SCHEDULE – H
DRAWINGS
1. DRAWINGS
In compliance of the obligations set forth in Clause 12.2 of this Agreement, the Conces-
-sionaire shall furnish to the Independent Engineer, free of cost, all drawings listed in
Annex-I of Schedule-H.
2. ADDITIONAL DRAWINGS
If the Independent Engineer determines that for discharging its duties and functions under
this Agreement, it requires any drawings other than those listed in Annex-I, it may by
notice require the Concessionaire to prepare and furnish such drawings forthwith. Upon
receiving a requisition to this effect, the Concessionaire shall promptly prepare and furnish
such drawings to the Independent Engineer, as if such drawings formed part of Annex-I of
this Schedule-H.
Annex - I
(SCHEDULE – H)
List of Drawings
All the Drawings that the Concessionaire is required to furnish under Clause 12.2 specifying the
Drawings for Four Laning/ Two Laning with paved shoulders are as under:
(a) Horizontal and Vertical Alignment with details of reference pillars. Horizontal Intersection
Point, Vertical Intersection Points, elements of curves, and sight distances.
(g) Drawings for Road sign, Markings, Toll Plaza, Bus bays, Parking areas, Truck lay-byes
(h) Detailed layout drawings for traffic circulation for service roads/slip roads and
detailed drawings for vehicular and pedestrian underpasses including cross- section
drawings through vehicular and pedestrian underpasses at the project road level and the
structures bed level.
(m) Detailed drawings of Drainage including RCC covered drains as per standard specifications.