Professional Documents
Culture Documents
DESIGN OF BRIDGES
Y V R A VISWANADH
REG.NO:17MST0039
PH.NO:8897189913
AKASHI KAIKYO SUSPENSION BRIDGE
DAMPERS:
In the two main towers 20 mass dampers, TMDs, were placed, pivoting in the direction opposite
to the wind when it blows on one side of the bridge, dampers sway in the opposite direction,
effectively balancing the bridge and placed negating the influence of wind. In the bridge design
system strengthening beams with two hinges allow the structure to withstand winds of 290 km /
hour, earthquakes with a magnitude of up to 8.5 on the Richter scale and strong currents was also
applied. The bridge also contains pendulums which are designed to operate at the resonant
frequency of the bridge to dampen forces.
Fig: Tuned dampers
TOWERS:
The two main supporting towers rise 282.8 meters above sea level, 297.30m to the end of the
anchor cable, the bridge can be expanded by the heat of up to 2 m in the course of a day. Steel
cables with a diameter of 112cm contain 36,830 lines of wire. The bridge is supported by two
cables basically the central section, considered the toughest in the world constructed.
SECTION TOWERS:
The primary tower is made of steel, and the shaft has a cruciform cross section which is insensitive
to wind-induced oscillation. However, tuned mass damper is installed within the shafts to suppress
oscillation is anticipated that during erection of the tower, and even at the stage of completing the
bridge. A shaft of the tower is divided into 30 levels and almost all levels are composed of 3 blocks.
Each block was made in factories and transported to the site and then hoisted by crane climbing
tower that had a lifting capacity of 160 tons. Articulating high tension bolts were used to connect
field.
A foundation of the main tower weight of 120,000 tn weighing bridge from the
main towers footbed transmitted. The footbed, 60 meters under water, was excavated by a dredger
bucket. To overcome the difficult conditions of the strait, including deepwater strong currents and
waves that caused vibration in the dredger during excavation, high-tech devices are used, such as
Remotely Operated Vehicle System.
The drawers are installed using the “method of adjustment”, which involved the manufacture of
the drawers in a factory, then towed to the site, submerging, and eventually, filling underwater
concrete. The circular-shaped drawer has no directional property, and thus makes them more stable
and easier to handle in strong currents of the Strait.
The construction of the stiffening beam, by the method of flat blocks, begins in the towers and
main anchors, where a floating crane was used to install six cell blocks in the towers, and 8 anchors.
CIRCULATION WAYS:
The 4km of the pathway for vehicles that crosses the Akashi Strait is divided into 6 lanes. Is
suspended and supported by the cables cover is held by its own weight, resulting in thousands of
steel beams positioned to form a triangular grid. It took 15 months to put the 280 beam sections.
As added reinforcement, below deck, a vertical stabilizer with a form like the fin of a plane
that runs through the center of the bridge and balances the pressure, both below and above
deck. A steel mesh was placed in the center and side rails to allow passage of the wind.
vertical stabilizer
MATERIALS
The main material used in the bridge superstructure is steel. Has also been used reinforced
concrete. For the foundation, underwater towers developed a new type of mixing a “concrete
submarine that is not broken” (a “non disintegration concrete).
LIGHTING
The Akashi Kaikyo Bridge-has a total of 1,737 light fixtures: 1084 for the main cables, 116 for the
main towers, beams and 405 to 132 for the anchors. In the main cables are placed three high
capacity lighting tubes, red, green and blue. The RGB model and computer technology contribute
in making a wide variety of combinations. A minimum of 28 patterns are used for special occasions
such as regional public holidays or commemorations.
CABLES
The length of the cables used in the bridge amounts to 300,000 kilometers, enough to circle the
earth 7.5 times. Steel cables with a diameter of 112cm contain 36,830 lines of wire.
CABLE SPECIFICATIONS:
• Method of construction: PS (Precast Strand) – ultimate tensile strength cable: approx.
62,500 tonnes
• Resistance to high tensile rope hanger approx. 560 tons – Material: galvanized steel wire
of high resistance
CABLE COMPOSITION
• Tensile cable: 180 kg / mm 2 – Cable diameter: 1122 mm (not including packaging
• Composition: 5.23 mm wire diameter * 127 / * 290 stranded wire / cable wire * 2 – Total
Number of Conductors: 36830
• Strand Length: 4,071m – 4,074m – Total cable length: 300,000 km
• Weight of main steel cable: 50,500 tons – suspension ropes, etc ashlar: 7,200 tons
BEAMS:
In beams were used 90.000tn reinforcement steel. Due to the large size of the bridge, the wind load
which must face is higher than that of any other existing bridge when construction was completed.
Using steel with high tensile strength for the beams made very strong yet lightweight, and thus
cheaper.
The reinforcing elements were prefabricated shaped panel were transported to the construction site
where they were erected into the interior of the anchorages and towers with floating cranes.
ARCHITECTURE:
The bridge has three spans. The central span is 1,991 m (6,532 ft), and the two other sections are
each 960 m (3,150 ft). The bridge is 3,911 m (12,831 ft) long overall. The central span was
originally only 1,990 m (6,529 ft), but the Kobe earthquake on January 17, 1995, moved the two
towers sufficiently (only the towers had been erected at the time) so that it had to be increased by
1 m (3.3 ft). The bridge was designed with a two-hinged stiffening girder system, allowing the
structure to withstand winds of 286 kilometres per hour (178 mph), earthquakes measuring to 8.5
on the Richter scale, and harsh sea currents. The bridge also contains pendulums that are designed
to operate at the resonance frequency of the bridge to damp forces. The two main supporting towers
rise 298 m (978 ft) above sea level, and the bridge can expand because of heating up to 2 metres
(7 ft) over the course of a day.
DESIGN CONCEPT:
The function of this bridge was to support the traffic load coming on the 6-lane freeway. But before
that the bridge had to carry its own self weight. The load coming on the bridge was distributed as
91% to support its own weight and only the remaining 9% was for traffic load. The basic concept
consisted of erecting two towers and passing steel cables through it. The girder was connected to
the cable by means of hangar cables.
DIFFICULLTIES FACED:
A) DURING CONSTRUCTION:
EARTHQUAKE: When the earthquake struck Kobe, the epicenter was just 4 km from the bridge,
it was partly due to luck and partly due to the fore-sight of the engineers that the bridge did not
sustain serious damage. Since the roadway had not been constructed by then, the structure did not
have to suffer extensive losses that would have resulted from the possible collapse of the bridge.
Since the tower had been constructed of steel, they were flexible to the effect of earthquake. Also,
there were 20 shock absorbers within each tower. This helped to keep the tower in place after the
earthquake. After the earthquake, detailed surveying showed that the tower on the Awaji side had
shifted a meter apart due to the quake. It could have been more dangerous than this.
b) DURING MAINTAINACE:
1.Maintenance for underwater steel structures:
The engineers used the Laying-Down Caisson Method to construct the underwater foundations of
the bridge. By inspection, they found that there were hole corrosion on the body of caissons. To
solve this problem, they could use Electro Deposit Method, which is one of the countermeasures
for corrosion of underwater structures and covers surface of structure with the deposit bonded by
slight electric current, in order to protect the steel from hole corrosions.
2.Dry Air Injection System for main cables:
• Dry air injection system to keep the interior surface of the main cable out of water
Fig: Dry air injection system
3. The non-destructive inspection for suspender rope:
A newly developed non0estructive inspection technique that used an electromagnetic method to
identify the degree of internal corrosion of the suspender ropes by comparing the amount of flux
between the intact cross section and corroded cross section. This could help to reduce the life
cycle cost of the ropes because they could realize the appropriate repair time and select the
adequate repair method by the calculation based on the data acquired by this method.
References:
1. General information of Akashi-Kaikyo Bridge by
http://homepage1.nifty.com/momotaroh/E_sub07_1
2. (html and Roads & Bridges magazine) http://www.roadsbridges.com/ Akashi-
Kaikyo-Bridge-article1145.
3. Bigg bigger biggest documentary-
https://www.youtube.com/watch?v=oPkC6dHEv4Y&t=14s
BOX GIRDER BRIDGE:
A box girder bridge is a bridge in which the main beams comprise girders in the shape of a
hollow box. The box girder normally comprises either prestressed concrete, structural steel, or
a composite of steel and reinforced concrete.
The box is typically rectangular or trapezoidal in cross-section. Box girder bridges are commonly
used for highway flyovers and for modern elevated structures of light rail transport. Although
normally the box girder bridge is a form of beam bridge, box girders may also be used on cable-
stayed bridges and other forms.
Structural Types
• Prestressed Concrete
• Masonry
• Steel
Mix of steel and reinforced concrete or mix of reinforced concrete and prestressed concrete
• Slab and girder (T-beam bridges) - Used for spans between 14 and 25 meters
• Hollow box girder - Used for spans between 25 and 70 meters - Characterized by a high
torsional resistance, is suitable for curved paths.
3. Masonry superstructures have been associated with arch bridges in the past centuries. This
type of bridges is not of relevant importance for this study, which is relative to new bridges under
construction.
4. Steel Superstructure typically consists in a steel truss deck and covers long spans.
• Longitudinal plate girder and transverse beam girder with concrete slab
• Longitudinal and transverse beam girder with concrete slab
The deck arrangement can be simple span or continuous span, or arch and covers medium and long
spans.
5. Special superstructure
• Suspended bridges
The continuing expansion of highway network throughout the world is largely the result of
great increase in traffic, population and extensive growth of metropolitan urban areas. This
expansion has lead to many changes in the use and development of various kinds of bridges. The
bridge type is related to providing maximum efficiency of use of material and construction
technique, for particular span, and applications. As Span increases, dead load is an important
increasing factor. To reduce the dead load, unnecessary material, which is not utilized to its full
capacity, is removed out of section, this results in the shape of box girder or cellular structures,
depending upon whether the shear deformations can be neglected or not. Span range is more for
box bridge girder as compare to T-beam Girder Bridge resulting in comparatively lesser number
of piers for the same valley width and hence results in economy.
A box girder is formed when two web plates are joined by a common flange at both the top
and the bottom. The closed cell which is formed has a much greater torsional stiffness and strength
than an open section and it is this feature which is the usual reason for choosing a box girder
configuration.
Box girders are rarely used in buildings (box columns are sometimes used but these are axially
loaded rather than in loaded in bending). They may be used in special circumstances, such as when
loads are carried eccentrically to the beam axis
When tension flanges of longitudinal girders are connected together, the resulting structure is
called a box girder bridge”.
Box girders can be universally applied from the point of view of load carrying, to their
indifference as to whether the bending moments are positive or negative and to their torsional
stiffness; from the point of view of economy.
The first box girder cross section possessed deck slabs that cantilevered out only slightly from
the box portion shown in figs a toe. With the prestressed concrete the length of cantilever could be
increased. The high form work costs caused a reduction in the number of cells fig (f, g, h). In order
to reduce the construction loads to minimum possible extent or to require only one longitudinal
girder in working states even with multiple traffic lanes.
It was only with the development of high strength prestressing steel that it became possible to
span longer distances. The first prestressed concrete bridges, most of I-cross sections were built
towards the end of the 1920’s.The great breakthrough was achieved only after 1945. “THE
SCLAYN” bridge over the river Maas, which was built by Magnel in 1948, was the first continuous
prestressed concrete box-girder bridge with 2 spans of 62.70m. In following years the ratio of
wages to material costs climbed sharply. This thereby shifted the emphasis of development of
Construction method. The box girder cross-section evolved structurally from the hollow cell-deck
bridge or T-beam Bridge. The widening of the compression zone that began as a structural
requirement at the central piers was in the extended throughout the entire length of bridge because
of advantages transverse load-carrying characteristics.
The spanning of bridges started with simple slabs. As the spans increased, the design depth of
slab is also increased. It is known that material near centre of gravity contributes very little for
flexure and hence can be removed. This leads to beam and slab systems. The reinforcement in
bottom bulb of beam provided capacity for tensile forces and top slab concrete, the capacity to
resist the compression. They formed a couple to resist flexure.
As the width of slab is increased more number of longitudinal girders are required resulting
in reduction of stiffness of beams in transverse direction and relatively high transverse curvature.
The webs of beams get opened out spreading radially from top slab. Under high transverse bending
these will no longer be in their original position. To keep it in their original position the bulbs at
bottom should be tied together which in-turn leads to evolution of box girder. Long spans with
wider decks and eccentric loading on cross-section will suffer in curvature in longitudinal and
transverse direction causing heavy distortion of cross-section. Hence the bridges should have high
torsional rigidity in order to resist the distortion of cross-section deck to a minimum.
Accordingly box girders are more suitable for larger spans and wider decks, box girders are to
be suitable cross-section. They are elegant and slender. Economy and aesthetics further lead to
evolution of cantilevers in top flanges and inclined webs in external cells of box girder. The
dimension of cell could be controlled by prestressing.
As the span and width increases the beams and bottom slabs are to be tied to keep the geometry
which in turn leads to evolution box girder.
Any eccentric load will cause high torsional stresses which will be counter acted by the box
section. The analysis of such sections are more complicated due combination of flexure, shear,
torsion, distortion. But it is more efficient cross-section. It is used for larger spans with wide cross-
section. It can be used for spans up to 150m depending upon the construction methods. Cantilever
method of construction is preferred most.
• In recent years, single or multi-cell reinforced concrete box Girder Bridge have been
proposed and widely used as economic aesthetic solution for the over crossings, under crossings,
grade separation structures and viaducts found in modern highway system.
• The very large Torsional rigidity of the box girder‘s closed cellular section provides
structures beneath is more aesthetically pleasing than open-web type system.
• In case of long span bridges, large width of deck is available to accommodate prestressing
cables at bottom flange level.
• Interiors of box girder bridges can be used to accommodate service such as gas pipes, water
mains etc.
• For large spans, bottom flange could be used as another deck accommodates traffic also.
• The maintenance of box girder is easier in interior space is directly accessible without use
of scaffolding.
• Alternatively space is hermetically sealed and enclosed air may be dried to provide a non-
corrosive atmosphere.
• It has high structural efficiency which minimizes the prestessing force required to resist a
given bending moment, and its great Torsional strength with the capacity this gives to re-centre
eccentric live loads, minimizing the prestress required to carry them.
Disadvantages:
One of the main disadvantages of box decks is that they are difficult to cast in-situ due to the
inaccessibility of the bottom slab and the need to extract the internal shutter. Either the box has to
be designed so that the entire cross section may be cast in one continuous pour, or the cross section
has to be cast in stages.
Specifications:
It can cover a range of spans from 25 m up to the largest non-suspended concrete decks built; of
the order of 300 m. Single box girders may also carry decks up to 30 m wide. For the longer span
beams, beyond about 50 m, they are practically the only feasible deck section. Below 30m precast
beams or voided slab decks are more suitable while above 50ma single cell box arrangement is
usually more economic.
Single cell box-girder cast-in-situ are used for spans form 40m to 270m.The box arrangement is
done in order to give aesthetic appearance where the web of box will act as a slender appearance
when combined with a slim parapet profile. Single box arrangements are efficient for both the
longitudinal and transverse designs, and they produce an economic solution for mot medium and
long span structures. This type of deck is constructed span-by-span, using full-height scaffolding
or trusses, or as balanced cantilever using form travellers. This could be particularly important for
medium length bridges with spans between 40m and 55m. Such spans are too long for twin rib
type decks, and too short for cast-in-situ balanced cantilever construction of box girders, while a
total length of box section deck of less than about 1,000 m does not justify setting up a precast
segmental facility.
Haunches:
The uprights have to carry the same bending moment as the haunch, but with the benefit of a
compression force due to the weight of the roof. Thus they may be slightly thinner than the
haunches. Haunches are always economical. They provide the twin benefits of attracting moment
away from mid-span and then providing a greater lever arm to resist this moment economically.
Even very short haunches are valuable in reducing the hogging reinforcement.
Design :
The selection of a box girder form usually results in relatively thin plate panels (in terms of
thickness to width ratio) for the webs and bottom flanges (and for top flanges, in all-steel boxes).
Avoidance of local buckling in compression zones and in shear requires appropriate stiffening and
longitudinal stiffeners are often required. Although box sections offer high torsional stiffness,
internal cross frames are usually needed to prevent distortion (when one web is subject to greater
shear than the other, one diagonal dimension across the cell increases and the other decreases).
Bearings at supports are normally within the width of the bottom flange (rather than directly under
the webs) and an internal diaphragm is needed to transfer the reactions.
When open-top boxes are used, they have very little torsional stiffness at the bare steel stage
and the narrow top flanges might be susceptible to lateral buckling (a later-torsional buckling mode
for the U-shaped section). It is therefore necessary to introduce some plan bracing to the top flange
(not necessarily over the full lengths of the spans) to restrict twist and slenderness for buckling.
Such bracing must avoid conflict with slab construction.
For any closed cell that requires internal access to construct it or to carry out inspection and
maintenance, Health and safety considerations require sufficiently large and well-placed openings
that an injured person could be quickly evacuated. All internal stiffening and diaphragms must
therefore be designed such that openings are big enough and that movement along the cell is
unimpeded.
Internal stiffening in a small steel box girder
References:
1. BS 5400-3:2000. Steel, concrete and composite bridges. Code of practice for design of
steel bridges. BSI
1. Hendy, C.R.; Iles, D.C. (2015) Steel Bridge Group: Guidance Notes on best practice in
steel bridge construction (6th Issue). (P185). SCI
2. Guidance Note 1.08, Box girder bridges
3. Iles, D.C. (2004) Design guide for composite box girder bridges. (P140). SCI
4. Iles, D.C. (2004) Design guide for steel railway bridges. (P318). SCI
5. Steel Bridges: A practical approach to design for efficient fabrication and construction,
2010, (Publication no. 51/10), BCSA
GOLDEN GATE BRIDGE
INTRODUCTION:
San Francisco grew rapidly in the early 1900s, but the mile-wide Golden Gate Strait limited access
and development to the north. Traveling north to Marin County and the Redwood Empire beyond
required a lengthy trip by ferryboat.
In 1923, popular support to build a bridge across the strait united behind the slogan “Bridge
the Gate.” Bridge supporters convinced the California state legislature to create a special district,
the Golden Gate Bridge and Highway District, as the entity to finance, build, and operate such a
bridge. In 1928, the District was incorporated and included the counties of San Francisco, Marin,
Sonoma, Del Norte, and parts of Napa and Mendocino.
A bridge over the Golden Gate Strait was the ambition of Joseph B. Strauss, who overcame
many obstacles to secure official approvals and win public support. Strauss faced strong
opposition from ferry operators, conservationists, and even some in the engineering community.
He assembled and directed an outstanding team of engineers, architects, geologists, and
construction workers to design and build a bridge that set a world record for longest span (the
distance spanned between the towers) and united a growing metropolis.
DATA:
• Total length of Bridge including approaches from abutment to abutment, plus the
distance to the Toll Plaza is 2,788 m.
• Length of suspension span including main span and side spans is 1.2 miles Length of
main span portion of suspended structure (distance between towers) is 1,280 m.
• Width of Bridge is 27 m.
• Width of sidewalk is 3 m.
At mid span, the maximum downward deflection (or the distance the Bridge was built to move
downward) is 10.8 ft. (3.3. m). The maximum upward deflection is 5.8 ft. (1.8 m).
Live load capacity per lineal foot is 4,000 lbs (1,814.4 kg).
As an example of how the Bridge is built to move, during the winter storms in 1982, the main
span bowed approximately 6 to 7 feet
The three maximum deflections noted above at the centre of the suspension bridge are due to the
following loading conditions:
1) The transverse deflection is due to a sustained transverse wind load. The maximum
transverse movement of 27.7 ft. is based on the maximum allowable longitudinal movement of
the wind locks at the support towers;
2) The maximum downward deflection is due to a condition with maximum live load on the
centre span, no live load on the side spans and maximum design temperature to elongate the
main cables; and
• The Golden Gate Bridge has two main towers that support the two main cables.
• The load on each tower from main cables is 61,500 tons (56,000,000 kg).
• The south tower foundation depth below mean low water is 110 ft. (34 m).
• To build south tower pier to support the south tower, construction workers pumped 9.41
million gallons (35.6 million litres) of water out of the fender that was constructed first.
Suspender Rope (vertical ones) Stats;
The Golden Gate Bridge has 250 pairs of vertical suspender ropes that are spaced 50 feet apart
across both sides of the Bridge. Each suspender rope is 2-11/16 inches in diameter. All of the
ropes were replaced between 1972 and 1976, with the last rope replacement completed on May
4, 1976.
Concrete Quantities:
These are the quantities when the bridge was built (1933-1937). After the original concrete
roadway deck was replaced, the amount of concrete is now less than when the Bridge was built
by 25,000 cubic yards.
To deal with this, the retrofit supercomputers are being used to simulate an earthquake's
effect on each part of the bridge, and a comprehensive vulnerability study of the bridge is
needed. The north and south approaches were determined to be vulnerable to collapse under a
major event because of the high support towers, which result in great ‘rocking’ force. The
signature span was also exposed to the possibility of significant damage. The connections from
the tower saddle to the main cable could sever, large longitudinal displacements could result in
adjacent spans striking the towers, the Fort Point arch could become unseated, and the
comparatively under reinforced south pylons flanking the arch span could sustain extreme
damage.
The seismic retrofit measures applied to the Bridge structures consist of various
methods of structural upgrades and include both the strengthening of structural components and
the modification of structural response of the structures so they can better respond to strong
motions without damage.
• Phase 2 would retrofit the San Francisco (south) Approach Viaduct, San Francisco (south)
Anchorage Housing, Fort Point Arch, and Pylons S1 and S2
• Phase 3 would Main Suspension Bridge and Marin (north) Anchorage Housing
First phase
The major strengthening measures implemented on the Marin (north) Approach Viaduct
included the following:
3. Replacement and addition of top and bottom lateral bracing and strengthening vertical truss
members and truss connections
Second phase
It is the most complex part of this project in terms of construction and design. This phase
encompasses structural retrofit of many different types of structures of the south approach,
including the south approach viaduct, anchorage housing, Fort Point arch, and south pylons.
Retrofit measures developed for each of these structures reflect their different behaviour
under seismic ground motions and their interaction at points of interface.
The steel support towers and bottom lateral bracing of the south approach viaduct will be
entirely replaced, seismic isolation bearings and joints will be installed at the roadway level. A
massive internal shear walls are constructed of the south anchorage housing. External and
internal steel plating will be added to south pylons walls. Addition of a new external concrete is
cover on the external surfaces of the pylons.
Third Phase
The third phase of the Golden Gate Bridge Seismic Retrofit Construction Project has been
separated into two sub phases as follows:
2. Phase 3B: Retrofit of the Main Suspension Span, Main Towers, South Tower Pier and Fender
Phase 3 involves retrofitting the suspension portion of the bridge, which comprises a
1,280 m main span and two 343 m side spans. The signature span towers, which rise 227 m
above mean sea level, are made up of multicellular built-up members constructed of riveted steel
plates and angles and have a combined weight of approximately 40,300 Mg.
Phase 3 retrofit measures include replacing some of the top lateral bracing and
connection strengthening within the stiffening truss, installing viscous dampers to "cushion" the
towers from potential adjacent span impact, and adding stiffeners and strengthening connections
within the towers. Horizontal steel tendon prestressing at the bases of the piers, expansion joint
replacements, concrete fender repairs, and the strengthening and immobilization of the
connections between the tower saddle and the main cable are included in additional measures.
CHALLENGES FACED:
North tower -relatively on dry land but south tower(below fig) which is located at 1100 feet
deep water.
Remedy followed:
Removing rock and soil under water up to required depth using dredges and using cassions
pouring concrete under water (it happened at 1930’s----great challenge without sophisticated
machinery)
2.Saftey of the workers at that tremendous height -----wind
Special safety nets are placed at under the deck slab and special Personal protective equipments
are supplied to each of the workers and monitoring wind is taken place.
3.Maintaince of the bridge due to extreme condition ----special type paints are used and daily
monitoring team actively participating in checking and painting of bridge.
References:
1. THE STUDY ON SAN FRANCISCO GOLDEN GATE BRIDGE, Kei Fung Sameul,
Kwan, Architecture and Civil Engineering Department, University of Bath, Bath, UK
3. Construction timeline,
http://goldengatebridge.org/research/ConstructionTimeline.php
已为 七a
一
( L
ト
PJ Ļ ' " ? Ťn G "
S o n S s .
V
ï
q
气
{7 É m ıı
吧 メ
Lo ' ļ
: Ì ンイ
toll V ''
ť iT L
"
X L\
300
4 50 \
Bmcnť
N ć> Ė T
L .
lk . \ ţ o Ł
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner