Designation: Engineer
Document Revision Status (to be completed by Contractor / Service Provider)
Rev Reviewed By Approved By
Date Details of Revisions / Changes
No. (Name & Signature) (Name & Signature)
Where an exclusion zone is required, the SWMS must clearly state the detail of the required
exclusion zone, including the person responsible for implementation and supervision.
1 Operation pre-planning Not complete planning, no Assign competence person to manage - Engineer,
worker induction, lack of mobilization procedures that involve - Site Safety
preparation. coordination and paper works to be in Supervisor,
place. It includes safety induction, - Superintendent
machineries inspection, permit to
work, security access etc.
5 Task Lighting for working at Electrocution - Electrical lighting to be used at all - Site
night times during night works Superintendent
- All electrical equipment to be - Site Supervisor
inspected prior to use. - Engineer
- Electric plant to be kept isolated - Site Safety
from ground water. Supervisor.
*No. shall continue base on the list of tasks to be performed.
Section 6: Verification
I have provided, accurate and sufficient information and instructions to the work crew pertaining to this Safe Work Method Statement - the aspects / hazards associated with each work process and activity, the type
of potential impact, incident or accident, and the risk controls / practicable measures to be taken in the course of work and during an emergency - to ensure their safe undertaking of the work.
Instructed by (print name): …………………………………………………………………….. Signed: ………………………………………….. Date: …..../…...../……… Time: .............. am / pm