Engineering Balance work for East Bound Tube

HANDOVER BY TAKE OVER BY REMARKS


S.NO DESCRIPTION OF WORK STATUS ACTION BY
NAME SIGNATURE NAME SIGNATURE
1 Tunnel lighting layout As build completed Completed saravanan Jack
2 Single Line Drawing Completed Submitted to SEWA saravanan Jack
3 Load schudule Completed Submitted to SEWA saravanan Jack
4 Load list Recived From Woobung Submitted to SEWA saravanan Jack
5 Disel Generator Layout To be re-submission Jeffery saravanan Jack
6 External-Duct Bank layout Submitted to ch2m Jeffery or woobung saravanan Jack
7 Tunnel-Under ground Duct bank Recived From Woobung Jeffery or woobung saravanan Jack After Jack review to be submitt
8 Tunnel Earthing drawing To be Resubmission Jeffery or woobung saravanan Jack
9 Tunnel & cross pages Interface drawing To be re-submission Jeffery or woobung saravanan Jack
10 1 to 6 Cross passage Interface drawings To be re-submission Jeffery or woobung saravanan Jack

11 Escape lighting drawing issue to be site To be re-submission Jeffery or woobung saravanan Jack

12 Portal Building cable Tray Drawing To be re-submission Jeffery or woobung saravanan Jack To be revise latest Arch Dwg
13 Portal Building Lighting ,Emergency Lighting, To be submitted Completed saravanan Jack To be revise latest Arch Dwg
14 Portal Building Power layout To be submitted Completed saravanan Jack To be revise latest Arch Dwg
15 Portal Building corrdination drawing To be submitt Jeffery or woobung saravanan Jack To be revise latest Arch Dwg
16 Portal Bulding Lighining Protection & Earthing To be Re-submission Jeffery or woobung saravanan Jack

17 Fire Pump Room all Drawing To be re-submission Jeffery or woobung saravanan Jack

18 Lux level Calculation EPB,FR Room, Cross passage To be submission Michael, Ifthikahar saravanan Jack

19 Transformer Installation SEWA SEWA to be Installed


20 Disel Generator Equipment contractor Wafa to be Installed
21 UPS contractor Wafa to be Installed
22 MDB,SMDB,DBs Installation contractor Wafa to be Installed
23 cable tray Installation EPB,FR Room contractor Wafa to be Installed
24 cable Laying EPB,FR room,Tunnel, contractor Wafa to be Installed
25 Lighting,Wiring and Accessiories Installation contractor Wafa to be Installed
26 Earthing Installation EPB, FR room vendor vendor
27 cable End Termination contractor Wafa to be Installed
28 Lightining Protection Portal Bulding contractor Wafa to be Installed

Material Requirement
26 Cable ladder and Cable Tray for portal Building After Drawing Completion to be recive from Woobung saravanan Jack

27 Cable Cleat After Drawing Completion to be recive from Woobung saravanan Jack

28 Cable support, Portal Building, & Accessiories Detail drawing After Drawing Completion After Drawing Completion saravanan Jack

29 Lugs For cable termination Lug bolt size finalize By vendor After panel drawing final saravanan Jack

30 Normal Lighting CP,EPB,FR ROOM MR Qty given to Purchase Michael saravanan Jack
31 Emergency Lighting Qty given to Purchase,CP,EPB,FR ROOM MR Qty given to Purchase Michael saravanan Jack

32 Wire for 2cx2.5sqmm/FR Emergency lighting,CP,EPB,FR ROOM MR Qty given to Purchase Michael saravanan Jack

36 Gland Qty given to Purchase MR Qty given to Purchase Michael saravanan Jack

37 "C" chennel & Accessiories for CP. EPB,FR ROOM qty after dwg After Drawing Completion Required Drawing saravanan Jack

38 3R-1C 2.5SQMM for lighting wiring for CP.EPB,FR ROOM to be recive from Woobung to be recive from Woobung saravanan Jack

39 3R-1C 4.0SQMM for Power wiring for CP.EPB,FR ROOM to be recive from Woobung to be recive from Woobung saravanan Jack

40 2CX2.5SQMM Emergency Lighting cable CP,EPB,FR ROOM to be recive from Woobung to be recive from Woobung saravanan Jack

41 Tunnel Jet Fan Conduit Qty Take off GRP BALACK completed Jack Review saravanan Jack

42 Cross passage to Tunnel Crossing conduit GRP BLACK Service Boq completed Jack Review saravanan Jack