COMMENT SHEET

Project Title : Project Code :

Contractor Name : Engineer Name:


Document No.: Issue Ref. No.
Document Description: Baseline Schedule Issue Date:
Rev. No.: 1 Received Date : 06/Aug/17
Rev. Date: 03/Aug/17 Reply Date:
Document Class: Reply Due Date: 20/Aug/17
Document Status Approved Approved with Comments ✘ Resubmit/ Rejected
SL. Ref. Section/ Clause
No. No. Page No. Engineer/ Employer's Comments Contractor's Reply Remarks

Narrative for Contractor did not expound on the different "Risk Category" of the
1 Programme of Works Project. Contractor to include in the narrative.

Activity SKB-KM-1000 "Project Commencement Date" already has a


progress, this shall be removed. Also, it has a Start Constraint. Instead
2 Usage of Constraint of putting start constraint, use Planned Start of 01-Jun-2017 on Dates
Tab under Project directory. This comment has not been complied
with.

No constraints allowed in the Baseline Programme. Contractor to


remove any constraints. Constraints found on activity "Project
Commencement Date". This comment has not been complied with.
3 Usage of Constraint Contractor did not removed the single constraint, instead it added as
Late as Possible constraint and now the Programme has 103 number of
contraints. This is not acceptable.

Extensive usage of lags is still observed in the schedule. To minimize as


4 Usage of Lags much as possible.

There are still invalid relationships shown on the "Schedule Log


5 Invalid Relationship Report". Contractor to check and rectify.

Page 1 of 1