Professional Documents
Culture Documents
Page
Table of Contents 1
1.0 Introduction 4
Strip Footing 5
Combined Footing 7
Introduction 9
2.1.1 Guideline 10
Soil Profile 10
Soil Type 10
Soil Parameter 14
Reduction Factor 20
Procedure to finding the soil Parameter (Sample Based On the Layer 1 in BH1) 27
1
Calculation Depth Of Foundation 33
Sample Calculation 33
Elastic Settlement 49
Angular Distortion 62
Site Clearance 71
Site Layout 72
Excavation 73
Lean Concrete 75
Footing 75
Curing of Concrete 77
7.0 Costing 79
General 93
2
Corrosion Protection Of Foundations 95
10.4.1 General 95
Ground Investigation 96
10.5.1 General 96
Shallow Foundations 97
NouvoSPT Software 99
Refrences 102
3
1.0 Introduction
For this project Exora Consult Sdn Bhd was giving task to design shallow foundation
based on the 2 borehole results provided. Factory column loading shows that there is two 0.5m
square columns with desugn loads of 1000KN (square footing) and 2000 KN (rectangular
footing) are located as shown in figure number 1. To fulfill all the requirement of the perfect
design, we need to consider that allowable footing differential settlements or limiting angular
distortion, βmax ≤ 1/300.
Figure 1.1
For the construction of the design, knowledge of the existing soil is required. For this
reason, a S.I contractor was appointed to conduct the soil investigation by the client. Using data
of the two boreholes as it shown is figure number 1, helps us to get detail of the soil profile
which is necessary in designing shallow foundation.
4
In this project, we are required to clearly shows the derivation of soil parameters and
design procedure used in the design. In the same time, it is necessary to have detail design
calculation (including shallow foundation capacity and settlement).
Figure 1.2
Basically, the depth of shallow foundations are less than 3m below the finished level
unless otherwise specified. The depth of shallow foundation are generally less than its width.
There are different types of shallow foundation which are:
i. Strip footing
ii. Spread or isolated footing
iii. Combined footing strap or cantilever footing
iv. Mat or raft foundation
Strip Footing
5
Figure 1.3
Figure 1.4
6
Combined Footing
A combined footing supports two columns. It is used when the two columns are
so close to each other that their individual footings would overlap. A combined footing
is also provided when the property line is so close to one column that a spread footing
would be eccentrically loaded when kept entirely within the property line. By
combining it with that of an interior column, the load is evenly distributed. A combined
footing may be rectangular or trapezoidal in plan.
Figure 1.5
A strap (or cantilever) footing consists of two isolated footings connected with
a structural strap or a lever. The strap connects the two footings such that they behave
as one unit. The strap is designed as a rigid beam. The individual footings are so
designed that their combined line of action passes through the resultant of the total load.
A strap footing is more economical than a combined footing when the allowable soil
pressure is relatively high and the distance between the columns is larger.
7
Figure 1.6
8
2.0 Soil Investigation
Soil Investigation is the process of establishing the type of soil strata at a specific area, by
drilling holes into the earth to obtain samples. In this project, basically there are total 2
boreholes was carried out for the purpose of testing the properties of soil. The parameter of soil
was corralate with the thory to find the most important parameter to include in the design. With
SPT value. The corrected SPT also need to carry out like N60, N1(60). This corrected value
need to use for finding the soil parameter.
BH
1
BH
2
Introduction
Soil profile and site invetigation is very important for every building. This is
because for ensure the soil is not failure when load is placed on the top of the soil. In
this project the visualization of soil profile is using VisLog. And the Corrolation of soil
parameter Using the graph and NovoSPT.
9
2.1.1 Guideline
a) Authority
i. Jabatan Kerja Raya Malaysia (JKR)
ii. Pejabat Tanah dan Galian Selangor
Soil Profile
The soil profile is one of the most important concepts in soil science. It is a key
to understanding the processes that have taken in soil development and is the means of
determining the types of soil that occur and is the basis for their classification. The soil
profile is defined as a vertical section of the soil from the ground surface downwards to
where the soil meets the underlying rock. The soil profile can be as little as 10 cm thick
in immature soils and as deep as several metres in tropical areas where the climate is
conducive to rapid alteration of the underlying rock to form soil. In temperate areas, the
soil profile is often around a metre deep and in arid areas somewhat shallower than this.
Soil Type
Many natural bodies, such as plants and animals, are discrete entities which can
be classified and guidelines for their identification followed. Soils are much more
difficult to identify and classify than these discrete bodies for two main reasons: (i) soil
is more or less a continuum covering the land surface of the earth, not a set of discrete
entities; and (ii) most of the soil is below ground and therefore not readily visible. Soils
grade into one another across the landscape usually without sharp boundaries between
10
one type of soil and another. Soil surveyors who make maps of soils have to use their
skills in reading changes in the landscape coupled with auger borings in the soil to
identify the nature of the soil.
There are several ways of classifying a soil, from the simple to the complex. A
soil type may be as simple as ‘a sandy soil’ or ‘a clayey soil’ and this is often the
perception of many land users, such as farmers or civil engineers, who see it as material
they have to deal with to achieve an end result, such as the growing of a crop of wheat,
or the building a road. Simple classifications tend to be of local and restricted relevance
only. At the other end of the spectrum is the soil scientist who needs to understand how
soils have formed, which types occur where, and for what the different types of soil can
be used. The soil scientist seeks a much broader understanding, with the aim of
underpinning the use and preservation of this important natural resource, and this has
manifested itself in a number of detailed soil classification systems worldwide
11
Figure 2.2 : Soil Classifications Group Symbol ASTM Standard
Vislong is the software to visualize the soil profile below the ground. VisLog is
a program that has been designed to assist all geoscience engineers of generating
subsurface soil layers. Generally, VisLog import most of our existing data and run the
model. The main usage of VisLog is to visualize the boreholes in the site. Input data
that essential for this application comprises of: Borehole Name, Total depth,
Coordinates, Water Level and other information. VisLog illustrates all boreholes in a
project and indicates the ground and water surface. Moreover, it’s automatically draw
the soil profiles through selected boreholes. Visualization of soil below the ground
using VisLog.
12
2. Classified
4. Pick The
the Soil Using 3.
Critical Soil
1. Data From The Group Visualization
Profile for
Bore log Symbol of Soil Profile
Using In The
ASTM Using VisLog
Design
Standard
13
Soil Parameter
Soil Parameter is very important to design the building. This is for estimating
the soil bearing capacity, to check settlement etc. the soil parameters for finding the
bearing capacity of the soil are;
14
Based on the soil profile, the soil parameter can be determined by using
correlation table and equation. And software also need to be used. List for all table
involved for soil parameter determination is list down below based on the
correlation made from scantiest. Mostly the correlation is made up differently mean
for example, if the type of soil is sand so the friction angle is for pure sand not for
mixture of soil. So the adjustment of the soil parameter need to be done using the
range value.
N correction =15+0.5(N60-15)
15
N Value From SPT/
N Value From SPT 300 mm
Finding Using
Corrected N value = Correlation Based
N60 and N1(60) on Graph
Figure 2.6 : Finding The Unit Figure 2.7 : Finding The Others
Weight Of the Soil Parameter Of Soi
𝑁 × 𝑛𝐻 × 𝑛𝐵 × 𝑛𝑆 × 𝑛𝑅
60 N1(60)
N Value
16
List Of Tables Using For Finding Soil Parameter
17
Figure 2.9 : For Finding Modulus of Figure 2.10 : For Finding The
Elesticity Cohesio
Table 2.1 : Soil Properties In borehoe 1 (Water Table was Consider Calculated by
NovoSPT)
Thickness Cu Es C’
N60 N1(60) Ɣ Ɣ*z Φ’
(m) (kN/m²) (Mpa) (kN/m²)
(kN/m3)
1. Φ’Avg = 29.95°
2. EsAvg (Mpa) = 12.56
3. C’Avg (kN/m²) = 112.29
4. ƔAvg (kN/m3) = 20.2
18
Table 2.2 : Soil Properties In borehole 2 without Reduction Factor
Depth,
Cu Es C’
SPT z N60 N1(60) Ɣ Ɣ*z Φ’
(kN/m²) (Mpa) (kN/m²)
(m) (kN/m3)
1. Φ’Avg = 28.711°
2. EsAvg (Mpa) = 6.56
3. C’Avg (kN/m²) = 23.156
4. ƔAvg (kN/m3) = 20.427
19
Reduction Factor
Redution factor if very important when using correlation. This is because the
correlation that used in this software or Graph is purly Sand or clay. This mean in every
soil layer, the soil was mix between sand clay gravel or silt. So we cannot take the 100
% value based on sapretly correlation graph to used in the design. For exmple In Layer
2. BH 1
The Φ value is 28.3 and the C value is 39.28 Kpa. This mean the friction angle
for the soil is higher and the undrained shear strength is also higher. This because the
correlation is used saperetly, so it will be cause in higher for the both value. In other
words, using N value on that soil layer, we find the friction angle and at the same time
used same N value in same layer to find the Undrain shear starain Cu also.
20
2.7.1 Correction in layer 1 Example
Mostly in this soil layer is sandy silt sand. So the fiction angle is lower
due to the most dominent soil in this layer was silt. The new friction angle may
reduced using reduction factor and Cu was remind based on the correction using
graph or Software.
21
Figure 2.11 : Soil Correlation and all Parameter in BH1
22
Figure 2.12 : Soil Correlation and all Parameter in BH2
23
Critical Soil Profile
BH2 BH1
Based on the analysis on the borehole 1 and 2. Borehole 1 is the most critical
borehole because the most fine grain in this type. Strength depends principally upon the
content of water, clastic materials and plastic materials. Soils are primarily of two types
cohesionless soils in which the strength is produced mainly by the friction of clastic
particles against one another, and cohesive soils in which the strength, among other
things, is influenced by forces between clay particles.
24
A clayey soil will not change its volume unless the water content changes.
Structural damage may occur if the change in moisture content is relatively rapid (say
over a few weeks or months) or if it affects only part of a building. Not only that,
situations which can cause this include changes in subsurface drainage (such as a water
leak from a burst or blocked pipe or drain), localized drying of a soil (due to plant
growth or proximity of trees), or a sudden change in the water regime (due to the
removal or pruning of a tree which was sheltering the soil and keeping it relatively dry,
for example).
25
26
Procedure to finding the soil Parameter (Sample Based On the Layer 1 in BH1)
1. Using the soil soil profile visualize in the software and SPT value in the Borelog
Soil Soil N
Type Value
Figure 2.15 : Sample Of The Bore Log
2. Using N value 1. Need to find the Unit Weight Of The Soil (In BH1 Layer 2 N
value Is 7/300 mean N blow per 300mm
Figure 2.16 : The value get it from this graph in (pcf) / Lb/ft3 , so we need to
convert to kN/m3
27
3. To find the Undraind Shear Strength ( Graph Terzaghi and Peck or Sower)
The Cu value in the first layer is 38.28 kPa. this exact value is getting from
NovoSPT software by using Sower 1979 correlation. The range is from the graph.
4. Friction angle
The Value got from this graph is around 27.9°. This exact value also we got
from NovoSPT software. The range is from the graph ( Reduction Factor need to Apply
in this value. Because of most dominent soil was Silt)
28
5. Modulus of Elesticity is determined by using the formula above or by also
NovoSPT software.
This step was repeated for the every layer until end of the soil layer in BH1
29
Figure 2.17 : Critical Soil Profile Without Reduction Factor
30
3.0 Factor Affecting the depth of Shallow Foundation
Before calculating depth of shallow foundation, the following factors have to be considered
well in advance.
1. Foundation should be placed at such a depth so that it is safe against damages due to
swelling, shrinkage or freezing of sub soil.
2. Bearing capacity of soil beneath the foundation must be adequate to support the load
coming from foundation.
3. If foundation has to be placed on cohesive soil then the settlement due to consolidation
should not be excessive.
4. Never place foundation on loose or disturbed soils which have a tendency to erode by
wind or flood.
5. If possible then foundation should be placed above ground water table as this can avoid
cost of pumping, and can prevent instability of soil due to seepage of water into the
bottom of an excavation.
6. Make an investigation on foundation soil to know its physical and chemical properties,
because presence of sulphate can damage foundation.
31
4.0 Bearing Capacity
The soil must be capable of carrying the loads from any engineered structure placed
upon it without a shear failure and with the resulting settlements being tolerable for that
structure. The bearing capacity of a shallow foundation can be defined as the maximum value
of the load applied, for which no point of the subsoil reaches failure point or else for which
failure extends to a considerable volume of soil.
Seldom has a structure collapsed or tilted over from a base shear failure in recent times.
Most reported base failures have occurred under embankments or similar structures where a
low factor of safety was deemed acceptable. Most structural distress attributed to poor
foundation design is from excessive settlements. Even here, however, structural collapse
seldom occurs. This may in part be due to settlements being time-dependent, so that when
cracks or other evidence first appears, there is sufficient time to take remedial measures.
It is necessary to investigate both base shear resistance and settlements for any
structure. In many cases settlement criteria will control the allowable bearing capacity;
however, there are also a number of cases where base shear (in which a base punches into the
ground usually with a simultaneous rotation) dictates the recommended bearing capacity.
32
5.0 Elastic Settlement
The minimum depth of shallow foundation for a soil can be calculated using the
following formula as suggested by Rankine. This is called Rankine’s Formula.
Where,
Dmin = Minimum depth of foundation in m
g = Density of unit weight of soil in kN/m3
Ø = Angle of repose in Degrees
q = Intensity of load or Safe bearing capacity of soil in kN/m2
q = Assume 2 x 2 Footing
Sample Calculation
𝟐𝟓𝟎
Dmin = × ((1 − sin 28.3) ÷ (1 + sin 28.3))2
𝟏𝟗.𝟐
Dmin = 52.08 × 0.129 = 1.49 m
33
1000 kN 2000 kN
1.5m
2.4m WT
Effective Depth H or
5B which one is
Effective Depth H or
smaller
5B to find the
average of the soil
parameter
Note: JKR standart maximum 1.5 meter from foundtion to soil this is because we need to
maintain the coloum stump. Coloum stump need to be 1.5 meter from the foundation to the
top soil.
34
Figure 5.1 : Soil Profile and Soil parameter with Placement of Foundation
Explanation:
For this case we use reduction factor for the friction angle. This is because of the most
of the soil layer stated in the bore long is majority was clay. So the undrained shear strength
value we maintained got from correlation and friction angle we need to reduce it. No specefic
way to reduce because we do not know how many percent of them is clay and how many
percent is sand. So the best way we look for the strength value get from correlation for example
if undrain shear strength is high so we reduce more on the friction angle but when undrain shear
is low so we reduce less from the friction angle.
35
Title: Trial 1. Square footing 2.0 m x 2.0 m
No Calculation Reference
19.2𝑥0.5+19.3+20.41+20.41+20.41+20.41𝑥1.5+20.41𝑥1.5+2−.41𝑥1
γavg = 10
= 19.13 KN/𝑚3
36
No Calculation Reference
𝑐 ΄ avg =
19.14𝑥0.5+21.88+71.51+101.49+195.98+310.43𝑥1.5+83.51𝑥1.5+85.13𝑥1.5+86.21
10
= 120.524 KN/𝑚2
22.64𝑥0.5+19.81+11.52+6+4.5+3𝑥1.5+9.24𝑥1.5+9.5𝑥1.5+8.9
ϕ avg = 10
= 9.466̊
𝑒𝐿 0.3 𝑒𝐵 0.2
= = 0.15 = =0.1
𝐿 2 𝐵 2
T
his case is similar to case II
𝐿1
≈ 1.0; 𝐿1 = (1.0)(2) = 2 𝑚
𝐿
And
𝐿2
≈ 0.25; 𝐿2 = (0.25) (2) = 0.5 m
𝐿
1 1
𝐴΄ = 2(𝐿1 + 𝐿2 )𝐵 = 2(2+ 0.5)(2) = 2.5 𝑚2
𝐿΄ = 𝐿1 = 2 m
𝐴΄ 2.5
𝐵΄ = = = 1.25 m
𝐿1 2
1
𝑞 ΄ 𝑢 = 𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 𝐹𝑐𝑖 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 𝐹𝑞𝑖 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 𝐹γ𝑖
for ϕ΄ = 9.466̊,
𝑁𝑐 = 8.120, 𝑁𝑞 = 2.35 and 𝑁γ = 1.11 thus,
𝐵΄ 𝑁𝑞 1.25 2.35
𝐹𝑐𝑠 = 1 + =1+ = 1.180
𝐿΄ 𝑁𝑐 2 8.120
37
No Calculation Reference
𝐵΄ 1.25
𝐹𝑞𝑠 = 1 + ( 𝐿΄ ) tan ϕ΄ = 1+( ) tan 9.466̊ = 1.1
2
𝐵΄ 1.25
𝐹γ𝑠 = 1 – 0.4 ( 𝐿΄ ) = 1 – 0.4 +( ) = 0.75
2
𝐷𝑓
𝐹q𝑑 = 1 + 2 tan ϕ΄ (1 − sinϕ΄ )2 𝐵
1.5
=1 + 2 tan 9.466 (1 − sin9.466)2 1.25 = 1.32
1−𝐹q𝑑 1−1.32
𝐹c𝑑 = 𝐹q𝑑 − 𝑁 ΄
= 1.32 - 8.120 tan 9.466 = 1.55
𝑐 tan ϕ
𝐹γ𝑑 = 1
So
1
𝑄𝑢𝑙𝑡 = 𝐴΄ 𝑞 ΄ 𝑢 = 𝐴΄ (𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 )
1
= 2.5 ( 120.524x8.120x1.180x1.55x1+ 28.695x2.35x1.1x1.32x1 + 2
x19.13x1.25x1.11x1x1)
= 4752 KN
𝟒𝟕𝟓𝟐
= 4.75 > 3.0 OK
𝟏𝟎𝟎𝟎
38
Title: Trial 2. Square footing 1.8 m x 1.8 m
No Calculation Reference
19.2𝑥0.5+19.3+20.41+20.41+20.41+20.41𝑥1.5+20.41𝑥1.5+2.41𝑥1.5
γavg = 9
= 23.48 KN/𝑚3
39
No Calculation Reference
𝑐 ΄ avg =
19.14𝑥0.5+21.88+71.51+101.49+195.98+310.43𝑥1.5+83.51𝑥1.5+85.13𝑥1.5
9
2
= 124.3 KN/𝑚
22.64𝑥0.5+19.81+11.52+6+4.5+3𝑥1.5+9.24𝑥1.5+9.5𝑥1.5
ϕ avg = 9
= 9.53̊
q = (1.5)(23.48) = 35.22 KN/𝑚2
𝑒𝐿 0.3 𝑒𝐵 0.2
= 1.8 = 0.167 = 1.8 =0.11
𝐿 𝐵
And
𝐿2
≈ 0.2; 𝐿2 = (0.2) (1.8) = 0.36 m
𝐿
1 1
𝐴΄ = 2(𝐿1 + 𝐿2 )𝐵 = 2(1.71+ 0.36)(1.8) = 1.863 𝑚2
𝐿΄ = 𝐿1 = 1.71 m
𝐴΄ 1.863
𝐵΄ = = = 1.08 m
𝐿1 1.71
1
𝑞 ΄ 𝑢 = 𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 𝐹𝑐𝑖 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 𝐹𝑞𝑖 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 𝐹γ𝑖
for ϕ΄ = 9.53̊,
𝑁𝑐 = 8.15, 𝑁𝑞 = 2.37 and 𝑁γ = 1.13 thus,
𝐵΄ 𝑁𝑞 1.08 2.37
𝐹𝑐𝑠 = 1 + = 1 + 1.71 8.15 = 1.18
𝐿΄ 𝑁𝑐
𝐵΄ 1.08
𝐹𝑞𝑠 = 1 + ( 𝐿΄ ) tan ϕ΄ = 1+(1.71) tan 9.53 = 1.10
𝐵΄ 1.08
𝐹γ𝑠 = 1 – 0.4 ( 𝐿΄ ) = 1 – 0.4 (1.71) = 0.74
𝐷𝑓
𝐹q𝑑 = 1 + 2 tan ϕ΄ (1 − sinϕ΄ )2 𝐵
1.5
=1 + 2 tan 9.53 (1 − sin9.53)2 1.08 = 1.32
40
No Calculation Reference
19.2𝑥0.5+19.3+20.41+20.41+20.41+20.41𝑥1.5+20.41𝑥1.5+2.41𝑥1.5
γavg =
9
= 23.48 KN/𝑚3
41
No Calculation Reference
1−𝐹q𝑑 1−1.32
𝐹c𝑑 = 𝐹q𝑑 − 𝑁 ΄
= 1.32 - 8.15 tan 9.53 = 1.55
𝑐 tan ϕ
𝐹γ𝑑 = 1
So
1
𝑄𝑢𝑙𝑡 = 𝐴΄ 𝑞 ΄ 𝑢 = 𝐴΄ (𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 )
1
= 1.863 (124.3x8.15x1.18x1.55+35.22x2.37x1.10x1.55+2x
23.48x1.13x0.74x1)
= 3735 KN
𝟑𝟕𝟑𝟓
= 3.735 > 3.0 OK
𝟏𝟎𝟎𝟎
42
Title: Trial 1. Rectangular footing 1.8 m x 3.5 m
No Calculation Reference
19.2𝑥0.5+19.3+20.41+20.41+20.41+20.41𝑥1.5+20.41𝑥1.5+2.41𝑥1.5
γavg = 9
= 23.48 KN/𝑚3
𝑐 ΄ avg =
19.14𝑥0.5+21.88+71.51+101.49+195.98+310.43𝑥1.5+83.51𝑥1.5+85.13𝑥1.5
9
43
No Calculation Reference
= 124.3 KN/𝑚2
22.64𝑥0.5+19.81+11.52+6+4.5+3𝑥1.5+9.24𝑥1.5+9.5𝑥1.5
ϕ avg = 9
= 9.53̊
q = (1.5)(23.48) = 35.22 KN/𝑚2
𝑒𝐿 0.2 𝑒𝐵 0.1
= 3.5 = 0.05 = 1.8 =0.05
𝐿 𝐵
And
𝐿2
≈ 0.29; 𝐿2 = (0.29) (3.5) = 1.01 m
𝐿
1
𝐴΄ = 𝐿2 B + 2 (B + 𝐵2)(L - 𝐿2 )
1
=1.01x0.9 + 2 (1.8+0.9)(3.5 – 1.01)
= 4.27 𝑚2
𝐿΄ = L = 3.5 m
𝐴΄ 4.27
𝐵΄ = = = 1.22 m
𝐿 3.5
1
𝑞 ΄ 𝑢 = 𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 𝐹𝑐𝑖 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 𝐹𝑞𝑖 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 𝐹γ𝑖
for ϕ΄ = 9.53̊,
𝑁𝑐 = 8.14, 𝑁𝑞 = 2.36 and 𝑁γ = 1.13 thus,
𝐵΄ 𝑁𝑞 1.22 2.36
𝐹𝑐𝑠 = 1 + =1+ = 1.10
𝐿΄ 𝑁𝑐 3.5 8.14
𝐵΄ 1.22
𝐹𝑞𝑠 = 1 + ( 𝐿΄ ) tan ϕ΄ = 1+( 3.5 ) tan 9.53 = 1.05
𝐵΄ 1.22
𝐹γ𝑠 = 1 – 0.4 ( 𝐿΄ ) = 1 – 0.4 ( 3.5 ) = 0.86
𝐷𝑓
𝐹q𝑑 = 1 + 2 tan ϕ΄ (1 − sinϕ΄ )2 𝐵
1.5
=1 + 2 tan 9.53 (1 − sin9.53)2 1.22 = 1.32
1−𝐹q𝑑 1−1.32
𝐹c𝑑 = 𝐹q𝑑 − 𝑁 = 1.32 - 8.14 tan 9.53 = 1.55
𝑐 tan ϕ΄
𝐹γ𝑑 = 1
44
No Calculation Reference
So
1
𝑄𝑢𝑙𝑡 = 𝐴΄ 𝑞 ΄ 𝑢 = 𝐴΄ (𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 )
1
= 4.27 (124.3x8.14x1.10x1.55+35.22x2.36x1.05x1.32x1+ 2
x23.48x1.22x1.13x0.86 )
= 7917 KN
𝟕𝟗𝟏𝟕
= 3.95 > 3.0 OK
𝟐𝟎𝟎𝟎
45
Title: Trial 2. Rectangular footing .0 m x 3.5 m
No Calculation Reference
γavg =
19.2𝑥0.5+19.3+20.41+20.41+20.41+20.41𝑥1.5+20.41𝑥1.5+2.41𝑥1.5+20.4𝑥1.5+20.4𝑥4.5
15
= 18.32 KN/𝑚3
46
No Calculation Reference
𝑐 ΄ avg =
19.14𝑥0.5+21.88+71.51+101.49+195.98+310.43𝑥1.5+83.51𝑥1.5+85.13𝑥1.5+86.21𝑥1.5+86.915𝑥4.5
15
2
= 109.29 KN/𝑚
22.64𝑥0.5+19.81+11.52+6+4.5+3𝑥1.5+9.24𝑥1.5+9.5𝑥1.5+8.9𝑥1.5+8.6𝑥4.5
ϕ avg = 15
= 9.187̊
q = (1.5)(18.32) = 27.48 KN/𝑚2
𝑒𝐿 0.2 𝑒𝐵 0.1
= 3.5 = 0.06 = =0.0333
𝐿 𝐵 3
And
𝐿2
≈ 0.7; 𝐿2 = (0.7) (3.5) = 2.45 m
𝐿
1
𝐴΄ = 𝐿2 B + 2 (B + 𝐵2)(L - 𝐿2 )
1
=2.45x3 + 2 (3+0.45)(3.5 – 2.45)
= 9.16 𝑚2
𝐿΄ = L = 3.5 m
𝐴΄ 9.16
𝐵΄ = = = 2.61 m
𝐿 3.5
1
𝑞 ΄ 𝑢 = 𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 𝐹𝑐𝑖 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 𝐹𝑞𝑖 + γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 𝐹γ𝑖
2
for ϕ΄ = 9.187̊,
𝑁𝑐 = 8, 𝑁𝑞 = 2.29 and 𝑁γ = 1.06 thus,
47
No Calculation Reference
𝐵΄ 𝑁𝑞 2.61 2.29
𝐹𝑐𝑠 = 1 + =1+ = 1.21
𝐿΄ 𝑁𝑐 3.5 8
𝐵΄ 2.61
𝐹𝑞𝑠 = 1 + ( 𝐿΄ ) tan ϕ΄ = 1+( 3.5 ) tan 9.187 = 1.12
𝐵΄ 2.61
𝐹γ𝑠 = 1 – 0.4 ( 𝐿΄ ) = 1 – 0.4 ( 3.5 ) = 0.70
𝐷𝑓
𝐹q𝑑 = 1 + 2 tan ϕ΄ (1 − sinϕ΄ )2 𝐵
1.5
=1 + 2 tan 9.187 (1 − sin9.187)2 2.61 = 1.31
1−𝐹q𝑑 1−1.31
𝐹c𝑑 = 𝐹q𝑑 − 𝑁 ΄
= 1.31 - 8 tan 9.187 = 1.54
𝑐 tan ϕ
𝐹γ𝑑 = 1
So
1
𝑄𝑢𝑙𝑡 = 𝐴΄ 𝑞 ΄ 𝑢 = 𝐴΄ (𝑐 ΄ 𝑁𝑐 𝐹𝑐𝑠 𝐹𝑐𝑑 +q 𝑁𝑞 𝐹𝑞𝑠 𝐹𝑞𝑑 + 2 γ 𝑁γ 𝐹γ𝑠 𝐹γ𝑑 )
1
= 9.16 ( 109.2x8x1.21x1.54x1+27.48x2.29x1.120x1.31+ 2
x18.32x1.06x0.70)
= 15819 KN
𝟏𝟓𝟖𝟏𝟗
= 7.90 > 3.0 OK
𝟐𝟎𝟎𝟎
48
Elastic Settlement
Load
Df
Δz
∑ 𝐸𝑠𝑖 Δz
Es =
𝑧
Esi = soil modules
Z = H or 5B whichever is smaller
49
Title: Checking settlement for 1.8 m x 1.8 m
No Calculation Reference
Foundation, H =9m
Width of foundation, B = 1.8 m
Length of foundation, L = 1.8 m
m' = L/B
=1
n' = H/(B/2)
= 10
A =4
A₁ = In(((m'+√(m'²+1))*(√1+n'²))/(m'+(√(m'²+n'²+1)))
= 0.782033338
A₂ = m'/(n'(√(m'²+n'²+1))
= 0.009901475
F₂ = (n'/2P)*(tanh A₂)
= 0.015758173
µs = 0.5
50
No Calculation Reference
Is = F₁+(((1-2µs)/(1-µs)) *F2)
= 0.545132404
If = 0.76
Average Modulus of Elasticity of the soil under the foundation from (extracted
from Table
Z = 0 to Z = 5B ,Es
17.5 in
textbook)
Elasticity
Depth, Δz
Soil Type modulus of soil, Δz*(Esi)
(m)
Es(i)
CL 0.5 900 450
CL 1 1000 1000
CH 1 1800 1800
CH 1 2500 2500
CH 1 4200 4200
CH 1.5 4200 6300
SC 1.5 23600 35400
ML 1.5 29100 43650
TOTAL 9 95300
51
No Calculation Reference
Elastic Settlement Based on Theory of Elasticity (Drained Soil),
Se (mm)
B' = B/2
= 0.9 m
Se(rigid) = 0.93(Se(flexible))
= 30.3224 mm
52
Title: Checking settlement for 1.8 m x 3.5 m
No Calculation Reference
Foundation, H = 9m
Width of foundation, B = 1.8 m
Length of foundation, L = 3.5 m
m' = L/B
= 1.944444444
n' = H/(B/2)
= 10
A =4
Aₒ = m' In(((1+√(m'² +1)) (m'² + n'²))/(m'(1+√(m'²+n'²+1))
= 0.769899155
A₁ = In(((m'+√(m'²+1))*(√1+n'²))/(m'+(√(m'²+n'²+1)))
= 1.226218378
A₂ = m'/(n'(√(m'²+n'²+1))
= 0.018995667
F₁ = (1/P)(Aₒ + A₁)
= 0.635383945
F₂ = (n'/2P)*(tanh A₂)
= 0.030228907
µs = 0.5
Is = F₁+(((1-2µs)/(1-µs))*F2)
= 0.726070667
53
No Calculation Reference
Depth Factor, If (Fox,1948)
If = 0.821 (extracted
from Table
17.5 in
textbook)
Elasticity
Soil Type Depth, Δz (m) modulus of soil, Δz*(Esi)
Es(i)
CL 1 1000 1000
CH 1 1800 1800
CH 1 2500 2500
CH 1 4200 4200
Total 9 95300
54
No Calculation Reference
Elastic Settlement Based on Theory of Elasticity (Drained Soil),
Se (mm)
B' = B/2
= 0.9 m
Se(flexible) = qₒ(aB')*((1-µs²)/Es)*IsIf
= 0.04825 m
= 48.253 mm
Se(rigid) = 0.93(Se(flexible))
= 44.8753 mm
55
Title: Checking settlement for 2.0 m x 2.0 m
No Calculation Reference
Foundation, H = 10 m
Width of foundation, B =2m
Length of foundation, L =2
m' = L/B
=1
n' = H/(B/2)
= 10
a =4
F₁ = (1/P)(Aₒ + A₁)
= 0.497857886
F₂ = (n'/2P)*(tanh A
= 0.015758173
µs = 0.5
Is = F₁+(((1-2µs)/(1-µs))*F2)
= 0.545132404
56
No Calculation Reference
Depth Factor, If (Fox,1948)\
(extracted
If = 0.78 from Table
17.5 in
textbook)
Elasticity
Depth, Δz
Soil Type modulus of soil, Δz*(Esi)
(m)
Es(i)
57
No Calculation Reference
qₒ = net applied pressure on the foundation in KN/m²
= 250 KN/m²
B' = B/2
=1m
Se(flexible) = qₒ(aB')*((1-µs²)/Es)*IsIf
= 0.02666 m
= 26.6641 mm
Se(rigid) = 0.93(Se(flexible))
= 4.7976 mm
58
Title: Checking settlement for 3.0 m x 3.5 m
No Calculation Reference
Foundation , H = 15 m
Width of foundation , B =3m
Length of foundation, L = 3.5 m
m' = L/B
= 1.166666667
n' = H/(B/2)
= 10
a =4
F₁ = (1/P)(Aₒ + A₁)
= 0.531276169
F₂ = (n'/2P)*(tanh A₂)
= 0.018351864
µs = 0.5
Is = F₁+(((1-2µs)/(1-µs))*F2)
= 0.586331761
59
No Calculation Reference
Depth Factor, If (Fox,1948)
(extracted
If = 0.868 from Table
17.5 in
textbook)
Elasticity
Soil Type Depth, Δz (m) modulus of soil, Δz*(Esi)
Es(i)
60
No Calculation Reference
qₒ = net applied pressure on the foundation in KN/m²
= 190.48 KN/m²
B' = B/2
= 1.5 m
Se(flexible) = qₒ(aB')*((1-µs²)/Es)*IsIf
= 0.02704 m
= 27.03396 mm
Se(rigid) = 0.93(Se(flexible))
= 25.1469 mm
61
Angular Distortion
i. First design
1.8*1.8 3*3.5
44.8 − 30.32
= 2.91 × 10−3
5000
1.8*1.8 1.8*3.5
30.32 − 25.15
= 1.034 × 10−3
5000
62
iii. Optimum design
2*2 1.8*3.5
25.15 − 24.79
= 7.5 × 10−5
5000
63
64
6.0 Method Of Statement
65
Foundation is an important part of every building, which interfaces the
superstructures to the adjacent soil or rock below it. The superstructure loads will be
transferred to the underlying soil or rock. Without a proper design and construction of
foundation, problems such as cracking, settlement of building may occur and even to
the extent, the whole building may collapse within its design life. Therefore, a proper
foundation system is required to maintain the safeness of a building.
Shallow foundations are used when the soil formation has adequate strength for
a safe bearing support. However, if the soil has lower shear strength or is highly
compressible, shallow foundations may not be a suitable option. Under such
circumstances, deep foundation may be used. The loads will be transmitted to a greater
depth or to a stiffer stratum or to rock by deep foundation.
However, using piled foundations would increase the bearing capacity but
possibly use more materials and at a higher cost. Since the bearing capacities we
calculated using shallow foundations were adequate, it would be considered a waste
and unjustified increased of risk in construction to use deep foundation.
66
General Requirements of a Building Foundation
i. The foundation, including the underlying soil and rock, must be safe against a
structural failure that could result in collapse. For example, the foundation for a
skyscraper must support the great weight of the building above on a relatively
narrow base without danger of overturning.
ii. The foundation must be feasible, both technically and economically, and
practical to build without adverse effects on surrounding property.
iii. During the life of the building, the foundation must not settle in such a way as
to damage the structure or impair its function.
67
Figure 6.3 : Shows the site investigation
This determines the selection of the optimum foundation system for the
proposed structure. It is important that the engineer planning the site
investigation and designing the foundations liaises closely with the designer of
the superstructure and the project coordinator so that specific requirements and
site constraints are fully understood by the project team. An oversimplified site
investigation is a false economy as it can lead to design changes and delays
during construction and substantial cost overruns. The investigation should
always be regarded as a continuing process that requires regular reappraisals.
The stage will all be interested and may occur in different sequences for
different types of site and project. The overall process may be recursive such as
Desk Study, Site Reconnaissance, Detailed site exploration, Laboratory testing
of sample and Reporting results.
68
Exploration of Construction Site
Purpose: To determine the bulk density of soil that have been placed by
compaction, or of natural soil. After measuring the water content the dry density
can be calculated.
69
Purpose: Determine the in-situ density of natural or compacted soils using sand
pouring cylinders.
Purpose: This test is use during the course of sinking test boreholes as a means of
estimating the relative density and shear strength characteristic.
70
Purpose: Pore water pressure refers to the pressure of groundwater held within a soil
or rock, in gaps between particles (pores). Pore water pressures in below the phreatic
level are measured in piezometers.
Site Clearance
The site should be in a cleared and graded condition. It involves the removal of
trees, demolishing buildings, removing any and all old underground infrastructure, and
any other obstacles that might affect the construction process in the future or hinder the
project to be done.
The site shall be cleared of vegetation, brushwood, stumps of trees etc. Roots
of the trees shall be removed to at least 30 cm below the foundation level. The pits
formed due to roots of trees, old foundations shall be filled up with soil and compacted.
71
Figure 6.9 : Shows a picture of site after clearance
Site Layout
Construction site layout involves layout site identifying, perimeter, sizing, and
placing temporary facilities within the boundaries of construction site. These temporary
facilities range from simple laydown areas to warehouses, fabrication shops,
maintenance shops, batch plant, and residence facilities. Required temporary facilities
and their areas are depending in many factors including project type, scale, design,
location, and organization of construction work.
72
Figure 6.10 : Shows a layout plan of construction site
Excavation
For small buildings, excavation is carried out manually by means of pick axes,
crow bars and spades. In case of large buildings and deep excavation, mechanical earth
cutting equipment can be used. Meanwhile, for hard soils when the depth of excavation
is less than 1.5 m, the sides of the trench do not need any external support. If the soil is
loose or the excavation is deeper, some sort of shoring is required to support the sides
from falling. Planking and strutting can be intermittent or continuous depending on the
nature of soil and the depth of excavation.
73
In general, foundations shall be excavated to the levels and dimensions as shown
on the drawings, with sides trimmed and bottoms levelled and stepped as required. All
excavation shall be carried down to required level. On no account shall shallow
foundations rest on made up or filled ground. Unless otherwise shown on the Drawings,
the depths of foundation shall be decided on the site. A good over excavation below the
required depth with suitable granular material or concrete should executed.
74
Lean Concrete
Lay a layer of lean concrete to prepare a clean and firm for base footing.
Footing
i. Construct Formwork
75
Figure 6.13 : Shows the constructed formwork
Spacer blocks are placed before reinforcement been laid. This is to provide
sufficient concrete cover for rebar. Rebar’s were bent and tied before the whole thing
been lowered and placed inside the formwork. Ensure the steel is place properly on
spacer blocks. Avoid touching the lean concrete below. After completed, then concrete
will poured into it followed with the compaction process.
76
Set up Stump Reinforcement
Stump reinforcement are then erected. The length of rebar should be extended
beyond the stump level and act as the starter bars for column. Provide the addition ties
to formwork. If it were necessary.
Curing of Concrete
Concrete will set and curing shall be performed to avoid excessive lost water
during hardening. When the concrete has gained sufficient length, then formwork can
be dismantled.
77
Figure 6.16 : Shows the curing of concrete
i. Site Investigation
ii. Site Clearance
iii. Site Layout
iv. Excavation
v. Lean Concrete
vi. Footing
a. Construct Formwork
b. Installed Reinforcement Rebar and Pour Concrete.
v. Set Up Stump Reinforcement
vi. Curing of Concrete
78
7.0 Costing
79
Project Supervisor
Person/
4 - supervising the progress of the work according to 1 100 7 700.00
Day
the proposed design.
TOTAL 4100.00
80
Rate/Day Days of Amount RM/day
No. Description Quantity Unit
(RM) Usage (RM)
Excavator
1 - to excavate the soil for earthwork 2 Nos 1200 3 7200.00
purpose.
Plant and Machinery
Cost Lorry 3 tonnes
2 - transporting the excavated soil. 3 Nos 500 3 4500.00
Crane
3 - to assist in the concreting of the 1 Nos 750 4 3000.00
foundation.
TOTAL 14700.00
81
No Description Quantity Unit PerRate (RM) Amount (RM)
Material Cost
Plywood
2 60 piece 35 2100.00
- for the construction of the formwork.
Vibrator
3 2 Nos 300 600.00
- vibrate the concrete.
TOTAL 2943.00
82
COST ESTIMATION FOR DESIGN
Type : Shallow foundation (Rectangular)
Length : 3.5 m
Width : 3.0 m Thickness : 0.5m
Total Cost : RM 22,812.50
83
Rate/Day Days of Amount RM/day
No. Description Quantity Unit
(RM) Usage (RM)
Excavator
1 - to excavate the soil for earthwork 2 Nos 1200 3 7200.00
Crane
3 - to assist in the concreting of the 1 Nos 750 4 3000.00
foundation.
TOTAL 14,700.00
84
No Description Quantity Unit PerRate (RM) Amount (RM)
Ready Mix Concrete Grade 30
1 5.25 m³ 250 1312.50
- premixed from the batching plant according to the gred required.
Material Cost Plywood
2 60 piece 35 2100.00
- for the construction of the formwork.
Vibrator
3 2 Nos 300 600.00
- vibrate the concrete.
TOTAL 4,012.50
85
COST ESTIMATION FOR DESIGN
Type : Shallow foundation (Rectangular)
Length : 3.5 m
Width : 1.8 m Thickness : 0.3m
Total Cost : RM 21,972.50
86
Rate/Day Days of Amount RM/day
No. Description Quantity Unit
(RM) Usage (RM)
Excavator
1 - to excavate the soil for earthwork 2 Nos 1200 3 7200.00
Plant and Machinery purpose.
Cost Lorry 3 tonnes
2 3 Nos 500 3 4500.00
- transporting the excavated soil.
Crane
3 - to assist in the concreting of the 1 Nos 750 4 3000.00
foundation.
TOTAL 14,700.00
87
No Description Quantity Unit PerRate (RM) Amount (RM)
Ready Mix Concrete Grade 30
1 - premixed from the batching plant according to the gred required. 1.89 m³ 250 472.50
Material Cost
Plywood
2 60 piece 35 2100.00
- for the construction of the formwork.
Vibrator
3 2 Nos 300 600.00
- vibrate the concrete.
TOTAL 3,172.50
88
8.0 Ranking Matrix
89
9.0 Construction Drawing
90
91
92
10.0 Additional Information
General
The allowable capacity of the soil/rock under working loads where any
foundation is founded shall be the lesser of :
93
Rational Design Method
Rational design method for calculating the ultimate capacity should be based on
sound engineering approach and should include :
In choosing the method for the determination of the ultimate capacity or for the
estimation of settlement, care must be taken to ensure that the site investigation, testing,
derivation of parameters, computations, method of construction and standards of
acceptance are mutually compatible and consistent with such method.
94
Corrosion Protection Of Foundations
10.4.1 General
95
Ground Investigation
10.5.1 General
Ground investigation works involve the field works carried out to obtain
information on the ground conditions, such as exploratory drilling, excavation
and probing of land, installation of instruments, sampling and field testing, and
the laboratory works for the testing of samples obtained from such operations.
All ground investigation field works, except field density tests, should
be carried out by a Registered Specialist Contractor (Ground Investigation Field
Works), whereas all laboratory testing of samples and field density tests should
be carried out by laboratories accredited. Sufficient ground investigation works
should be carried out to ensure that adequate information on the subsurface
conditions within and nearby the site can be obtained prior to the design of the
foundation.
Proper supervision should be provided for the carrying out of all ground
investigation works. To ensure quality of the works, supervision for the
different stages of pre-design ground investigation field works should comply
with the requirements set out in the relevant PNAP or code of practice issued
by the Buildings Department.
Boreholes and trial pits should be carried out to sufficient depth such
that all strata that are likely to be affected by the foundation loads will be
adequately explored. The depth of ground investigation will depend on the type
of the structure, the size, shape and disposition of the loaded areas and the nature
of the strata. following should be considered :
96
In general, the
a) Care should be taken to ensure that boulders are not mistaken for
bedrock, particularly on sites where borings are made through highly
weathered rock. Where bedrock is encountered, it should be proved by
coring to a minimum depth of 5 m.
b) Where compressible cohesive soils are likely to contribute significantly
to the settlement of the foundations, the investigation should reach such
depth where stress increase would cause insignificant strain or
displacement.
c) For the design of a pile foundation or for the settlement analysis of the
foundation, the exploration should be deep enough to cover the
characteristics of the underlying strata.
d) For spread footings, the investigation depth should be :
i. 5m into rock; or
ii. A depth that can be readily demonstrated that the induced strain
and displacement are negligible.
Shallow Foundations
97
10.6.2 How To Use Vislog
First of all, new borehole data needs to fill in by clicking on "Add new
borehole" icon on the toolbar; a new empty row will be added to the end of the
boreholes and soil layers table.
Secondly, the Field Test table on the right hand-side of the page will be
empty as well. After that, we entered borehole data in the new row and then
entered our soil layers and field test data on corresponding tables.
98
Once our soil profile is defined, it is updated in the viewer. Each soil
layer along the profile showed with corresponding texture image. Similar soil
layers in adjacent boreholes will be automatically connected together.
NouvoSPT Software
A lot of correlation can be used by various reference to finding the all shear
parameter including bearing capacity etc. this software very helpful in oder to find the
good foundation design.
99
Black Cotton Soil
Black cotton soil has a tendency to shrink and swell excessively. When these
type of soil come in contact with water, they swell and when becomes dry, it shrinks.
This alternate process of swelling and shrinking results in the differential
settlement of foundation which in turn causes cracks in building. The cracks thus
formed are sometimes 15 to 20 cm wide and 2.5 to 4.5 m deep.
100
ix. For less important structures (such as boundary wall construction), the
foundation should preferably taken at least 15 cm below the depth at which
cracks in soil cease to occur.
x. Construction should be done in dry season.
xi. For main walls or for load bearing walls, the width of the trench should be dug
40 cm wider than width of foundation. Then fill the space on either side of the
trench (i.e. 20 cm in each side) with coarse sand. This is done to separate the
foundation masonry from direct contact with black cotton soil. In case of
compound wall this width of sand filling can be reduced to 15 cm on each side.
xii. Under reamed pile foundation is also a good choice of foundation in black
cotton soil.
101