J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-
KERJA BERKAITAN.

MONTHLY AHEAD PLANNING (FROM 1st APRIL 2018 - 30th APRIL 2018)

NO LOCATION Description of Work for Monthly Ahead Plan Duration Date Start Date Finish
(From 1st April 2018 - 30th April 2018) (Days)
A CIVIL WORKS - WWCT & SBT TASK DESCRIPTIONS Start 8AM Finish 7PM
A1 1st Lift (1.5m & 2.4) - WALL '2' Continue curing works 2 01/04/2018 02/04/2018
*Refer 'Attachment B' in the email Dismantle formwork & scaffold 1 03/04/2018 03/04/2018
A2 2nd Lift (2.1m) - WALL '1' Continue installation of scaffold & stagging 2 01/04/2018 02/04/2018
*Refer 'Attachment C' in the email Continue installation of foamties 2 01/04/2018 02/04/2018
Continue installation of formwork 2 01/04/2018 02/04/2018
Installation 200mm & 300mm pipe flange 2 01/04/2018 02/04/2018
Inspection 1 02/04/2018 02/04/2018
Concreting works 1 03/04/2018 03/04/2018
Curing works 3 04/04/2018 06/04/2018
Dismantle formwork & scaffold 1 07/04/2018 07/04/2018
A3 2nd Lift (2.1, 1.45 & 2.15m) - WALL '2' Installation of scaffold & stagging 3 04/04/2018 06/04/2018
*Refer 'Attachment C' in the email Installation of reinforcement bar (Y12 & Y16) 4 04/04/2018 07/04/2018
Installation of additional reinforcement bar at the top of wall 1 07/04/2018 07/04/2018
Inspection 1 08/04/2018 08/04/2018
Concreting works 1 09/04/2018 09/04/2018
Curing works 3 10/04/2018 12/04/2018
Dismantle formwork & scaffold 1 13/04/2018 13/04/2018
A4 Cantilever Beam & Top Slab Installation of scaffold & stagging 1 04/04/2018 04/04/2018
*Refer 'Attachment D' in the email Installation of reinforcement bar (Y12 & Y16) 4 05/04/2018 08/04/2018
Installation of additional reinforcement bar at the top of wall 1 09/04/2018 09/04/2018
Erect & install formwork, t-props & soffit 1 10/04/2018 10/04/2018
Inspection 1 11/04/2018 11/04/2018
Concreting works 1 12/04/2018 12/04/2018
Curing works 3 13/04/2018 15/04/2018
Dismantle formwork, t-props, soffit & scaffold 1 16/04/2018 16/04/2018
A5 Wall for Overflow Slab (Wall A & C) Installation of scaffold & stagging 1 13/04/2018 13/04/2018
Installation of reinforcement bar (Y12 & Y16) 3 14/04/2018 16/04/2018
Erect & install formwork, t-props & soffit 1 17/04/2018 17/04/2018
Inspection 1 18/04/2018 18/04/2018
Concreting works 1 19/04/2018 19/04/2018
Curing works 3 20/04/2018 22/04/2018
Dismantle formwork, t-props, soffit & scaffold 1 23/04/2018 23/04/2018
A6 External Finishes To procure & fabricate cat ladder & handrail 3 20/04/2018 22/04/2018
To deliver cat ladder & handrail at site 3 23/04/2018 25/04/2018
To intsall cat ladder & handrail 1 26/04/2018 26/04/2018
A7 Internal Finishes To do painting of internal wall of WWCT & SBT 1 26/04/2018 26/04/2018
A8 Cold Joints & Honeycomb Setting up works 1 15/04/2018 15/04/2018
Waterproof (Specialits Team) To repair cold joints & honeycomb 4 16/04/2018 19/04/2018
To install waterproofing for internal wall of WWCT & SBT 2 20/04/2018 21/04/2018
A9 Backfilling Works at RHS-WWCT & SBT To do 1st backfilling works (400mm per layer) 2 20/04/2018 21/04/2018
(1st & 2nd) To reinstate existing sump & pipes 4 22/04/2018 25/04/2018
To do 2nd backfilling works (400mm per layer) 2 26/04/2018 27/04/2018
A10 Dewatering Container To carry out levelling works 1 26/04/2018 26/04/2018
(GEOTUBE) To do excavation works 2 27/04/2018 28/04/2018
B PIPEWORKS TASK DESCRIPTIONS Start 8AM Finish 7PM
B1 Installation Works Excavation & backfilling works 7 15/04/2018 21/04/2018
Pipe laying & jointing 7 22/04/2018 28/04/2018
C MECHANICAL WORKS TASK DESCRIPTIONS Start 8AM Finish 7PM
C1 WWCT & SBT
Procurement & Delivery Horizontal Screw Pump 28 01/04/2018 28/04/2018
Pipes, Fittings & Valves 28 01/04/2018 28/04/2018
C2 EXISTING SEDIMENTATION TANK
Procurement & Delivery Submersible Sludge Pump 28 01/04/2018 28/04/2018
Pipes, Fittings & Valves 28 01/04/2018 28/04/2018
C3 POLYMER PLANT
Procurement & Delivery Metering Pumps (Diaphragm type) 28 01/04/2018 28/04/2018
Static Mixer & Sludge Blender 28 01/04/2018 28/04/2018
C4 PIPEWORKS
Procurement & Delivery 150mm ND PE Both End Welded Flange 5m Length 28 01/04/2018 28/04/2018
150mm x 65mm Taper Both End Welded Flange 28 01/04/2018 28/04/2018
200mm ND Mild Steel Pipe PE Both End Welded Flange 28 01/04/2018 28/04/2018
Bends, Tees, Reducer and Mechanical Coupling C/W Bolts & Nuts 28 01/04/2018 28/04/2018
C5 MISCELLANEOUS WORKS
Procurement & Delivery Booster Pump 28 02/04/2018 29/04/2018
Air Compressor Set 28 02/04/2018 29/04/2018
Submersible Pump (Portable & Gasoline Engine) 28 02/04/2018 29/04/2018
Portable Water Jet 28 02/04/2018 29/04/2018
Penstock & Valves 28 02/04/2018 29/04/2018
D ELECTRICAL WORKS TASK DESCRIPTIONS Start 8AM Finish 7PM
D1 SWITCHBOARD / MCC PANEL
Procurement & Fabrication To procure & fabricate Panel 30 01/04/2018 30/04/2018
D2 SUBMAIN CABLING MCC-SDP-PALONG
Procurement & Delivery To procure & deliver Cable 30 01/04/2018 30/04/2018
D3 DISTRIBUTION & EARTHING SYSTEM
Procurement & Delivery To procure & deliver Distribution Board & Earthing System 30 01/04/2018 30/04/2018
D4 COMPOUND LIGHTING SYSTEM
Procurement & Delivery To procure & deliver Compound Lighting System 30 01/04/2018 30/04/2018
E INSTRUMENTATION WORKS TASK DESCRIPTIONS Start 8AM Finish 7PM
E1 IP54 INSTRUMENT PANEL & OTHERS
Procurement & Fabrication To procure & fabricate Instrument Panel 30 01/04/2018 30/04/2018

By completing all above tasks at the End of April 2018, overall progress is 95.76% vs 54.76% (30/04/2018)