You are on page 1of 14

ID WBS Name Duration

Project ALPHA House


1.0 Project Management
1 1.1 Contracts 1.00d
2 1.1.1 Supply Lot Sale Agreement 2.00d
3 1.1.2 Supply Construction Agreement 2.00d
4 1.1.3 Supply Contract Plans 2.00d
5 1.1.4 Supply Contract Specifications 2.00d
6 1.1.5 Supply Contract Site Plan 2.00d
7 1.1.6 Secure Financing 2.00d
8 1.1.7 Construction Loan Settlement 2.00d
9 1.2 Document Review & Revision 25.00d
10 1.2.1 Review & Finalize Plans 15.00d
11 1.2.2 Review & Finalize Specifications 21.00d
12 1.2.3 Review & Finalize Site Plan 1.00d
13 1.2.4 Print Construction Drawings 5.00d
14 1.2.5 Approve Revised Plans 1.00d
15 1.2.6 Approve Revised Specifications 1.00d
16 1.2.7 Approve Revised Site Plan 1.00d
17 1.3 Bids & Contracts 24.00d
18 1.3.1 Make Copies of Plans 3.00d
19 1.3.2 Make Copies of Specifications 2.00d
20 1.3.3 Distribute Plans & Specifications 1.00d
21 1.3.4 Receive Bids 11.00d
22 1.3.5 Review Bids 5.00d
25 1.3.6 Execute Subcontractor Agreements 5.00d
1.40 Project Planning (Create Plan)
1.4.1 Scope Management Plan 1.00d
1.4.2 Schedule Management Plan 1.00d
1.4.3 Cost Management Plan 1.00d
1.4.4 Quality Management Plan 1.00d
1.4.5 Risk Management Plan 1.00d
1.4.6 Human Resource Plan 1.00d
1.4.7 Risk Management Plan 1.00d
1.4.8 Communications Management Plan 1.00d
1.4.9 Stakeholder Management Plan 1.00d
1.4.10 Integrate the Plans 1.00d
1.4.11 Project Kickoff Meeting 1.00d
1.50 Other PM Activities and Budget 0
2.00 Mobilization
2.1 Temporary Facilities
2.2 Construction Equipment Ingress
26 3.00 Grading & Building Permits 17.00d
27 3.1 Schedule lot stakeout 1.00d
28 3.2 Stake lot 1.00d
29 3.3 File Grading Permit Application 1.00d
30 3.4 File Building Permit Application 3.00d
31 3.5 Post Lot Identification 1.00d
32 3.6 Meet Sed. Control Insp. 1.00d
33 3.7 Walk Lot w/ Owner 1.00d
34 3.8 Install Construction Entrance 1.00d
35 3.9 Install Sediment Controls 2.00d
36 3.10 Sediment Control Insp. 1.00d
37 3.11 Grading Permit Issued 1.00d
38 3.12 City Permit Process 11.00d
39 3.13 Building Permit Approved 1.00d
40 3.14 Pay Permit Fees and Excise Taxes 1.00d
41 3.15 Building Permit Issued 1.00d
42 4.00 Site Work 7.00d
43 4.1 Clear Lot 3.00d
44 4.2 Strip Topsoil & Stockpile 1.00d
45 4.3 Stake Lot for Excavation 1.00d
46 4.4 Rough grade lot 1.00d
47 4.5 Excavate for foundation 2.00d
Stakeholder Meeting 1.00d
48 5.00 Foundation 24.00d
49 5.1 Layout footings 1.00d
50 5.2 Dig Footings & Install Reinforcing 1.00d
51 5.3 Footing Inspection 1.00d
52 5.4 Pour footings 1.00d
53 5.5 Pin Footings 1.00d
54 5.6 Stock Block, Mortar, Sand 1.00d
55 5.7 Build Block Foundation 15.00d
56 5.8 Foundation Certification 1.00d
57 5.9 Draw #1 (Location Survey) 1.00d
58 5.10 Fill Block Cores w/ Concrete 1.00d
59 5.11 Steel Delivery 1.00d
60 5.12 Set Lintels, Bolts, Cap Block 2.00d
61 5.13 Lumber Delivery 1.00d
62 5.14 Waterproofing and Drain Tile 1.00d
5.15 Stakeholder Meeting 1.00d
63 6.00 Rough Carpentry 44.00d
64 6.1 Set Steel 1.00d
65 6.2 1st Floor Deck Framing 4.00d
66 6.3 1st Floor Wall Framing 4.00d
67 6.4 Draw #2 (First Floor Deck) 1.00d
68 6.5 2nd Floor Deck Framing 2.00d
69 6.6 Draw #3 (Second Floor Deck) 1.00d
70 6.7 2nd Floor Wall Framing 3.00d
71 6.8 Set Roof Trusses 2.00d
72 6.9 Frame Roof 7.00d
73 6.10 Install Roof Plywood 5.00d
74 6.11 Install Windows & Doors 2.00d
75 6.12 Frame Basement 3.00d
76 6.13 Frame Basement Bulkheads 2.00d
6.14 Stakeholder Meeting and Communications 1.00d
77 7.00 Concrete Slabs 8.00d
78 7.1 Basement Slab Preparation 2.00d
79 7.2 Termite Treatment Basment Slab 1.00d
80 7.3 Slab Inspection 1.00d
81 7.4 Pour Basement Slab 1.00d
82 7.5 Prep Garage Slab 1.00d
83 7.6 Termite Treatment Garage Slab 1.00d
84 7.7 Pour Garage Slab 1.00d
85 8.00 H.V.A.C. 17.00d
86 8.1 HVAC Layout & Measure 1.00d
87 8.2 HVAC Roughin 5.00d
88 8.3 HVAC Set Indoor Units 2.00d
89 8.4 HVAC Temporary Heat 2.00d
90 9.00 Plumbing Roughin 37.00d
91 9.1 Plumbing Subslab 2.00d
92 9.2 Plumbing Layout 1.00d
93 9.3 Plumbing roughin 5.00d
94 9.4 City Plumbing Subslab Inspection 1.00d
95 9.5 City Plumbing Roughin Inspection 1.00d
96 10.00 Electric Roughin 19.00d
97 10.1 Set Electric Boxes 2.00d
98 10.2 Install Electric Service Panel 2.00d
99 10.3 Electrical Walkthrough 1.00d
100 10.4 Electrical Roughwire 14.00d
101 11.00 Specialty Roughins 5.00d
102 11.1 Central Vacuum Roughin 5.00d
103 11.2 Alarm System Roughin 5.00d
104 11.3 Telephone System Roughin 5.00d
105 11.4 Television System Roughin 5.00d
106 11.5 Audio Visual Roughin 5.00d
107 11.6 City Electrical inspection 1.00d
108 11.7 Draw #5 (Roughins complete) 1.00d
109 11.8 City Framing Inspection 1.00d
110 12.00 Roofing 68.00d
111 12.1 Roofing Paper Installed 3.00d
112 12.2 Draw #4 (Roof, windows, doors) 1.00d
113 12.3 Stock Roof Shingles 1.00d
114 12.4 Install Roof Shingles 7.00d
115 13.00 Exterior Finishes 56.00d
116 13.1 Siding 3.00d
117 13.2 Exterior Trim 7.00d
118 13.3 Brick Arch Forms 1.00d
119 13.4 Brick Veneer 45.00d
120 14.00 Insulation 5.00d
121 14.1 Caulk & Air Seal 1.00d
122 14.2 Draft & Fire Stop 1.00d
123 14.3 Batt Insulation 3.00d
124 14.4 City Insulation Inspection 1.00d
125 14.5 BGE Energy Wise Inspection 1.00d
126 15.00 Drywall 26.00d
127 15.1 Stock Drywall 1.00d
128 15.2 Hang Drywall 5.00d
129 15.3 Remove Scrap Drywall 1.00d
130 15.4 Tape and Finish Drywall 15.00d
131 15.5 Sand Drywall 1.00d
132 15.6 Drywall Pointup 3.00d
133 15.7 Draw #6 (Insulation & drywall applied) 1.00d
134 16.00 Floor Finishes 76.00d
135 16.1 Ceramic Tile 15.00d
136 16.2 Install Hardwood Floor 4.00d
137 16.3 Sand, Stain, Seal Hardwood 5.00d
138 16.4 Install Carpet 4.00d
139 16.5 Final Coat Hardwood 2.00d
140 17.00 Paint 59.00d
141 17.1 Prep Drywall for Prime Coat 2.00d
142 17.2 Prime Paint Drywall 2.00d
143 17.3 Prep Trim for Prime Coat 2.00d
144 17.4 Prime Trim 2.00d
145 17.5 Finish Coat Trim 11.00d
146 17.6 Finish Coat Drywall 14.00d
147 17.7 Caulk Exterior Windows & Doors 1.00d
148 17.8 Finish Coat Exterior Trim & Siding 1.00d
149 17.9 Draw #7 (Roofing, masonry, siding) 1.00d
150 18.00 Interior Trim 29.00d
151 18.1 Interior Trim Delivery 1.00d
152 18.2 Install Interior Doors 5.00d
153 18.3 Install Interior Trim 15.00d
154 18.4 Install Cabinetry 5.00d
155 18.5 Install Appliances 1.00d
156 18.6 1st Punchout Interior Trim 2.00d
157 19.00 H.V.A.C. Trim 1.00d
158 19.1 Install Grills & Registers for Paint 1.00d
159 19.2 Set Outdoor Units 1.00d
160 20.00 Plumbing Trim 5.00d
161 19.1 Set Fixtures 4.00d
162 19.2 Connect Appliances 1.00d
163 19.3 City Final Plumbing Inspection 1.00d
164 21.00 Exterior Landscaping 32.00d
165 21.1 Rough Final Grade 1.00d
166 21.2 Patios 7.00d
167 21.3 Porches 5.00d
168 21.4 Sidewalks 7.00d
169 21.5 Decks 7.00d
170 21.6 Driveways 2.00d
171 21.7 Final Grade and Seed 3.00d
21.8 Stakeholder Meeting 1.00d
172 22.00 Electrical Final Trim 161.00d
173 22.1 Switch & Plug 2.00d
174 22.2 Install Fixtures 1.00d
175 22.3 Connect Appliances 1.00d
176 23.00 Hardware 12.00d
177 23.1 Door Hardware 2.00d
178 23.2 Bath Hardware 2.00d
179 23.3 Mirrors 5.00d
180 23.4 Shower Doors 11.00d
181 23.5 Draw #8 (Prime paint, cabinets, doors) 1.00d
182 23.6 Draw #9 (Trim, furnace, hrdwd, tile, rails) 1.00d
183 23.7 Draw #10 (Plumbing & elec. trim, final paint) 1.00d
184 23.8 Final Building Inspection 2
185 23.9 Use & Occupancy Certificate 1
186 23.10 First Walkthru 1
187 23.11 Draw #11 (Final payment per contract) 1.00d
188 24.00 Final Punchout 9.00d
189 24.1 Punch Out Walkthru List 4.00d
190 24.2 Trim and Adjust Doors 2.00d
191 24.3 Paint Touchup 3.00d
192 25.00 Cleaning 14.00d
193 25.1 Windows 3.00d
194 25.2 Rough Clean 3.00d
195 25.3 Final Clean 2.00d
26.00 Site Demobilization
196 27.00 Final Walkthrough 1.00d
197 28.00 Movein, Acceptance and Sign in 1.00d
29.00 Closing Project Process 1.00d
Predecessors Start Finish

.
.
.
3
3
3
.
.
.
4
5
6,10
10,11,12
13
13
13
.
14
15
18,19
20
.
23
.
13
27FS+3d
16
14,15,16
28,29,30
29FS+2d,28,31
32
32,33
32,33
34,35
36
30
38,37
39FS+2d
40
.
37
43
43
43,45
39,45,43,46

.
47
49
50
51
52
53
53,54
55
56
55
58
59
58
61

.
60
64
65
66
67
68
69
70
71
72
73,111
72,81
75,87,93

.
65,91
78
79
80
81
82
83
.
72
86,111
81,87
88
.
65
91,87
92
91
93
.
74
97
98
99
.
100
100
100
100
100
96,101
95,107
95FS+1d,107FS+1d
.
73
74,111
112
113,119
.
74
116
117
118
.
109
121
121,122
123,120
124
.
124
127
128
128,129
130
131
128,126
.
142
146
196
137
196
.
131
141
142,152
143
144,156
145,132
146,117
147
114,157
.
142
151
152
153
154
155,144
140
131
165
.
135,136,146,154
161
160
.
119
165,119
166,119
167,119
168,119
165,169
170,166,167,168

.
142,100
146
155,162
.
145,146
145,146
178
178
142,152,154
153,181
146,182
183
184FS+3d
185
186
.
186
184,189
190
.
145,146
193
176,188
187,188,192
196FS+1d