Larsen & Toubro Limited :: CWSS to Natham Scheme

Productivity Details for Pick & Carry Crane for Last 06 Months
Oct'17 Nov'17
SI Description No of No of
No Work done Qty
Crane Crane
914mm dia - 0.01 Kms
813mm dia - 0.30 Kms
MS Pipeline
1 ( including Gap 3 914mm SLV - 9 Nos, AV - 25 Nos, SCV - 4 2
Closing) Nos, 813mm SLV - 4 Nos, AV - 15 Nos &
SCV -04 Nos & 711mm dia SLV - 1 Nos, AV -
7 Nos & SCV - 01 Nos

500mm - 0.11Kms & 350mm - 0.03Kms


2 DI Pipeline 2 2
300mm - 0.08Kms, 250mm - 0.64Kms,
200mm - 0.72Kms

3 Piling Works

4 EMI Works 1 Erection of Electrical Panels 1

For Loading & Unloading of Pipes, Specials,


5 Store 1 1
Valves and EMI Items
7 6
o Limited :: CWSS to Natham Scheme
for Pick & Carry Crane for Last 06 Months
Nov'17 Dec'17
No of
Work done Qty Work done Qty
Crane
914mm dia - 0.07 Kms 914mm dia - 0.08 Kms 72
813mm dia - 0.06 Kms 813mm dia - 0.04 Kms
711mm dia - 0.02 Kms
1
914mm AV - 15 Nos, SCV - 2 Nos, 711mm dia SLV - 1 Nos, AV - 6Nos &
813mm SLV - 3 Nos, AV - 20 Nos & SCV - 01 Nos
SCV -03 Nos & 711mm dia SLV - 1
Nos, AV - 5Nos & SCV - 01 Nos

500mm - 0.13Kms & 350mm - 500mm - 0.46Kms, 450mm - 0.41Kms


0.03Kms & 350mm - 0.03Kms
1
300mm - 0.01Kms, 250mm - 300mm - 0.08Kms, 250mm -
0.25Kms, 200mm - 0.97Kms 0.11Kms, 200mm - 0.30Kms

Erection of Electrical Panels Erection of Electrical Panels


1
For Loading & Unloading of Pipes, For Loading & Unloading of Pipes,
Specials, Valves and EMI Items Specials, Valves and EMI Items
3
Larsen & Toubro Limited
Productivity Details for Trailer,
July'17 Aug'17 Sep'17
SI
No Description No of Work done Details No of Work done Details No of
Assets Assets Assets

MS Pipe Shifting and Panel


1 Trailer 1 MS Pipe Shifting 1 Board, Pumps, Motors and 1
Transformer Shifting Works

DI Pipes Shifting, Valve DI Pipes Shifting, Valve


Shifting, Cement and Shifting, Cement and
2 Truck 3 3 2
Formwork Materials Shifting Formwork Materials Shifting
Works Works

PVC Pipes and Specials PVC Pipes and Specials


3 Mini Truck 3 Shifting Works & 49.30Kms 3 Shifting Works & 56.27Kms 3
Laying completed Laying completed
Larsen & Toubro Limited :: CWSS to Natham Scheme
roductivity Details for Trailer, Truck and Eicher for Last 06 Months
Sep'17 Oct'17 Nov'17
No of No of
Work done Details Work done Details Work done Details
Assets Assets

MS Pipe Shifting and Panel MS Pipe Shifting and Panel MS Pipe Shifting and Panel
Board, Pumps, Motors and 1 Board, Pumps, Motors and 1 Board, Pumps, Motors and
Transformer Shifting Works Transformer Shifting Works Transformer Shifting Works

DI Pipes Shifting, Valve DI Pipes Shifting, Valve


DI Pipes Shifting, Valve Shifting, Shifting, Cement and Shifting, Cement and
Cement and Formwork Materials 2 2
Formwork Materials Shifting Formwork Materials Shifting
Shifting Works Works Works

PVC Pipes and Specials Shifting PVC Pipes and Specials PVC Pipes and Specials
Works & 31.52Kms Laying 3 Shifting Works & 18.56Kms 3 Shifting Works & 33.03Kms
completed Laying completed Laying completed
Dec'17
No of Work done Details
Assets

DI Pipes Shifting, Valve


Shifting, Cement and
1 Formwork Materials
Shifting Works

PVC Pipes and Specials


Shifting Works &
2 15.20Kms Laying
completed