Professional Documents
Culture Documents
DESIGN METHODOLOGY
The urban roads usually are in flat terrain. Urbanization of the area and intense
density of construction needs well planned drainage. For effective drainage,
water from roads be taken to peripheral drains which in turn should join main
or trunk drain for ultimate discharge into the natural drain.
Existing drains pass through highly developed and thickly populated are. As
such there is a problem of availability of land for increasing the capacity of
drains further. Besides, these drains should be able to cater the increased
discharge due to new colonies & urbanization. An important aspect of such
drain is to ensure a good velocity in the drains not only when drain is running
full but also when the drain is partial full. Thus design needs to be made to
ensure self cleansing velocities during dominant and lean flow conditions.
1
computer models & empirical formulas. Of the different methods available,
rational method is most commonly used & serves the purpose of design.
The road side drains are not designed for the peak flow of rare occurrences
such as once in 100 years or 50 years- as in the case of design of important
structures such as bridges or weirs. However, it is necessary to provide
sufficient capacity to prevent too frequent flooding of the drainage area. There
may be some water accumulation on the roads when the rainfall exceeds the
design value which has to be permitted. The frequency of such occurrence
which can be permitted varies from place to place, depending upon the
importance of such place and expectancy of the public.
Based upon the practice being followed in metropolitan cities in our country
and cost consideration in mind, it is recommended that a return period of 1 to
2 years be adopted to estimate runoff.
Ic = 0.87 (L3)0.385
H
Where Ic = Time of concentration in hours
L = Length of critical point to the drain in Km
H = Fall level from remote point to drain level in meters
Rainfall Intensity: It has been observed that the shorter the duration of
critical rainfall, greater would be the expected average intensity during that
period. The critical duration of rainfall is the rainfall duration which produces
maximum runoff. This duration is equal to the time of concentration, since
shorter period do not allow the whole area to contribute in runoff & longer
duration will give a smaller average rainfall intensity. The problem, thus
reduces to one of establishing a relationship between time of rainfall duration &
probsblr or expected rainfall intensity.
2
The current practices being followed in metropolitan cites (Delhi ) is as under:
The average value of runoff which is adopted for different categories of drain
are:
a. Internal drains 0.177 m3/Ha 1cft/acre
b. Intercepting drains 0.132 m3/Ha 0.75cft/acre
c. Main drains 0.088 m3/Ha 0.5 cft/acre
To convert one hour duration rainfall into any duration intensity, IRC SP 13
have provided formulae
i= F (T+1)
T (t+1)
Where
i = intensity of rainfall within a shorter period of ‘t’ hours within a storm
F = Total rainfall in storm in cm falling in duration of storm of T hours
t = Smaller time interval in hours within the storm duration of T hours
For smaller water bodies not exceeding 50 Sq Km, rational method is widely
used for estimating peak runoff rates. The formulae is:
Q = 0.028 P A Ic
Where Q Designed peak runoff in cumecs
P Coefficient of runoff for catchment characteristics
A Catchment are in Heactres
Ic Critical rainfall intensity in cm per hour for the selected
frequency & duration
3
The coefficient of runoff (P) can be estimated as:
SN Description of surface Coefficient of
runoff (P)
Watertight pavement surface (concrete or bitumen) , 0.9
steep bare rock
2 Green area (Loamy) 0.3
3 Green area (Sandy) 0.20
4 Unpaved area along roads 0.30
5 Lawns & Parks 0.15
6 Flat built up area with about 60% area impervious 0.55
7 Moderately steep built up area with about 70% area 0.80
impervious
Hydraulic Design:
Capacity of drain is normally designed by Mannings Formulae
4
The mannings rugosity coefficient ‘n’ may be estimated as:
SN Description of surface Value of n
1 Brick pitched drain 0.017
2 Plastered brick surface 0.015
3 Plastered brick surface with neat cement finish 0.013
4 Concrete pipes upto 600 mm dia 0.015
5 Concrete pipes above 600 mm dia 0.013
6 Dry rubble masonry 0.033
7 Dry stone pitching 0.020
8 Kutcha drain 0.025
Note: To ensure self cleaning of the drain, a minimum velocity of 1.5 m/s may
be desirable. However, this may require installation of concrete or paved
drains.
5
Minimum Free Board:
6
2
STUDY AREA OF THE PROJECT
2.1 Introduction:
The study area comprises of the following :-
1 Four lane CC road from S.P. Police line to Mala Fatak railway crossing.
2 Drain after IHSDP Scheme drain at Purohit Ji ki Tapri to Chandresal road.
3 Drain along Chandresal road from Mala Fatak to chandresal Village.
4 Final disposal from Chandresal village to Chandresal river and through to
the Chambal river
7
STUDY AREA AS PER MASTER PLAN
8
TOTAL STATTION URVEY OF THE STUDY AREA (ENLARGED DWG ENCLOSED AT END)
9
STUDY AREA ON GOOGLE PLATFORM
The study area detailing as on Google platform is shown through various slides
as follows :
10
11
12
13
14
15
16
2.2 Salient Features of Study Area
Development in area:
As already proposed in Kota Master Plan 2023, Canal road from Borekheda to
Sogaria has been constructed.
S.P. Office Police line circle to Mala Fatak railway crossing fourlane cc road has
already been constructed .
Railway over bridge at Mala Fatak crossing is under construction.
After railway crossing road leads to Chandresal village construction activities
for road widening and drain along road are being done by UIT from Mala Fatak
to Mahatma Gandhi Colony.
After Mahatma Gandhi Colony (Rang Talab road Junction) drain along the
Chandresal road is not constructed and lying in its natural way.
On north side there is a village named Sogaria is situated nearby which
massive urbanization activities have started taking place.
Purohit Ji ki Tapari is a notified slum of Nagar Nigam in which a main drain of
has been constructed resently and after words private colonizers have started
developing authorized/Unauthorized colonies a main drain to discharge the out
flow of this area flows towards Chandresal road.
Population Density:
As per Kota Master Plan 2023, the area has started developing at very fast
growth rate area with population density of 100-151 people / acre. With the
proposed population density, the present & forecasted population of the study
area is:
The study area lies in the northern sub-urban of Kota city & is developing at
faster rate. As discussed earlier, the area is mostly developed by private
Colonizes & Developers. This resulted in requirement of drainage
channelization of the area and its final discharge.
17
2.4 Bottlenecks:
Lack of Basic Infrastructural Facilities like Roads, Drains & Water
Supply
Lack of integration of Natural Drainage Network
Prevailing enchroachments in the flow path of natural drains
Disintegrated and Haphazard Development resulting
¾ Number of improper culverts.
¾ Irregular building line
¾ Non uniformity in natural drainage network.
The existing situation of the area and its drainage is shown in the enclosed
Google map and reconnaissance survey of the study area.
2.6 Rainfall:
The Kota is blessed with good annual rainfall. The monthly rainfall at Kota city
since 1957 is as:
TOTAL RAINFALL in mm
Rain
Total Gauge
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec rainfall Station
1957 37.6 0 0 0 0 73.4 353.9 283.6 107.2 5.1 0 0 860.8 KOTA (A)
1958 4.1 0 0.8 0.8 0 28.1 417.2 195.6 249.8 0.6 2.6 0 899.6 KOTA (A)
Chambal
1959 0.1 0 3.1 1 13.6 80.6 296 404.8 36 5.4 0 0 840.6 Dam
Chambal
1960 0.1 0 3.1 1 13.6 80.6 296 404.8 36 5.4 0 0 840.6 Dam
Chambal
1961 24.4 0 0 0 7.3 13.2 336.8 201.1 707.4 18.2 3.3 2 1313.7 Dam
1962 0 0.2 0 3.2 1.6 0 346.9 276.6 166.9 0 1.2 1.8 798.4 KOTA (A)
1963 1.2 0 2.4 2.6 4.2 15.6 193.2 341.6 94.2 3.2 19.8 0 678 KOTA (A)
1964 0 0 0 0 39.9 87.5 172.3 278.9 64.8 0 0 0 643.4 KOTA (A)
1965 4.4 0 4.1 1.4 1.8 29.2 239.7 23.7 127.8 8.2 0 0 440.3 KOTA (A)
1966 0 0 34.4 0 0 118.9 229 382.6 149.8 0 0 7.8 922.5 KOTA (A)
1967 0 0 34.4 0 0 118.9 229 382.6 149.8 0 0 7.8 922.5 KOTA (A)
1968 0 0 13.6 0 2.6 1.8 305.9 273.7 8.2 0 0 0 605.8 KOTA (A)
1969 2.2 0 0 0 1.4 1.8 449.8 401.8 60.4 0 0.4 0 917.8 KOTA (A)
1970 13 13 3.4 0.2 3 165.5 234.4 320.8 109.5 8 0 0 870.8 KOTA (A)
1971 0 0 0 0 7.8 151 559.1 182.5 368.8 12 0 0 1281.2 KOTA (A)
1972 0 7.4 0.2 0 3.6 64.8 60.8 242.9 0 0 0 0 379.7 KOTA (A)
1973 0 0 0 0 3.6 16.6 446.6 212.7 123.6 22 0 3.2 828.3 KOTA (A)
1974 0 0 0 0 16.4 0 475.6 127.6 2.2 N.A. 0 0 621.8 KOTA (A)
1975 0 0 0 0 0 N.A. 46 330.2 74 0 0 0 450.2 KOTA (A)
1976 0 0 0 0 0 28 133 181 74 0 N.A. 0 416 KOTA (A)
1977 0 0 0 0 41.6 175.9 496.1 244.4 132.6 0 8 0 1098.6 KOTA (A)
1978 0 13.2 12.1 0.5 0 163.9 248.4 462.1 24.3 0 1 42.6 968.1 imd
1979 8.9 15.4 6.8 0 31.5 159.8 303.8 123.1 2.3 1.3 124 6.8 783.7 imd
1980 0 3 0.1 0 0.2 65.4 152.5 95 60.8 0 0 7.3 384.3 imd
1981 2.3 0 16 0 5 56.8 228.9 110.6 99.2 1.6 40.6 0 561 imd
1982 33.1 4.9 1.7 0.4 46.1 29.7 186.7 370.4 10.3 1.3 0 0 684.6 imd
1983 1.8 0 0 14.9 33.5 35 173.5 155.1 67.3 25.3 0 0 506.4 imd
18
1984 8.4 0 0 0 0 13.5 103.9 273.8 209.4 0 0 0 609 airport
1985 0 0 8.6 2.1 3.4 22.6 167.6 304 40.8 0 0 2.6 551.7 airport
1986 5.1 71.5 1 0 23.8 41.8 499.7 217.2 2.7 0 0.5 0 863.3 airport
1987 12.4 0 0 0 0 71.6 68.8 184.8 61 58.2 0 33.8 490.6 ladpura
1988 12.2 0 2.9 2 1.2 144 291.1 166.6 146.4 31.2 0 0 797.6 KOTA (A)
1989 11 0 20.8 0 0.8 52 135.6 286.8 13.1 0 0 0 520.1 KOTA (A)
1990 0 19.6 0 0 20 131.5 137 179 94.1 0 0.4 0 581.6 KOTA (A)
1991 1.2 9 0 37.9 0 1.6 388.1 296.5 59 0 4 10.6 807.9 KOTA (A)
1992 0 0 0 0 12 11.8 139.4 246.5 159.3 109.9 6.8 0 685.7 KOTA (A)
1993 0 10 0 0 6 91.9 281.1 179.2 223.1 12.5 0 0 803.8 KOTA (A)
Chambal
1994 0 0 0 0 0 169 330.4 291.9 88.3 0 0 0 879.6 Dam
Chambal
1995 0 0 0 0 0 8 331.8 497.2 86 0 0 0 923 Dam
1996 0 1 6.2 3.2 4.8 19 267.4 381.6 98 0 0 0 781.2 ladpura
1997 0 0 0 0 0 41 218 344 50 0 0 0 653 KOTA (A)
1998 0 0 0 21.2 0 56 287 56.9 85.2 13 0 0 519.3 ladpura
1999 0 8.2 0 0 0 56.6 292.8 105.8 103.2 2 0 0 568.6 ladpura
2000 0 0 0 4.6 200.2 49.2 383.6 121.5 31 0 0 1.2 791.3 ladpura
2001 0 0 0 0.4 70.4 210.8 607.8 188 0 3.8 0 0 1081.2 ladpura
2002 0 59 0 0 1 70 55 221 55 0 0 2 463 ladpura
2003 3 30 0 16 5 57 209 119 79 0 0 7.5 525.5 ladpura
2004 3 0 0 0 4.5 38.5 65 422.3 9.7 29 0 0 572 ladpura
2005 0 0 9 2.4 6 30.6 370 40 0 0 0 0 458 ladpura
2006 0 0 15 0 7 107 144 235 170 1 0 0 679 ladpura
2007 0 26 5 0 0 135 401 110 119.5 0 0 4 800.5 ladpura
2008 0 0 3 24 17 197 197 187 79 0 8 0 712 ladpura
2009 0 0 0 0 0 46 393 126 32 19 32 0 648 ladpura
2010 0 1 0 0 0 19.4 160.6 204.7 130.3 0 54 1 571 ladpura
2011 0 15 0 0 12 381 140.1 275.6 144.3 0 0 0 968 ladpura
Avera
ge 3.4 5.6 3.8 2.5 12.2 74.7 266.9 241.3 99.6 7.4 5.7 2.6 724
The main season of rainfall starts from June & last till September (4 months).
This rainfall occurs in 4 months. The observed rainy days are:
19
1973 0 0 0 0 0 1 12 15 10 1 0 0 39
1974 0 0 0 0 2 0 12 6 0 N.A. 0 0 20
1975 0 0 0 0 0 N.A. 3 8 4 0 0 0 15
1976 0 0 0 0 0 2 6 10 2 0 N.A. 0 20
1977 0 0 0 0 4 6 15 11 6 0 1 0 43
1978 0 2 1 0 0 7 14 17 1 0 0 1 43
1979 1 2 1 0 4 6 8 7 0 0 6 2 37
1980 0 0 0 0 0 6 9 7 2 0 0 1 25
1981 0 0 1 0 0 6 13 10 4 0 1 0 35
1982 2 0 0 0 1 4 10 17 1 0 0 0 35
1983 0 0 0 2 3 4 8 11 7 3 0 0 38
1984 1 0 0 0 0 3 5 12 4 0 0 0 25
1985 0 0 1 0 1 2 12 13 6 0 0 1 36
1986 1 3 0 0 2 4 14 9 0 0 0 0 33
1987 1 0 0 0 0 4 7 12 2 3 0 1 30
1988 1 0 1 0 0 6 15 11 6 2 0 0 42
1989 1 0 2 0 0 4 9 15 3 0 0 0 34
1990 0 3 0 0 2 5 9 10 9 0 0 0 38
1991 0 1 0 1 0 0 14 11 5 0 1 1 34
1992 0 0 0 0 1 2 9 12 5 4 1 0 34
1993 0 1 0 0 1 8 11 7 13 2 0 0 43
1994 0 0 0 0 0 6 14 15 5 0 0 0 40
1995 0 0 0 0 0 1 16 16 3 0 0 0 36
1996 0 0 1 1 1 2 13 16 9 0 0 0 43
1997 0 0 0 0 0 1 13 9 5 0 0 0 28
1998 0 0 0 1 0 6 9 6 7 1 0 0 30
1999 0 1 0 0 0 3 11 7 8 0 0 0 30
2000 0 0 0 1 4 2 9 6 2 0 0 0 24
2001 0 0 0 0 2 11 12 7 0 1 0 0 33
2002 0 1 0 0 0 4 3 10 3 0 0 0 21
2003 1 3 0 1 1 4 13 7 5 0 0 1 36
2004 1 0 0 0 1 4 5 14 1 2 0 0 28
2005 0 0 2 0 2 2 13 3 0 0 0 0 22
2006 0 0 2 0 2 5 9 13 5 0 0 0 36
2007 0 3 1 0 0 3 11 6 7 0 0 1 32
2008 0 0 0 2 2 8 10 9 5 0 1 0 37
2009 0 0 0 0 0 4 12 8 4 2 1 0 31
2010 0 0 0 0 0 2 8 18 6 0 6 0 40
2011 0 1 0 0 2 9 5 14 9 0 0 0 40
Avera
ge 0.33 0.42 0.40 0.16 0.87 4.17 10.20 11.15 5.02 0.61 0.41 0.20 33.84
20
CHAPTER-3
METHODOLOGY
Aims and Objectives
9 To Discharge Municipal Waste water
9 To cater storm water discharge for average rainfall intensity
9 Renovate existing drainage network if required
9 Improvement of cross drainage works.
9 Designing of branch & main drain network
Limitations:
Action Plan:
21
9 Organizing consultation meeting with the stakeholders
9 Identification of missing links
9 Estimation of average & maximum flood discharge
9 Estimation of waste water discharge
9 Proposing the missing links
9 Strengthening/rehabilitation of existing natural drainage
9 Incorporation of suggestions/feedbacks after consultation
meeting
9 Identification & survey of natural outfall
9 Preparing engineering proposal/estimates for providing
drainage based on average rainfall intensity
9 Determination of detention time & accordingly critical
rainfall intensity
9 Preparing engineering design & drawings
9 Preparing engineering estimates for the works
9 Phasing the programme for implementation
9 Preparing tender documents
9 Bidding for execution of the proposal
22
CHAPTER-4
CONCEPTUAL PLAN
Based upon design methodology given at Chapter 1,
Peak flood discharge can be estimated through rational formula:
For smaller water bodies not exceeding 50 Sq Km, rational method is widely
used for estimating peak runoff rates. The formulae is:
Q = 0.028 P A Ic 1
Where Q Designed peak runoff in cumecs
P Coefficient of runoff for catchment characteristics
A Catchment are in Heactres
Ic Critical rainfall intensity in cm per hour for the selected
frequency & duration
i= F (T+1) 3
T (t+1)
Where
23
i = intensity of rainfall within a shorter period of ‘t’ hours within a storm
F = Total rainfall in storm in cm falling in duration of storm of T hours
t = Smaller time interval in hours within the storm duration of T hours
24
Disposal of waste water/Strom water:
As the area has only one outfall through natural drainage that too passing
through heavily populated area with lot of encroachment in the drain, it is not
possible to cater for the peak rainfall intensity. Besides, limited natural
drainage, following reasons also contributes to the inadequate drainage
capacity of the area:
These factors limits the drainage disposal capacity of the area. Hence, it is
proposed to provide drainage system for average rainfall intensity and during
peak rainfall, flood detention time of duration 2 to 3 hours may be resulted.
25
Zoning of the Project Area:
26
Existing Drainage
The drainage network & ground profile is enclosed at Annexure I
Following storm water drain sections are proposed for preliminary estimations:
Zone 1: Four lane CC road from S.P. Police line to Mala Fatak railway crossing
Under this zone, it is proposed to built RCC drain on both sides of Roads from
SP Office circle to Mal Phatak ROB junction. The drain of 1.5m width & 2.0 m
depth is suggested. The drain encounters about 10 nos culverst along both
side. Hence, the abstract drain requirement of Zone 1 is:
27
Existing Drain in front of APS
28
Existing Drain in Zone 2
Existing & Proposed Drain in Zone 2 near Rang Talab (Guru Govid Vihar)
Drain after purohit ji ke Tapri (village sogaria) to Node 4 i.e. junction with main
drain in RCC open drain 3.5 X3.5 mm in length of 2225 m & 10 nos culverts
are also proposed.
29
Zone 3: Drain below Sogaria to Chandresal
The length of drain channelization is in the width of 5.0 m to cater future needs
also. The length of this channelization will be 5000 m. The drain will encounter
around 5 nos culverts.
Zone 4: Final disposal from Chandresal village to Chandresal river and through
to the Chambal river
The existing condition of drainage in Zone 4 is:
30
31
•
•
•
32
•
• Final Disposal Point
33
The ABSTRACT of Drain Proposal is as under:
34
CHAPTER-5
PRILIMINARY ESTIMATES AND PROJECT COST
35
5.3 Abstract of Cost:
Component and Zone wise quantification has been done for the purpose of
project estimation and they are summarized as below.
36