Professional Documents
Culture Documents
INTRODUCTION
1.1 GENERAL
Dry dock is a dock into which the ship floats. The dock gates are
closed behind it, the water is pumped out, and the ship rests on the docking blocks
ready for its hull to be repaired or cleaned. There are various types of dry docks as
follows,
GRAVING DOCKS
FLOATING DOCKS
SHIPLIFTS
SLIPWAYS
TRANSFER SYSTEMS
SMALL CRAFT LAUNCHING RAMPS
1
Fig 1.1
Fig 1.2
Fig 1.3
2
There is no need to worry about ship/dock stability, pumping plans or
longitudinal deflection of the dock while docking ships. (Ship stability
and block loading must still be addressed, however)
The basin can be equipped with an intermediate gate that allows
flooding of the aft half of the dock while the forward half remains dry.
3
1.7 SLIDING OR ROLLING CAISSONS
These are built up box sections with a sliding or rolling surface at the
base. The gate slides or rolls into a notch built into the side of the dock.
1.8 ADVANTAGES
Fast operating
1.9 DISADVANTAGES
Cleaning and maintenance of rollers or slide paths is difficult.
Operating mechanism is expensive
Major repairs require removal of gate
Recesses must be built into walls.
4
The secondary system, consisting of smaller pumps, collects the last few
inches of water in the basin as well as rain water, flushing water and water
from the under drain system.
5
visualization and result verification, STAAD Pro is the professional’s choice of
steel , concrete, timber, aluminums, and cold –formed steel design of low and
high-rise buildings, culverts, petrochemical plants, tunnels, bridges, piles and much
more.
It is used to generate the model, which can than be analyzed using the
STAAD engine. After analysis and design is completed, the GUI can also be used
to view the results.
1.12 OBJECTIVES
To design a dry dock for Chennai harbor using Indian Standard codal
provisions.
To draw and draft the layout using AutoCad software package.
To analyze the same using StaadPro software, to serve all types of ships.
6
CHAPTER 2
LITERATURE REVIEW
Design and construction as main contractor of dry dock, length 130m, width
27m, depth 10.80m
DESIGN
1. Organization
a. Bureau: The constructions of the dry dock were standard
construction, in accordance with plans supplied by the Bureau.
b. Station: Designs were not developed by the station.
c. Architect and Engineer: Assistance in design was given, as
consultants, by F.R. Harris, Inc., of New York, consulting engineers.
2. Criteria (General): Although the Robbins Dry Dock, at Erie Basin, New
York,has been designed and constructed using (in part) tremie concrete floor slab
(circa 1927), relatively few criteria existed, at the time that the work being
discussed was begun, for a structure of the magnitude of Dry Dock No. 2.
The conventional (circa 1910), braced, sheet-pile cofferdam method, employed in
the construction of Dry Dock No. 1, had failed, and thus necessitated
reconstruction, applying the costly laborious floating-caisson design which had
consumed some six years. A repetition of the experience was to be avoided.
Certain data as the "Robbins" and similar structures were available - and were
availed of. Briefly, the philosophy of the design assumed that, when the deck
was unwatered, the combined weights of (1) the floor slab and sidewalls; (2)
a small part of the frictional wedge of the backfill on the sidewalls; and (3)
U.S. NAVAL BASE, PEARL HARBOR, DRY DOCK No. 2 HAER HI-66 some
30% of the theoretical uplift value of the H-section steel piles; would resist the
hydrostatic upward pressure. The dock floor was designed as a beam to transmit
7
this upward pressure, or thrust, to the under sides of the walls. As will be elsewhere
noted in the text of this report, the construction methods stipulated in the plans and
specifications were supplemented, and to some extent modified, by the disclosures
reveled by experimental fieldwork. Several weeks before the Japanese attack of
December 7, 1941, (and less than twenty months after its construction was begun),
Dry Dock No. 2 had been brought to a stage of completion such that it could be -
and was - used to repair Navy craft affected by the "blitz." Criteria developed from
this dock's design and construction (and from those of Dry Dock No. 4,
Philadelphia Navy Yard, constructed concurrently) were of inestimable value in
facilitating (and thus expediting) "rush" completion of eight of the world's
largest dry docks, all built by the Navy under war-time pressure; one of them,
the recently completed Dry Dock No. 5, at Pearl Harbor.
DETAILS OF SITE
The dry docks' (Nos. 2 and 3) location is well suited to the function of
docking deep-drift ships, dry Dock No. 2 is on the northerly water frontage of the
Pearl Harbor Navy Yard, adjacent to the site of previously-constructed Dry Dock
No.1; repair and transportation facilities, power and water, were readily accessible,
and had been extensively developed for use by Dry Dock No. 1.
Core-boring tests had been made during 1938 and 1939. They showed
an overlay of adobe over (successively) volcanic tuff; volcanic sand (loose, strong,
hard);limestone, coral-reef formation (hard, coarse, and fine, silty); below the
elevation of the floor slab, compact clay (brown and gray); and, still lower, loose,
fragmentary limestone formations, extending indefinitely. Tests were run, too, to
determine the extent of the abrasive and corrosive effects of coral and salt water
on (structural) metal.
With the test results known, it was decided that the site was suitable for the
projects construction. Designs were developed and the work begun.
8
2.2 SOLETANCHE BACHY (2001) -CONCARNEAU DRY DOCK
Design and construction as main contractor of dry dock, length 130m, width
27m, depth 10.80m
DESIGN
The dry dock is 130m long, 27m wide and 10.80m deep, controlled on
the seaward side by trolley-mounted sliding gate. The remote end has a spiral
access ramp for more efficient operational use by the commercial companies
operating there.
A pump room is provided to control wash water and gate leakage.
Three pumps can discharge up to 4000 m3 per hour to dewater the dock in four
hours when a ship is being docked. There are all the usual fittings conventionally
found in harbors works such as bollards, capstans and winches.
WORKS
One of the challenges facing the consortium was how to deal with the
mud covering the lagoon bed to depths of up to 7 meters, considering that the
finished dock was to be surrounded by earth platforms for normal harbor
operations, with a specified bearing capacity of at least 3 tones per square meter.
Excavation of the mud would have been difficult and disposal even more
problematical, and it was decided to consolidate it in situ by preloading. Apart
from the excavation for the dock itself, therefore, all the mud has been left in place.
An interceptor channel was dug to divert the river around the lagoon, then the
lagoon was emptied to expose the mud. A geo-textile was laid over the whole area
and covered with the same thickness of free-draining gravel. Strip drains were sunk
from this platform down to bedrock in a 1-metre square array. The subsequent
weight of the fill gradually expelled the water from the mud through sumps
collecting the water in the free-draining layer. Settlement of approximately one
meter was observed before construction work proper could commence.
The dock sidewalls were built as diaphragm walls, tied back at the top
with passive anchors to sheet piling and fixed at the bottom by the concrete floor of
the dock.
9
The floor is a drained raft to prevent the build-up of uplift. Works on
the dock entrance proceeded behind a watertight cofferdam built in the port: pump
room, floor under the gate, gate recess (rock excavation with concrete and nail
support). The contract required a turnkey graving facility, and ancillary works
included a perimeter road around the dock, drinking water, electricity and gas
supply, fire-fighting system, two-storey control building and all fittings for ship
docking (keel blocks, winched cradles, etc.). One of the last operations was
assembly of the dock gate, by assembling four caissons to form a single unit 28m
long, 11m high and 4m thick, weighing 170 tonnes. The gate was launched by a
nearby boat hoist, towed to station and sunk onto its trolleys, standing ready on
their rail tracks.
Fig 2.1
10
2.3 MURRAYLANDS DRY DOCK(2009)
INTRODUCTION
Dynamic Project Delivery (DPD) was engaged by the Murray lands
Regional Development Board (MRDB) on behalf of the Murray lands Dry Dock
Working Party to undertake an evaluation to determine the viability of building a
dry dock facility in the Mid Murray Council region. DPD were also asked to define
the optimum site for construction.
The four key stages for the evaluation of the potential to establish a
Murray lands Dry Dock facility identified were:
1. To identify an ideal site for the construction of a dry dock
2. To obtain costs, timelines and parameters for the construction of the dry
dock
3. To identify potential funding or investors for the construction of the dry
dock
4. To recommend the ownership and management structure for the dry dock.
The Murray lands Dry Dock Working Party determined that firm
concept designs must be obtained and endorsed prior to lodging a Pre-Lodgment
Agreement / Development Application, and prior to funding being sought. The
development of conceptual designs will therefore form an interim stage between
this report and the pre-lodgment process.
11
Randell. The dry dock was actually built at Milang, by A.H. Landseer, and towed
across Lake Alexandrina by the steamer Nildesperandum. It was during the boom-
days that the dock and wharf were used to their capacity due to a huge trading
enterprise built by J.G. Arnold. The dry dock now has a heritage listing.
� Entec – Wallsend, Tyneside UK - The proposed dry dock replaces the existing
slipways, which are inclined and fall into the River Tyne. These are of reinforced
concrete construction, founded over significant areas on bearing piles of steel,
concrete and timber.
12
Chapter 3
METHODOLOGY
13
1CLRD i
.AmEe
PDDiPs t i
leDsOg
as
tRn
ni
dagTa
vnrtn
iaed
eowma
wf
ien
nta
ghl
soy
ds i
s
Fig 3.1 FLOW CHART OF DRY DOCK DESIGN AND ANALYSIS
14
judgement. The purpose of standards is to ensure and enhance the safety, keeping
careful balance between economy and safety.
This design process includes the design of dry dock components
Manually. The components of dry dock designed in this process are as follows,
1. Staircase
2. Slab
3. Retaining wall
4. Steel section
5. pile
The analysis of the bending moment and deflection is done by the
STAAD Pro software.
Chapter 4
16
4.1.1 REQUIREMENTS FOR PILE DESIGN
Clay sand 1 6
Hard rock - -
GIVEN DATA
qb =14*100*(7/1) KN/m2
qb = 9800 KN/m3
18
SKIN FRICTION FOR THE PILE (TOTAL SKIN FRICTION)
Total skin friction = 24937.95KN
Factor of safety = 2.5
Allowable skin friction = 9975.18KN
19
4.2.2 BULK DENSITY
Loam 1.45-1.6
20
4.2.3 SOIL PRESSURE
Soil layer γsat γsat K0 Q Surcharge Hydraulic Dry soil Total Cummalativ
-10 pressure head density pressure e pressure
(q* K0) pressure(γw*z) pressure(γsat
-10)( q* K0)
Water 2.31 -7.69 0.7 20 14 72.5 -39.03 47.47 47.47
Silty 3.35 -6.65 0.7 20 14 70 -32.59 51.41 98.88
clay(layer 1)
Clayey sand 3.81 -6.19 0.7 20 14 10 -4.33 19.67 118.55
Silty 3.35 -6.65 0.7 20 14 10 -4.66 19.34 137.89
clay(later 2)
Silty sand 4.04 -5.96 0.7 20 14 60 -25.03 48.97 186.86
Concrete(laye 5.54 -4.46 0.7 20 14 100 -31.22 82.78 269.64
r 1)
Concrete(laye 5.54 -4.46 0.7 20 14 10 -3.12 20.88 290.52
r 2)
21
4.2.4 WAVE PRESSURE
Fig 4.1
GIVEN DATA
High sighted wave (ds)= 2.5m
wave length L @ D = 2.5m is 48.7m
D = 11m
h= 11m
R = 5m
r =5m
Hb =3m
22
P1 = (A1+A2)*W*Hb
=(0.82+0.038)*10*3
P1 =25.74 KN/m2
P2 = A3*P1
=0.282*25.74
P2 =7.26KN/m2
P3 ={1-(r /R)} – P1
={1-(5/5)} – 25.74
P3 =5.148 KN/m2
M =F* hc
=158.202*2
M =316.404KN.m
GIVEN DATE
Assume the following,
23
Safe bearing capacity(p) = 2000KN/m3
Height of embankment above ground level = 10m
Density of soil (w) =18 KN/m3
Angle of repose = 300
Friction between soil and concrete (µ) = 0.5
Use M35 grade concerte and Fe500 steel bars
SOLUTION
Step 1
Dimensions of retaining wall
Minimum depth of foundation = ((p/w)*((1-sin�) / (1+sin�))0.5)
= ((2000/18)*(1/3)0.5)
= 12.35m
Height of stem(h) = H - 2
= 23- 2
= 21m
Step 2
Design of stem
Height of stem (h) = 21m
24
Maximum working moment in stem (M) = (Cp *w*h3) / 6
M = ((1/3)*18*213) / 6
= 9261 KN.m
Step 3
Main reinforcement
FROM SP 16, (From table 4)
Pt = 0.951
Distribution reinforcement
25
Ast = 0.12%*b*d
= (0.12 / 100)*1000*2000 mm2
= 2400 mm2
Provide 4 bars of 30mm diameter
Step 4
Stability calculations
Heel projection = ((2/3)*13) - 2
= 6.67 m
Load calculations
Earth pressure
P0 = K0*γ*z
= 0.8*18*21
= 302.4 KN / m2
Z = ξM / ξW
= 5.67 m
26
Eccentricity (e) = ( z – (b/2))
= 5.67 – (13/2)
= -0.83
(b/6) = 13/6
= 2.17
Therefore , e < (b/6)
Fig 4.2
(318.15 / 6.23 ) = (x / 2)
x = 100.52 KN/m
(246.33 / 13) = (x / 6.67)
x = 126.33 KN/m2
Step 5
Design of heel slab
27
Load Magnitude of Distance from Moment (KN.m)
load(KN) ‘a’(m)
W3 = 6.67*21*18 2521.261 6.67 / 2 = 3.33 8408.4
Self weight 333.5 6.67 / 2 = 3.33 1112.22
= 6.67*2*25
ξM = 9520.62
Deduction
Uplift pressure 1322.39 6.67 / 2 = 3.33 4410.17
= 198*6.67
(ghi) = 421.3 6.67 / 2 = 3.33 1405.03
0.5*6.67*126.33
ξM = 5815.2
Step 6
Main reinforcement
FROM SP 16, (From table 4)
Pt = 0.34
28
Distribution reinforcement
Ast = 0.12%*b*d
= (0.12 / 100)*1000*2000 mm2
= 2400 mm2
Provide 4 bars of 30mm diameter
Step 7
Check for safety against sliding
Total horizontal earth pressure (P) = (Ka*w*H2) / 2
= ((1/3)*18*233) / 2
= 1587 KN
Step 8
Design of shear key
Passive force (Pp ) = Kp*P
Kp = (1+sin�) / (1-sin�)
=3
P = 1323 KN/m
Pp = 3*1323 KN/m2
29
= 3969 KN/m2
If ‘a’ is depth of shear key = 2 m.
Step 9
Check for shear stress at junction of stem and base slab
Net working shear force (V) = (1.5*P) – W
= (1.5*1587) – 2089
= 291.5 KN
Pt = (100*Astpro) / (b*d)
= (100*19634.6) / (1000*2000)
= 0.98
Hence it is safe.
30
4.3 SLAB DESIGN
4.3.1 REQUIREMENTS FOR SLAB DESIGN:
Hydraulic conductivity
Hydraulic gradient
Seepage flow
Uplift pressure
TABLE 4.4
MEDIUM K (m/s)
31
= (12-7) / 160
= 0.03
BY DARCY’S LAW,
32
Fig 4.3
4.3.6 DESIGN OF SLAB
GIVEN DATA
Depth (D) = 5m
(Depth is taken from the book ‘DESIGN AND CONSRUCTION OF DRY
DOCKS’ by ‘B.K MAZURKIEWICZ )
SOLUTION
33
Step 1
Effective span (lx) = (Lx + cover)
= (10 + 0.15) m
= 10.15 m
Effective span (lx) = 10.15 m
Step 2
Load calculations
Step 3
Moment and shear calculations
From IS 456:2000 , (TABLE 26 , PAGE NO:91)
Assume the condition => ONE LONG EDGE DISCONTINOUS
And using Ly / Lx =1.0, we get ,
Negative moment at continuous span (αx = 0.037)
Positive moment at mid-span (αx = 0.028)
34
Bending moment
From IS 456:2000 , (CLAUSE D-1.1 , PAGE NO:91)
Shear force
Vux = 0.5*Wu*lx
= 0.5*1634.89*10.15
= 8297.07 KN.
Step 4
Reinforcement details
FROM IS 456:2000 , (G-1.1.b, PAE NO:96)
Step 5
a) Check for depth:
Mmax = 0.138*fck*b*d2
6231.94*106 = 0.138*35*1000* d2
d = 1.135 m < (depth (D) = 5 m)
hence it is safe.
Pt = (100*Astpro) / (b*d)
= (100*3141.5) / (1000*5000)
= 0.1
36
From IS 456:2000 , (TABLE 20, PAGE NO:73)
τC max= 3.7
τC max >τv
hence it is safe
4.3.6.2 DESIGN OF SLAB WITH CEMENT MORTAR LOAD
GIVEN DATA
Depth (D) = 4m
(depth is taken from the book ‘DESIGN AND CONSRUCTION OF DRY
DOCKS’ by ‘B.K MAZURKIEWICZ )
SOLUTION
Step 1
Effective span (lx) = (Lx + cover)
= (10 + 0.15) m
= 10.15 m
Effective span (lx) = 10.15 m
Step 2
Load calculations
ii. Dead load due to weight of cement mortar = area of cement mortar* unit
Weight of concrete
= 0.5*10*1*25 KN/m
= 125 KN/m
Total dead load = 225 KN/m
37
= 1000 KN/m
Live load = 1000 KN/m
Step 3
Moment and shear calculations
Bending moment
From IS 456:2000 , (CLAUSE D-1.1 , PAGE NO:91)
Step 4
Reinforcement details
FROM IS 456:2000 , (G-1.1.b, PAE NO:96)
Step 5
Pt = (100*Astpro) / (b*d)
= (100*4532.89) / (1000*4000)
= 0.11
GIVEN DATA
Depth (D) = 5m
Weight of Keel block = 200KN/m
(depth and weight of keel block is taken from the book ‘DESIGN AND
CONSRUCTION OF DRY DOCKS’ by ‘B.K MAZURKIEWICZ )
40
M35 grade concrete with Fe500 steel bars is used
Ly / Lx = 10 / 10 => 1 < 2(FROM IS 456:2000, PAGE NO:90)
Therefore design two way slab
SOLUTION
Step 1
Effective span (lx) = (Lx + cover)
= (10 + 0.15) m
= 10.15 m
Effective span (lx) = 10.15 m
Step 2
Load calculations
Step 3
Moment and shear calculations
From IS 456:200 , (TABLE 26 , PAGE NO:91)
41
Assume the condition => ONE LONG EDGE DISCONTINUOUS
And using Ly / Lx =1.0, we get ,
Negative moment at continuous span (αx = 0.028)
Positive moment at mid-span (αx = 0.037)
Bending moment
From IS 456:2000 , (CLAUSE D-1.1 , PAGE NO:91)
Shear force
Vux = 0.5*Wu*lx
= 0.5*3055.95 *10.15
= 15508.94 KN.
Step 4
Reinforcement details
FROM IS 456:2000 , (G-1.1.b, PAE NO:96)
Step 5
Mmax = 0.138*fck*b*d2
11648.69 *106 = 0.138*35*1000* d2
d = 1.552 m < (depth (D) = 5 m)
hence it is safe.
τv = Vu / (b*d)
= (15508.94 *103) / (1000*5000)
= 3.1
Pt = (100*Astpro) / (b*d)
= (100*6333.45) / (1000*5000)
= 0.12
43
From IS 456:2000 , (TABLE 19, PAGE NO:73
Using Pt = 0.12
τC = 0.29
τC < τv
GIVEN DATA
Depth (D) = 5m
(depth is taken from the book ‘DESIGN AND CONSRUCTION OF DRY
DOCKS’ by ‘B.K MAZURKIEWICZ )
SOLUTION
Step 1
Effective span (lx) = (Lx + cover)
= (10 + 0.15) m
= 10.15 m
Effective span (lx) = 10.15 m
Step 2
Load calculations
44
= 125 KN/m
Step 3
Moment and shear calculations:
From IS 456:2000 , (TABLE 26 , PAGE NO:91)
Assume the condition => ONE LONG EDGE DISCONTINUOUS
And using Ly / Lx =1.0, we get ,
Negative moment at continuous span (αx = 0.028)
Positive moment at mid-span (αx = 0.037)
Bending moment
From IS 456:2000 , (CLAUSE D-1.1 , PAGE NO:91)
Mux (+ve) = αx*Wu*(lx)2
= 0.028*1944.17 *(10.15)2
= 5608.2 KN.m
45
Mux (+ve) = αx*Wu*(lx)2
= 0.028*1944.17 *(10.15)2
= 5608.2 KN.m
Mux (-ve) = αx*Wu*(lx)2
= 0.037*1944.17 *(10.15)2
= 7410.8 KN.m
Shear force
Vux = 0.5*Wu*lx
= 0.5*1944.17 *10.15
= 9866.66 KN.
Step 4
Reinforcement details
FROM IS 456:2000 , (G-1.1.b, PAE NO:96)
a) M = 0.87*fy*Ast*d (1 – ((fy*Ast) / (b*d*fck)))
5608.2 *106 = 087*500*Ast*5000 (1 – ((500*Ast) / (1000*5000*35)))
5608.2 *106 = 2175000Ast – 6.21Ast2
Ast = 2597.66 mm2
Provide 8 bars of 22mm diameter
46
= (1000 * (π / 4)*222) / 3801.3 mm
= 100 mm.
Provide 10 bars of 22mm diameter at 100mm centre to centre spacing
Step 5
Check for depth
Mmax = 0.138*fck*b*d2
7410.8*106 = 0.138*35*1000* d2
d = 1.238 m < (depth (D) = 5 m)
hence it is safe.
τv = Vu / (b*d)
= (9866.66 *103) / (1000*5000)
= 1.97
Pt = (100*Astpro) / (b*d)
= (100*3801.3) / (1000*5000)
= 0.11
hence it is safe.
Step 1
47
DETERMINATION OF FACTORED LOAD
Service load = 160 KN / m
Load factor =3
Step 2
BENDING MOMENT
M = (W*L2) / 8
=(480*103*102) / 8
M = 6*106 N.m
SHEAR FORCE
V =(W*L) / 2
=(480*103*10) / 2
V =2.4 * 106 N
Step 3
PLASTIC SECTION MODULUS
ZP = MγM / FY
= (6*106 * 1.1 ) / 500
ZP = 13.2*103mm3
Step 4
Consider a section ISMB 450
A=92.27cm2
D= 450mm
bf=150mm
tf=174mm
tw=9.4mm
rz=18.15cm
Zez=1350.7 cm3
Zpz = 1533.36cm3
Zpz / Zez = 1.15 (shape factor)
48
Step 5
To check
B / tf = 125 /17.4
= 7.18 < 10.5€
From table 2, (IS 800 : 2007)
It is considered to be class 2 . Hence the section is compact.
Step 6
Check for shear
(i) Vd = {fy / (√3*γm)} * h*tw
={500 / (√3*1.1)} * 10*103*9.4
=24.6*106 N
Vd > V
Hence safe
Deflection
49
Fig 4.4.1
E =200*109N/mm2
I = 2*108mm4
1*∆ = ∫0l (Mm / EI) ds
Fig 4.4.2
Mx = -160*x*(x/2)
= - (160*x2) / 2
50
Fig 4.5
Mx = -1x
∆ = (1/ EI) ∫0l (-160x2 / 2) * (-1x)dx
= (1/ EI) ∫0l0 (160*x3 / 2) dx
=(1/ EI) [ 80x4 / 4 ]010
=(20*104) /EI
= 5*10-3mm
Deflection check
L / 300 = (10*103) / 300
=33.33
∆ < L/300
Hence it is safe
SOLUTION
Step 1
Number of steps = vertical height / rise of step
= 2 / 0.17
=11.76 => 12 steps.
Number of steps = 12 steps.
Step 2
a) Effective span (l) = ((number of steps) * (tread)) + width of landing beams
= ((12)*(0.27)) + 0.5 m
= 3.74m.
Effective span(l) = 3.74m.
52
ii. Dead load of slab (horizontal) (w) = (ws(R2+T2)0.5) / T
= (5 (0.172+0.272) 0.5) / 0.27 KN/m
= 5.9 KN/m
Dead load per metre length (w1 ) = dead load of one step / T
= 0.57 / 0.27 KN/m
= 2.12 KN/m
Step 4
a) Bending moment (M) = (Wu * l2) / 8
= (76.54 * 3.742) / 8 KN.m
= 133.83 KN.m
Bending moment (M) = 133.83 KN.m
53
b) Shear force (V) = (Wu* l) / 2
= (76.54 * 3.74) / 2 KN
= 143.1 KN
Shear force (V) =143.1 KN.
Step 5
a) Main reinforcement details
FROM IS 456:2000 , (G-1.1.b, PAE NO:96)
Step 6
c) Check for depth
54
M = 0.138*fck*b*d2
133.82*106 = 0.13*35*1000* d2
d = 0.171m < (Effective depth (d) = 0.18m)
hence it is safe
τC = 0.84
τC > τv
Hence it is safe.
CADD DRAWINGS
55
Fig 4.6 PLAN
56
Fig 4.7 CROSS SECTION
57
Fig 4.8 RETAINING WALL
58
Fig 4.9 SLAB WITH STAIRCASE LOAD
59
Fig 4.10 SLAB WITH CEMENT MORTAR LOAD
60
Fig 4.11 SLAB WITH SHIP AND KEEL BLOCK LOAD
61
Fig 4.12 SLAB WITH GATE LOAD
62
Fig 4.13 STAIRCASE
63
STAADPRO ANALYSIS
64
Fig 4.16 BOTTOM VIEW
65
CHAPTER 5
ESTIMATION OF DRYDOCK
CONCRETE ESTIMATION
RATES ASSUMED
Cement = 7650.00 per Cu.m
Sand = 700.00 per Cu.m
Ballast = 650.00 per Cu.m
ESTIMATION OF SLAB
DATAS
Lenght of Slab = 10 m
Breadth of Slab = 10 m
Depth of Slab = 5 m
ESTIMATION
Volume of Slab = lxbxh
= 10 x 10 x 5
= 500 Cu.m
66
Total cost for slabs =Rs 111,33,96,000
ESTIMATION OF PILE
DATAS
No. Of Piles = 80
Height of Pile = 7m
Height of Cylinder = 5 m
Height of Cone = 2m
ESTIMATION
FOR CYLINDER
π r 2h
Volume of Cylinder =
= π x 0.5 x 2 x 5
= 3.925 Cu.m
COST ESTIMATE
Cement = Rs. 75,965
Sand = Rs. 13,916
Ballast = Rs. 19,364
FOR CONE
Volume of Cone = 1/3 π r2 h
= 1/3 x π x 0.5 x 2 x 2
= 0.523 Cu.m
COST ESTIMATE
Cement = Rs. 10,120
Sand = Rs. 1,855
Ballast = Rs. 2,580
67
Cement = Rs. 86,085
Sand = Rs. 15,771
Ballast = Rs. 21,943
1.TRIANGLE
Volume of Triangle = ½ x l x b
= ½ x 1 x 21
= 10.5 Cu.m
COST ESTIMATE
Cement = Rs. 2,03,222
Sand = Rs. 37,240
Ballast = Rs. 51,798
2.RECTANGLE IN STEM
Volume of Rectangle = lxbxh
= 1 x 1 x 21
= 21 Cu.m
68
Ballast = 7.59 x 21 = 159.39 Cu.m
COST ESTIMATE
Cement = Rs. 4,06,444
Sand = Rs. 74,485
Ballast = Rs. 1,03,603
COST ESTIMATE
Cement = Rs. 5,03,217
Sand = Rs. 92,220
Ballast = Rs. 1,28,271
COST ESTIMATE
Cement = Rs. 77,418
Sand = Rs. 14,182
Ballast = Rs. 19,734
STEEL ESTIMATION
Main reinforcement
20mm dia @ 2.47kg/m , straight bars @ 125mm c/c
70
Length = 10-0.3+(18*0.02) = 10.06m
Distribution reinforcement
20mm dia @ 2.47kg/m , 125mmc/c
Main reinforcement
24mm dia @ 3.33kg/m , straight bars @ 100mm c/c
71
= {(10-0.3) / 0.1}= 97 bars
Distribution reinforcement
20mm dia @ 2.99kg/m , 100mmc/c
Main reinforcement
24mm dia @ 3.35kg/m , straight bars @ 100mm c/c
72
Total length = (98*10.132)+(97*10.162) =1978.65m
Distribution reinforcement
24mm dia @ 3.55kg/m , 100mmc/c
Main reinforcement
22mm dia @ 2.99kg/m , straight bars @ 100mm c/c
73
Distribution reinforcement
22mm dia @ 2.99kg/m , 125mmc/c
RETAINING WALL
STEM
Main reinforcement
50mm dia @ 15.432 kg/m @ 100mm c/c
Distribution reinforcement
30mm dia @5.56kg/m @250 c/c
74
No of bars = {(25-0.05-0.05) / 0.250 } +1 = 101
BASE SLAB
Main reinforcement
50mm dia @ 15.432 kg/m @ 250mm c/c (TOP AND BOTTOM)
Distribution reinforcement
30mm dia @5.56kg/m @250 c/c
Weight = 39266.64m*5.56=218322.518kg
75
TOTAL COST OF DRY DOCK = RS204,47,03,148
CHAPTER 6
CONCLUSION
76
Finally the project reveals that structure of dry dock is adopted in
Indian climatic conditions for economical way of ship and boat under the limits of
dry dock designed for repairing and maintaining works.
Refernces
77
2. Francis wentworth-shields, john mowlem company& edmund nuttall sons
& company (july 1933) – ‘KING GEORGE V GRAVING DOCK’-
Southampton's Western , journal on on design of dry dock.
IS 456:2000
IS 456:2007
IS 456:1978
IS 456 (PART 2):1989
IS 6403:1981
78