Engineering Works

Planned Actual
PPW % Weightage Submissions Approval Total Submissions Approval Total % Completed PPW
(B/B7) Cx7/100 Nos Nos Nos Nos Nos Nos (J/G) (KxD)
Shop Drawing 36583 52.26 3.66 2000 2000 4000 837 325 1162 0.29 1.06
Method Statement 11593 16.56 1.16 62 62 124 37 22 59 0.48 0.55
Material Submittal 20790 29.70 2.08 90 90 180 121 41 162 0.90 1.87
Sub contractor 1034 1.48 0.10 7 7 14 6 5 11 0.79 0.08
70000 7.00 Total 3.57

Mobilization
Establishment of Site Office 1
Establishment of Site Laboratory 0.88
Total 1.88

Construction
General 0.1

Total 5.55
Engineering Works
Planned Actual
PPW % Weightage Submissions Approval Total Submissions Approval Total % Completed PPW
(B/B7) Cx7/100 Nos Nos Nos Nos Nos Nos (J/G) (KxD)
Shop Drawing 36583 52.26 3.66 2000 2000 4000 878 452 1330 0.33 1.22
Method Statement 11593 16.56 1.16 62 62 124 39 28 67 0.54 0.63
Material Submittal 20790 29.70 2.08 90 90 180 132 85 217 1.21 2.51
Sub contractor 1034 1.48 0.10 7 7 14 7 6 13 0.93 0.10
70000 7.00 Total 4.45

Mobilization
Establishment of Site Office 1
Establishment of Site Laboratory 0.88
Total 1.88

Construction
General 0.1

Total 6.43