi- ager for medium-voltage gas-insulated switchgear
for North America and the Caribbean.
astic about installing different equipment, and the electrical in-
spectors were pleased with the equipment, especially as it was
third-party labeled. The owner is pleased with the decision to David B. Staley (S’80–M’92) received the B.S. de-
use the equipment, and now that the installation is complete, gree in physics, the B.S.C. degree in chemistry, and
the real benefits of minimum maintenance, enhanced reliability, the B.S.E.E. degree in 1981, and the M.B.A. degree
in 1992 from Seattle University, Seattle, WA.
and operational simplicity will be realized. From 1981 to 1988, he was with Westinghouse
Inevitably, one question occurs. Would we do it again? Fol- Electric Corporation, where he was engaged in
lowing the selection of GIS for the R&D facility project, a major equipment testing, power system studies, and project
management. From 1988 to 1997, he was with
expansion of the company’s manufacturing facility on the East Boeing Company, where he was the Lead Electrical
coast was undertaken. The electrical system configuration and Engineer in the Central Engineering Group. From
concerns were similar to those of the R&D facility, so it was 1997 to 2000, he was with Raytheon Engineers
and Constructors, where he was responsible for power system distribution
elected to apply the GIS switchgear for this project as well, in- and analysis projects. Since 2000, he has been with the Amgen/Immunex
cluding the 34.5-, 12.47-, and 4.16-kV system equipment. In Corporation, Seattle, WA, where he is presently an Electrical Engineer in the
addition, the commonality between sites would allow for stan- Corporate Engineering Group.
Mr. Staley is a Registered Professional Electrical Engineer in the State of
dardization of training and spare parts. Washington.

T. W. (Ted) Olsen (S’64–M’68–SM’02) received the


REFERENCES B.S.E.E. degree from Bradley University, Peoria, IL,
in 1968, and the M.B.A. degree from the University
[1] IEEE Standard for Metal-Clad Switchgear, ANSI/IEEE C37.20.2-1999. of Wisconsin, Milwaukee, in 1976.
[2] Procedure for Testing the Resistance of Metal Enclosed and Metalclad In 1968, he joined the Allis-Chalmers (now
Switchgear Under Conditions of Arcing due to an Internal Fault, Siemens Power Transmission & Distribution, Inc.)
EEMAC G14-1-1987. Graduate Training Program in West Allis, WI.
[3] IEEE Guide for Testing Medium Voltage Metal-Enclosed Switchgear for After several training assignments, he accepted a
Internal Arcing Faults, ANSI/IEEE C37.20.7-2001. permanent position in the Switchgear Application
[4] IEEE Standard for 4.76 kV to 38 kV Rated Grounding and Testing De- Engineering Department. Over the years since,
vices Used in Enclosures, ANSI/IEEE C37.20.6-1997. he has held a variety of positions in Application
[5] A.C. Metal-Enclosed Switchgear and Controlgear for Rated Voltages Engineering, Marketing, Design Engineering, Materials, and Product Man-
Above 1 kV and Up to and Including 52 kV, IEC 60298-1990. agement. Currently, he is Manager of Technology in Raleigh, NC, responsible
[6] Conformance Test Procedures for Indoor Alternating Current Medium- for providing consulting assistance to other disciplines and to customers. In
Voltage Circuit Breakers Applied as Removable Elements in Metal-En- addition, he is heavily involved with standards activities.
closed Switchgear, ANSI C37.54-1996. Mr. Olsen is a Member of the IEEE PES Switchgear Committee and Secre-
[7] Metal-Clad Switchgear Assemblies—Conformance Test Procedures, tary of the Switchgear Assemblies Subcommittee. He is Chair of the NEMA
ANSI C37.55-1989. Switchgear Section and of the NEMA HV Circuit Breaker Technical Com-
[8] High-Voltage Switchgear and Controlgear—Use and Handling of Sulfur mittee. He is Chair of the ANSI Accredited Standards Committee C37, for
Hexafluoride (SF ) in High-Voltage Switchgear and Controlgear, IEC Power Switchgear. He is a member of the IEEE Standards Association Stan-
61 634-1995. dards Board.

You might also like