MEMBINA DAN MENYIAPKAN SALIRAN GONG PASIR FASA I,SERTA KERJA-KERJA

BERKAITAN BAGI PROJEK TEBATAN BANJIR,DUNGUN,TERENGGANU DARUL IMAN.

NO TENDER : JPS/N/TG/TB/6/15

BILL NO.3 – SUB KERJA : PEMBINAAN STRUKTUR RUBBER DAM

All Quantities Are Provisional

NEW RATE AMOUNT NEW


ITEM DESCRIPTION OF WORK UNIT QTY QTY (RM) (RM) AMOUNT

3.1 RUBBER DAM STRUCTURE


Reinforced Concrete Slab

3.1.1 Grade 30 reinforced concrete m3 850 558 300 255,000.00 167,400.00

3.1.2 Lean concrete grade 15 as


describe 75mm thick blinding
Screed, spread and levelled
beneath foundation. m2 800 388 15.00 12,000.00 5,820.00

3.1.3 Sawn formwork as described


a) Vertical fair surface m2 530 410 35.00 18,550.00 14,350.00

3.1.4 High tensile reinforcement to


BS 4449
a) T16 kg 18,950 20,200 3.3 62,535.00 66,660.00
b) T20 kg 47,000 26,500 3.3 155,100.00 87,450.00
c) T25 kg 7,100 24,500 3.3 23,430.00 80,850.00

3.2 SUBSTRUCTURE
Excavation
3.2.1 Excavate for structure
Irrespective of depth including
backfilling with excavated spoil
and disposing surplus spoil or
material not suitable. m3 9,200 8,434 12.00 110,400.00 101,208.00

Structure Of Rubber Dam


3.2.2 Supply and place 70kg to 110kg
Rip Rap ( 1200mm thick ) m2 700 673 85.00 59,500.00 57,205.00
3.2.3 Lean Concrete Grade 15 as
described 75mm thick blinding
screed , spread and levelled
beneath foundation m2 400 673 15.00 6,000.00 10,095.00

3.2.4 Vibrate reinforced concrete

grade 35A as describe m3 1,100 1,280 32.00 352,000.00 409,600.00

3.2.5 High tensile reinforcement to

BS 4449

a) T16 Kg 13,900 13,800 3.3 45,870.00 45,540.00

b) T20 Kg 39,300 32,600 3.3 129,690.00 107,580.00

c) T25 kg 56,800 7,100 3.3 187,440.00 21,300.00

3.2.6 Sawn formwork

a) Base & Wall m2 800 120 35.00 28,000.00 4,200.00

3.2.7 River Bed Protection

a) Supply and place geotextile


MXC 70 or equivalent m2 1,800 1,487 7.00 12,600.00 10,409.00

b) Supply and place granitic


rocks ( 70kg – 100kg ) to form
under layer of the groynes
from toe to crest. m3 5,055 4,956 82.00 414,510.00 406,392.00

3.2.8 ROCK BOLT

a) Supply and install rock bolt


with 6m length T25 high
tensile steel bars embedded
3m in bed rock as part of
foundation system. Rate to
include supply all necessary
machaneries, equipment and
materials for drilling , and
grouting of anchor bolt No 333 95 180.00 59,940.00 17,100.00
Supply and install chemical hilti
product HT500 No 95

Total Carried To Collection 1,932,565.00 1,613,159.00

COLLECTION FROM :

BQ 2 1,932,565.00

BQ 2– (NEW AMOUNT) 1,613,159.00

TOTAL BILL NO.3 CARRIED TO SUMMARY OF WORK 3,545,724.00