Government of India (Ministry of Road Transport & Highways)

Through
Roads & Buildings Department ( National Highways)
Rehabilitation and upgradation of NH-67 from km 695+000 to km 741+950 (Atmakur to Nellore section) to two lane with paved shoulder in the State of Andhra
Pradesh under NHDP –IV through Engineering, Procurement & Construction (EPC) Basis Contract
AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICE LTD.
CONTRACTOR : M/s BSCPL Infrastructure Ltd Date 5/20/2018
RFI Submission RFI Inspection
Sl.No RFI NO. Description of Item Side RFI Status Remarks
Date Time Date Time

Inspection for to collection of Pipe culverts


Inventory data at KM
136+032,137+267,139+492,140+082,141+
1 REP/NH-216/Str/003 5/20/2018 5.00 PM 508,142+656,144+678,145+506,154+628,1 BHS 5/21/2018 2.00PM
54+919,154+939,155+164,155+281,156+4
06,164+230,164+702,165+147.

2 REP/NH-216/Str/004 5/20/2018 5.00 PM Inspection for to collection of Box culverts


Inventory data at KM 139+772,147+941. BHS 5/21/2018 11.00AM

Check the excavation for Box culvert @


3 REP/NH-216/Str/005 5/20/2018 5.00 PM 161+984 BHS 5/21/2018 10.00AM
Government of India (Ministry of Road Transport & Highways)
Through
Roads & Buildings Department ( National Highways)
Rehabilitation and upgradation of NH-67 from km 695+000 to km 741+950 (Atmakur to Nellore section) to two lane with paved shoulder in the State of Andhra Pradesh under NHDP –IV
through Engineering, Procurement & Construction (EPC) Basis Contract
AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICE LTD.
CONTRACTOR : M/s BSCPL Infrastructure Ltd Date 5/23/2018
RFI Submission RFI Inspection
Sl.No RFI NO. Description of Item Chainage Side RFI Status Remarks
Date Time Date Time

1 REP/NH-216/Str/006 5/23/2018 5.00 PM Check the excavation for Pipe culvert Head
wall
162+666 BHS 5/24/2018 10.00AM

2 REP/NH-216/Str/007 5/23/2018 5.00 PM Check the excavation for Pipe culvert Head
wall
167+754 BHS 5/24/2018 11.00AM