Procedures and Notices required Under FIDIC 1999
< 28 days
Monthly Payment
< 56 days
Contractor
submit final Employer shall
Contractor submit
Statement and pay to the
draft of final
the written contractor the
Statement
discharge Final Statement
amount
____________________________________________________________________________________
Page 2 of 31
Procedures and Notices required Under FIDIC 1999
Either of the
parties shows
Either of the parties his
refers the dispute to dissatisfaction
D.A.B
____________________________________________________________________________________
Page 3 of 31
Procedures and Notices required Under FIDIC 1999
L.O.I
28 days
The contractor shall give notice to the Engineer whenever the works are
likely to be delayed or disrupted, the notice shall include details of the
necessary drawings or instruction, details of why and by when it should
be issued, and details of the nature and amount of the delay or
disruption likely to be suffered if it is late.
Extension of time
____________________________________________________________________________________
Page 4 of 31
Procedures and Notices required Under FIDIC 1999
Extension of time
28 days
42 days
Employer shall issue such
evidence
____________________________________________________________________________________
Page 5 of 31
Procedures and Notices required Under FIDIC 1999
2 days
2 days
If no contradiction in writing
Engineer to make a letter to
within 2 days, it shall be
contradict
deemed to be an instruction of
the Engineer.
____________________________________________________________________________________
Page 6 of 31
Procedures and Notices required Under FIDIC 1999
42 days
____________________________________________________________________________________
Page 8 of 31
Procedures and Notices required Under FIDIC 1999
____________________________________________________________________________________
Page 9 of 31
Procedures and Notices required Under FIDIC 1999
Contractor shall give the engineer not less than 21 days’ notice of the
date on which any plant or a major item of other Goods will be
delivered to the site
Commencement date
Contractor to submit
monthly progress
reports
____________________________________________________________________________________
Page 10 of 31
Procedures and Notices required Under FIDIC 1999
If the contractor suffers delay and/or incurs cost from complying with
the instructions of the engineer related to fossils.
24 hours
____________________________________________________________________________________
Page 11 of 31
Procedures and Notices required Under FIDIC 1999
Letter of acceptance
Notice of Commencement
28 Days
Page 12 of 31
Procedures and Notices required Under FIDIC 1999
84 days
28 days
Suspension affect part of the scope, this part can be Suspension affects the full project; this will
considered by the contractor as omitted and shall be entitle the contractor to termination of the
treated under clause 13 contract and shall be treated under clause
16.2
____________________________________________________________________________________
Page 13 of 31
Procedures and Notices required Under FIDIC 1999
21 days
14 days
Delay on Tests
____________________________________________________________________________________
Page 14 of 31
Procedures and Notices required Under FIDIC 1999
14 days
Engineer shall issue the taking- Engineer shall reject the If the Engineer fails to
over certificate application, giving reasons and either issue the taking –
specifying the work required to over certificate or to reject
be done by the Contractor the Contractor’s
application within 28 days
and if the works are
substantially in accordance
with the Contract, the
taking –over certificate
shall be deemed to have
been issued on the last day
of that period.
____________________________________________________________________________________
Page 16 of 31
Procedures and Notices required Under FIDIC 1999
Cost is at Contractor’s risk if work is attributable to: If due to any other cause, the Contractor will
Any design for which to contractor is responsible be notified by the employer/ representative,
Plant, materials or workmanship not being in accordance and it shall be treated as a variation
with the contract
Failure by the Contractor to comply with any other
obligation
28 days
For unfulfilled obligations, even after the issuance
Engineer shall issue a of the performance certificate, each party is liable
Performance Certificate for the unperformed obligations
after the latest of the
expiry dates of notice
Contractor to remove all
equipment, materials, etc.
28 days
Clause 12.1 “Works to be Measured”
Works to be
____________________________________________________________________________________
measured and valued
Page 17 of 31
Procedures and Notices required Under FIDIC 1999
14 days
Contractor to give If no notice,
notice to the Engineer Contractor, it is
to which records are deemed as
inaccurate if he accepted and
disagrees to the accurate
measurement
____________________________________________________________________________________
Page 19 of 31
Procedures and Notices required Under FIDIC 1999
If Contractor
cannot
Contractor, in compliance, Contractor shall Contractor Contractor readily obtain
submits: inform the shall execute to the goods
A description of the proposed Engineer if he and be promptly required for
work to be performed and a cannot comply bound by give notice the variation
programme for its execution and give reasons each to the
The Contractor’s proposal for Engineer
therefor variation
any necessary modifications
stating the
to the programme
Contractor’s proposal for reasons
evaluation of the variation with
supporting
particulars
Engineer to
act on the
proposal
Changes in
price
The adjustment of
prices shall be based
on whatever is more
favorable to the
Employer, either:
42 days 21 days
56 days
Whichever is later
Employer shall pay to the
contractor the final payment
Employer shall pay to the
contractor the first installment Note: if the contractor has not
of the advance payment applied for a final Payment
Certificate in accordance with
this Sub-Clauses, the engineer
Performance security received shall request the contractor to
do so. If the contractor fails to
56 days submit an application within a
____________________________________________________________________________________
period of 28 days, the engineer
shall issue the final payment
Page 21 of 31
certificate for such amount as
he fairly determines to be due
Procedures and Notices required Under FIDIC 1999
Disputed
Agreed
Contractor shall submit the final statement along with Engineer shall deliver to the employer
a written discharge which confirms that the total of with a copy to the contractor an interim
the Final statement represents full and final payment certificate for the agrees parts
settlement of all the moneys due to the contractor of the draft final statement, and a
under or in connection with the contract dispute should be referred to D.A.B
28 days
____________________________________________________________________________________
Page 22 of 31
Procedures and Notices required Under FIDIC 1999
“Statement of Completion”
Contractor to
submit Statement
of Completion
with supporting
documents in six
copies
Page 23 of 31
Procedures and Notices required Under FIDIC 1999
28 days
If the Contractor failed to
submit an application
Contractor to submit
an application
Page 24 of 31
Procedures and Notices required Under FIDIC 1999
Immediate effect
21 days
Notice of Suspension
To the Employer
____________________________________________________________________________________
Page 26 of 31
Procedures and Notices required Under FIDIC 1999
Notice of Termination
Grounds:
Non receipt of evidence w/in 14 days
Immediate effect
42 days after giving notice of prior notice
termination w/ respect to
Financial Arrangements Grounds are:
Engineer fails to issue payment To the Employer
Prolonged suspension
certificate after 56 days after Bankruptcy/ insolvency of
receipt of statement and the Employer or has gone
supporting documents into liquidation
Non- payment of interim
payment certificate w/in 42
days after expiry of 56 days for
Employer to pay interim
payments
Non- performance of
obligation by the Employer
Failure to comply with the
Contract agreement by the
employer as regards signing of
contract agreement and
assignment of contract
Clause 17.5 “Intellectual and Industrial property Rights”
Infringement (or
alleged infringement)
of Intellectual and/ or
industrial property Failure to do so, WAIVER
rights 28 days
of right to indemnity
Page 27 of 31
Procedures and Notices required Under FIDIC 1999
Occurrence of
Force Majeure
or should have
become aware
Within 14 days
Effective Termination
____________________________________________________________________________________
Page 28 of 31
Procedures and Notices required Under FIDIC 1999
If the contractor considers himself to be entitled to any extension of the Time and/or
any additional payment under any Clause of these Conditions or otherwise,
The contractor became aware or should have become aware of the event or
circumstance
< 28 days
42 days
28 days
< 28 days
84 days or other
period agreed by DAB shall be appointed
the parties by the Parties
DECISION on the
NO DECISION Dispute Replacement of a
member of DAB
____________________________________________________________________________________
Page 30 of 31
Procedures and Notices required Under FIDIC 1999
ARBITRATION
NOTICE OF
Notes:
Under the rules of arbitration
of international chamber of
commerce
56 days after notice
May be commenced prior to or
of dissatisfaction after the completion of the
Works
Obligations of the parties, the
On or after this period, to Engineer and the DAB shall
commence even without not be altered by any
attempt to settle amicably. arbitration being conducted.
____________________________________________________________________________________