2) Daily Physical Progress For Main Item As In Work Breakdown Structure (WBS)
Weightage
Item Main Activities/Tasks Completion Date Period ending 30/3/2018 Period ending 31/3/2018
%
1 W. Water Collection Tank & SBT 4/5/2018 14.91 96.00% 49.00% -47% 96.00% 49.00%
6 Electrical Switchboard & Panel 5/12/2018 14.42 48.00% 41.00% -7.0% 49.0% 41.00%
NOTE: THIS TABLE COULD ALSO BE USED FOR MANPOWER RECORD AT SITE
3) Summary of Daily Physical Progress For Delay Activities And Variance >-10% OR Total Float > -15 days
Weightage
Item Activities/Tasks Completion Date Period ending 13/11/2013 Period ending 14/11/2013
%
LEGEND:
Improved activities
ITEM RECOMMENDATION /
SITE ISSUES ACTION TAKEN TO DATE
SOLUTION
CURRENT ISSUES
Stop work order from Department of Occupational Safety & Health (DOSH) due to poor Improve safety issue recommend Issue is closed on 27.03.2018
housekeeping & excavation works. by DOSH representative. (En
1 Wahab)
PAST ISSUES
6
Period ending (Yesterday)
ending 31/3/2018 REMARKS
01/04/2018
Ahead / Ahead /
Sch. (%) Act. (%)
Delay (%) Delay (%)
Ahead / Ahead /
Sch. (%) Act. (%)
Delay (%) Delay (%)
TAKEN TO DATE
ed on 27.03.2018
SUMMARY OF DAILY PROGRESS REPORT AS AT 1-Apr-18
1) Summary of Manpower
DATE
13-Nov-13 14-Nov-13 15-Nov-13
PREVIOUS 2 PREVIOUS
NO. # DESCRIPTION YESTERDAY
DAYS DAY
1 Site Management / Supervisory Staf
2 C&S Workers
3 M&E Workers
4 Machinery Operator
5 Site Management / Supervisory Staf
TOTAL (NOS)
NOTE: # TO BE PROPOSED BY CONSULTANT
TOTAL (NOS)
NOTE: # TO BE PROPOSED BY CONSULTANT
REMARKS
REMARKS
SUMMARY OF DAILY PROGRESS REPORT AS AT
PROJECT CODE : N0….
PACKAGE: ….
CONTRACTOR:
ENG. CONSULTANT :
QS CONSULTANT:
GREEN
AMBER
Variance ≥ -20%
RED
Total Critical Path Activities 0 0 0
GREEN
AMBER
Variance ≥ -20%
RED
Total Critical Path Activities 0 0 0
ACTION BY / REMARKS
ACTION BY / REMARKS
28-Mar-18
PREVIOUS 2
DESCRIPTION DAYS
Schedule (%)
Actual (%)
Ahead / Delay (% / Day)
2) Daily Physical Progress For Main Item As In Work Breakdown Structure (WBS)
OVERALL PROGRESS
3) Summary of Daily Physical Progress For Delay Activities And Variance >-10% OR Total Float > -15 days
Item Main Activities/Tasks Completion Date
Total in Completed
Contract todate
MIP
OVERALL PROGRESS
CURRENT ISSUES
PAST ISSUES
6
DATE
29-Mar-18 30-Mar-18
PREVIOUS YESTERDAY REMARKS
DAY
Weightage
Completion Date Period ending 28/03/2018 Period ending 29/03/2018
%
Adjusted
Ahead / Ahead /
Date Sch. (%) Act. (%) Sch. (%) Act. (%)
Delay (%) Delay (%)
(Recovery)
0.00
Adjusted
Ahead / Ahead /
Date Sch. (%) Act. (%) Sch. (%) Act. (%)
Delay (%) Delay (%)
(Recovery)
0% 0%
0% 0%
0% 0%
0% 0%
0.0% 0.0%
0% 0%
0.00% 0.00%
CURRENT ISSUES
PAST ISSUES
Period ending (Yesterday)
REMARKS
30/03/2018
Ahead /
Sch. (%) Act. (%)
Delay (%)
Period ending (Yesterday)
REMARKS
15/11/2013
Ahead /
Sch. (%) Act. (%)
Delay (%)
0.0%
0.0%
0.0%
0.0%
0.00%
0.0%
0.00%