Professional Documents
Culture Documents
Abstract—In a recent biotechnology facility project, the de- controls for critical cell banks. In addition, the facility cri-
cision was made to require arc-resistant medium-voltage (MV) teria included maintaining operation through and after major
switchgear for the safety of operating personnel. The available ser- seismic events.
vice voltage was 26.4 kV, limiting the availability of proven designs
The utility service was arranged to accept two incoming
of arc-resistant switchgear. As a result, the owner considered use
of medium-voltage gas-insulated switchgear (GIS) with vacuum lines, although the utility was only able to serve the facility
circuit breakers. Once this decision was made, consideration was initially with one feeder. Backup power for emergency loads
given to using the same class of switchgear for the 4.16-kV voltage was provided by battery powered inverters, and for the standby
equipment in the facilities. This offered advantages of uniformity, loads by on-site diesel generators. Due to the high density of
commonality of spares, and simplification of operator training. standby loads and the potential need for frequent reconfigura-
This paper focuses on the rationale for selection of GIS tion, it was elected to re-feed the normal power system from
switchgear, and the design considerations that had to be addressed
as the project moved from concept to installation to operation. the standby generation system, and implement an automated
Among the issues discussed are the following: load-shedding and load restoration scheme. For reliability
• space requirements for conventional and GIS equipment; and maintainability, the distribution system was arranged in
• arc-resistant performance of GIS equipment; dual-radial primary feeder configuration, with both primary
• design commonality between 4.16- and 26.4-kV equipment; and secondary unit substations being secondary selective.
• installation (cable issues, foundations, workspace, etc.);
• environmental considerations; II. PROJECT REQUIREMENTS AND CONSIDERATIONS
• total cost of ownership;
• reliability/availability; The requirements for the project included a variety of func-
• operational experience. tional and operational elements, including the following.
Index Terms—Arc resistant, gas-insulated switchgear (GIS), 1) Space constraints: The central utility plant electrical room
vacuum circuit breaker. incorporated the primary distribution switchgear, the MV
switchgear for the chillers and the backup generation, plus
I. PROJECT OVERVIEW large secondary unit substations. The room was on the
second floor, adjacent to the generator room, further em-
8) Experience: The experience of the manufacturer would be ground faults on the 26.4-kV system that would exist if the
considered in the evaluation. primary winding of the transformer were ungrounded.
9) Total cost of ownership: Total estimated cost of owner- The 4.16-kV switchgear includes two generator buses, sep-
ship and operation over the life of the facility would be arated from each other and from the main bus sections by tie
evaluated. circuit breakers. This scheme allows great flexibility in connec-
tion of the generation to the balance of the system, whether for
III. DESIGN CONCEPT periodic maintenance and exercise, or for backup supply to the
complex.
The project requirements led to a project one line arrange-
Among the design features incorporated in the overall system
ment as shown in Fig. 6. The system configuration includes dual
are the following.
26.4-kV incoming sources from the utility (although only one is
initially installed), with distribution at the utility voltage to the 1) Utility Sources: There are provisions for two separate
various substations in the complex. The major portion of the sources from the utility (although only one initially is
load is served at 480 volts from substations located in the re- installed).
spective buildings. The largest individual loads are the chillers, 2) Automatic Operation: The system includes automatic
located in the central utility plant, for which 4.16 kV was the transfer to the second utility source in the event of loss
logical system voltage. Since this voltage level was needed for of one source. Initially, with only one utility source,
the largest loads, it was decided to also use this voltage for the the standby generation system is activated by loss of
standby generation system. the incoming utility service.
Most of the processes used in the complex can tolerate a 3) Bus Protection: Since there are multiple sources of
short-duration outage. However, the financial cost of extended power to the complex, bus differential protection is
outages requires that standby generation be provided. The ini- provided in the switchgear.
tial installation includes 6000 kW of generation, but this can be 4) Synchronism Check: Transfers between the various
expanded to 12 000 kW of standby generation, and provisions sources include synchronism-check supervision to
are included for future cogeneration. prevent paralleling of sources that are not synchro-
The 26.4-kV equipment is configured in a dual-source form nized.
with a normally open tie circuit breaker. The loads are approx- 5) Multifunction Relays: Protective relays are multifunc-
imately evenly divided between the two sources. In the event tion digital-microprocessor-type devices with commu-
of an outage on one of the utility incoming lines, the respective nications capabilities.
main circuit breaker can be opened and the tie circuit breaker 6) Building Feeders: The bulk load for most buildings is
closed to pick up the entire facility load. Upon loss of a utility served from dedicated 26.4-kV feeders in the main dis-
incoming source, the control system is arranged to wait for a tribution switchgear. These feeders serve double-ended
normal utility reclosing attempt, which occurs during the first substations in each building. Buildings with smaller
15 s of an outage. An outage in excess of 15 s is assumed loads are served with looping feeders from circuit
to be “permanent.” The system then opens the affected main breakers in the main distribution switchgear.
circuit breaker and closes the tie circuit breaker. Closing of 7) Chillers: The large chiller loads are served at 4.16 kV
tie circuit breakers is supervised by a synchronism-check relay from the 10/15.3-MVA transformers.
(device 25). 8) Standby Generation: The generators are connected to
If both 26.4-kV incoming sources experience an outage ex- generator buses in the 4.16-kV switchgear, with mul-
ceeding 15 s, the control system automatically disconnects loads tiple bus tie circuit breakers to allow for maximum flex-
and initiates the starting sequence for the backup generators. ibility in the connections.
The generator control system is designed to bring the first ma- 9) 26.4-kV Switchgear: This switchgear includes a total of
chine on line within 10 s. Additional machines are synchronized 19 circuit breakers (one main, one bus tie, 12 feeders
and connected so that all machines are on line within 20 s from for 480-V substations, two feeders for chiller and
the initiation of the start sequence. standby generation, and two capacitor bank feeders).
As the backup generation supply is established, the control It also includes provisions for future connection to
system automatically reconnects loads according to a defined external voltage regulators.
sequence. Thus, power can be restored to all critical loads within 10) 4.16-kV Switchgear: This switchgear includes two
1 min following a major outage. main buses feeding the large chillers. The chillers are
The 4.16-kV system voltage is established in a double-ended normally supplied from the transformers connected to
substation, with two 10/15.3-MVA vacuum pressure im- the 26.4-kV main distribution system. The switchgear
pregnated dry-type transformers. The transformers are also includes two generator buses, which can be con-
three-winding type, with solidly grounded wye primary, nected to the chiller main buses by bus tie circuit
resistance grounded wye secondary, and an embedded delta breakers. For increased flexibility, a bus tie breaker
tertiary winding. The – – transformer connection with is included between the two generator buses. Thus,
delta tertiary was chosen to provide effective grounding for the the equipment includes a total of 17 circuit breakers
26.4-kV system when the facility is operating from the on-site (two main, two bus ties between chiller buses and
generation. This eliminates the potential for undetectable arcing generator buses, one bus tie between generator buses,
LAV et al.: PRACTICAL DESIGN CONSIDERATIONS FOR APPLICATION OF GIS MV SWITCHGEAR 1429
five chiller feeders, six generator breakers for 2-MW found to remain operational during the test. The standby
diesel generators, and one generator breaker for a system is required to remain operational after a seismic
future cogeneration installation). event.
11) Generation Control System: Each generator is pro- 3) Local Codes and Regulations: The selected GIS equip-
vided with multifunction microprocessor control and ment was available with third-party (UL) listing, satisfac-
protection. The control system provides for automatic tory to the authority having jurisdiction as required by the
synchronism check, synchronizing and matching of NEC.
the number of machines to the demand. 4) Arc Resistance: The GIS equipment was the only equip-
ment found that met the requirement for arc resistance on
IV. CHARACTERISTICS OF EQUIPMENT SELECTED the 26.4-kV equipment. As a bonus, the 4.16-kV equip-
ment would also be arc resistant. This reduced the need
During preliminary planning, it was learned that conven- for certain kinds of personal protective equipment (PPE)
tional switchgear equipment might not meet all of the competing during maintenance and operation.
needs of the project. Accordingly, proposals were requested 5) Commonality: It was initially expected that there would
for conventional metal-clad (MC) switchgear (conforming to be few similarities between the 26.4- and 4.16-kV equip-
ANSI/IEEE C37.20.2-1999 [1]) and alternate proposals for ment, but the selection of the GIS provided a large benefit
competing gas-insulated switchgear (GIS). in terms of commonality of spare parts.
All equipment on the project was required to meet the local 6) Environmental Considerations: The selected equipment
code requirements, which require that the equipment must be provides an IP65 degree of protection (equivalent to
listed and labeled by a third-party testing laboratory acceptable NEMA 6) for the high-voltage portion of the equipment.
to the local jurisdiction. The installation is in a region of high Isolation of high-voltage conductors from the atmosphere
seismic activity (UBC seismic zone 3). eliminated the need for space heaters, reducing operating
The base bid required the following. expenses and reducing maintenance requirements.
1) 26.4-kV MC indoor switchgear, rated 25-kA interrupting 7) Maintenance: The GIS offered an extremely long interval
class, 125-kV BIL, of conventional drawout-type MV between maintenance. The nature of the activities at the
MC switchgear design to the requirements of ANSI/IEEE site makes it difficult to accommodate outages of any sig-
C37.20.2-1999 [1] was required. Provisions for utility nificant duration.
revenue metering equipment were specified. In addition, 8) Experience: The manufacturer of the selected GIS equip-
arc-resistant construction, meeting the requirements of ment had nearly two decades of successful field expe-
EEMAC G14-1-1987 [2] was specified. (EEMAC G14-1 rience worldwide, including over five years experience
is no longer supported, and ANSI/IEEE C37.20.7-2001 with installations in the U.S. The global installed base
[3] is the preferred replacement.) Provisions for attach- of the design is quite extensive. The manufacturer also
ment of safety grounds were specified at each incoming has a cadre of experienced factory-trained field service
or outgoing connection, and on each main bus section. representatives.
In addition, an electrically operated fault-making ground 9) Total Cost of Ownership: The purchase price of the
and test device conforming to ANSI/IEEE C37.20.6-1997 4.16-kV GIS equipment was higher than for conventional
[4] was also specified. MC switchgear. However, the purchase price for the
2) 4.16 kV MC indoor switchgear, nominal 350-MVA 26.4-kV GIS equipment was significantly lower than the
class (41-kA interrupting at 4.76 kV), 60-kV BIL, using price of conventional MC switchgear. After consideration
conventional drawout-type MC switchgear conforming of the other benefits associated with GIS equipment, the
to ANSI/IEEE C37.20.2-1999 [1] was also required. overall evaluation favored the use of the GIS switchgear.
Arc-resistant construction was not specified for the
4.16-kV equipment. Except for equipment arrangement,
ratings, omission of utility revenue metering provisions, V. GIS
and omission of the arc resistant feature, the 4.16-kV GIS differs greatly from traditional MV MC switchgear
equipment requirements were similar to those of the widely used in the U.S. A functional schematic view of one
26.4-kV switchgear. pole of a typical unit of GIS switchgear is shown in Fig. 1.
The alternative bid required the functional equivalent of the As in the familiar MC switchgear, vacuum circuit breakers are
base bid, with modifications to reflect the unique aspects of GIS. used for interruption.
After evaluation, it was determined that the alternate bid, with MV GIS switchgear differs from high-voltage GIS
GIS, provided the best performance and value for the project. switchgear in that the SF gas is used for its insulating
Among the factors considered in this decision are the properties, not for interruption. Conventional MC switchgear
following. relies on a combination of air and solid insulating materials,
1) Space Constraints: The GIS was significantly smaller in but GIS switchgear uses bare bus conductors on insulating
size than conventional switchgear, freeing space for main- supports, immersed in insulating gas. Hence, GIS switchgear is
tenance and additional equipment in the room. much smaller than equivalent MC switchgear.
2) Seismic Capability: The particular line of GIS selected Since SF gas provides the major insulation, it is not fea-
had been previously subjected to seismic testing and sible to incorporate drawout provisions for the circuit breaker.
1430 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 40, NO. 5, SEPTEMBER/OCTOBER 2004
Fig. 4. 26.4-kV (right) and 4.16-kV (left) GIS switchgear installed on raised Fig. 5. Throat connection between 10-MVA transformer and 4.16-kV
platform. secondary switchgear.
to be directly connected to the adjacent switchgear. Since the flat to within 1.6 mm for the full length using laser level mea-
switchgear was located on the raised platform, the connection surements.
between the transformer and the switchgear was made with To provide a clean environment for the equipment, the as-
short lengths of capacitive-graded epoxy-insulated conductors, sembly area was isolated with plastic sheets, as much of the
which simply plugged into the switchgear and bolted to the building siding and windows had not been installed. Attention to
transformer bus bars. Fig. 5 shows the short “throat” that was cleanliness during the assembly of the gas enclosures was also
used to enclose the conductors between the transformer and necessary, to avoid contamination of the gas enclosure and the
the switchgear. The lower portion of Fig. 6 shows the one risk of reduced dielectric capability.
line diagram of the 4.16-kV switchgear and the close-coupled Another major difference involves cable terminations. GIS
10-MVA transformers at each end. switchgear uses plug-in inner-cone-type primary connections,
The installation required listing by a third-party organization instead of bolted cable lugs and preformed stress-relief termina-
acceptable to the local jurisdiction. The high-voltage portion tions. The installing contractor had no experience with this type
of the GIS was manufactured in one location, while the sec- of termination, but after learning to use the kits, they found they
ondary control and relaying compartments were manufactured could install them as fast as the conventional cold or heat shrink
at a second location. This made it necessary for the third-party termination kits. One significant difference in the kits that was
listing agency (UL) to inspect the assembled equipment at the discovered was the plug-in inner cone kits were closely sized
installation site before the listing mark (labels) could be applied. to the cable insulation diameter, so eleven (11) different sizes
This also provided the opportunity for the inspector for the local were available, whereas the same span of sizes is accomplished
jurisdiction to observe the process. The state agency responsible with three sizes of conventional stress relief terminations. This
for electrical worker’s safety reviewed the camera system used makes it advisable to have an exact sample of the cable that will
to provide visual evidence of isolation, and approved the system. be used when ordering these terminations.
The equipment has been in operation for approximately two
years, initially providing construction power, and subsequently
VI. ASSESSMENT AND CONCLUSIONS in regular service. In that time, the equipment has operated
without incident. The electrical workers have become proficient
The installation was performed by contractors who had no with using the video cameras and monitor to view the position
previous experience with GIS switchgear. Supervision was pro- of the three-position switch.
vided by factory-trained field engineers. The most significant The operators have come to appreciate the differences in the
installation issues involved the need for proper alignment. The lockout and tagout procedures for the GIS equipment compared
foundation must be level and in a single plane to allow for proper to those used with conventional MC switchgear. In contrast to
assembly of the shipping sections. The foundation height could conventional switchgear where the breaker is withdrawn and re-
only vary by 1 mm per meter, with a maximum deviation of placed with a ground and test (G&T) device, each unit of the GIS
2 mm over the full length of the assembly. The platform was switchgear includes the three-position switch that can be placed
constructed using standard structural shapes, and was verified in the READY TO GROUND position. With the switch in this
LAV et al.: PRACTICAL DESIGN CONSIDERATIONS FOR APPLICATION OF GIS MV SWITCHGEAR 1433
position, when the circuit breaker is closed, the outgoing circuit Chun Ty (Shawn) Lav (S’92–M’94) received the
is positively grounded, and can be padlocked in the grounded B.S.E.E. degree from North Carolina State Univer-
sity, Raleigh, in 1994.
position. He joined Cutler-Hammer in 1994. In 1995, he
The use of GIS switchgear was received very differently by moved to Siemens Power Transmission & Distribu-
the various entities involved. The operations staff, consulting tion, Inc., Raleigh, NC. He has held several positions
within Siemens, including a two-year expatriate
engineers, and utility engineers were split between being satis- assignment in Germany involving gas-insulated
fied with the equipment, and being apprehensive about their lack switchgear. He is currently the Business Unit Man-
of familiarity with the product. The contractors were enthusi- ager for medium-voltage gas-insulated switchgear
for North America and the Caribbean.
astic about installing different equipment, and the electrical in-
spectors were pleased with the equipment, especially as it was
third-party labeled. The owner is pleased with the decision to David B. Staley (S’80–M’92) received the B.S. de-
use the equipment, and now that the installation is complete, gree in physics, the B.S.C. degree in chemistry, and
the real benefits of minimum maintenance, enhanced reliability, the B.S.E.E. degree in 1981, and the M.B.A. degree
in 1992 from Seattle University, Seattle, WA.
and operational simplicity will be realized. From 1981 to 1988, he was with Westinghouse
Inevitably, one question occurs. Would we do it again? Fol- Electric Corporation, where he was engaged in
lowing the selection of GIS for the R&D facility project, a major equipment testing, power system studies, and project
management. From 1988 to 1997, he was with
expansion of the company’s manufacturing facility on the East Boeing Company, where he was the Lead Electrical
coast was undertaken. The electrical system configuration and Engineer in the Central Engineering Group. From
concerns were similar to those of the R&D facility, so it was 1997 to 2000, he was with Raytheon Engineers
and Constructors, where he was responsible for power system distribution
elected to apply the GIS switchgear for this project as well, in- and analysis projects. Since 2000, he has been with the Amgen/Immunex
cluding the 34.5-, 12.47-, and 4.16-kV system equipment. In Corporation, Seattle, WA, where he is presently an Electrical Engineer in the
addition, the commonality between sites would allow for stan- Corporate Engineering Group.
Mr. Staley is a Registered Professional Electrical Engineer in the State of
dardization of training and spare parts. Washington.