Professional Documents
Culture Documents
NOTES:
CLOSED BOOK (C.B), OPEN BOOK (O.B) -
The following questions are the combination of 3 tests for 3 individuals -
Almost 90% of CLOSED BOOK Exam questions from API 570 -
Piping Classes, Table 2&3 in API 570 are ESSENTIAL PARTS in the Exam -
A LOT of questions came from 2012 Exam (Listed Below) -
QUESTIONS:
(C.B)
# What is the cause for rejection of the “B” image on a film due to excessive
backscatter? A light image.
# Which of the following materials should be hydro tested with potable water or
steam condensate? 300 series stainless steel.
# For class 1 piping the risk – based inspection (rbi ) assessment should be
reviewed and and approved at intervals not to exceed : 5 years
# A welding procedure specification (WPS) is selected for a repair on cold
service piping. Impact testing of the weldment is required. Which of the
following is /are required on the WPS? All essential,non essential, and
supplementary variables.
# Of four measurements taken , thickness of 0.180 inch (4.5 mm) , 0.200 inch
(5.1 mm) , 0.210 inch ( 5.3 mm) , and 0.230 inch (5.8 mm) were obtained within
an area of a test point . The thicknesses that may be used to calculate the
corrosion rate could be either: 0.180 inch (4.6 mm) or 0.205 inch ( 5.2 mm).
# Long –term and short –term corrosion rates should be compared in order to:
Determine the shortest remaining life.
(O.B)
# Under what circumstance must a welder requalify? When the welder’s foreman
discovers that the welder is not making acceptable welds
# Which of the following is not an acceptable temporary repair patch for an NPS 12
(DN 300) carbon steel pipe with localized corrosion? 8-inch (203 –mm) circular
patch.
# A buried pipe designed for 100-psing (0.689 MPa) Service is hydrostatically tested
at 125 psig (0.861 MPa ) for 8 hours .After 4 hours, the pressure has dropped 5 psig (
0.03 MPa ), and the system is pumped back up to 125 psig (0.861 MPa) . During the
remaining 4 hours of the test , the pressure drops by 5 psig ( 0.03 MPa ) .A
ccording to instructions in API standard 570 , the inspector should : accept the
test as successful.
# Threaded carbon steel piping in an NPS 1 ½ (DN 40) piping system in normal
service is being replaced. What is the minimum pipe schedule to be used? Schedule
80.
# A piping system is designed for 300 psig at 700 F .The allowable stress value at
test temperature is 20,000 psig .The allowable stress value at design temperature
is 15,000 psig. Which of the following is the pneumatic test pressure? 330 PSIG.
-8.2.1 Any welding conducted on piping components in operation shall be done in accordance
with API 2201.
- 8.2.3.3 Local PWHT may be substituted for 360° banding on local repairs on all materials,
The application is reviewed, and a procedure is developed by the piping engineer.
- 8.2.5 The materials used in making repairs or alterations shall be of known weldable quality,
shall conform to the applicable code, and shall be compatible with the original material. For
material verification requirements, see 5.8.
- 9.2.3 Pipe Coating Holiday Survey: it is used to evaluate
coating serviceability for buried piping that has been in-service for an extended period of time.
- 9.3.1 The owner/user should, at approximately six month intervals survey the surface
conditions on and adjacent to each
pipeline path.
API 571
- 4.2.16.5 Mechanical Fatigue: The signature mark of a fatigue failure is a “clam shell” type
fingerprint that has concentric rings called “beach marks” emanating from the crack initiation
site.
- 4.3.3.3 1) 10°F (–12°C) and 350°F (175°C) for carbon and low alloy steels, (C.B)
2) 140ºF (60°C) and 400ºF (205°C) for austenitic stainless steels and duplex stainless steels
(O.B)
- 4.3.3.6 Since the majority of construction materials used in plants are susceptible to CUI
degradation, mitigation is best achieved by using appropriate paints/coatings and maintaining
the insulation/sealing/vapor barriers to prevent moisture ingress.
- 4.4.2.7 Proactive and retroactive PMI programs are used for alloy verification and to check
for alloy mix-ups in services where sulfidation is anticipated.
- 4.5.1.7 PT or phase analysis EC techniques are the preferred methods (CL SCC) (O.B)
- 5.1.2.2.2 Amine Stress Corrosion Cracking: Carbon steel and low alloy steels.
- Figure 4-146 NAOH 30%, 140 F (Stress Relieve Welds and Bends). (O.B)
API 574
- 3.1.1 alteration: The following are not considered alterations: comparable or duplicate replacement;
the addition of any reinforced branch connection equal to or less (LARGER IS CONSIDERED
ALTERATION) than the size of existing reinforced branch connections; and the addition of branch
connections not requiring reinforcement.
- 10.3.2.2 Spot checking by magnetic particle, liquid penetrant, or ultrasonic testing should be
considered even if visual inspection revealed no cracks. (NOT R.T).
- 4.1.1.1.1 The size refers to the approximate inside diameter (ID) of standard weight pipe for
NPSs equal to or less than 12 in. (305 mm).
- 4.1.2.2 The extruded, generally homogenous nonmetallics, such as high- and low-density
polyethylene are excluded.
API 577
- 3.1.4 arc blow: The deflection of an arc from its normal path because of magnetic forces.
API 578
- 4.1 General: The owner/user should establish a written material verification program
indicating the extent and type of PMI testing to be conducted …..
- 4.2.4 Mill Test Report: Mill test reports should not be considered a substitute for a PMI test.
- T-277.3 Shims Under Hole IQIs: the radiographic density throughout the area of interest shall
be no more than minus 15% from (lighter than) the radiographic density through the IQI.
(4 Density IQI … 3.4 Density Area of interest) (O.B)
-T-282.1 Density Limitations: The transmitted film density through the radiographic image of
the body of the appropriate hole IQI or adjacent to the designated wire of a wire IQI and the
area of interest shall be 1.8 minimum for single film viewing for radiographs made with an X-
ray source and 2.0 minimum for radiographs made with a gamma ray source.
M.T
- T-761.1 Magnetizing equipment with an ammeter shall be calibrated at least once a year, or
whenever the equipment has been subjected to major electric repair, periodic overhaul, or
damage.
- T-762 Lifting Power of Yokes: (d) Each weight shall be weighed with a scale from a reputable
manufacturer and stenciled with the applicable nominal weight prior to first use.
V.T
- T-923 Physical Requirements: Personnel shall have an annual vision test to assure natural or
corrected near distance acuity such that they are capable of reading standard J-1 letters on
standard Jaeger test type charts for near vision.
U.T
LEAK TESTING
- T-1031 Gages: Gage Range – graduated over approximately double the maximum test
pressure – but not less than 1.5 – 4.0 x Test Pressure. (C.B)
ASME IX
- Change from Downhill to Uphill from welder ALONE (Reject). (C.B)
- WPS & PQR: (1) Mechanical Tests (Tensile & Bend) acceptance criteria.
(2) Base Metal THK. Qualification range
(3) Joint Shown (Non-essential variables) listed in WPS or not ? (O.B)
- QW-161.7 Longitudinal Root Bend: The weld is parallel to the longitudinal axis of the
specimen, which is bent so that the root surface becomes the convex side of the bent
specimen. (O.B)
ASME B31.3
- 300.2 Definitions tempering: reheating a hardened metal to a temperature below the
transformation range to improve toughness. (C.B)
- Table 323.2.2A (Given materials & THK.) min temp ?
- Minimum Thickness Calculation Question. (O.B)
- PWHT Table TEMP RANGE ? (O.B)
- Table 331.1.1 Hardness Max Values for a Given P Number
- Table 314.2.1 Minimum Thickness of External Threaded Components. (O.B)
- 345.4.2 Test Pressure: Hydrostatic test pressure Calculation Question (O.B)
- Acceptance Criteria (Under cut) Table 341.3.2 (O.B)
- Acceptance Criteria (Weld reinforcement) Table 341.3.2 (O.B)
- 341.4.1 Examination — Normal Fluid Service: at least 5% of fabrication. For welds, each
welder’s and welding operator’s work shall be represented. (O.B)
ASME B16.5
- 5.3.4 Low-Strength Bolting: Class 150 and 300 flanged joints. (C.B)
- Determine Temperature (Class & Design Pressure are given) Pressure–Temperature
Ratings Tables. (O.B)
- 2.5.2 High Temperature: At temperatures above 200°C (400°F) for Class 150 and above
400°C (750°F) for other class designations,flanged joints may develop leakage problems.
(C.B)
- 6.4.1 Classes 150 and 300 pipe flanges and companion flanges of fittings are regularly
furnished with 2 mm (0.06 in.) raised face, which is in addition to the minimum flange
thickness, tf. Classes 400, 600, 900, 1500, and 2500 pipe flanges and companion flanges of
fittings are regularly furnished with 7 mm (0.25 in.) raised face, which is in addition to the
minimum flange thickness, tf.