Professional Documents
Culture Documents
*Email: prof_ossama11@yahoo.com
Abstract: This paper presents electrostatic and magnetic effects of the overhead
transmission lines (OHTLs) on the well-insulated or aboveground metallic gas
pipelines. The induced voltages by capacitive and inductive couplings between the
overhead transmission line and aboveground or laid on a metallic gas pipelines,
under normal operation condition of the overhead transmission lines, and in case
of line to ground fault are calculated. The calculations take into account the effects
of various parameters, such as: separation distance between the OHTL and the
aboveground or laid on a foundation and the screening factor on the magnitude of
the capacitive induced voltage along the length of the pipelines. The induced
voltage between the OHTL and metallic gas pipelines, under normal operating
condition of the OHTL, is measured and compared with the calculated values.
146
PA-19
The Natural gas is supplied to Fayum area, Where; M12 is the mutual inductance between the
through 72 km steel buried pipeline of diameter earth wires and each phase of the power line and
equals 16 inch. It is coated by three layers of High L2 is the earth wire inductance.
Density Polyethylene (HDPE), which has a
resistance of , relative permittivity of 5, and 2.2 Conductive coupling between pipe
its thickness is 4 mm. The pipeline is buried at lines and OHTLs
depth of 1.5 m in soil. The soil resistivity varies The ground potential will be very high under line-
from 2500 to 100 . Pipeline pathway, is in to-ground fault conditions of the overhead
parallel to three high voltage overhead transmission lines, where heavy currents will flow
transmission lines with different separation through the ground in these cases. So, ground
distances. These distances vary from 35m to more potential domain will be increased under fault
than 6 km, as shown in Figure 1. conditions. Pipeline induced voltage may exceed
the coating strength of the pipeline. So, the
2 PIPELINE INDUCED VOLTAGE pipeline coating may be damaged [5]. In this paper
ATP software is used to simulate the overhead
2.1 Inductive coupling between pipelines transmission lines in case of line-to-ground fault
and OHTLs condition [10]. In this paper, it is assumed that the
line-to-ground fault is occurred at each kilometer
Pipeline induced voltage, by the inductive coupling along the overhead transmission, which is parallel
mechanism, depends on the currents of the to the pipeline. Hence, the fault current is obtained
overhead transmission lines, the separation at each kilometer along the overhead transmission.
distance between the overhead transmission lines From these fault currents the induced voltage
and the pipeline, and the soil resistivity [5]. The along the length of the pipeline is calculated. The
total driving electric induced voltage, Ez, is the magnitude of ground potential rise can be
superposition of the contribution of each phase calculated as follows [11]:
current. Hence, Ez can be positive or negative, and
it can be expressed as follows: [6, 7]
(5)
(3)
(7)
(4) (9)
147
PA-19
is the distance between the conductor x and MATLAB program is used to calculate power lines
the ground surface , is the distance from the electrostatic field above the ground pipeline. The
data of electrical power lines are given in appendix
conductor x to the conductor y , is the distance A. Figure 2 shows the pipeline capacitive induced
from the conductor y to the image of conductor x voltage at average conductors' height by using the
and GMR is the geometric mean radius of the actual separation distances between the power
conductor at the present of the sub-conductors . lines and the pipeline, as shown in Figure 1.
4 EXPERIMENTAL MEASUREMENTS
Where: is the sub-conductor radius, is the Pipeline induced voltage is measured by using
sub-conductor separation distance and is the digital voltmeter, and copper/copper sulphate
number of sub-conductors. After obtaining the ( ) reference electrode [12]. One
coefficient matrix, the sub-conductors charges will common type of half-cell contains a copper
be obtained as follows: electrode immersed in an electrolyte of dissolved
copper sulfate, which is shown in Figure 3. The
(13) measurement method is illustrated in Figure 4.
50
Where: is the charge matrix, is the
Pipeline line induced voltage (V)
45
conductor voltage. In the two dimensional region, 40
the electrostatic field has two components. These 35
two components may be described as follows 30
Horizontal component 25
20
15
(14)
10
5
0
And Vertical component 0 10 20 30 40
Pipeline length in (km)
50 60 70
148
PA-19
Measured (summer)
40 Measured (spring)
Measured (autumn)
20].
35
Measured (winter)
30
25
20
15
10
0
0 10 20 30 40 50 60 70
Pipeline length (km)
Figure 5 Pipeline calculated and measured
induced voltages in normal operating condition of
the transmission lines
Figure 7 Pipeline AC corrosion on Fayum gas
Figure 5 gives the Pipeline calculated and pipeline
measured induced voltages in normal operating
condition of the transmission lines .Figure 6 shows The current density in metallic pipelines is
a comparison between the measured induced calculated by the following relation:
voltage at different seasons and the calculated
induced voltage in case of normal operation of
overhead transmission lines, along the length of (21)
the pipeline.
Where, is the current density in , is
10000 the AC induced voltage in volt, is the soil
El-Kurimate-Cairo
resistivity in , and is the diameter of coating
Pipeline induced voltage (V)
Samaloute-Cairo
6000
relationship between the corrosion rate and the AC
current density. This relation shows that if the AC
4000 current density is 20 , AC corrosion occurred
by rate of 0.2 gram per year [18]. The AC
2000
discharging current density in due to the
resultant pipeline induced voltages under normal
operating condition is given in Fig. 9. It can be
0
0 10 20 30 40 50 60 70
Pipeline length (km)
noticed that, there are some points, which are
closed to OHTL, that have current densities
Figure 6 Total pipeline inductive and conductive
exceed 20 . So, the pitting corrosion is usually
voltages in case of single line-to-ground fault of the
occurs at lengths starting from 44 km to 46 km and
three power lines, individually
starting from 55 km to 62 km. See Fig. 9
149
PA-19
1.4
Delivery, Vol. 22, No. 4, pp. 2466-2472,
October 2007.
1.2
[5] Australian/New Zealand
Corrosion rate (g/cm2 yr)
100
th
60 2006, IEEE 11 . International conference on
transmission and distribution construction,
operation and live-line maintenance.
40
150
PA-19
Item value
MVA 158/circuit
Line voltage (r.m.s) in kV 220
Length in km 90
Positive & negative sequence
Figure A1 Power line tower dimensions of 500kV 3.6+ j 15.3
impedance per phase in ohm
Zero sequence impedance per 12.2+j50.95
phase in ohm
No of circuit per tower 2
No of conductors per phase 2
No of ground wires 1
Diameter of a single conductor 27
in mm
Spacing between 30
151