Professional Documents
Culture Documents
1 Software simulation
Ethanol production processes using the methods of the present study were
The software offers two operation modes for production simulations: batch
mode and continuous mode. The characteristics describing these two modes are
The operations for enzyme production using SmF method was set as “batch”
in the Figure 7.1, the annual operating time is set as 7,920 hours by default, which
corresponds to 330 working days per year. However, the operating mode and the
annual operating time can be changed at any time by using the “Task: Set Mode of
166
Figure 7.1 Dialog box for selecting operation mode
Materials are divided into two groups--components and mixtures--in the software.
contrast, components are pure raw elements, for simulation purposes. All materials
used was specified within the software. In this thesis, the mixtures used to efficiently
utilize the sugarcane bagasse for enzyme, ethanol and ruminant feed production
include air (component ingredients: nitrogen and oxygen) and cellulase (CMCase,
Cellobiase and FPase). Other components beyond the ones specified as ingredients of
Acetic Acid
Biomass
Calcium Chloride
167
Calcium Oxide
Carbon (Charcoal)
Ethyl Alcohol
Potassium Chloride
Potassium Di-hydrogen Phosphate
Magnesium Sulfate
Sodium Hydroxide
Trichoderma longibrachiatum
Urea
Yeast
Yeast Extract
Some of the mixtures and components are provided by the databank within the
SuperPro Designer 5.5 software but for some components the user must create the
relevant components at the beginning of the computer simulation process. Figure 7.2
168
7.1.2 Building simulation flowsheets
Based on the experiments performed in this thesis, the first step in building a
simulation flowsheet is to add equipment (procedures). For the current study, the
required equipment includes: three blending tank, one belt filter, two mixer, two
stirred reactor, two air filter, one microfilter, one centrifuge, one freeze dryer, one
The second step in building a simulation flowsheet is to add material streams, which
unoccupied area with an inlet port of destination equipment creates feed streams.
equipment with an unoccupied area creates product streams. The information on the
streams contained in the Table 7.1 corresponds directly to the flowsheets in Figures
7.11.
169
Table 7.1 Stream specifications in the processes
170
S – 116 P11/MX-102 P20/V-108
S – 126 INPUT P20/V-108
S – 128 INPUT P20/V-108
S – 129 P20/V-108 P17/V-107
S – 130 P20/V-108 P13/HX-101
S – 131 P14/C-101 P13/HX-101
S – 132 P13/HX-101 P14/C-101
S – 133 P13/HX-101 OUTPUT
S – 134 P14/C-101 OUTPUT
S – 135 P17/V-107 OUTPUT
S – 139 P17/V-107 P18/AF-102
S – 147 P18/AF-102 OUTPUT
171
7.1.3 Procedural operations
Within the SuperPro Designer 5.5 software, the first step toward initialization
from the left “Available Operations” column and specified in the right column. The
next step was to initialize all the selected operations that have been added to the
equipment. Two operations out of the six-- “CHARGE - SCB” and “AGITATE - 1”-
- are given as examples to illustrate the process to initialize operations. These two
172
examples are chosen because the first one is the typical operation dealing with a feed
stream (inputs) and the second one is one of the key operations for initialization of
the simulation.
173
After selecting “Operation Data: CHARGE-SCB” from the menu as shown in
the Figure 7.4, the dialog box will come up and is shown in Figure 7.5. The dialog
box shown in Figure 7.5 allows the user to specify the operating conditions, emission
data, labour, description and scheduling, etc. for the operation. To initialize the
Operating Conditions tab for the first charge operation in this example, the source of
the material must be specified in the software. Click on the “Composition” button to
access the stream data information for this feed stream (see Figure 7.6).
Ingredients list on the left side of the above figure. For example, the amount 100
174
kilograms (kg) per batch in the “Total Flowrates” category can be specified as a
After specifying the charge amount of mixture medium, click “OK” to return
to the dialog box for the “Charge-water” (see Figure 7.7). Equipment setup time is
equals 0.17 hrs based on a flowrate 100 kilograms per hour (kg/h) by default. There
are several other tabs for the dialog box, including “Volumes,” “Emissions,”
“Labour, etc,” “Description” and “Scheduling.” These tabs are all self-explanatory
simulations begin.
175
7.1.4 Simulation process
All the data specified as per the procedure mentioned above provide a starting
point for software simulation. Given simulation inputs specified as above, the
the “Tasks: Solve M&E Balance” option from the main menu. This will cause the
program to calculate the mass and energy balances for the entire flowsheet, estimate
decrease the annual outputs to determine the influence of the production scale on the
product unit costs, for example. In order to do that, the SuperPro Designer 5.5
software offers the option to change all the stream flowrates and equipment sizes in
one step by selecting the “Tasks: Adjust Throughput” option from the main menu
(Figure 7.8).
In the dialog box shown in Figure 7.8, scale up (or down) could be realized
based on either a factor or target output (per batch or per year). By choosing the scale
up (or down) criteria and clicking “OK” in the dialog box in Figure 7.8, the software
will simulate the new production process by solving new mass and energy balances
for the entire flowsheet, estimating the new equipment sizes and remodel the
equipment scheduling.
176
Figure 7.8 Dialog box for “Process Throughput Adjustment”
All the data specified above provide a starting point for simulation of
proposed study. Given simulation inputs specified above, the SuperPro Designer 5.5
software is capable of conducting this simulation by using the “Tasks: Solve M&E
Balance” option from the main menu. This will cause the program to calculate the
mass and energy balances for the entire flowsheet, estimate the equipment sizes, and
In the dialog box shown in Figure 7.9, scale up (or down) could be realized
based on either a factor or target output (per batch or per year). By choosing the scale
up (or down) criteria and clicking “OK” in the dialog box in Figure 7.9, the software
will simulate the new production process by solving new mass and energy balances
for the entire flowsheet, estimating the new equipment sizes and remodel the
equipment scheduling.
177
Figure 7.9 Dialog box for “Process Throughput Adjustment”
The present study could be divided into two major parts (i) enzyme
production and (ii) ethanol production. As a starting point, the cellulase enzyme
production scale from the main fermentor is assumed to be 1 kilograms (kg) per
batch. Zhang and Lynd (2003) reported that the cellulase enzyme represented 20% of
cellulose). Thus, for every 125 kg of SCB consumed, the final product will be 5 kg
178
of new T. longibrachiatum. Following equation represents this simplified
fermentation process and provides a basis for economic analysis in this thesis.
T.
SCB Cellulase Enzyme FEP
longibrachiatum + +
(125 kg) (1 kg) (119 kg)
(5 kg)
The FEP was further used for the ethanol production. Thus, for production of
ethanol, the feedstock available, after enzyme production and detoxification of FEP,
is 119 kg. As per our study, 6.14% ethanol production could be achieved at
increase in inoculums size did not result in the considerable enhancement of ethanol
fermentation process
feed. Thus, at final stage 97.73 kg of ruminant protein could be produced. The
equipment occupancy chart also exhibits that the process is completed in two
179
V-101
BF-101
MX-101
V-102
V-103
MF-101
Equipment
MX-102
V-108
HX-101
DS-101
V-104
FDR-101
180
Figure 7.11 Flowsheet of the proposed study
181
7.2 Economic evaluation
Economic analyses are conducted to examine the unit costs of the present
experimental plant, as measured by dollars per kilogram ($/kg) and the profitability,
as measured by two profitability indicators: payback period and net present value
(NPV) at 7%.
These two objectives are realized by identifying equipment costs and economic
parameters used as input into the simulation software. Economic items (such as
direct fixed capital costs, operating costs and annual net cash flows) are calculated
based on these inputs. For objective one, unit costs are specified by the software
and net present value are calculated, using the data for both production costs and sale
revenues.
discussed, five groups of input data are of interest in this thesis: (1) properties of
components and mixtures and their corresponding economic data; (2) feed stream
data; (3) equipment cost data; (4) data for economic parameters such as project life
and discount rates; and (5) data for other technical parameters, including setup time,
processing time, temperatures, flowrates, among others. The data is either obtained
from the procedural operation descriptions or obtained directly from the default
182
7.2.1.1 Estimation of Equipment Costs
Assuming new equipment is similar to a base item where cost data (C0 ) is
available, SuperPro Designer 5.5 software predicts equipment purchase costs (EPC)
by using a power relationship for equipment capacities. Equation 5.1 explains the
equipment cost estimation process, where Q and Qo are the new and base equipment
capacities, respectively, and a is the exponent of the power law function given by the
software or specified by the user. By default, this exponent is set as 0.6 for
(Q)a
EPC = C0-----------
Q0
costs based on its capacity ( Q ), the user can either choose a “built-in model,” where
data are provided by the software, or choose a “User defined-model,” where base
equipment data ( C0 , Qo and a) must be entered into the software by the user.
183
Table 7.2 : Major equipment specification and FOB cost (2015 prices)
Quantity/ Description Unit Cost Cost
Stand-by ($) ($)
V-101 Blending Tank 167000 167000
Volume = 105.82 L
Diameter = 0.36 m
BF-101 Belt Filter 282000 282000
Belt Width = 0.06 m
MX-101 Mixer 500 500
Rated Throughput = 710.51 kg/h
V-103 Blending Tank 229000 229000
Volume = 1447.31 L
Diameter = 0.85 m
MF-101 Microfilter 51000 51000
Membrane Area = 13.03 m^2
DS-101 Disk-Stack Centrifuge 124000 124000
Sigma Factor = 5533.94 m^2
FDR-101 Freeze Dryer 114000 114000
Tray Area = 0.12 m2
Capacity = 4.59 kg H2O/cycle
V-104 Blending Tank 167000 167000
Volume = 7.24 L
Diameter = 0.15 m
AF-101 Air Filter 21000 21000
Rated Throughput = 0.00 m^3/s
MX-101 Mixer 500 500
Rated Throughput = 2240.50 kg/h
HX-101 Heat Exchanger 1000 1000
Area = 0.00 m^2
184
C-101 Distillation Column 19000 19000
Number of Stages = 14
V-107 Stirred Reactor 340000 340000
Volume = 458.76 L
Diameter = 0.62 m
V-102 Stirred Reactor 445000 445000
Volume = 3349.89 L
Diameter = 1.19 m
AF-102 Air Filter 8000 8000
Rated Throughput = 0.00 m^3/s
V-108 Fermentor 555000 555000
Volume = 77.86 L
Diameter = 0.32 m
All Listed Equipment 2524000 2524000
Unlisted Equipment (0.25×All Listed Equipment) 631000 631000
Total equipment purchase cost 3155000 3155000
parameters for the entire project (Figure 7.12); (2) capital cost parameters and (3)
operating cost parameters. All economic parameters are chosen by the default data
Parameters” from edit button of the main menu in the simulation software. The
dialog box for the “Time Valuation” tab is shown in Figure 7.12. In this thesis, all
parameter values are specified by their default values within the simulation software.
185
Figure 7.12 Dialog box: economic parameters for entire project
In order to calculate unit costs, direct fixed capital (DFC) and operating costs
was calculated.
The direct fixed capital costs calculation is the basis for further economic
analyses such as the operating cost analysis (used to determine the unit costs) and
cash flow analysis (used to determine the profitability). Based on the specification of
major equipment costs, direct fixed capital (DFC) costs are estimated in Table 7.3.
Following equation was used to calculate the DFC costs, which consist of Total plant
direct costs (TPDC), Total plant indirect costs (TPIC) and other costs (OC):
186
Table 7.3. Direct fixed capital costs estimates (2015 price in $)
2. Installation 1753000
4. Instrumentation 1261000
5. Insulation 95000
6. Electricals 315000
7. Buildings 1419000
187
7.2.2.2 Annual operating cost calculation
Annual operating costs were calculated and equal the sum of the following
items as specified within the software: (1) Raw materials; (2) Labour-Dependent; (3)
Analysis); (5) Waste treatment disposal; and (6) Utilities. The cost of consumables
Eight different raw materials are examined in the process for this thesis and
production process viz., electricity and heat transfer agents such as steam, cooling
water, and chilled water. The electricity costs were calculated as $7780 per year. The
cost of heat transfer agents viz., steam ($4.2 / 1000kg), cooling water ($0.1/1000kg)
and chilled water ($0.4/1000kg) was calculated to be $69, $173 and $15173,
respectively.
The total labour cost (TLC) is calculated as the sum of the labour demand per
type (LDT) multiplied by the labour rate per type (LRT). That is:
In this software, the default single labour rate is set as $69.00 per hour. The
total labour hours required is calculated and equals 20373 hours annually. So, the
188
The facility-dependent costs (FDC) accounts for depreciation (DEP) of direct
fixed capital (DFC) costs, equipment maintenance (MAI), insurance (INS), local
taxes (LT), and the possibly other overhead-type of factory expenses (FE). Equation
method, considering a salvage value fraction (f) of the direct fixed capital (DFC),
which is assumed 5% in this analysis by default. The depreciation period (n) is set to
DFC (1-f)
DEC = ----------------
n
(MAI), insurance (INS), local taxes (LT), and other overhead-type of factory expenses
control costs. In this thesis, it is estimated by default as 15% of total labour costs.
The waste generated during the process is divided in solid and liquid waste
materials. The default calculation of the waste material resulted as $19000 for solid
189
Once the above cost components were calculated, then total operating costs
were derived as listed in Table 7.4. The annual operating cost was found to be
$5395000.
Labour-Dependent 1406000
Facility-Dependent 3741000
Laboratory/QC/QA 211000
Utilities 15000
Total 5395000
researchers because they are concerned with the long-run industry sustainability.
However, potential may be more concerned with the profitability of their investment.
190
recover the initial investment in the simulated production plants. The projects with
payback period is calculated as the quotient of the total capital investment divided by
Shown in the Table 7.5, the payback period is calculated and equals 8.13
years, which implies that it takes more than eight years to recover the initial
investment for the enzyme, ethanol and animal feed production plant using the
current study. This number can be compared with corresponding payback period
values of alternative projects facing potential investors. The gross margin of the
191
Table 7.5 Cash flow and profitability indicators ($1000)
192