Professional Documents
Culture Documents
Lewis Evans
Professor of Economics
NZ Institute for the Study of Competition and Regulation, VUW
16 December 2011
Key Issues
Open Access may apply (also) to contract carriers, whereby gas pipelines
provide accessibility on a first-come first-served basis to all clients willing
to pay the pipeline's maximum tariff. Once capacity is fully utilized, the carrier
must refuse new clients.
• Common carrier:
and
• Contract Carrier: with multiple shippers
• The social investment criterion, however, should remain the same: but should
Incorporate all effects (e.g. storage implications).
Social timing/quantum
Invest when expected present value of additional total surplus exceeds K (≥ 1)
times expected present value cost of investment
Private timing/quantum
Invest when additional present value extra profit (producer’s surplus) exceeds
K* (≥1) times cost of the expected present value of investment
Common Carriage
The service is quantum of gas shipped and hence the price should be $/GJ/period
transhipped
But
Funding investment appropriately will generally require fixed and variable charges
in order that the pipeline be funded and produce the “right” throughput: i.e. require
two (or more) part tariffs
Efficiency requires fixed and variable charges ex post variable charge may not
cover cost
Once physical capacity of the pipeline is reached price should rise to the point
that an additional chunk of capacity is justified (recall that the price is only a
partial signal): Where capacity is reached there is an argument that a fixed charge
be introduced as an additional signal.
Because of scale economies there will need be a fixed charge for self financing
pipelines
Again price (in this case the fixed charge/capacity) is only a partial signal .
Because fixed charges scoop off some consumer surplus the capacity price is a
better indicator of investment desirability
Under contract carriage there may be capacity unused but paid for by a shipper
is this efficient?
• It can be e.g.
• where it provides a shipper with surety (a real option) for future use:
perhaps attendant with upstream investment and downstream costs of
storage;
• Where it provides a shipper the ability to absorb almost all of its
customer supply risks
• It may not be
• where a shipper seeks to limit downstream competition : this is more
likely where upstream competition is relatively more vigorous than downstream
• Where transactions costs inhibit transfer of capacity by individual capacity-holders.
A. If total capacity is contracted: and down-stream demand continues to grow and total
capacity is priced fully
• There will for contract shippers be increased direct or opportunity costs in holding
spare capacity, and
• The threat of an additional chunk of capacity (investment) on the horizon
Under the contract model these (subcontract) exchanges may have various terms but they
need be written around capacity.
A pipeline that is managed for either contract carriage or common carriage has the
governance structure that might contemplate a mix of approaches. It could
• Contract out capacity to shippers for a proportion of the existing capacity and
• Manage the remaining capacity as common carriage
In this setup
• contract holders of capacity would be charged for capacity and they could voluntarily
trade their capacity with other shippers or the network manager for utilisation as
common carriage.
At the same time shippers with capacity could trade capacity with Vector’s
pool or other shippers
Need consider
• Vector’s position under regulation, and
• How governance interacts with the investment framework
Some issues are so important they may affect the framework for investment
as well as the assessment of individual capacity investments
• Does the presence of the North pipeline mean that bypass pipelines
have a significant cost disadvantage vs North pipeline owner? i.e. are
economies of scale that important?