You are on page 1of 5

M.O.R.T. & H.

- BITUMINOUS CONSTRUCTION

Sr. No. Unit Rate for 2008-2009


& Item DESCRIPTION OF ITEMS ( In Rs.)
Code Completed Labour

1 Prime coat
(Providing and applying primer coat with bitumen emulsion Sq.M. 24.00 0.10
on prepared surface of granular Base including clearing
of road surface and spraying, primer at the rate of 0.60
kg/sqm using mechanical means.)
Spec. No. M.O.R.T. & H - 502

2 Providing and applying tack coat on the prepared surface


heating by fames in roller and spraying bitumen with spray
set footed in bitumen boller on B.T. surface
Spec. No. : M.O.R.T. & H.- 503

1) 60/70 Bulk
a) 3 Kg/10 Sq.M. Sq.M. 14-00 --
b) 5 Kg/10 Sq.M. Sq.M. 23-00 --

2) 80/100 Bulk
a) 3 Kg/10 Sq.M. Sq.M. 13-60 --
b) 5 Kg/10 Sq.M. Sq.M. 21-00 --

3 Bituminous Macadam
(Providing and laying bituminous macadam with 40-80 TPH .
hot mix plant producing an average output of 35 tonnes
per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid
over a previously prepared surface with paver finished to
the required grade, level and alignment and rolled as per
clause 501.6 and 501.7 to achieve the desired compaction.)
Spec. No. M.O.R.T. & H - 504

50 / 75 mm compacted thickness with 3.3 % Bitumen


for Grading (40 mm nominal size)

i) 60/70 Grade 3,980.00 17.90


ii) 30/40 Grade 4,180.00 17.90

165
Sr. No. Unit Rate for 2008-2009
& Item DESCRIPTION OF ITEMS ( In Rs.)
Code Completed Labour

4 Built-Up-Spray Grout
(Providing, laying and rolling of built-up-spray grout layer
over prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates, key stone chips spreader
may be used with application of bituminous binder after
each layer and with key aggregates placed on top of the
second layer to serve as a Base conforming to the line,
grades and cross-section specified the compacted layer
thickness being 75 mm) excluding cost of prime / tack
coat.
Spec. No. MORT & H - 506

i) using 60 / 70 bulk Sq.M. 173.00 0.60

ii) using 30 / 40 bulk Sq.M. 181.00 0.60

5 Dense Graded Bituminous Macadam


(Providing and laying 40 mm thick dense bituminous
macadam with 40 - 60 TPH batch type HMP producing an
average output of 35 tonnes per hour using crushed
aggregates of specified grading, premixed with bituninous
binder @ 4.25 % by weight of totak mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic
paver finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheelad, vibratory
and tandem rollers to achieve the desired compaction as
per MORTH specification clause No. 507 excluding cost
of prime / tack coat.
Spec. No. MORT & H - 507

i) 60 / 70 Bulk with stone dust filler Cu.M. 5,380.00 18.90

ii) 30 / 40 Bulk with stone dust filler Cu.M. 5,640.00 18.90

166
Sr. No. Unit Rate for 2008-2009
& Item DESCRIPTION OF ITEMS ( In Rs.)
Code Completed Labour

6 Semi - Dense Bituminous Concrete


(Providing and laying 25 mm thick semi dense bituminous
concrete with 40-60 TPH batch type HMP producing an
average output of 35 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous
binder @ 4.5 mix and filler, transporting the hot mix to
work site with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling
with smooth wheeled, vibratory and tandem rollers to achieve
the desired compaction as per MORTH specification clause
No. 508 complete in all respects.) excluding primer / tack
coat.
Spec. No. M.O.R.T. & H. - 508

With ordinary roller

i) 60 / 70 Bulk with stone dust filler Cu.M. 5,630.00 18.85

ii) 30 / 40 Bulk with stone dust filler Cu.M. 5,905.00 18.85

7 Bituminous Concrete
(Providing and laying 40 mm thick bituminous concrete
with 40-60 TPH batch type hot mix plant producing an
average output of 35 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous
binder @ 5 % of mix and cement filler, transporting the
hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers
to achieve the desired compaction as per MORTH
specification clause No. 509 complete in all respects.)
Spec. No. M.O.R.T. & H. - 509

i) 60 / 70 Bulk with cement filler Cu.M. 6,530.00 19.20

ii) 30 / 40 Bulk with cement filler Cu.M. 6,840.00 19.20

167
Sr. No. Unit Rate for 2008-2009
& Item DESCRIPTION OF ITEMS ( In Rs.)
Code Completed Labour

8 Open Graded Premix Surfacing


(Providing, laying and rolling of open graded premix surfacing
of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade bitumen or cut-
back or emulsion to required line, grade and level to serve
as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a smooth
wheeled roller 8-10 tonne capacity finished to required
level and grades on B.T. Surface excluding coat of primer
/ tack coat.
Spec. No. M.O.R.T. & H.- 511

a) using 60 / 70 grade bulk asphalt. Sq.M. 86.00 0.35

b) using 30 / 40 grade bulk asphalt. Sq.M. 90.00 0.35

9 Providing & laying open graded premix carpet of 25 mm


thick with specified graded crushed aggregates for wearing
course including loading of aggregates with F.E. loader,
heating bindeer & aggregates in hot mix plant 30 / 40
tonnes transporting the mixed material with tipper & laying
with paver finisher to the required level & grade, rolling
with power roller 8 - 10 tonnes excluding cost of tack coat
Spec. No. M.O.R.T. & H.- 511

i) 60 / 70 grade bitumen with 80/100 tack coat Sq.M. 107.00 0.35

ii) 30 / 40 grade bitumen with 80/100 tack coat Sq.M. 112.00 0.35

168
Sr. No. Unit Rate for 2008-2009
& Item DESCRIPTION OF ITEMS ( In Rs.)
Code Completed Labour

10 Seal Coat
(Providing and laying seal coat seeling the voids in a
bituminous surface laid to the specified level and cross
fall using Type A and B seal coats)
Spec. No. M.O.R.T. & H. - 513
a) Type A i) Using 60 / 70 bulk Sq.M. 48.00 0.10

ii) Using 80 / 100 bulk Sq.M. 46.00 0.10

b) Type B (Providing and laying of premix send seal


coat with HMP of appropriate capacity not less than 75
tonnes / hours using crushed stone chipping 6.7 mm size
and penetration bitumen of suitable grade.)
i) Using 60 / 70 bulk Sq.M. 34.00 0.10

ii) Using 80 / 100 bulk Sq.M. 33.00 0.10

11 Providing and applying thermo plastic reflective Sq.M. 660.00 --


paint of any colour or compound for trafic lane strips
100 mm wide and 3 mm. thick of Pigment 10% on clean
dry and good road surface with 10% glass beads, 20%
binder, 10% extender and 60% of filler material as per
M.O.S.T. Specification No. 803.4
Spec. No. : M.O.S.T. & H 513

12 Providing and painting centre line/dashes arrows etc.


in two coats on new/old work with ready mix road marking
paints confirming to I.S. 164 on Bituminous surface including
cleaning the surface demarking of site and traffic controlled
involved (10 cm wide)
Spec. No. M.O.R.T. & H. - 803
i) New surface Rmt 6.50 2.95

ii) Old surface Rmt 5.25 2.95

13 Providing and applying zebra painting of pedestrain


on the carriage way with approved road marking paint in
two coats etc. (10 cm wide)
i) New surface Sqm 75.00 35.85

ii) Old surface Sqm 50.00 26.30

169